Interrogatory responses

Answers to questions 836, 841, 842, 843, 844, 845, 846, 847, 848, 850, 851, 852, 853

Files15

Text of OCC-842 Attachment 1.pdf

Extracted from the file · 4 pages · 9,255 characters

Text of OCC-843_Final.pdf

Extracted from the file · 3 pages · 8,944 characters

Text of OCC-844_Final.pdf

Extracted from the file · 1 page · 802 characters

Text of OCC-845_Final.pdf

Extracted from the file · 3 pages · 9,019 characters

Text of OCC-846_Final.pdf

Extracted from the file · 1 page · 796 characters

Text of OCC-847_Final.pdf

Extracted from the file · 1 page · 1,098 characters

Text of OCC-848_Final.pdf

Extracted from the file · 1 page · 1,284 characters

Text of OCC-850_Final.pdf

Extracted from the file · 1 page · 1,378 characters

Text of OCC-851_Final.pdf

Extracted from the file · 1 page · 745 characters

Text of OCC-852_Final.pdf

Extracted from the file · 3 pages · 6,892 characters

  1. Page 1

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 22, 2026 OCC-852 Attachment 1 Page 1 of 6 CL&P dba Eversource Energy Docket No. 25-12-13 Set OCC-17 Date Issued February 23, 2026 OCC-501, Attachment 2 Page 1 of 6 Classification of Major Event Days Prepared by: Cheryl A. Warren, James D. Bouford, Richard D. Christie, Dan Kowalewski, John McDaniel, Rodney Robinson, David J. Schepers, Joseph Viglietta, Charlie Williams, Senior Members, IEEE On behalf of the Working Group on System Design MT WA Abstract-- A paper that explores the basis, need, and benefit of classifying reliability performance relative to major events. Today, many internal and external goals are set based on reliability performance. Internal as well as external comparison is difficult to make due to variations in weather, collection methods, and a plethora of other variables. The Working Group on System Design has developed a statistics based methodology that classifies reliability data into normal and major event days. After classification, analysis can be performed on each data set using separate processes to arrive at sound business decisions and to make internal comparisons possible. This paper describes the newly developed methodology, the “Beta Method”. OR ID ND WY MN WI SD NV UT CO MI IA NE IL KS IN MO AZ NM AR LA WV TN MS AL TX OH KY CA OK NY ME VT NH PA MA,CT,RI VA MD,DE,NJ NC GA SC FL Alaska Hawaii Reliability Standards in place Reliability Standards being considered Figure 1. US States involved with distribution reliability regulation. Index Terms— Distribution Reliability, Major Event Day, 2.5 Beta Methodology, lognormal statistical approach, Storms. A few short years ago, only a hand full of states had formal distribution reliability reporting requirements. Today, the number has grown to over half of all US states and is continuing to rise. Some regulators have initiated extensive reporting requirements. Many regulators review not only annual statistics, but also lists of worst performing circuits, reliability expenditures and a variety of other detailed data items. Some states have extended regulatory boundaries to require utilities to purchase outage management systems (“OMS”). It is clear, that executives and regulators alike require a reasonable method for tracking and reporting reliability performance, a method that provides information for proper decision-making. I. INTRODUCTION Deregulation and re-regulation have led electric utility regulators and customers alike to scrutinize the electric power industry. Claims of improved service for less cost have been used to foster deregulation. Regulators have tried to ensure a continuation, and in some cases, an improvement in electric service reliability under the new operating environment. Electric utility executives have endeavored to continue to maintain service levels without increasing cost, and in some cases, by decreasing expenditures. As a result both internal and external goals have been set around reliability performance, yet there has been no uniform methodology for removing events that are so far away from normal performance that they are known as outliers. Without removal of such events, the variation in annual performance is too great to set meaningful targets. This paper discusses the need to classify reliability performance. Normalizing reliability data will reduce the variability, thus making trending/goal setting possible. It will also segment performance during large-scale events so that appropriate post analysis can be performed. The IEEE Working Group on System Design, the group that authored the Full-Use Guide on Electric Power Distribution Reliability Indices-1366-2001, has recently developed a statistics based methodology (herein referred to as the “Beta Method”) for identifying outlying performance (otherwise known as Major Event Days or MEDs). The method is known as the “Beta Method” because of its use of the naturally occurring log normal distribution that best describes reliability performance data, where Beta is a key parameter. Using the Beta Method, utilities can calculate indices on both a normalized and unadjusted basis (identifies abnormal performance). Appropriate decisionmaking can be performed on each set of indices. Normalized indices provide metrics that can, and should, be used for both internal and external goal setting. Unadjusted indices, when compared to the normalized indices, provide information about utility performance during major events. The Beta method identifies the occurrence of abnormal Distribution re-regulation has been sweeping the country as evidenced1 by Figure 1. This paper was produced by the Working Group on System Design. Please see the last section of the paper for group membership. 1 “Reliability on the Regulatory Horizon” by Cheryl A. Warren and Michael J. Adams, Presented by Charlie Williams at the IEEE T&D Conference in Atlanta 2001. 1
  2. Page 2

