Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 888, 889, 890

Files5

Search terms highlighted
Eversource rate increase is on 2 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
2 pages match
  1. Page 270 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 270 of 297 19 20 Inspect secondary and service cables to ensure connections are clean and tight and that the insulation is in good condition. Ensure neutral connections are made with permanent connection (compression or Secondary, Neutral, And shear bolt). Neutral connections to the ground bus may be made with bolted Service Cables connections. Verify secondary ring bus or alternate crab design is built in accordance with standards DTR Section 84 Verify secondary neutrals are in good condition and constructed in accordance with the appropriate standard DTR 84.181, 84.191, 84.195, 84.281, 84.285, 84.291, & 84.381. Verify secondary neutrals are properly grounded in each manhole in accordance with standards. DTR 84.181, 84 191 84 195 84 281 84 285 84 291 & 84 381 Ensure that all grounds, neutral, and drain (or bleed) wire connections, such as Grounds, Neutrals, Drain primary, secondary, etc. are in place and in good condition. Wire Connections 21 Ground Bus 22 Secondary Sheath Voltage Testing 23 Primary/Secondary Equipment 24 Supports & Mounting Hardware 25 Sumps &Drains 26 Cathodic Protection 27 Safety Concerns ITEM # INSPECT 28 Deficiencies (Other) Ensure ground bus is constructed in accordance with standards DTR 76.451, DTR 76.453, DTR 76.571 or DTR 76.451 as appropriate Ensure ground bus and connections are in good condition. Verify that voltage values between vault system ground and sheath/equipment sample points is less than 40 volts. Refer to M4-WP-3059 • Ensure that primary/secondary equipment, are in good condition. Check for signs of arcing, tracking, chipping, stress, etc. for all connections. • Note the absence of elbow arrestors that should be installed. • • Check all mounting hardware to ensure that it is stable and free of corrosion. Ensure all installed equipment is set properly on its concrete slab/pad. • Ensure drains, if present, are cleared of any blockages. • Ensure drains, if present, have functional traps. (NESC) • Check proper operation of installed oil-water separators, if one is present. • Ensure sump pump, if present, is working and installed in accordance with standards DTR 76.111 through Check anodes if installed Refer to DTR 88.013 – 88.016 Notify supervision of safety concerns that require correction INSPECTION ATTRIBUTES Note any other deficiencies found that require correction Corrective work orders NOT required 29 Clearing Work Space • • Horizontal dimensions shall not be less than 3 feet horizontally between cable racks on opposite walls. (Horizontal dimension may be decreased to 30 inches if cables are installed on only one wall.) (NESC) Vertical dimension shall not be less than 6 feet except in manholes where the manhole opening is within 1 foot , horizontally of the adjacent interior side wall of the manhole (NESC)
  2. Page 271 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 271 of 297 Required Repairs STRUCTURE / LOCATION NO. INSPECTED BY DATE STREET ADDRESS TOWN STATE W/O# INSPECTED BY ITEM # REQUIRED CORRECTIVE WORK REVIEWING SUPERVISOR SIGNATURE DATE NOTE: Deficient conditions noted, other than Clear Working Space, shall be entered into CASCADE as Corrective Work Orders.
  3. Page 272 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 272 of 297 ATTACHMENT 1 CL&P – Routine Inspection Reporting Form NOTE: This form shall be forwarded to CL&P Asset Management. No CASCADE entry is required
  4. Page 273 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 273 of 297 . Attachment 2 Vault Sketch NOTE: This form shall be forwarded to CL&P Asset Management. No CASCADE entry is required
  5. Page 274 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 274 of 297 NOTE For CONNECTICUT, this instruction supersedes guidance contained in the following instructions: • EMP 6.59 Under Ground Cables • EMP 6.54 Underground Corrosion • EMP 6.53 Underground Customer Vaults • EMP 6.59 Underground Vaults and Manholes • EMP 6.63 Sump Pumps 6.59B Manhole Instructions Underlining has been used throughout this document to mark those revisions that were made in compliance with order No. 1 of the July 18, 2012 Public Utilities Regulatory Authority Decision Docket 1005-09, or otherwise made as a consequence of the findings of the Consultant Report as filed by the Company on July 29, 2012 in compliance with order Nos. 1 through 3 of the Interim Decision in this Docket. Manholes Inspection Instructions Before You Begin Prior to assigning work in Manholes, Supervision shall: 1. Ensure that all employees are properly trained and qualified to perform this work, and that all appropriate PPE and safety requirements are met, including but not limited to those defined within the following documents: TD 211, “When to Wear FR Clothing” TD 952, “Protection of Personnel Entering Enclosed Spaces” TD 955, “Confined Space Requirements” Eversource Employee Safety Manual 2. Ensure those performing the work are aware of the following PPE requirements whenever working in Underground Manholes: Safety Glasses with side shields EH (Electrical Hazard) rated boots High Voltage gloves FR (flame resistant) clothing, as specified in TD 211 3. Whenever “Work”, as defined in paragraph 4 of this procedure, is performed in a manhole containing a network unit the following PPE is required : • Protective Arc Flash Hood (Beehive), (Stock Code 442151) or company approved equivalent. • Safety glasses with side shields • Minimum of low voltage (Class 0) rubber gloves (use of High Voltage Rubber Gloves is preferred)
