Interrogatory responses

Answers to questions 874, 885, 886

Files5

Text of OCC-886_Final.pdf

Extracted from the file · 1 page · 1,819 characters

  1. Page 52 of 191

    Docket No. 98-01-02 f. The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 52 of 191 Page 45 Millstone Unit 2 Plant Additions As discussed in Section II.E.2, above, the Department removed $11,961,500 for MP2 plant additions that will not be incurred in 1999. Consequently, the Department must also adjust depreciation expense for the plant additions. Therefore, the Department assumes CL&P would have recovered this investment over the remaining life of the unit, 16 years, and removes depreciation expense of $747,594 ($11,961,500 / 16 years). 2. Potential Employee Settlements The Company included $970,000 for potential settlements of employee lawsuits based on the 1998 employee settlement budget. Response to Interrogatory OCC-71. However, the Company could not supply information about the claims, on the basis that the personnel information is subject to statutory nondisclosure obligations and that litigation information is protected by attorney-client privilege. CL&P Brief, p. 33. According to the Company, it did not budget for this item prior to 1998. Late Filed Exhibit No. 168, Read-In F. OCC states that the projected employee settlement expenses of $970,000 should be removed from the rate year. OCC believes that in Docket No. 92-11-11 CL&P’s employee settlement and related legal expenses were recorded below the line. OCC also states the Company did not provide any information concerning the specific types of employee settlements that were included in the test year. OCC Brief, p. 37. The Company states that its inability to provide the details of these matters does not render the settlement costs unrecoverable or improper. CL&P Brief, p. 33. The Department disagrees. The Department cannot blindly accept costs and allow ratepayers to pay for ones that have not been justified. As the presiding Commissioner stated during the hearings, “. . . the burden of proof is on the Company to show that it acted in a reasonable manner . . . and to demonstrate that each of the costof-service components underlying a proposed rate is reasonable.” Tr. 9/10/98, p. 269. The Company has failed to do so in this case, therefore, the Department will disallow the $970,000 for potential employee settlements. 3. Employee Relocation Expenses The Company projected relocation expenses of $1.1 million for 1999. This is a 160% increase over the year-to-date actual of $426,000. The Company explained that the 1999 level was predicated on known relocation costs for specific individuals that were identified by cost control managers. The Human Resources Department calculated the budget based upon the recognition that there are generally some level of internal staff and new hires that will be relocated. Tr. 9/18/98, p. 1878. According to the Company, the increase from 1998 to 1999 is due to the movement of the nuclear employees at Millstone Station. Tr. 10/15/98, p. 3543. OCC believes that the past two years have seen an unusually high level of relocation expenses because of the large turnover of senior management. OCC attributes this turnover to CL&P’s financial problems resulting from imprudent operations
  2. Page 53 of 191

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 53 of 191 Docket No. 98-01-02 Page 46 of it’s nuclear plants. Hiring new senior management has led to a high level of travel, moving, housing and real estate expenses. OCC proposes the use of a five-year average for the calculation of the appropriate rate year expense level. OCC recommends utilizing actual annual expenses for the years 1994-1997 and the annualization of actual 1998 expenses through August. As can be seen in the table below, this results in an annual expense allowance of $456,000. OCC Brief, pp. 17 and 18. Relocation Expense 1994 1995 1996 $ 317,000 $ 255,000 $ 118,000 1997 $ 951,000 YTD* 1998 1999 $ 426,000 $ 1,100,000 The Department concurs with OCC and reduces employee relocation expenses by $644,000. 4. Advertising Expense a. Grassroots Program The Company has included $550,000 in its advertising expense for the grassroots program, which it describes as a voluntary program for NU employees, retirees and shareholders that seeks to educate its participants on state and federal public policy issues, provide them with the tools to get involved in the political process and to mobilize them to take action to affect the outcome of public policy issues. Response to Interrogatory OCC-46. OCC states that the $550,000 cost clearly falls under those specifically disallowed in §16-19d of the Conn. Gen. Stat. and should be disallowed. OCC Brief, pp. 39 and 40. Conn. Gen. Stat. §16-19d, (2) states that: ‘Political advertising’ means any advertising for the purpose of influencing public opinion with respect to any legislative, administrative or electoral decision or with respect to any controversial issue of public importance. The grassroots program is clearly political in nature, as defined in §16-19d; therefore, the Department reduces advertising expense by $550,000. b. Industry Restructuring The Company also has included $1.4 million in its advertising expense for industry restructuring. This includes $773,000 in Account 930 that relates to bill inserts and other educational communications designed to increase customer awareness on topics such as electric industry restructuring and customer choice and $626,000 in Account 909 that relates to general restructuring. Response to Interrogatory EL 406; Late Filed Exhibit No. 6, AR-OCC-32.