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 22, 2026 OCC-852 Attachment 1 Page 2 of 6 CL&P dba Eversource Energy Docket No. 25-12-13 Set OCC-17 Date Issued February 23, 2026 OCC-501, Attachment 2 Page 2 of 6 conditions that grossly affect the reliability of a system and using it allows the investigation of utility performance during major events. Events that may be included in unadjusted information are major weather events, major substation events, or unexpected catastrophic events such as earthquakes. Major events are events that are beyond the design and/or operational limits of a utility. It is anticipated that both executives and regulators will scrutinize those events that cause MEDs and take appropriate action to mitigate their future impact on reliability. There could be cases where no additional action is required, as would be the case when an event was beyond control and beyond the design and/or operation limits of the utility (e.g., Class 4 hurricane). The Beta Method is used to identify major event days. A major event day is a day in which daily SAIDI exceeds a threshold value TMED. In calculating daily SAIDI, interruption durations that extend into subsequent days accrue to the day on which the interruption begins. This technique simplifies calculations and ties the customer-minutes of interruption to the instigating event. The major event day identification threshold value TMED is calculated at the end of each reporting period for use during the next reporting period. For utilities that have six years of reliability data, the first five are used to determine TMED and that threshold is applied during the sixth year. The methodology follows: II. METHODOLOGY DEVELOPMENT The Working Group is comprised of over 100 active members from thirty-one states and six countries that hail from universities, utilities, regulatory agencies and consultancies. The Working Group has spent the last two years creating a methodology that would: • • • • • 1. Values of daily SAIDI for a number of sequential years, ending on the last day of the last complete reporting period, are collected. Consistency of future results is enhanced if five or six years of data are used, but, if fewer than five years of historical data are available, all of the available complete year, historical data should be used. Use of more than six years of data may distort the effects of major events and minimize the impact of the analysis. Be fair to all utilities regardless of size, Allow segmentation of reliability data into normal and abnormal categories, based on the identification of outlier events that cause Major Event Days, Allow use of normalized indices for internal and external goal setting, Be consistent for various amounts of data availability and for all utilities, and Be easy to understand and execute. 2. Replace any day in the data set that has a value of zero for SAIDI with the lowest non-zero SAIDI value in the data set. (This permits the calculation of the logarithm of a SAIDI value for every day. While not technically precise, this does enhance the overall accuracy and consistency of the method.) 3. The natural logarithm (ln) of each daily SAIDI value in the data set is calculated. Many working group members anonymously provided their outage data for methodology development. A contingent of volunteer members from the working group performed rigorous analysis on all provided data while evaluating the efficacy of a number of proposed methods. Before the final methodology was chosen, several other methods were developed and abandoned due to their inability to meet the criteria noted above. Rich Christie authored “Statistical Classification of Major Reliability Event Days in Distribution Systems”, a paper that describes some of the thinking. The working group has selected the Beta Method as the method best meeting the above criteria. 4. The average of the logarithms, α (Alpha), (also known as the log-average) of the data set is calculated. 5. The standard deviation of the logarithms, β (Beta), (also known as the log-standard deviation) of the data set is calculated. 6. The major event day threshold, TMED, is calculated by using the equation: TMED = e (α +2.5 β ) (Note that this value should in theory give, on average, 2.3 major event days per year. In practice, using the donated utility data, higher numbers of major event days per year, from two to eight, are seen. This is not unexpected since the actual data does not conform precisely to the log-normal distribution.) III. THE BETA METHOD The method is easily applied to reliability data and can be set up to run automatically from an OMS, or be manually applied by using MS Excel™ and/or MS Access™. Its purpose is to allow major events to be studied separately from reliability performance that occurs during what would be considered normal operation, and, to better reveal trends in normal operation that would be hidden by the large statistical effect of major events. 7. Any day that occurs during the subsequent reporting period with daily SAIDI greater than the threshold value TMED is designated a major event day. The data for this day 2
  3. Page 3

