  1. Page 21 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 21 of 191 Page 14 the Company can avoid an estimated cost of $112 million to bring the unit back to service. In addition, the Company hoped to end the out of rate base treatment and reduce operational risks it would face with electric restructuring by requesting full recovery of its unamortized rate base balance with a return from the date the plant was retired. The Department has discussed the shortcomings in the Company’s analyses and changes that could increase the benefits of continued operation; however, other factors particularly lower purchased power costs, could offset the benefits. The Department will therefore accept the Company’s reference case forecast of benefits/penalties as filed for ratemaking purposes. The Department believes that some sharing of the remaining costs between ratepayers and shareholders is appropriate because the study indicates that it may be economic to retire MP1 in the future for economic reasons. Further, the Department believes that ratepayers are entitled to the benefits from 1999 and 2000 that they would have received if the unit had not been retired prematurely. In addition, the Company should not benefit from retiring MP1 before its expected return to service date of July 1, 1999. In its written exceptions, the Company urges the Department to adjust the $109 million in economic benefits to reflect the following: (1) CL&P’s 81% ownership of MP 1; (2) the present value of the economic benefits; (3) lower energy and capacity costs approved elsewhere in the Decision; and (4) lower decommissioning costs consistent with decommissioning costs allowed in the Decision. CL&P Written Exceptions, p. 8. The Department agrees that the economic benefits should be adjusted to reflect CL&P’s ownership share of MP 1 and will do so. In addition, the Department agrees that the economic benefits should be calculated on a present value basis since they are presented in the CUO study in nominal dollars. However, the Department does not agree with the Company’s calculation or the present value adjustment. Since the rate year is 1999, 1999 benefits are on a present value basis and no adjustment is necessary. The Department will discount 2000 economic benefits by one year at a discount rate of 9.2%, as used in the CUO study. The revised economic benefit ratepayers will forgo due to the early retirement of MP 1 is $84.5 million. The Department does not agree that the economic benefits should be adjusted to reflect lower fuel prices or decommissioning costs. It is unclear how the Company calculated their adjustments for energy and decommissioning. These adjustments are not supported by the record and therefore inappropriate at this time. While adjusting these components in the CUO study might seem consistent with the Department’s ratemaking in this Decision, it would be inconsistent with the other components of the CUO study. Many of the assumptions in the CUO study have changed since the Company conducted its analysis. It is not appropriate to selectively adjust assumptions that benefit the Company. Updating or quantifying other factors could increase the economic benefits of the continued operation of MP 1, which would offset the adjustments proposed by the Company. The Department notes that it did not increase the economic benefits for the $8.4 million associated with the Watch List items identified above that should be removed for the costs of continued operation. In addition, CL&P
  2. Page 22 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 22 of 191 Page 15 did not request that the Department update the CUO results to reflect reduced nuclear employee levels approved in the Decision. Doing so would reduce O&M costs and increase the economic benefits of continued operation. Finally, the Department has not attempted to quantify benefits such as fuel diversity, employment and environmental impacts, which the Company did not include in its analysis. For these reasons, the Department will not adjust the economic benefits for changes in fuel prices and decommissioning as requested by the Company. a. Treatment of Millstone Unit 1 in the Application The Company originally forecast MP1 to restart on July 1, 1999. Consequently, the 1999 forecast contains incremental restart costs for the first six months and normal operating costs for the last six months of the year. Response to Interrogatory EL-152. As of March 1, 1998, ratepayers have not been supporting MP1 and have received a 1.39% credit on their monthly bills to reflect removal of MP1 costs. The total credit for MP1 was dependent upon actual sales and the time before rates are adjusted. If MP1 remained out of service at the conclusion of phase two of this docket, the Department would determine the appropriate rate treatment for crediting customers in the phase two Decision. This credit was not subject to true-up, as waived by the Company in Docket No. 97-05-12. Interim Decision, pp. 3 and 4. The total credit was not dependent on the retirement of MP1. The Company reflected the MP1 credit in revenues for the first six months of 1999, effectively eliminating MP1 costs for that period. The Company then adjusted the forecast to reflect the continuation of the