  3. Page 54 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 54 of 191 Page 47 OCC believes that the entire restructuring advertising costs of $1.4 million should be disallowed. It is the OCC’s position that any advertising regarding restructuring to be recovered from ratepayers should be done through the joint effort under the restructuring legislation not base rates. OCC cites Section 17 of the Act, which states that restructuring-related advertising costs will be recovered through the SBC. OCC Brief, pp. IV-40 and 41. The Company believes that the program described in Section 17 is not exclusive of all other customer education efforts regarding restructuring. CL&P seeks to recover these costs on a current basis in 1999; but will entertain their deferral should the Department determine that these costs belong in the SBC. CL&P Reply Brief, p. 36. Section 17 of the Act specifically states that it is the Department’s responsibility to develop a public outreach program that will educate consumers on the issue of restructuring. If the Department determines that it needs the assistance of the electric companies in its educational campaign, any costs they incur will be recoverable through the SBC. The Department disallows the $1.4 million of advertising costs related to restructuring activities. 5. Niantic Bay Fuel Trust Expenses In the case of the Niantic Bay Fuel Trust (Trust), the Company has incurred additional financing costs that have resulted from higher interest rates and fees associated with the prolonged nuclear outages at the Millstone plants. On June 2, 1998, CL&P, in conjunction with Western Massachusetts Electric Company (WMECO), issued the Series G Intermediate Term Notes (Series G IT Notes) at an average aggregate principal amount of $180 million, of which CL&P has a pro rata share of 74.5%. The Series G IT Notes have a five-year maturity and a coupon rate of 8.59%, or 300 basis points over a five-year US Treasury note of 5.59%. The Company testified that if it were rated BBB+ rather than BB, the coupon rate would have been approximately 150 basis points over the five-year US Treasury note, or 7.09%. Docket No. 91-06-04, Application of The Connecticut Light and Power Company and Western Massachusetts Electric Company with respect to Nuclear Fuel Financing Arrangements, Decision dated May 27, 1998, p. 6. The Company further testified that due to its financial difficulties associated with the Millstone plant outages, the Trust banks were unwilling to extend the lower cost short-term revolving credit financing in the Trust beyond July 31, 1998. Prior to the Company’s nuclear problems, it had received short-term financing in the Trust at London Interbank Offered Rate (LIBOR) plus 50 basis points. Response to Interrogatory EL-50 in Docket No. 91-06-04, Decision dated May 27, 1998, p. 5. To issue the Series G IT Notes, CL&P incurred a placement fee of 2.0% of the $180 million gross proceeds, or $3.6 million. This is a higher fee than the 0.88% fee that was estimated to have applied had the Company been rated BBB+. Id., p. 6. The Department will allow the expenses and capitalized costs associated with CL&P’s pro rata share of $180 million in the Trust assumed to have been financed in the following manner: $90 million Series G IT notes at 7.09% at a placement fee of
  4. Page 55 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 55 of 191 Page 48 0.88%, and $90 million in short-term financing at a rate of LIBOR plus 50 basis points. 3 These allowed financing costs result in a reduction in the Company’s expenses of $3,870,000 in Account 518, and a decrease in the allowed capitalized amount of $1,325,000 in the Company’s Account 120. Late Filed Exhibit No. 25. CL&P’s revised fuel simulations reflect an adjustment to the Trust expense, reducing it by $2,601,000. Schedule C-3.6 Revised; Late Filed Exhibit No. 138 SP 1; Response to Interrogatory OCC-254. Therefore, based on the foregoing, the Department further reduces this expense by $1,269,000 ($3,870,000 - $2,601,000). The Department will include all adjustments in the calculation of the final base fuel rate. See Section II.G.1.s. 6. Other O&M Costs Escalation Rate The Company has used an inflation adjustment of 1.8% for Other O&M costs in its forecasted 1999 budget. This represents a slight adjustment from the escalation rate of 1.6% for Other O&M costs used in the 1998 budget year. Supplemental Filing, June 30, 1998, p. 38. The Company’s escalation factor for Other O&M costs is obtained directly from Data Resources, Inc. (DRI) forecasts of the Producer Price Index (PPI) finished goods, capital equipment. Response to Interrogatories EL-133 and 134. Mr. Wiater testified that the forecasted 1999 escalation rates are considered upper bounds for planning purposes; individual departments are expected to have cost increases below those targets. Tr. 9/18/98, p. 1847. An examination of recent annual rates of increase of producer prices shows minimal and occasionally negative inflation rates. For the years 1992 though 1996, the average annual rate of change for the PPI was 1.86%; during 1997 and the first two quarters of 1998, the PPI averaged a slight negative rate of change. Response to Interrogatory EL-138. In the case of the PPI finished