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 22, 2026 OCC-852 Attachment 1 Page 3 of 6 CL&P dba Eversource Energy Docket No. 25-12-13 Set OCC-17 Date Issued February 23, 2026 OCC-501, Attachment 2 Page 3 of 6 should be removed when calculating normal reliability performance. Utility 4 Adjusted vs. Unadjusted SAIFI (2.5 Beta Method) It is the group’s recommendation that major event day performance be reviewed in a different, possibly more rigorous, manner than normal day performance. Customer Interruptions per Customer Served 1.8 SAIDI was chosen as the metric in order to capture the effects on customer minutes interrupted (“CMI”) or duration of events. SAIDI is the division of CMI and total customers served. Dividing by total customers served allows utilities to use the methodology even after a merger has occurred. Despite the fact that SAIDI is used as the metric to determine MEDs, the methodology is applied to all indices. 1.6 0.29 0.07 0.09 1.4 1.2 1 0.8 1.46 1.41 1.43 2000 SAIFI 2001 SAIFI 0.6 0.4 0.2 0 1999 SAIFI Normalized Indices Abnormal Contribution Figure 2. Utility 4 SAIFI Because the methodology classifies all performance into two data sets, 1) normal performance and 2) abnormal performance, it cannot favor a poorly performing utility. All data is provided in one of the two classifications. It is up to executive management and regulators to review both data sets to draw conclusions about overall performance. Figure 3 illustrates the significance of identifying abnormal events. In evaluating three years of provided data, it is evident that 2000 had the most major event activity. In this case major event days were caused by weather. For that year (2000), over 42% of the utility’s overall CAIDI could be attributed to the abnormal event CAIDI. Notice that normalized CAIDI was fluctuating within a reasonable band (no more than 8% variation from year to year). It is likely that the system is performing within acceptable design and or operational limits. The fact that major event contributions vary from year-to-year is to be expected, and may be directly correlated to weather variations. If the major event variation is due to conditions within the utility’s control, then executives and regulators should take appropriate action. . Furthermore, if over time there is indeed a true and sustained change in the weather patterns affecting a utility’s service territory, this “normalization” process will reflect (and include) that change. If that occurs, then there are strong and supported reasons for the utility to change it operating practices. IV. EXAMPLES OF THE METHODOLOGY RESULTS For a detailed calculation example please refer to Draft 9 of the Full-Use Guide on Electric Power Distribution Reliability Indices 1366-D9. Using data provided by member utilities, two illustrative examples are presented here. Utility 4 used three years of data to determine threshold values while Utility 10 used seven years of data. A. Example 1 - Utility 4 Figure 2 and Figure 3 show analysis results from Utility 4. The lower light blue bars show the normalized values for SAIFI and CAIDI. Utility 4 is required to report SAIFI and CAIDI, not SAIDI to their regulator. The upper orange bars show the contribution from abnormal events to SAIFI and CAIDI. The summation of the two bars is the total system SAIFI and CAIDI or unadjusted SAIFI and CAIDI. Note that normalized SAIFI performance was constant, with no more than 3% variation from year to year. The normalized CAIDI was relatively constant, with no more than an 8% variation. Unadjusted, SAIFI varied 11% from year to year and CAIDI varied between 56% and 70% over the period. Utility 4 Adjusted vs. Unadjusted CAIDI (2.5 Beta Method) 250 200 90 Minutes 150 18 12 100 121 112 2000 CAIDI 2001 CAIDI 117 50 0 1999 CAIDI Normalized Indices Abnromal Contribution Figure 3. Utility 4 CAIDI 3
  4. Page 4