credit for the last six months. The Company also removed all MP1 costs from the Application. The end result is that revenue requirements and proposed rates for 1999 do not include MP1 costs; they do, however, include MP1 RPC. Tr. 9/17/98, pp. 1401-1415. The Department notes and the Company agrees, that the costs in the 1999 forecast do not equate to the current MP1 credit, which was based on an estimate of 1998 costs. Tr. 9/17/98, pp. 1411 and 1412. However, because the Company proposes to roll the credit into base rates and the expenses have been removed, any difference from the credit that would be calculated based on estimated 1999 expenses is captured in the calculation of revenue requirements and ultimately in the revenue sufficiency. The Department concludes that CL&P’s treatment of MP1 costs in the Application is appropriate. b. Retirement of Millstone Unit 1 Pursuant to the Act The Company retired MP1 on July 24, 1998. Roman Supp. PFT, p. 1. Therefore, its next set of financial statements must reflect this change in plant status. Section 8(j)(2) of the Act contains specific provisions for regulatory treatment for MP1 should it be prematurely retired. The Company may not receive stranded costs for MP1 if the Department determines that it was not retired for economic reasons. The treatment differs if the Department should find that the retirement was due solely for economic reasons. The Company claims the retirement decision was made solely based on economic reasons. Consequently, the Company asks the Department to rule
  3. Page 23 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 23 of 191 Page 16 that CL&P’s decision to retire MP1 was prudent. Morris Supplemental PFT, pp. 3-7; Tr. 10/16/98, p. 3880. The Company continued to depreciate the MP1 plant asset while it was out of rate base before it was retired. In effect, that expense flowed directly to the bottom line because the Company was not receiving revenues from ratepayers in support of the expense. Tr. 9/17/98, pp. 1517-1520. The Company ceased recording depreciation when the unit was retired. Any future recovery of the plant (i.e., depreciation) from the date of retirement will depend on future regulatory decisions. CL&P requests approval to reclassify the undepreciated plant balance at retirement along with its associated construction work in progress (CWIP), deferred taxes, nuclear fuel and materials and supplies, net of CMEEC costs, as a regulatory asset for a total of $228.7 million. Roman Supplemental PFT, p. 2; Tr. 10/8/98, pp. 3239-3242; Tr. 10/16/98, pp. 3860 and 3861; Late Filed Exhibit Nos. 15 and 165. MP1 was placed in extended maintenance mode prior to 1998. The Company decided that it did not have sufficient funds to restart the three Millstone units and it was going to concentrate on MP2 and 3. Tr. 9/10/98, pp. 353 and 354. CL&P has incurred about $5.5 million ($6.8 million x 81% ownership) per month to keep MP1 in extended maintenance mode and expects that level to continue through 1998. The Company would not seek recovery of costs incurred to keep MP1 in extended maintenance mode. Response to Interrogatory OCC-169; Tr. 9/11/98, p. 565. The Company did not make many capital expenditures for MP1 while it was in extended maintenance mode. Tr. 9/11/98, p. 567. The Company reclassified the extended maintenance mode costs as post shutdown, pre-decommissioning costs when MP1 was retired. These costs contain expenditures for certain activities that were performed prior to retirement and will continue to be performed after retirement. The Company requests explicit Department approval to create a new regulatory asset for these expenditures. CL&P believes the post shutdown, pre-decommissioning costs it has incurred prior to new rates being effective are different from regular operating costs and the requested deferral is consistent with the treatment contemplated by the Act. The Company has not requested that the Department come to a conclusion on the level of recovery. The Company believes that the primary vehicle for reviewing the appropriateness of these costs is the proceeding to begin in 1999 for the calculation of the SBC. Roman Supp. PFT, p. 5; Tr. 10/8/98, pp. 3212-3218 and 3247; Late Filed Exhibit No. 166. The Company has not requested to receive a return on its investment during 1999, the rate year in this docket; however, it has requested that the Department allow it to create a regulatory asset for the return on the investment (i.e., carrying costs) from retirement to January 1, 2000, and defer discussions on the amount recoverable. The Company would file for recovery of deferred balances when it begins collecting the Competitive Transition Assessment permitted in the Act. The proposal to defer the carrying costs is a reversal from the current out of rate base treatment and the Company’s original filing, where it removed MP1 rate base effectively eliminating recovery of carrying costs. The Company also has created a regulatory asset for the unrecovered decommissioning liability that it must now recognize. The Company will only have to write off the components of the regulatory assets that the Department explicitly or Department precedent says are not likely to be recovered. Right now CL&P believes there is no reason to write off any assets. Roman Supp. PFT, p. 4; Tr. 9/11/98,