goods capital equipment index, the years 1992 though 1997 showed an average annual rate of change of 1.47%. During 1997, the index had virtually no annual increase, and the first two quarters of 1998 showed an annual rate of change of approximately -0.6%. Late Filed Exhibit No. 91, p. 2. In a publication prepared by NU’s economic and load forecasting department, the Company stated that, “for now, inflation is low,” and that “problems in Asia will help keep prices low.” Federal Reserve Board Chairman Greenspan characterized the current economy as expansionary “. . . with the price level, inflation rate, staying down, and by some measures even continuing to fall.” Late Filed Exhibit No. 175, pp. 7 and 20. DRI’s May 1998 update of its 1999 forecast of the PPI finished goods, capital equipment for 1999 shows a downward revision to 0.7%. For 1998, the index is projected to fall 0.4%. CL&P argued that the PPI finished goods capital equipment has been heavily influenced by price weakness in vehicles, aircraft and other goods that are 3 None of the seven Decisions issued in Docket No. 91-06-04 specify the maturity length of the LIBOR rate used in computing the interest rate for the short-term financing in the Niantic Bay Fuel Trust Facility. To obtain a LIBOR rate, the Department averaged LIBOR rates for maturity lengths of one month to one year. As of the closing date of the hearing, November 9, 1998, LIBOR rates averaged 5.263%.
  5. Page 56 of 191

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 56 of 191 Docket No. 98-01-02 Page 49 a relatively small portion of CL&P O&M expenditures. Tr. 10/20/98, pp. 3975 - 3980. The Company pointed out that the DRI Total Utility O&M index is projected to rise 1.9% in 1999, and is “more representative of likely price changes that CL&P will encounter in 1999.” Late Filed Exhibit No. 90. However, the Company’s 1999 Other O&M costs escalation rate is taken directly from the May 1997 DRI forecast of the PPI finished goods, capital equipment index. The Department concludes that it is appropriate to use an escalation rate of 0.7% for Other O&M costs for ratemaking purposes, based on the updated 1999 DRI forecasted PPI finished goods, capital equipment index. This lower rate is also supported by recent minimal to negative rates of change in producer prices. OCC also supports an escalation rate of 0.7% based on the revised DRI forecast. OCC Brief, p. IV-43. The adjustment to a 0.7% escalation factor for O&M costs results in an expense adjustment of $1.9 million. OCC Brief, pp. 56-59. Therefore, the Department reduces expenses by $1.9 million. 7. Nuclear O&M Expense The Company’s filing includes higher than historical O&M expense at MP2 and MP3. The Company analyzed the differential expense based on comparison to the historical average for the years 1990 through 1995. The expense for MP2 is $34.5 million higher than the 1990-1995 average; for MP3 this differential is $11.8 million. Kenyon Testimony, p. 6. The following table shows the 1990-1995 historical amounts and the 1999 budgeted amount for each unit, on a CL&P basis. Projected vs. Historical Nuclear O&M Amount (In $million) MP2 1990-1995 Average 72.6 1999 107.1 Difference 34.5 Response to Interrogatory OCC-172. MP3 Total 53.2 65 11.8 125.8 172.1 46.3 The Company analyzed the O&M differential by identifying those costs that account for the differential and segregated them into costs related to the current outage and costs related to new or heightened industry standards. The following table shows these amounts, on a CL&P basis: MP2 and MP3 Differential O&M vs. Historical (in $million) Costs Related to Current Outage Costs Related to Industry Standards Total Dente Testimony, Exhibit TJD-1. MP2 MP3 Total 15.0 19.5 34.5 5.5 6.3 11.8 20.5 25.8 46.3
  6. Page 57 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 57 of 191 Page 50 The Company is not seeking to recover those costs related to the Millstone outages that began in 1996. AG and OCC state that the Company’s base 1990 - 1995 period should be adjusted downward by the cost of the nuclear Performance Enhancement Program (PEP). According to AG and OCC, this program was intended to address deficiencies in the Company’s nuclear program, and, since the program did not prevent the Millstone outages, it was ineffective and should not be included in the base O&M comparisons. AG Brief, p. 5; Schlissel Testimony, pp. 7-10. The Company states that the base years should not be adjusted for PEP, since the Department previously approved most of the PEP expenses, and that historical nuclear costs are similar to other nuclear units, including PEP. CL&P Brief, pp. 21 and 22. The Department ruled on the recovery of PEP costs in the Decision dated June 16, 1993, in Docket No. 92-11-11. In that proceeding, the Department examined the history of PEP and the objectives of the PEP action plans. The Department concluded the following: When analyzing the background and merit of PEP, the Authority believes that it is inappropriate to view PEP as one program with one goal. The Action Plans which comprise PEP have their own degree of merit. Some Action Plans are associated with regulatory requirements unrelated to the prior performance of NU's nuclear power plants. Some Action