Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 888, 889, 890

Files5

Search terms highlighted
Eversource rate increase is on 2 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
2 pages match
  1. Page 186 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 186 of 297 enclosure frame, just behind the breaker. NOTE: This step applies to all CM52 enclosure sizes. See Network Protector Tool Table. Figure 7 Figure 7 – Installing the Vertical Barrier Board
  2. Page 187 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 187 of 297 Figure 8 – Vertical Barrier Board Correctly Installed 8. Insert the 10mm socket on the crank and remove the front cover bolts. See Figure 9. Figure 9 – Removing the Front Cover Bolts
  3. Page 188 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 188 of 297 Caution: To prevent the protector from tipping forward, place your hand on the center arc chute to steady breaker mechanism. 9. Pull down slightly on the charge handle and remove the cover. Inspection of Arc Chutes and Contacts 10. Remove the arc chutes and inspect them to ensure the vents are free and clear. See Figure 10. Figure 10 – The Arc Chutes Caution: To prevent the protector from tipping forward, place your hand on the center arc chute to steady breaker mechanism. 11. Manually charge the breaker with the charge handle. See Figure 11. Operating the Charge Handle Figure 11 – Charging the Breaker • The flag will indicate “Charged” after the closing spring is compressed. Press here to keep the protector from tipping forward
  4. Page 189 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 189 of 297 12. Push the button labeled “CLOSE” to close the breaker. See Figure 12. Note: If there is a plastic shield which covers the close button, carefully remove the hinged cover and remove and discard the plastic shield and reinstall the hinged covers. Figure 12 – The “CLOSE” Button 13. Check for contact wear. Side-by-side ledge acts as a contact wear indicator. Check the wear indicator by looking straight down into the arc chamber. See Figure 13. • If the ledge is covered by the back edge of the moving contacts, the contacts are in good condition. • If the ledge is not completely covered by the back edge of the moving contacts, replace the contacts. Ledging acting as wear indicator Back edge of the moving contacts (must extend over the edge) Figure 13 – Checking for Contact Wear NOTE: There are no adjustments needed for contact pressure or lubrication required. Do not wipe away or add any grease or lubricant.
  5. Page 190 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 190 of 297 14. 15. Push the button labeled “OPEN” to open the breaker. Dress the arc contacts if there is black carbon residue from arcing, using only Scotch Brite. Do not use a file on the contacts. Internal Visual Inspection: 1. 2. 3. 4. Record the counter reading. Check for any signs of liquid entry into enclosure, transformer throat, etc. Check for indication of overheating. Inspect the condition of the wiring. Look for frayed or damaged wires. Test Sequence: The next section is a series of tests defined to ensure proper operation at normal condition and at fault duty. It is important to perform the following tests in this order: 1. Manual Breaker Operation Test 2. Relay Testing 3. Ground Fault Test (480V Unit Only) (Account Executive to coordinate with Customer contact) Test 1 – Manual Breaker Operation Test Caution: To prevent the protector from tipping forward, place your hand on the center arc chute to steady breaker mechanism. 1. 2. 3. Operate the breaker manually while it is on rails by charging the breaker using the charging handle. Once charged, press the CLOSE button. rip the breaker by pressing the TRIP button. Repeat these steps 5 times. Relay Testing - Please see the following Relay Test Section for testing procedure. Preparation for Tests 2 through 4 Caution: Test for zero voltage on the potential studs on the test switch as follows: 1. Use a Multi-meter to check for voltage on the stud positions labeled: See Figure 11. • N1, N2, N3 (See Figure 11.) • T1, T2, T3 (See Figure 11.)
  6. Page 191 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 191 of 297 The Network Side The transformer Side CT Jacks Figure 14 – The Test Switch Phasing Block 2. Ensure that ZERO volts are present. Reminder: Proper PPE must be worn while attaching leads to an energized bus. 3. Attach Test Set grounds and jumper between the shutter and the cassette frame. See Figure 12.
  7. Page 192 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 192 of 297 Connection of jumper to Ground connection and jumper connection to shutter plate Figure 15 – Attaching the Test Set Grounds 4. 5. Connect test kit leads N1, N2, N3 and T1, T2, T3 on the studs of the test block. Remove the dead front upper compartment cover. See Figure 13. NOTE: The fuse links shown in Figure 13 may differ from those used at your location. Figure 16 – The Dead Front Upper Compartment 6. 7. Connect the power leads of the Test Set to the energized network bus. Place the outside handle in the AUTO position.
  8. Page 193 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 193 of 297 8. Pull the Electrical Interlock forward until the spring detent ball is in front of the Interlock bracket. See Figure 14. Interlock bracket Figure 17 – The Electrical Interlock 9. Test in accordance with the Microprocessor relay tests. Test 2 – Relay Tests 1. 2. 3. 4. Replace the breaker cover. a) Push slightly down on the charging handle and insert the handle through the cover slot. b) Tighten the bolts using a cross pattern. Being careful not to overtighten bolts or the cover may crack. Relay Testing will be performed with the breaker out on the rails and not with the breaker in the relay test position. Connect the jumper cables between the breaker and the lower relay drawer wiring. Document the results from the testing and the MPCV-D serial number as well as the nameplate information of the network protector on the maintenance form and the Cascade database. Test 3 – Relay Tests (continued) Microprocessor Relays 1. Perform an Overvoltage test and adjust the relay in accordance with the following documents. Record the As-Found and As-Left values. • Network Protector Test Set Instructions • Relay Instructions • Network Protector Instructions 2. Perform a Reverse Current Trip test in accordance with the following documents. Record the As-Found and As-Left values. • Network Protector Test Set Instructions • Relay Instructions • Network Protector Instructions
