  1. Page 21 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 21 of 297 APPENDIX 3 CL&P ANNUAL VEGETATION MANAGEMENT PLAN
  2. Page 22 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 22 of 297 Appendix 3 Section 1 Eversource Vegetation Management 2020 Backbone Lateral EXPENSE PROGRAMS Note Budget Miles Miles Roadside Maintenance Reclaim Backbone ROW Brush Control (Cir. Miles) ROW Side Pruning Vine Control Traffic Control Customer Request Work Mid-Cycle Emergency Restoration Transformer Enclosure Other 1 2 3 4 5 6 7 8 9 10 11 $26,445,000 1,082 2,384 $453,000 212 $600,000 $200,000 $280,000 $1,265,000 $10,000 $847,000 EXPENSE SUMMARY $30,100,000 CAPITAL PROGRAMS Budget Customer Focus ETT Tree Removals (not in cycle miles) 12 13 CAPITAL SUMMARY 2,384 Backbone Lateral Miles Miles 2,144 2,563 $5,200,000 80 $32,800,000 $38,000,000 CAPITAL TRACKER PROGRAMS SMT ETT 1,294 14 15 CAPITAL TRACKER SUMMARY 80 Backbone Lateral Budget Miles Miles $2,150,000 81 $15,250,000 TOTAL Included in Cycle % of Total System Miles (Approx) 179 247 $13,100,000 81 426 Backbone Lateral Miles Miles 1,375 2,890 $83,350,000 25.2% NOTES 1 Roadside Maintenance includes, Standard Maintenance Trimming (SMT) on laterals , Backbone Maintenance Trimming (BMETT) on bac Enhanced Tree Trimmed, Lateral Maintenance Trimming (LMETT) on laterals previously Enhanced Tree Trimmed 2 Re-establishing ETT clearance where on backbones where new trees have grown in or over the wire zone 3 Brush removal and treatment in right-of-ways (ROW). Work performed on 4-year cycle 4 Performed on ROWs scheduled for brush removal and involves the pruning of trees growing into the ROW from the side 5 Performed on laterals 2 years after they have been cleared by scheduled maintenance, and 1 year on backbones. Vines growing on poles 6 Town or State mandated traffic control during scheduled work - included in unit price of maintenance 7 Inspection and completion of customer requested work and recent reliability issues 8 Performed on circuit backbones 2 years after maintenance 9 Expense for tree crews during restorations not associated with major storms 10 Vegetation control performed on 2-year cycle within customer owned transformer enclosures 11 Town Mower program / Efficiency Incentive / Other 12 Performed large laterals and critical infrastructure laterals experiencing emerging reliability issues 13 Targeted removal of risk trees along Roadside Maintenance and Reclaim backbone lines 14 SMT performed on mileage not trimmed under ETT to maintane 4 year cycle 15 Pre-selected large laterals and critical infrastructure on laterals experiencing reliability issues
  3. Page 23 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 23 of 297 Town ANDOVER ASHFORD AVON BARKHAMSTED BEACON FALLS BERLIN BETHANY BETHEL BETHLEHEM BLOOMFIELD BOLTON BRANFORD BRISTOL BROOKFIELD BROOKLYN BURLINGTON CANTERBURY CANTON CHAPLIN CHESHIRE COLCHESTER COLUMBIA CORNWALL COVENTRY CROMWELL DANBURY DARIEN DEEP RIVER DURHAM EAST GRANBY EAST HADDAM EAST HAMPTON EAST HARTFORD EAST LYME EAST WINDSOR EASTFORD EASTON ELLINGTON ENFIELD ESSEX FAIRFIELD FARMINGTON GLASTONBURY GOSHEN Maintenance on Backbone Miles 0.37 0.00 7.69 1.76 4.52 0.00 3.05 9.85 0.00 9.01 2.12 10.42 37.23 26.17 4.23 0.00 0.00 19.65 5.27 5.85 7.25 10.48 0.00 4.64 3.99 28.70 5.87 0.00 10.81 13.28 2.44 18.13 8.76 11.61 4.00 0.00 0.00 0.80 24.05 1.70 0.47 0.00 26.92 1.35 Standard Maintenance on ETT on Grand Total Laterals Miles Laterals