  6. Page 275 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 275 of 297 • Double layer of full body FR Clothing (i.e., FR shirt and pants plus full body FR coverall) 4. In manholes containing Network Units, all persons performing “Work”, as defined below, and those persons within the immediate work zone while “Work” is being performed shall wear at minimum double layer full body FR clothing, minimum 25 cal. FR rated hood (beehive type with built-in arc rated face shield), safety glasses and, minimum of low voltage (Class 0) rubber gloves (high voltage rubber gloves preferred). As defined in this document, “Work” includes the following tasks: • • • • • • • 5. Installing or removing transformer links and network fuses Rolling or racking out the protector Phasing the unit Connecting test leads to an energized bus Obtaining transformer and network voltages Using a test probe prior to installing links and network fuses Or any other work performed inside the network protector enclosure with the transformer and/or network bus energized Prior to accessing manholes containing a single network unit in order to perform work, or conduct investigations or inspections, the maintenance records for that network unit will be reviewed to determine its condition. • • • If the records indicate that a major maintenance was completed within the maintenance cycle per the Eversource Employee Safety Manual and the unit has no major deficiencies, work may commence in the manhole with the unit energized following all applicable company procedures and protocols. If the records do not indicate that a major maintenance was completed on the unit within the maintenance cycle per the Eversource Employee Safety Manual or major deficiencies have not been addressed, then the primary feed to the unit will be deenergized prior to commencement of maintenance work. The maintenance work in the manhole will then take place with the unit de-energized, and only the secondary cables will be energized back from the street grid during the work. This will only apply to single transformer manhole units. The deficiencies described below, require the primary circuit to be de-energized in accordance with the operating policy. o Major maintenance not performed within the maintenance cycle required by the Eversource Maintenance Program o Low oil level (below sight glass / gauge level) in primary switch or transformer or dielectric quality of oil below acceptable level o Any other significant defect or abnormal condition that may affect the safe operation of the network protector
  7. Page 276 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 276 of 297 or transformer, such as: free standing water in the primary switching or transformer oil sample, excessive damage / corrosion in the network protector or other defect that requires immediate repair to return to service 6. For cases in which multiple network transformers exist in a manhole, it will generally not be possible to de-energize all of those units for a variety of reasons. Therefore, prior to working in the manhole in which multiple network transformers exist, maintenance records shall be reviewed for major deficiencies and/or major maintenance completion within the maintenance cycle in accordance with the Eversource Maintenance Program prior to working in the manhole. • If records indicate that major maintenance for all transformers within the manhole is up-to-date, and that there are no major deficiencies, then work may proceed. If existing major deficiencies were not corrected or if major maintenance was not completed within the required schedule, management will jointly work with employees to determine the appropriate steps to follow. • 7. Job Setup: Work zones, requirements for various jobs, switching requirements. All arrangements should be completed or setup prior to beginning the job. These include cones, signage, and police or traffic control. Check holes prior to entry for cleaning needs, i.e. pumping water, debris, contaminates, and visible oil. If any contaminates are found, provide samples for lab analysis. 8. Review the manufacturer’s manuals for all safety notations (Danger, Warnings, and Cautions), as needed. These may be in sections of the manual other than with the instructions. 9. Prepare the manhole for entry. a) Check for dangerous atmospheric conditions before entering the manhole using company-approved atmospheric sampling equipment. b) Ventilate the manhole, if required, in accordance with the Eversource Employee Safety Manual. c) Remove any standing water or debris from the manhole in accordance with ENVIROWI-0105 or company-specific requirements, as required. This is located in the Environmental and Facility Procedures section of the Distribution Engineering Standards Bookshelf. Any enclosed space that is found to have a potential hazard will be identified with a yellow streamer barrier across the entrance. The identified enclosed space will be inaccessible to personnel for routine work until repairs are made or the hazard made safe so other work can be performed safely in the enclosed space. d)
