  1. Page 126 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 126 of 297 Appendix 1 – Battery Replacement Cooper Form 4C Power Supply Replacement
  2. Page 127 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 127 of 297 Appendix 1 – Battery Replacement Cooper Form 4C Power Supply Replacement
  3. Page 128 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 128 of 297 Appendix 1 – Battery Replacement Cooper Form 4C Power Supply Replacement
  4. Page 129 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 129 of 297 Appendix 1 – Battery Replacement Cooper Form 4C Power Supply Replacement
  5. Page 130 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 130 of 297 Appendix 1 – Battery Replacement Cooper Form 4C Power Supply Replacement
  6. Page 131 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 131 of 297 Appendix 1 – Battery Replacement Cooper Form 4C Power Supply Replacement
  7. Page 132 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 132 of 297 Appendix 1 – Battery Replacement Replacing the Cooper Form 6 Battery 1. 2. 3. 4. Remove the control from service as follows: Enable GND TRIP BLOCKED to allow for ground trip to be disabled when reenergized. a) Press the CHANGE button on the Operator Panel to enter the CHANGE mode. b) Press the GND TRIP BLOCKED button within ten seconds after entering the CHANGE mode. Note: If the GND TRIP BLOCK button is not pressed within ten seconds, the function is not activated. Disconnect the battery. Remove the control AC sensing and power connections from the control using a separate disconnect switch. WARNING: Hazardous voltage. If the recloser is energized while the control cable is disconnected, the CT secondaries can generate high voltages. Contact with high voltage can cause severe personal injury or death. CAUTION: Equipment misoperation. Disconnect all control power sources prior to disconnecting the control cable from the control. Failure to comply can result in recloser misoperation at the time of disconnection or reconnection of the control cable to the control. 5. Disconnect the control cable from the control. Note: Do not disconnect any of the three recloser cables from the Reclosers or junction box unless all of the above steps have been completed. CAUTION: Hazardous voltage. Cable conductors attached to NOVA Reclosers will remain at 53VDC potential after disconnection of source power to the recloser. Contact with any pins at the end of cables directly or indirectly connected to a NOVA recloser can result in personal injury or equipment damage. 6. 7. 8. 9. 10. Remove any control input and status output wiring from TB1, TB3, and TB4. Disconnect any serial communications ports and IRIG-B timing connections. Disconnect the ground from the control. Disconnect and remove the battery. Install the replacement battery. CAUTION: Equipment misoperation. Do not connect this control to an energized recloser until all control settings have been properly programmed and verified. 11. 12. Reconnect the ground cable to the control. Ensure the cable is properly connected and supported. 13. Plug in the control battery.
  8. Page 133 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 133 of 297 Note: The Form 6-TS recloser control will not power up until AC power is applied. CAUTION: Equipment misoperation. Verify that the 120/240 VAC selector switch is correctly set for incoming voltage. Failure to comply may cause misoperation (unintentional operation) of the control and/or equipment damage resulting in personal injury. 14. 15. 16. Verify the selector switch on the Power Supply / Battery Charger Board is set to the correct position based on the incoming power supply: • For 120 VAC incoming power, the selector switch must be set to the 115V position. • For 240 VAC incoming power, the selector switch must be set to the 230V position. Apply AC power to the control. Disable GND TRIP BLOCKED. a) Press the CHANGE button on the Operator Panel to enter the CHANGE mode. b) Press the GND TRIP BLOCKED button within ten seconds after entering the CHANGE mode. Note: Once selected (or after ten seconds), the control returns to normal operation. 17. Verify the control clock is set to the current time after AC power has been reapplied. Note: The control clock may require resetting if the operating power has been disconnected for more than 30 days. Refer to the manufacturer’s technical manual for details.
  9. Page 134 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 134 of 297 APPENDIX 10 INSPECTION, TREATMENT, RESTORATION AND REPLACEMENT GUIDELINES DISTRIBUTION SYSTEM WOOD POLES
  10. Page 135 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 135 of 297 5.61 Wood Poles General Description This procedure establishes a uniform approach for distribution wood pole inspection, treatment, restoration and replacement. It defines the schedule, inspection, and reporting requirements for these facilities. This applies to all wood distribution poles within the custodianship or the maintenance responsibility of Eversource Energy. It shall include push braces and guying stub poles as well as line poles scheduled for the given year. Facilities/Equipment • Wood Poles 5.61.1 Inspection and Maintenance Activity Schedules 5.61.1.1 Table 1 – Wood Poles Maintenance Intervals Wood Poles All Maintenance Schedule PM Task Condition Monitoring N/A Time-Directed Routine Inspection 15Y (Notes 1 & 2) Condition-Based Priority Reject Schedule repairs or replacement. (Note 3) A/R (Note 4) Failure Finding Corrective Maintenance A/R In Table 1, the intersection of the row and column indicate the age-based inspection or maintenance interval for wood poles based on the preservation treatment listed in the column heading. For example, the age requirement for a Routine Inspection is 15Y (or 15 Years). The abbreviations used for the intervals are: Y = Year, i.e. 2Y = 2 Years A/R = As Required N/A = Not Applicable Note 1 = 15 years is the minimum requirement for pole inspection. This interval may be changed due to contractual requirements with joint owners. Note 2 = The type of inspection performed shall be determined by the age of the pole and its type of treatment, as shown in the following table:
Words on different pages

Text of OCC-890_Final.pdf

Extracted from the file · 1 page · 553 characters

Words on different pagesRead the text of OCC-890_Final.pdf

As listed on the current system

Question(s) Answered 888, 889, 890 (The Connecticut Light and Power Company) Date Filed: 10/09/2026

This filing on the current system (opens in a new tab)