Miles Miles 2.01 0.00 2.38 6.63 0.00 6.63 10.96 1.02 35.67 9.96 2.07 13.79 5.04 0.11 9.67 0.03 0.00 0.03 3.02 1.44 7.51 16.92 1.27 28.03 2.30 0.00 2.30 3.61 0.78 13.40 7.63 0.65 10.40 16.79 0.00 27.21 38.43 0.25 75.91 37.45 4.05 67.67 16.28 3.37 23.88 0.09 0.00 0.09 0.59 0.83 1.42 26.84 5.26 51.75 29.06 6.14 40.47 14.25 0.39 20.49 22.92 1.87 32.03 31.62 0.00 42.10 4.89 0.00 4.89 21.86 0.03 26.53 4.20 0.00 8.19 28.64 2.97 60.31 19.52 2.77 28.16 0.48 0.00 0.48 20.44 0.97 32.22 21.31 2.04 36.64 9.33 0.00 11.76 45.49 5.07 68.69 34.37 0.00 43.12 34.83 7.37 53.82 12.01 0.12 16.14 2.05 0.00 2.05 0.05 0.00 0.05 0.00 0.00 0.80 54.18 1.04 79.27 8.44 0.00 10.14 0.54 0.00 1.02 2.03 0.00 2.03 51.36 0.00 78.28 5.42 0.00 6.77
  4. Page 24 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 24 of 297 Town GRANBY GREENWICH GRISWOLD GROTON GUILFORD HADDAM HARTFORD HARTLAND HARWINTON HEBRON KENT KILLINGLY LEBANON LEDYARD LISBON LITCHFIELD MANCHESTER MANSFIELD MARLBOROUGH MERIDEN MIDDLEBURY MIDDLEFIELD MIDDLETOWN MONROE MONTVILLE MORRIS NAUGATUCK NEW BRITAIN NEW CANAAN NEW HARTFORD NEW LONDON NEW MILFORD NEWINGTON NEWTOWN NORTH BRANFORD NORTH CANAAN NORTH STONINGTON NORWALK OXFORD PLAINFIELD PLAINVILLE Standard Maintenance on Maintenance on ETT on Grand Total Laterals Miles Backbone Miles Laterals Miles Miles 1.77 8.62 1.04 11.43 53.48 70.82 0.00 124.30 0.00 1.08 0.00 1.08 0.00 0.03 0.00 0.03 6.35 9.80 0.14 16.29 1.70 12.28 1.12 15.10 3.92 7.08 0.00 11.00 0.00 17.67 0.97 18.64 0.00 3.84 0.05 3.89 5.19 24.25 1.41 30.85 0.23 4.76 4.98 9.97 1.09 6.65 1.19 8.93 2.82 10.85 3.81 17.48 6.88 26.97 2.43 36.28 10.35 38.41 1.09 49.85 7.56 26.42 9.37 43.35 12.36 28.80 1.74 42.91 7.19 24.97 3.82 35.98 6.06 19.00 0.00 25.06 13.53 27.48 0.28 41.29 8.28 38.45 8.47 55.21 5.69 3.67 0.00 9.35 30.24 55.97 0.00 86.21 5.12 0.00 0.00 5.12 17.06 26.59 0.12 43.77 1.85 5.27 0.43 7.56 2.71 6.15 0.40 9.25 10.34 21.05 0.00 31.39 22.43 39.27 1.95 63.65 12.21 36.70 7.97 56.88 16.48 16.79 0.17 33.44 26.83 64.35 13.61 104.79 0.52 0.06 0.00 0.57 27.01 47.49 15.07 89.57 0.00 0.10 0.00 0.10 2.89 10.68 0.62 14.19 6.98 35.54 9.12 51.64 27.40 44.40 2.00 73.80 9.15 15.42 1.82 26.39 5.63 28.34 4.30 38.27 0.00 0.28 0.00 0.28
  5. Page 25 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 25 of 297 Town PLYMOUTH POMFRET PORTLAND PRESTON PROSPECT PUTNAM REDDING RIDGEFIELD ROCKY HILL ROXBURY SALISBURY SEYMOUR SHEFFIELD SIMSBURY SOMERS SOUTH WINDSOR SOUTHBURY SOUTHINGTON SPRAGUE STAFFORD STAMFORD STONINGTON SUFFIELD THOMPSON TOLLAND TORRINGTON VERNON VOLUNTOWN WARREN WASHINGTON WATERBURY WATERFORD WATERTOWN WEST HARTFORD WESTBROOK WESTPORT WETHERSFIELD WILLINGTON WILTON WINCHESTER WINDHAM Standard Maintenance on Maintenance on ETT on Grand Total Laterals Miles Backbone Miles Laterals Miles Miles 3.55 10.12 0.00 13.66 0.09 0.00 0.00 0.09 11.66 47.42 1.16 60.24 5.76 4.73 1.79 12.29 0.00 2.31 0.57 2.88 5.47 17.70 3.82 26.99 0.93 0.96 0.00 1.89 0.00 0.04 0.00 0.04 5.92 7.62 0.00 13.54 0.00 10.99 0.16 11.15 11.06 42.55 2.08 55.68 3.51 10.46 0.00 13.97 0.00 0.04 0.00 0.04 14.58 33.45 3.71 51.74 0.43 0.00 0.00 0.43 10.47 12.49 0.47 23.43 13.27 33.01 12.13 58.41 11.78 25.25 0.00 37.03 1.19 1.73 0.00 2.92 0.72 0.99 0.00 1.71 38.01 58.29 0.86 97.15 3.25 0.73 0.00 3.98 0.73 0.04 0.00 0.77 11.00 37.50 3.27 51.78 5.80 20.12 4.46 30.37 23.99 61.22 14.39 99.60 5.43 6.08 0.33 11.83 0.00 0.19 0.00 0.19 4.24 6.10 0.00 10.34 18.49 52.68 9.11 80.28 65.69 103.10 0.32 169.11 11.12 30.69 0.10 41.90 9.06 12.71 1.89 23.66 11.59 26.05 0.41 38.06 0.41 5.64 0.00 6.05 32.19 64.55 5.15 101.89 7.76 19.68 0.10 27.54 9.63 25.11 7.31 42.05 5.56 23.74 3.57 32.87 8.13 22.95 8.45 39.52 9.21 14.46 0.00 23.66