  4. Page 24 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 24 of 191 Page 17 pp. 599, 600, 611 and 612; Tr. 10/8/98, pp. 3236 and 3254. If the Department denies the deferral of the carrying costs, the Company would not be able to recognize those carrying costs. If the Department concludes that the Company would never be allowed to receive carrying costs on the remaining investment, SFAS 90 requires the Company to recognize a level of return on the unrecovered balance that is at least equal to its incremental cost of borrowing. The Company would have to discount the cash flows associated with recovering the balance at its incremental borrowing rate and compare that discounted amount to the amount on the Company’s books. The difference, which CL&P estimates to be $40 million, would have to be written off. Tr. 10/8/98, pp. 32553259; Tr. 10/16/98, p. 3879. SFAS 71 and SFAS 121 give guidance as to when a regulated entity can record an item as an asset on its books and when it must write off that asset if the future revenue stream is not sufficient to recover all costs. On each balance sheet date, the Company must determine that recovery of its assets, including regulatory assets associated with MP1, is likely. If it determines that recovery has been impaired, then it must write off the amount it is not likely to recover. The Company believes that based upon Department precedent, the Act and a Department ruling in this proceeding that the retirement of MP1 was made for prudent reasons, it can create all regulatory assets it believes are required and will not need to write off any costs. The Company has not asked the Department to make a finding on the amount of the regulatory assets the Company will be allowed to recover. The Company has asked that the Department agree that the appropriate proceeding to determine the amounts to be recovered is in a restructuring proceeding. As a result of that proceeding, the Company would true-up the initial entries for any changes that occur. Tr. 9/11/98, pp. 564, 583-587; Tr. 10/8/98, pp. 3252 and 3253. The Company believes it would have to take a write down if the Department said that a certain amount of the unrecovered plant will never be recovered. That would be a clear signal that an asset has been impaired. Tr. 10/8/98, p. 3238. CL&P has requested the Department be very careful with its language regarding creating a regulatory asset for carrying costs and future recovery of the asset. Without any specific denials, the Company believes it can record all the regulatory assets it needs and not incur any write-offs at this time. Tr. 10/16/98, pp. 3878 and 3879. The Department has set September 28, 1998, as the effective date of new rates in phase two. By reclassifying MP1 costs as regulatory assets as of the retirement date, the Company is seeking not to be denied recovery of MP1 costs from the retirement date until the conclusion of phase two. The Department concludes that it is not appropriate for CL&P to recover any MP1 costs from July 24, 1998, to September 28, 1998, the time period for which the Department, in the Interim Decision, ordered the Company to credit ratepayers for MP1 costs. MP1 was not expected to restart until July 1, 1999. Response to Interrogatory EL-152. The Company did not expect to recover the costs of restarting MP1. Morris Supp. PFT, p. 8. If CL&P had not decided to retire MP1, it would have continued to depreciate the plant, would not have been earning a return on its investment, and would have been expensing extended maintenance mode and restart costs as they were incurred. Therefore, the Department concludes that CL&P is not entitled to recover any MP1 costs through July 1999.
  5. Page 25 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 25 of 191 Page 18 The Department will include in rates the recovery of rate base as of July 1, 1999, based on the projected unamortized balance at that time, which includes amortization of $18.1 million minus $84.5 million associated with the benefits if the unit had continued to operate though 2000. The amortization is equal to the depreciation contained in Schedule C-2. Therefore, the total regulatory asset to be recovered, net of CMEEC, is $126.1 million, as shown on the following table: Millstone Unit 1 Regulatory Asset ($ Millions) CL&P Estimate $196.2 21.1 50.0 14.2 281.5 DPUC Allowed $196.2 21.1 50.0 14.2 281.5 -43.4 238.1 -43.4 238.1 Less: Benefits Through 2000 Amortization of Unrecovered Plant CMEEC 4.3% of Unrecovered Plant & CWIP -9.4 -84.5 -18.1 -9.4 Total Net Unrecovered Millstone Unit 1 Balance 228.7 126.1 Net Unrecovered Plant In-Service CWIP Nuclear Fuel Materials and Supplies Sub-total Unrecovered Assets Accumulated Deferred Income Taxes Net Unrecovered Balance The Department will not allow a return on the Company’s remaining investment since the plant is not operating. The Department believes it is crucial to strike a balance between the Company and ratepayers on recovery of MP1 costs. Since CL&P will be allowed to recover some MP1 costs, which are now reclassified as a regulatory asset, and the Act contemplates mitigation and recovery of regulatory assets, the MP1 regulatory asset should not be subject to further analysis in the future. The Department also believes it is not appropriate to have that regulatory asset remain long into the future and determines that recovery over three years is appropriate. Therefore, the Department allows amortization of the regulatory asset in the amount of $42.033 million for the rate year. The Department does find that it is appropriate to establish regulatory assets for the post shutdown, predecommissioning costs CL&P will incur subsequent to July 1, 1999, and the decommissioning costs. The Department will examine the appropriate amount of recovery in an upcoming restructuring docket. 