Plans have a direct impact on plant operation and maintenance (although they may not be cost-beneficial), while the impact of others is more subtle. Some Action Plans represent programs that were under evaluation by the Company prior to formulation of PEP and some represent initiatives that have already been implemented throughout a large segment of the nuclear industry. Other Action Plans represent programs that directly result from lack of timely management attention to certain issues. These programs have all been placed under the umbrella of PEP. The Authority believes that a reasonable decision on this issue is possible only by analyzing the constituent Action Plans. Decision, p. 52. Based on its review, the Department determined that 65% of the costs of PEP should be allowed, while the remainder was deferred to Docket No. 93-09-28, DPUC Review of The Connecticut Light and Power Company Nuclear Performance Enhancement Program, for further review. The remaining 35% was dispositioned by the July 1, 1996 Settlement Agreement in Docket No. 92-11-11. By requesting exclusion, AG and OCC are requesting the Department to rule that PEP was an imprudently incurred expense. As outlined above, the Department has already ruled on the necessity and propriety of most of PEP, and noted that many of the expenses of PEP were irrelevant to the performance of the Company’s nuclear program. It would be inappropriate to reverse a prior Decision by judging it from the ultimate fate of the Company’s nuclear program. If PEP costs are excluded from the comparison, there would presumably be other expenses that would account for the differential from the historical comparisons. Additionally, the Company has formally requested O&M based on projections for 1999, and the base period was used for
  7. Page 58 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 58 of 191 Page 51 comparison purposes only. The Department views the position of OCC and AG on this matter as supporting retroactive ratemaking and will not reduce nuclear O&M as these parties have requested. The Company identified the costs related to industry standards by function. OCC states that costs associated with a number of these functions should be disallowed. The following sections address each of these functions. a. Work Planning and Control The Company’s improvements to its work planning and control program include establishing a full time outage management staff, and ancillary costs associated with maintaining this staff. Response to OCC-177, Bulk, p. 1. OCC states that costs associated with the Work Planning and Control function should be disallowed since the Company did not identify any new or heightened industry standard requiring it, and these activities are necessary to raise the Company’s standards. Schlissel Testimony, p. 40. The Company states that the costs of this program are driven by the Maintenance Rule, which was an NRC regulation established in 1991 that became effective in 1996. The objective of the Maintenance Rule is to establish a performance-based maintenance system at each nuclear power plant that would result in performance of maintenance based on an assessment of risk. Response to Interrogatory OCC-182, Supplement 1, Bulk, Letter dated March 4, 1997, to NRC Commissioners from Joseph Callan, p. 2. The Company’s documentation on the Work Planning function indicates that implementation of the Maintenance Rule has increased quality requirements, resulting in increased training requirements and more work while the unit is on line. Response to Interrogatory OCC-177. Documentation submitted by the Company to support this function was largely linked to the Maintenance Rule. Response to Interrogatory OCC-182. The justification submitted consists largely of NRC documentation regarding Maintenance Rule inspections at other nuclear units. The documentation contains numerous references to Maintenance Rule requirements regarding safety risk assessments prior to removing equipment from service while the unit is on line. The NRC found this to be a common weakness at several plants. Id., NRC Information Notice 97-18, Problems Identified During Maintenance Rule Baseline Inspections, pp. 2 and 3. The NRC documentation includes references to utility programs that were implemented to comply with the Maintenance Rule, shows how these programs have evolved over time beyond the scope of the initial Maintenance Rule, and contains statements showing that the NRC endorsed these efforts. Id., Letter dated March 4, 1997, from Joseph Callan to NRC Commissioners, p. 5. The Maintenance Rule has been amended twice since it was issued, last in 1996. Id., p. 7. The picture that develops from this documentation is of an industry struggling to comply with a complex regulation, whose implications were not fully foreseen when initially promulgated. However, it is clear that the Maintenance Rule requires daily vigilance on the part of Company personnel who are familiar with the complex requirements of that rule. This is consistent with the Company’s establishment of a full-time outage management staff. Regardless of the existence of any standard for such a group, this function is clearly not related to the outages at Millstone nor does any party make such a claim.