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 22, 2026 OCC-852 Attachment 1 Page 4 of 6 CL&P dba Eversource Energy Docket No. 25-12-13 Set OCC-17 Date Issued February 23, 2026 OCC-501, Attachment 2 Page 4 of 6 Figure 3 is a clear example of why normalizing indices is critical to customers, regulators and internal utility goals. If the unadjusted data were used to target spending, then this utility might be focused on the wrong issues (e.g., events that occurred as a result of one major storm and are unlikely to occur again in the foreseeable future). Utility 10 Unadjusted vs. Adjusted CAIDI (2.5 Beta Method) 160 140 Minutes 100 B. Example 2 - Utility 10 Figure 4 and Figure 5 show results from Utility 10. SAIFI, even adjusted, is still increasing at a steep rate, while CAIDI is oscillating and is fairly constant. Given this type of information, executives from this utility may alter spending and action plans if no recent IT systems changes have been implemented that might account for the steep rate of SAIFI change. If this utility recently implemented a fully connected outage management system that more accurately captures reliability information, then these graphs could be explainable by that fact alone. It is well known that after fully connected IT systems are implemented, that reliability appears to worsen since more accurate information is being collected. For this example, we assume that no system changes occurred. 40 Customer Interruptions per Customer Served 1.00 1999 C. Example 3 – Worst Performing Circuits Many state regulators are requesting reports on worst performing circuits (“WPC”). Typically, all interruption data is used to determine the WPC list. The number of circuits reported to regulators across the US varies from 4% to 10% of the total circuits on the system with each state allowing different reliability data adjustments. There are only a few states, at the present time that review circuit performance based on storm-adjusted or major event classified information. Consequently, utilities may be required to investigate solutions to problems that would only occur during a major event. This may not be the most cost-effective approach. The Beta Method will allow utilities to apply worst performing circuit criteria to adjusted data, thus identifying circuits that are most likely to remain worst performing if actions are not taken. In cases where WPC criteria is applied to all events, circuits often become members of this group due to one extreme event. Using non-classified data seems to defeat the regulatory purpose, which presumably is to solve repetitive reliability issues on problem circuits. 1.16 0.93 0.73 0.20 0.00 2000 Abnormal Contribution Figure 5 Utility 10 CAIDI 0.36 2001 Year Normalized Indices 2001 Year 0.42 1999 67 2000 Normalized Indices 0.80 0.40 77 60 0 0.26 0.60 22 30 20 1.60 1.20 80 60 Utility 10 Unadjusted vs. Adjusted SAIFI (2.5 Beta Method) 1.40 75 120 Abnormal Contribution Figure 4. Utility 10 SAIFI Figure 4 shows unadjusted CAIDI varies as much as 69% while adjusted CAIDI varies only as much as 28% a year for this utility. While 28% is a high percentage, it is significantly better than unadjusted statistics. This information may indicate crew overload on major event days. It appears that the major events were significant enough to completely saturate crew availability and thus restoration efforts were excessively delayed. This paper has provided two simple examples using the Beta Methodology. During methodology development, many utilities used the beta method on their own data and determined it to be a fair methodology. It is important to remember that when using the 2.5 Beta Method, no data is excluded, instead it is classified, analyzed and reported upon using separate processes. V. BENEFIT SUMMARY Daily, decisions are made at utilities based on perceived risk versus anticipated reward. The Beta Method provides a mechanism to segment information into appropriate categories allowing different decision paths to occur. It is the hope of this group that classification will result in better business decision-making. Regulators, utilities, and customers benefit from the Beta Method 4
  5. Page 5