3. Millstone Unit 2 The 1998 Study indicates net benefits of $669 million or $433 million on a present value basis with the continued operation of MP2 over the remaining years of its license. 1998 Study, Exhibit 2. The Company concludes that MP2 is economic for ratepayers. Id., p. 1. The Company indicated that the continued operation of MP2 was significantly more cost effective than MP1 primarily due to its longer remaining life. MP2
  6. Page 26 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 26 of 191 Page 19 has an additional five years to generate power and since it is more economic on a yearly basis, the benefits are additive. The differential in O&M costs between nuclear plants are nearly the same regardless of the size of the plant. Since MP2 is about a third larger than MP1, it produces more kilowatt-hours over which to spread the costs. Tr. 9/25/98, pp. 2703-2705. The Department examined the Company’s assumptions and asked it to provide a sensitivity analysis. The Company’s analysis of MP2 continued operation assumes that MP1 is also operating. Response to Interrogatory EL-386. Given the decision to shut down MP1 the economic value to operate MP2 should be adjusted by $71 million to about $362 million. Response to Interrogatory EL-386. Like MP1, the 1998 Study of MP2 is limited to a “first level” economic analysis and does not consider other important impacts. However, the Department believes that the assumptions are generally reasonable. The savings are sufficiently robust to enable the facility to remain economic under other possible operating scenarios. The Department finds that MP2 is economic and its continued operation is in the best interest of the ratepayers of Connecticut. B. MILLSTONE UNIT 2 RESTART In the Application, CL&P had projected to restart MP2 on July 1, 1998. Schedule C-3, p. 2. The Company later revised the restart date to December 1, 1998. Schedule C-3.11 (Revised). The Company later indicated that MP2 may not return to service until early 1999. The most current anticipated restart date is April 1, 1999. CL&P believes that updating the Application to reflect a date certain would not resolve the dilemma of accommodating subsequent shifts in the restart schedule. Roman Supp. PFT, p. 5. There was discussion throughout the hearings on what CL&P would do should the Department order further rate reductions than those it proposed. CL&P gave conflicting testimony on whether or not further rate reductions would affect the restart effort for MP2. Mr. Morris stated that CL&P will not slow down the restart effort of MP2 if the Department orders further rate reductions. It will find a way to go forward with the restart efforts. Tr. 9/10/98, p. 341. Mr. Forsgren testified that the Company would not let financial pressures affect the restart effort of MP2 if it could possibly avoid it. However, Mr. Morris also testified that some things the Company intended to get done might not get done. According to Mr. Morris, money only comes from the customers; something has to give. However, the Company would realign where it would spend its money in 1999 and try to protect as much as it could the restart effort of MP2. Tr. 9/10/98, pp. 409-411. In accordance with the Decision dated April 29, 1998, in Docket No. 92-11-11, on May 1, 1998, CL&P began recording an out-of-rate-base (ORB) non-cash accrual for MP2 of $3.14 million per month, which offsets the CY deferral. With interest, this accrual totals $16.018 million through September 30, 1998. Response to Interrogatory OCC-97-SP01. On September 16, 1998, the Company requested revised treatment of MP2 for the rate year. The Company proposes to replace the current ORB non-cash accrual with a cash credit on customers’ bills for MP2 costs contained in the rate year effective September 28, 1998, for the period MP2 is shutdown. In addition, for the period September 28, 1998, until new rates are implemented, the Company would