  8. Page 59 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 59 of 191 Page 52 Also, the Department does not believe that the Company should be held to making only those expenditures necessary for minimal compliance with standards. In fact, the Department has found that a culture of minimal compliance was one of the root causes of the decline of Millstone station performance, resulting in the current outages. Tr. 6/27/97 in Docket No. 96-10-06 (Oral Decision), DPUC Investigation into Whether The Connecticut Light and Power Company Fulfilled Its Obligations with Regard to its Nuclear Operations, p. 847. As stated by the Department at that time, “the public and the citizens of Connecticut have a right to expect that the management of a nuclear power plant will always strive for excellence.” Id., p. 856. The Company should certainly not be held to a standard where any expenses beyond those necessary to comply with minimal regulatory standards should be viewed as wasteful, as OCC implies. Also, “industry standards” are sometimes inherently difficult to establish, since they may be set by a common approach to problems that is not codified in any documentation. Often, standards are established and understood by interaction among staff assigned to different nuclear plants. Since the cost associated with Work Planning and Control is not a consequence of the current outage, the Department will allow its inclusion in rates. b. Material Condition Improvement Program The Company is establishing a program that consolidates all painting and coating work into one organization. OCC states that the costs of this program should be disallowed, since they cannot be linked to new or heightened industry standards. Schlissel Testimony, p. 42. Also, the Company had painting and coating programs during the reference 1990-1995 time period, therefore OCC believes the additional cost cannot be justified. Id., p. 43. The Company states that the proposed costs incorporate recent industry experience with coatings at other nuclear power plants and the program achieves greater accountability by consolidating all similar work in one department. Response to Interrogatory OCC-177. The Company provided supporting documentation from the NRC that describes significant deficiencies in the application of coatings at other nuclear power plants. Response to Interrogatory OCC-182. The reported events, from as recently as 1997, highlight the importance of coatings in certain applications, where defects in coatings could have major safety implications. The record shows that industry experience with protective coatings is continually evolving. This is supportive of the Company’s efforts to focus more attention on this area of its nuclear operations. No party claims that the expenses associated with this function are the result of the current outages. As in Section II.F.7.a, above, the Department believes the Company should have the flexibility to operate and maintain its nuclear plants beyond minimal industry standards, and that it is not appropriate to include in rates only those costs required for minimal compliance with industry standards or NRC regulations. Therefore, the Department will allow this program’s costs to be included in rates. c. Commitment Tracking System The Commitment Tracking System function includes expenses for creating a centralized tracking system for all commitments made to the NRC by the Company. Response to Interrogatory OCC-177, p. 3. OCC states that the costs associated with
  9. Page 60 of 191

    Docket No. 98-01-02 The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 60 of 191 Page 53 this function should not be allowed, since the system was developed in response to the NRC 10CFR50.54(f) demand for information. Schlissel Testimony, p. 45. The Company provided documents from the NRC and the Nuclear Energy Institute that describe industry standards and NRC expectations for managing NRC Commitments. Response to Interrogatory OCC-182. The documents describe the importance of establishing processes and procedures for controlling commitments made to the NRC. The changes to the Commitment Tracking System improves the Company’s ability to track and maintain future commitments as well as presently existing ones. However, documentation provided by the Company states “The RCD [Regulatory Commitment Database] was developed as part of the response to the 10CFR50.54(f) letter to (1) ensure compliance with the Licensing Basis and (2) establish programs to ensure continued compliance.” Response to Interrogatory OCC-182, Letter dated 5/28/98 from Mario Robles to Walkesl. Since this program was necessitated by the 10CFR50.54(f) demand for information, the program is related to the Millstone outages and the Department will remove its costs from rates. The CL&P portion of the expense for this program is (0.81 * $500,000) [MP2] + (0.53 * $500,000) [MP3] = $670,000. Dente Testimony, Exhibit TJD-1. d. Personal Computer Leasing Program The Company has instituted a program