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 22, 2026 OCC-852 Attachment 1 Page 5 of 6 CL&P dba Eversource Energy Docket No. 25-12-13 Set OCC-17 Date Issued February 23, 2026 OCC-501, Attachment 2 Page 5 of 6 because it segments reliability performance to reveal trends that utilities can then address. Peter Gelineau – Canadian Electricity Association David Gilmer – Yampa Valley Electric Association Jeff Goh – PG&E Manuel Gonzalez – Reliant Energy John Grainger – University of North Carolina Don Hall – CES International Mark Halpin – Mississippi State University Dennis Hansen – PacifiCorp Randy Harlas – El Paso Electric Company Mostafa Hassani – PEPCO Harry Hayes – Ameren Charles Heising – Alaska Power & Telephone Company Eric Helt – Exelon – PECO Energy Richard Hensel - Consumers Energy Company Jim Hettrick - MidAmerican Energy Francis Hirakami - Hawaiian Electric Company Dennis B. Horman - Utah Power & Light Co. George E. Hudson - Virginia Power Brent Hughes - BC Hydro Joseph Hughes - Electric Power Research Institute Carol Jaeger - Puget Power Kevin Jones - Advantica Stoner Karim Karoui - Tractebel Mark Kempker - AES - IPALCO John Kennedy - GA Power Company Tom Key - EPRI-PEAC Mladen Kezunovic - Texas A&M University Mort Khodaie - Public Service CO NM Margaret Kirk - Peninsula Light Co Don Koval - Universiy of Alberta Dan Kowalewski – Exelon - Commonwealth Edison* David Kreiss - Kreiss Johnson Thomas M. Kulas – Xcel Energy Frank Lambert - Georgia Tech/NEETRAC Larry Larson - Otter Tail Power Co Ken Lau - PG&E Jim Laurich - FirstEnergy Corp. Robert E. Lee - Pennsylvania Power & Light Co. Jim Lemke - Cinergy Gene Lindholm - AES/CILCO Raymond M. Litwin - Northeast Utilities Vito Longo - Power Technology Consultants LLC Andrea Mansoldo - Pirelli Cavi e Sistemi S.p.A Arshad Mansoor - EPRI-PEAC Corporation Mike Marz - Cooper Power Systems John McDaniel - Detroit Edison Co.* Stephen Middlekauff - CP&L Bill Montgomery - Con Edison J.C. Montgomery - Detroit Edison Co. Chris R. Mueller - RTE Zellweger Jerry Murray - Oregon PUC Peter Nedwick - Dominion - Virginia Power Gregory Olson - Public Service Electric & Gas Anil Pahwa - Kansas State University Dan Pearson - PGE Theodore Pejman - USDA-RUS Christian Perreault - Hydro Quebec A large group, with representation from all interested parties, created this methodology. The Beta Method allows utilities and regulators to confidently set goals/targets based on normal, and expected future performance. It also provides a technique to review performance during severe events. VI. WORKING GROUP MEMBERS Cheryl A. Warren* - Chair * Indicates participation on sub group that performed analysis and wrote text. John Ainscough - Xcel Energy Greg Ardrey - Alliant Energy Ignacio Ares - Florida Power & Light Company Gene Baker - Florida Power Corp. MT3B John Banting - Cooper Power Systems Jerry Batson - Alliant Energy Steve Benoit - Minnesota Power Lina Bertling - Royal Institute of Technology Roy Billinton, D.Sc., P.Eng. - University of Saskatoon Dave Blew - PSEG Math Bollen - Chalmers University of Technology James D. Bouford - National Grid* Richard Brown - ABB Joe Buch - Madison Gas and Electric James Burke - ABB Ray Capra - Consultant Mark Carr - AEP Donald M. Chamberlin - Northeast Utilities Jim Cheney - Arizona Public Service Simon Cheng - Puget Power Dave Chetwynd - BC Hydro Ali Chowdhury - MidAmerican Energy Richard D. Christie, Ph. D. - University of Washington* Rob Christman - FPL Larry Conrad - Cinergy Corp Ed Cortez - Stoner Associates Inc. Grace Couret - Florida Power & Light Company Tim Croushore - Allegheny Power System Peter Daly - Power System Engineering Rich D'Aquanni - Applied Resources Group Inc. Bill Day - Distribution Management Consultants Al Dirnberger - TXU R. Clay Doyle - El Paso Electric Russ Ehrlich - Conectiv Charlie Fiajnvandratt - Navigant Consulting, Inc. Doug Fitchett – American Electric Power Robert Fletcher - Snohomish County PUD Mahmud Fotuhi-Firuzabad - University of Saskatoon Keith Frost – Exelon – Commonwealth Edison Chris Gedemer – Advantica Stoner 5
  6. Page 6