  7. Page 27 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 27 of 191 Page 20 accrue the credit to customers, plus interest, and include the accrued credit in base rates in the rate year. The Department could then decide to apply the accumulated MP2 non-cash accrual against the CY deferral or use it for something else. Roman Supp. PFT, pp. 1-3; Tr. 10/13/98, pp. 3455-3461. In Exhibit 1-SP01, the Company filed an ORB calculation based on the revised Application. It was similar in format to the current ORB calculation. The rate base data were also contained in the response to Interrogatory OCC-98. The Company annualized first quarter 1999 revised simulated replacement energy and capacity costs (RPC) as a proxy for 1999 RPC. The annualized RPC was used to match the annualized numbers used in the rest of the ORB calculation. The Company believes the credit is most likely to be in effect only for the first quarter of 1999, and, therefore, wanted the RPC and the credit to reflect what it projects the actual costs will be. The RPC would continue to be subject to true-up in the Energy Adjustment Clause (EAC), as is done currently. Tr. 10/13/98, pp. 3464-3466. OCC believes that MP2 should continue its ORB status, although on a cash reduction basis. However, OCC believes the proper MP2 ORB calculation should remove property taxes and not allow recovery of replacement capacity costs. OCC believes that ratepayers should not be required to fund property taxes for a generation plant that is not used and useful. OCC Brief, pp. VI-8 and 9. OCC did not identify any record evidence in support of its belief that CL&P does not need to buy capacity. OCC also would like to change the terms under which the MP2 surcredit would end. OCC believes the unit should run at 95% power for 200 hours and that specific Department approval should be required. OCC Brief, pp. VI-9 and 10. The Decision dated April 29, 1998, in Docket No. 92-11-11 states that upon notification to the Department that MP2 or Millstone Unit 3 (MP3) has operated at no less than 95% power for 100 continuous hours, the corresponding accrual would end without further Department action. Decision, pp. 7 and 9. The Department finds no basis to use OCC’s recommended terms to end the ORB treatment. When MP3 returned from the 10CFR50.54(f) outage, the unit required an extensive power escalation and testing program prior to returning to full power. This program required a slow, deliberate escalation in reactor power and long hold points at pre-defined power levels for testing purposes. This program required several weeks to complete. Given that MP2 will require a similar power escalation program, the unit will have operated for a long period of time prior to exceeding 95% power. The Department believes that this requirement should therefore be relaxed for MP2, and deems that MP2 will be returned to service when it has operated at no less than 75% power for 100 continuous hours. Once MP2 meets that standard, it will be returned to rate base without further Department action. While the Department finds CL&P’s method of calculating MP2 costs for 1999 reasonable, it disagrees with the amounts used and the final ORB estimate. The rate base calculation filed in response to Interrogatory OCC-98 did not contain a materials and supplies (M&S) component. The M&S component of the prior ORB calculation was $13,248,000. Docket No. 97-05-12, Response to Interrogatory EL-95. Consistent with the discussion in Section II.F.6, the Department increases the M&S component to calculate an average M&S for 1999 and includes it in the ORB calculation. The
  8. Page 28 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 28 of 191 Page 21 Department has not removed the MP2 refueling outage accrual, as calculated in Section II.F.23, in the O&M to assure the Company that it will continue to collect the accrual while MP2 is out of rate base. The Department also adjusts MP2 working capital to reflect changes made to total allowed working capital in Section II.E.6.e. The Department also adjusts rate base and O&M by the MP2 adjustments made in Sections II.E.2 and II.F.7.c and f of this Decision. The Department’s adjustments result in a rate base reduction of $325,136,000 and O&M removal of $114,534,000 as compared to CL&P’s proposed rate base reduction of $333,061,000 and O&M removal of $115,696,000. The Department calculates replacement energy costs based on production and costs contained in this Decision less direct nuclear fuel. The Final Fuel Simulation, as discussed in Section II.G.1, demonstrates total production for MP2 for 1999 to be 5,257,000 MWhs and direct nuclear fuel cost of $24,466,800. Revise WPC-3.1. This total includes an adjustment to the production for January through June to reduce production to a CL&P basis. The adjusted marginal cost as calculated by the Department is $19.46/MWh. Total estimated replacement energy for MP2 is $77,834,420 [(5,257,000 MWhs x $19.46) - $24,466,800]. Consistent with the discussion in Section II.G.1.k, the Department has not removed nuclear fuel indirect costs to assure the Company that it will continue to collect D&D while MP2 is out of rate base. The Department finds CL&P’s method of calculating replacement capacity costs of $19,164,000, using an annualized estimate of first quarter 1999 for MP2, reasonable and accepts that number. Late Filed Exhibit No. 167. The Department finds no basis for OCC’s statement that CL&P need not buy replacement capacity for MP2; therefore, net RPC for MP2 is $96,998,420. This compares to CL&P’s estimate of $150,824,000. The primary difference is the estimate for the marginal cost of energy due to the fact that oil prices have dropped significantly and were not reflected in CL&P’s estimate. The final ORB change to CL&P’s retail revenues is $79,032,000 as can be seen on the following table. The RPC will continue to be subject to true-up in the energy adjustment clause, as is done currently.