  6. Page 26 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 26 of 297 Town WINDSOR WINDSOR LOCKS WOLCOTT WOODBURY WOODSTOCK Maintenance on Backbone Miles 12.90 11.93 22.26 22.53 0.00 Standard Maintenance on ETT on Grand Total Laterals Miles Laterals Miles Miles 12.54 0.15 25.59 13.95 1.24 27.13 57.35 0.00 79.61 75.47 8.78 106.79 0.07 0.00 0.07
  7. Page 27 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 27 of 297 SPECIFICATION for LOCAL DISTRIBUTION LINE CLEARANCE TREE WORK and BRUSH CONTROL Revision 2014-B
  8. Page 28 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 28 of 297 Table of Contents Section Page Number General Requirements .................................................................... 1 Scope of Work ................................................................................. 2 Scheduled Maintenance Trimming (SMT)...................................... 2 Enhanced Tree Work....................................................................... 4 Maintenance Enhanced Tree Trimming ......................................... 5 Mid-Cycle Trimming .........................................................................6 New Business and Capital Construction ....................................... 6 Tree Removal................................................................................... 6 Stumps ............................................................................................. 7 Brush and Vine Removal ................................................................ 7 Wood and Chip Disposal ................................................................ 7 Substation Perimeter Clearing ....................................................... 8 Definitions ..................................................................................... 10 2019 William Van Dam, Director - Vegetation Management Robert D. Allen, Manager – Massachusetts & New Hampshire Vegetation Management Sean D. Redding, Manager - Connecticut Vegetation Management - Transmission Allen Carey, Manager - Connecticut Vegetation Management Paul Sellers, Manager – Massachusetts Vegetation Management
  9. Page 29 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 29 of 297 Eversource Specification for Local Distribution Tree Work and Brush Control 1. General Requirements This document describes the scope of work and technical requirements for the Eversource Distribution Line Clearance Program. All work shall be performed by qualified line clearance contractors. Safety shall take precedence over all requirements described herein and at no time shall work be performed in an unsafe manner. • All contact with the public and government officials shall be done in a courteous manner. • Work shall be subject at all times to inspection by Eversource and government officials. The crew foreman, or the contractor's designee, shall notify Eversource of the crew's daily work location and of any change made during the day. • Work shall be performed in such a manner that it will not interfere with or affect in any way the operation of any existing energized lines or electrical equipment, except as specifically directed by Eversource. • All line clearance work shall be performed in strict accordance