  8. Page 277 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 277 of 297 FOR CONNECTICUT - this instruction supersedes guidance contained in the following instructions: EMP 6.59 Under Ground Cables EMP 6.54 Underground Corrosion EMP 6.53 Underground Customer Vaults EMP 6.59 Underground Vaults and Manholes EMP 6.63 Sump Pumps Routine Inspection – Preparation Supervisor, Planner, or Working Foremen (as appropriate) 1. Check for open work orders (such as leaking splices) for this location that may indicate unsafe conditions or that may present the opportunity for combining maintenance at this or adjacent vaults. Ensure Copies are provided to the crew performing the inspection. 2. Provide equipment prints / schematics / circuit maps for this location so that the actual field conditions, i.e. transformer size, etc can be verified by the crew performing the inspection. 3. Supervision shall ensure the assigned workers have primer, paint, and any additional material needed for cleaning and preservation of the exterior of the unit prior to departing the work center. Routine Inspection – Performance Inspection Crew. NOTE It is the company’s expectation that whenever possible, repairs shall be made during the course of the routine inspection. 1. Clear foreign materials from the manhole entrance and the manhole, as required. 2. Inspect frames for signs of snow plow impacts, excessive elevation difference, either above or below grade. 3. Perform touch potential testing as required and described on section 5.62 of the Eversource Maintenance Program. CAUTION Use caution when replacing or installing missing tags, especially when identifying the cable by duct position and cable size. 4. Ensure standard signs, cable tags, and labels and other equipment nomenclature are in place and in good condition. Clean as needed. Replace missing or plastic cable ID tags with brass tags, as appropriate. 5. Perform manhole physical inspection as follows:
  9. Page 278 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 278 of 297 a) Inspect the walls and ceiling for any signs of: • Excessive cracking or flaking concrete • Exposed or corroded reinforcing steel • Severely rusted I-beams • Severely pitted or rusty structural components, etc. • Signs of bowing out • Corrosion and spalling on horizontal and vertical concrete beams • Fatigue on the bottom steel beam flanges b) Inspect Beam Pockets to ensure: 6. • Sufficient bearing surface • Beams lay flat in the pocket, with no torsion • Shims, concrete, and bearing surfaces are in good condition • Beams have proper embedment into the pocket c) Inspect the manhole for excessive mid-span deflection of: • Walls • Floors • Lids • Supports. d) Check pulling eyes for: • Corrosion • Condition of hardware Ensure the duct shield is present and in good condition and install or replace it as necessary. a) Check duct banks for: • Cracked concrete • Collapsed conduit • Abandoned cable cut • Collapsed header b) Verify actual field conditions (i.e. transformer size) using: • Equipment prints • Schematics • Circuit maps c) Check Structure Location to street, alley, etc. If the map is incorrect then mark-up the changes using Attachment 2 I. Check Structure concrete features to Structure drawing on map. If the map is incorrect, mark-up the changes. II. Check the Primary and Secondary Tags at each structure duct to the duct on map. If the map is incorrect, mark-up the changes. III. Check all Primary Cutouts, Switches, Transformers, Elbows, Splices, and other primary equipment to the map. If the map is incorrect, markup the changes.
  10. Page 279 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 279 of 297 7. Perform an infrared inspection to check for heat anomalies on primary connections, secondary connections and accessories, as applicable. Refer to NOTE: Perform the Infrared (IR) inspection using an infrared camera. If an infrared camera is not available, a temperature reading tool, such as the Fluke 63 (SC 0435572) may be used to take spot temperature readings of the equipment in place of the IR inspection. EMP 5.22 for additional guidance. Primary cables and connecting devices include: • PILC Splices • Premolded Splices • Heat Shrink Splices • Cold Shrink Splices • 200 AMP Load Break Elbows • 600 AMP Load Break Elbows Secondary cables and devices to check include: • • • • • • Mains • Services Bus Bars • Bus Limiters Line Limiter Molded Crabs (both limited and non-limited Network Transformer Secondary Connection Secondary and Service Splices 8. Verify that limiters are installed in accordance with standards DTR 84.601 & 84.602 and that they are not blown or open. 9. Verify the integrity of the secondary (network) grid. Amp each conductor on the secondary mains (preferred) or verify the limiters are not blown. Report secondaries with zero (0.0) amps. 10. Ensure all fault indicators (as applicable) are in good condition and working. Replace them every ten years or as necessary. 11. Clean or replace equipment status indicators. 12. Inspect primary cables splices and terminations for the following abnormal conditions: • • • • • • • Oil leaks, soft spots and insulation swelling Cracked or corroded lead sheaths Damaged fireproofing Poor connections, signs of arcing/tracking Collapsed or bulged cables Bulged splices Physical damage, sharp bends and excessive tension
Words on different pages

Text of OCC-890_Final.pdf

Extracted from the file · 1 page · 553 characters

Words on different pagesRead the text of OCC-890_Final.pdf

As listed on the current system

Question(s) Answered 888, 889, 890 (The Connecticut Light and Power Company) Date Filed: 10/09/2026

This filing on the current system (opens in a new tab)