  9. Page 29 of 191

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 29 of 191 Docket No. 98-01-02 Page 22 Millstone Unit 2 ORB Calculation Rate Base Changes ($000's) Rate Base Reduction Return on Rate Base (325,136) 8.05% Reduction in Operating Income Revenue Conversion Factor (26,173) 1.758 Revenue Reduction - re Rate Base & Capitalization Interest Synchronization (46,013) 9,474 Operating Expenses O&M Depreciation Replacement Power: 1999 Gross Receipts & Bad Debts Factor Total Change in Revenues Less: CMEEC Ownership Entitlement TOTAL CHANGE IN CL&P RETAIL REVENUES (114,534) (26,500) 96,998 (44,036) 1.0456 (46,044) (82,583) 3,551 (79,032) The Department believes it is most appropriate to continue the non-cash accrual for the MP2 disallowance to be used as an offset to the potential ratepayer liability for the accumulated Connecticut Yankee RPC deferral (CY Deferral). As of September 28, 1998, the monthly accrual will be $6,586,000 ($79,032,000 / 12) and will earn interest at the Company’s weighted cost of capital approved in Section II.M.6. As the Company has already recorded a monthly accrual of $3.1 million per month plus interest for the period from September 28, 1998, through February 5, 1999, the Company should record an additional monthly accrual from February to May 1999 to account for the additional $3,486,000 monthly accrual plus interest for the previous period. Once the accrual exceeds the deferred balance, CL&P shall return the excess MP2 accrual to ratepayers through the EAC. If it is determined that ratepayers are not responsible for CY RPC the Department will determine the ratemaking treatment in a future EAC proceeding. However, if it is determined that ratepayers are responsible for CY RPC and the MP2 accrual plus interest is less than the deferral at that time, the MP2 accrual will be applied in its entirety against the CY Deferral. Thereafter, the remaining CY Deferral will be amortized at the rate of the monthly revenue reduction associated with MP2 being removed from rate base until the deferral is eliminated or MP2 returns to service. If the deferral is not eliminated before MP2 returns to service, the balance will be recovered through the EAC. C. ISSUES FROM DOCKET NO. 97-05-12 In the Decision dated December 31, 1997, in Docket No. 97-05-12, the Department concluded that CL&P could potentially overearn during 1998 by approximately $261 million. Decision, Table III. The Department opened this docket to
  10. Page 30 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 30 of 191 Page 23 continue its review undertaken in Docket No. 97-05-12 and to conduct a full rate review. In phase one of this docket, the Department concluded that $110.479 million in overearnings should be used for additional amortizations of regulatory assets subject to true up in the phase two Decision. Interim Decision, pp. 1 and 4. The Application prescribes rate reductions of $21 million representing 1999 forecasted current outage costs for MP2 and 3 and applies $19 million in revenue sufficiency overearnings to amortization of the deferred balance of Financial Accounting Standard (SFAS) 109. Morris PFT, pp. 3 - 5. The Company filed an exhibit that addressed $150 million in potential overearnings identified in Docket No. 97-05-12 that were not addressed in phase one, summarized them and indicated how the Company treated them in the Application. The Company removed some costs from the rate year, adjusted the amounts of others, and left some in 1999, as it believed was appropriate. The Company believes it addressed all issues from Docket No. 97-05-12; therefore, the rate year is clean. Late Filed Exhibit No. 9; Tr. 9/11/98, pp. 495-506; Tr. 10/16/98, pp. 3797-3808. The Company’s efforts to exclude some of the Docket No. 97-05-12 Decision items from the rate year should have lead to a greater rate decrease than proposed. However, the Company contends that other items contained in the Application, such as depreciation, fuel costs and cost of capital, have increased since the Department’s review in Docket No. 97-05-12. In the September 30, 1998, revised schedules, the Company recommended adjustments to the Application that it deemed necessary to arrive at appropriate rates that it should be allowed to charge customers. OCC, AG, PRO, CIEC and CCM also recommended adjustments in their briefs. The Department has reviewed the rate base, expenses, revenues and the cost of capital contained in the Application and has taken into consideration recommended adjustments. Based on that comprehensive review, the Department has made appropriate adjustments to the Application and orders additional reductions and amortizations for the rate year. When the Orders are implemented, the Company will have the opportunity to earn the allowed return on equity set in Section II.M, below, and will no longer be collecting revenues in excess of its needs. Therefore, the potential overearnings that were identified in Docket No. 97-05-12 and partially addressed in the phase one Decision are moot.

As listed on the current system

Question(s) Answered 874, 885, 886 (The Connecticut Light and Power Company) Date Filed: 10/09/2026

This filing on the current system (opens in a new tab)