with all applicable federal, state and local governmental laws and regulations or approved standards and safety practices – ANSI A300 (Part 1)-2008, Best Management Practices – Utility Pruning of Trees, ANSI Z133.1-2012, OSHA 29 CFR 1910.269. The contractor shall be responsible for the knowledge, supervision and enforcement of them. • Each crew will have on the vehicle the Eversource Image Summit forms and door hanger. Administration of the process will be in accordance of all Eversource Image Summit procedures and guidelines. • When necessary, the contractor requests permission from tree owners and others to perform line clearance tree work around electrical conductors. Where the tree owner is not at home, use the appropriate permission card and customer brochure. For all refusals, light trims or no contacts the contractor shall fill out a copy of form DISTRIBUTION LINE CLEARANCE MODIFICATION FORM and submit the form weekly, or approved electronic form. • The crew foreman shall complete and submit weekly company approved reporting forms, adding information daily for all T&M work. Paper forms of this report shall be submitted to Eversource no later than Tuesday of the
  10. Page 30 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 30 of 297 week following the completed work week. Electronic forms shall be submitted at least weekly, depending on syncing and uploading system requirements. • The line clearance crew shall work progressively along the distribution system starting at the substation, or as directed by Eversource, and shall complete all work on a given portion of the line before starting work at another location, unless otherwise approved by Eversource. • Re-trimming will be required to correct all situations where trimming quality is determined by Eversource to be improper. • Climbing irons shall not be used in any tree unless the tree is to be removed. • Wherever Eversource is solely responsible for clean-up on scheduled work, clean-up shall be completed daily and the site shall be left in at least as neat and orderly condition as it was found. 2. Scope of Work This Specification covers the trimming and removal of trees and brush, including the use of herbicides (CT only) for brush control along rural and urban overhead electrical lines and around substations owned or used by Eversource. This includes clearing for existing lines as well as for new lines, and applies to local distribution only, along and off-roads, and not bulk supply distribution rights-of-way. Each tree must be evaluated on its own at the time it is trimmed. The tree crew must consider the variables including tree species, condition, growth rate and location. 2.1. Scheduled Maintenance Trimming (SMT) 2.1.1. Primary Conductors Conductor clearances relative to various primary wire positions are shown in Figure 1. Normally, remove all branches within the clearance zone bounded by the dashed line perimeter and all overhead hazards within reach of a 55’ aerial lift. Watersprouts and suckers shall not be trimmed; they shall be removed back to the originally established clearance level.
Words on different pages

Text of OCC-890_Final.pdf

Extracted from the file · 1 page · 553 characters

Words on different pagesRead the text of OCC-890_Final.pdf

As listed on the current system

Question(s) Answered 888, 889, 890 (The Connecticut Light and Power Company) Date Filed: 10/09/2026

This filing on the current system (opens in a new tab)