to lease personal computers for employees, instead of buying them. OCC states that the costs associated with this program should not be allowed, since they are not associated with a new or heightened industry standard. Schlissel Testimony, p. 47. The Company states that it is leasing personal computers because it has found it to be more cost effective than purchasing them. Tr. 9/25/98, pp. 2606 and 2607. There has been no claim by any party that leasing personal computers is a result of the Millstone outages. There is no evidence that suggests leasing personal computers is a wasteful use of ratepayer funds, particularly when the alternative to leasing computers is buying them. Similar to Section II.F.7.a, above, the Department will not disallow expenses for the sole reason that they are not necessary to meet industry standards. Therefore, the Department will allow these expenses to be included in rates. e. Consolidation of Information Technology and Support The Company has instituted a program to consolidate all information technology and support functions in one department, to improve administration of these functions and achieve synergies. OCC states that the costs associated with this program should be disallowed, since it is not related to a new or heightened industry standard. Schlissel Testimony, p. 47. There has been no claim by any party that the consolidation of information technology functions is a result of the Millstone outages. Consolidation of these similar functions should result in long-term cost savings. Again, the Department will not disallow expenses for the sole reason that they are not necessary to meet industry standards. Therefore, the Department will allow these expenses to be included in rates.
  10. Page 61 of 191

    Docket No. 98-01-02 f. The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 886 Attachment 1 Page 61 of 191 Page 54 Non-capital Plant Modifications Non-capital modifications (NCMs) are low-cost changes to plant that are treated as expense items. The Company’s initial filing included $11,800,000 for NCMs at MP2 and $930,000 at MP3, on a whole-unit basis. Dente Testimony, Exhibit TJD-1. The CL&P portions of these amounts are $9,558,000 and $493,000, respectively. The Company stated that these amounts were based on historical experience adjusted for known commitments to the NRC. Response to Interrogatory EL-1. The Company subsequently revised its expectations for 1999 NCMs when the projects were identified and submitted a list of the projects on October 29, 1998. The NCM amounts on a total unit basis are $2,720,000 for MP2 and $8,850,000 for MP3. Response to Interrogatory EL-1, Supplement 1. The CL&P portions of these amounts are $2,203,000 and $4,691,000, respectively. NCM expenses for the three years prior to the Millstone outages, 1993-1995, averaged $3,200,000 for MP2 and $9,700,000 for MP3. Response to Interrogatory EL-354. The proposed NCM amounts are consistent with historical expenses. The expense items are typical of small modifications that occur throughout the life of a nuclear plant. Therefore, the Department accepts the revised amounts and decreases the original MP2 amount by $7,355,000 and increases the original MP3 amount by $4,198,000, for a net reduction of $3,157,000. g. Calculation Tracking System The Company’s filing includes expenses for a new system for tracking calculations, which eases the retrieval of the calculations when a future need arises to access them. Previously, calculations were not comprehensively tracked on a centralized computer system. Response to Interrogatory OCC-177, Supplement 1, Bulk p. 5. OCC states that the costs associated with this program should not be allowed, since the program is not related to industry standards and is a result of the NRC 10CFR50.54(f) order that resulted in the Millstone outages. Schlissel Testimony, pp. 55 and 56. However, OCC did not cite any evidence supporting this position. The system is intended to be used on a going-forward basis to ensure future calculations are properly tracked. This should result in improved efficiencies by reducing the administrative burden of retrieving calculations from diverse locations. Tr. 9/25/98, pp. 2623-2625. Again, the Department will not disallow expenses for the sole reason that they are not necessary to meet industry standards. Therefore, the Department will allow these expenses to be included in rates. h. Material Equipment Parts List The Material Equipment Parts List (MEPL) is a database of plant components that contains information important to the maintenance of that equipment. Response to Interrogatory OCC-177, Supplement 1, p. 7. The Company’s filing includes incremental expenses for completing the MEPL. The changes to the MEPL include adding components and increasing efficiencies in the procurement and storage of replacement parts. Response to Interrogatory OCC-182, Supplement 2, Maintenance of Material Equipment Parts List. OCC states that expenses associated with this program should