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 22, 2026 OCC-852 Attachment 1 Page 6 of 6 CL&P dba Eversource Energy Docket No. 25-12-13 Set OCC-17 Date Issued February 23, 2026 OCC-501, Attachment 2 Page 6 of 6 Charles Perry - EPRI - PEAC Robert Pettigrew - Beckwith Electric Company C.Y. Pi - Moore Systems Steven L. Puruckner - ORNL Steve Quade - Northern States Power Company Gary Rackliffe - ABB/Automated Distribution Ignacio Ramirez-Rosado - University of La Rioja Wanda Reader – Exelon –Commonwealth Edison John Redmon - John R Redmon, Inc. Sebastian Rios - Catholic University Chile Rodney Robinson - Westar Energy* Fred A. Rushden - Rushden Consulting & Research David Russo - Seattle City Light Dan Sabin - Electrotek Concepts Shafi Sabir - Scarborough PUC Jim Sagen - Fort Collins Light & Power Dept. Bob Saint - NRECA Joe Santuk - Dominion - Virginia Power David J. Schepers – Ameren* Ken Sedziol - Cinergy Peter Shaw - Consultant Michael Sheehan - Puget Sound Energy Tom Short - EPRI-PEAC Hari Singh - Cooper Power Systems John Spare - KEMA Consulting John Sperr - Rochester Instrument Systems Lee Taylor - Duke Power Co. Rao Thallam - Salt River Project, ISB 240 Ridley Thrash - Southwire Company Betty Tobin - Seattle City Light Hahn Tram - SchlumbergerSema Hector Valtierra – Exelon - Commonwealth Edison S.S. (Mani) Venkata – Iowa State University Joseph Viglietta –Exelon PECO Energy Company* Marek Waclawiak - United Illuminating Co. Daniel J. Ward - Dominion - Virginia Power Carl Warn - Rochester Gas & Electric Corp. Neil Weisenfeld - Con Edison Greg Welch - ABB Power T&D Company, Inc. Lee Welch - Georgia Power Company Val Werner - Wisconsin Electric Charlie Williams - Florida Power - A Progress Energy Company* Bill Winnerling - EPRI Mike Worden - NY PSC 6

Text of OCC-853_Final.pdf

Extracted from the file · 1 page · 1,942 characters

As listed on the current system

Question(s) Answered 836, 841, 842, 843, 844, 845, 846, 847, 848, 850, 851, 852, 853 (The Connecticut Light and Power Company) Date Filed: 10/06/2026