  9. Page 194 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 194 of 297 3. If a Time Delay is used, perform a Time Delay test in accordance with the following documents. Record the As-Found and As-Left values. • Network Protector Test Set Instructions • Relay Instructions • Network Protector Instructions Test 4 – Ground Fault Test (480V units only) CAUTION: The ground fault protection circuit between the protector and the customer main service is owned and maintained by the customer. Testing the lock out may call for all protectors to trip. An up-to-date drawing must be made available and reviewed to determine those steps which must be taken to prevent tripping of all protectors. Verify trip from lockout and block the close of the protectors on all units having a ground fault scheme. NOTES: 1. The Ground Fault system is typically Customer-owned, and the Lockout is typically Eversource owned. It is important to have an up-to-date print of the scheme prior to performing a test. 2. This test is only to be performed on those units equipped with a ground fault system. CM-52 Re-install Procedure 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Inspect the network protector enclosure for chipped, cracked or missing paint, corrosion, etc. Remove any loose paint and/or rust with a wire brush and repaint those areas to prevent further corrosion. Check the condition of the external tank. Check cooling fins to ensure that they are not clogged, missing, or in need of replacement. Check the door gasket to ensure it is still in good condition. Apply gasket preservative to the door gasket. Apply anti-seize grease to the door bolt hardware. Verify that the External Handle is in the OPEN position. Lift the Lever-in drive shutter door and insert the 3/8” square end of the wrench into the Lever-in drive socket. Turn the socket clockwise until the RED indicator appears. Remove the crank and secure it. Close the door. Tighten the hinge bolts. Tighten all door bolts (The tank is secure once the 2 jam (stop) nuts touch the tank.) NOTE: The use of impact tools is not recommended and could lead to moving stop nuts for proper sealing and premature door gasket damage.) Verify the protector enclosure is holding pressure using a pressure gauge/fill device. If it is not, perform a leak check on those network protectors with submersible enclosures as follows: a) Pressurize the enclosure with 5 PSI of dry nitrogen. b) Apply a soap solution to the door gaskets, enclosure penetrations, throat gaskets, operating handle gaskets, welds, etc. c) Let this sit for 30 minutes.
  10. Page 195 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 195 of 297 14. 15. d) Check for leaks by looking for soap bubbles. Fix any leaks if possible. e) Record any leaks on the inspection form and alert supervision. f) Reduce the pressure within the enclosure to 1.5 PSI. Place the operating handle in the as-found position. Record the as-left counter reading. 6.29B - CMD Network Protectors – Major Maintenance CAUTION 1. 2. No modifications to network protectors shall be made, either temporary or permanent, without prior approval of the Distribution Engineering Department. Stop the job, place equipment in a safe condition, and contact Supervision if the process does not proceed as expected, if unusual situations occur during the performance of the process, or any significant problems occur during maintenance activities. Before You Begin Prior to assigning work on network protectors, Supervision shall: 1. 2. 3. 4. The Supervision shall, prior to assigning personnel to perform “Work” on a network protector, ENSURE the person(s) responsible for performing the “Work” is fully qualified in accordance with operating company requirements The Supervision shall, ensure that all employees are properly trained and qualified to perform this work, and that all appropriate PPE and safety requirements are met, including but not limited to those defined within the following documents: • TD 211, “When to Wear FR Clothing” • TD 952, “Protection of Personnel Entering Enclosed Spaces” (Connecticut, Western MA only) • TD 955, “Confined Space Requirements” • Eversource Employee Safety Manual • TD -877 Managing Arch Flash Hazards on CL&P Distribution Facilities (CL&P ONLY) The Supervision shall, ensure those performing the work are aware that of the following PPE requirements whenever working in Underground Vaults & Manholes: • Safety Glasses with side shields • EH (Electrical Hazard) rated boots • High Voltage gloves • FR (flame resistant) clothing, as specified in TD 211 Whenever “Work” is performed on a network unit as defined in paragraph 5 of this procedure, the following PPE is required : • Protective Arc Flash Hood (Beehive), (Stock Code 442151) or company approved equivalent. • Safety glasses with side shields
Words on different pages

Text of OCC-890_Final.pdf

Extracted from the file · 1 page · 553 characters

Words on different pagesRead the text of OCC-890_Final.pdf

As listed on the current system

Question(s) Answered 888, 889, 890 (The Connecticut Light and Power Company) Date Filed: 10/09/2026

This filing on the current system (opens in a new tab)