  1. Page 286 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 286 of 297 23 • Horizontal dimensions shall not be less than 3 feet, horizontally between cable racks on opposite walls. (Horizontal dimension may be decreased to 30 inches if cables are installed only on one wall.) (NESC) • Vertical dimension shall not be less than 6 feet except in manholes where the manhole opening is within 1 foot, horizontally of the adjacent interior side wall of the manhole. (NESC) Clear Working Space
  2. Page 287 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 287 of 297 Attachment 1 Bubble Inspection Form for CL&P NOTE: This form shall be forwarded to CL&P Asset Management. No CASCADE entry is required.
  3. Page 288 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 288 of 297 Attachment 2 Sketch of the Manhole NOTE: This form shall be forwarded to CL&P Asset Management. No CASCADE entry is required. References: • • Eversource Maintenance Program, Section U6, “Inspection and Maintenance , Subway System-Customer Vaults and Manholes” Eversource Maintenance Program, Section U4, “Inspection and Maintenance of Subway System Switches”
  4. Page 289 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 289 of 297 • • • • • • • • • • • • • • • • • • • • • • • • • Eversource Maintenance Program, Section U2, “Inspection and Maintenance , Subway System-Cable” TD 853 Infrared Thermographic Inspections TD 900. Electric System Nomenclature TD 921 UG/DB System: Guidelines for Replacement of Suspect Molded Rubber Components TD952 Confined Space Requirements DTR 70-891. Identification of UG Cables DTR 07-201. Fault Indicators DTR 76.451 Conduit System – Grounding, Below Grade Manholes and Vaults DTR 76.453 Grounding Details, Installation in Customer Service Vaults DTR 76.571 Customer Service Vault – 1000 KVA Maximum, Notes for NU Personnel DTR 84 Conduit System – Secondary and Service. Refer to sections: 181,191,195, 281, 285, 291, 381. DTR 84.601 and 84.602 Limiter Guide – Secondary Network Conduit System – 216Y / 125 Volt DTR 44.221 – 44.223 Fault Indicator Guide, Solid Dielectric Cables DTR 78.151 4 CT Cable Splices – Conduit System Grounding DTR 78.153 3/C Cable Splices – Conduit System Grounding DTR 78.113 Splicing Instructions – General - Paper & Lead Cables – 5KV thru 30 KV DTR 84.111 Alternate Secondary Network Ring Bus Phase Connections PR-132. Product Review for Elbow Pullers PR-133, Product Review – Elbow Pulling Tool. Alternate tool to loosen and remove “stuck” elbows PR-163, Product Review Alert – Failed Elbow Pulling Hot Stick M4-SO-3103. Direct Buried Switching. CL&P Unified Switching Practice M4-WP-3059 Sheath Voltage Testing in Vaults and Manholes Safety Alert 02-2003. Elbow Flashovers Safety Alert 06-2003. DB Elbow Flash Distribution Work Practice "Testing of UG Getaways / Cables in Urban Areas".
  5. Page 290 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 290 of 297 APPENDIX 18 APPENDIX NO LONGER USED
  6. Page 291 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 291 of 297 APPENDIX 19 INFRARED SURVEY PROGRAM
  7. Page 292 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 292 of 297 5.22 Infrared Surveys General Description The Infrared (IR) Survey Program utilizes technology known as Thermography to identify degraded components. Thermography is a non-destructive test method that remotely senses and measures heat emitted from a component, allowing a temperature comparison between the component, and adjacent or contiguous materials. A significant rise in temperature on a specific component referred to as a “hot spot” or “finding”, indicates that the component is in a degraded condition. The magnitude of the temperature rise is in part proportional to the relative resistance of the device, and is therefore an indicator of the severity of the degradation. In classifying the severity of a finding, the thermographer must also consider a variety of factors that influence the measured temperature. Two attributes of the material of which the item being scanned is made, emissivity and reflectivity, impact the readings obtained with thermal imaging equipment. Whenever possible, comparisons should be made between components made of like material. The relative load on the circuit must be considered, since higher load will result in a higher temperature rise. In addition to the above, environmental conditions (e.g., direct sunlight, overcast, precipitation, ambient temperature, wind speed, etc.) must also be considered, as they relate to cooling being provided to the component. The type of component is a factor in determining appropriate corrective actions. Passive, air-cooled components, such as hot-line clamps or splices, can typically tolerate higher temperatures before failure becomes imminent and are generally allowed more latitude in terms of response/repair time. Oil-filled or active devices, such as Capacitors or Vacuum Reclosers, cannot tolerate very high temperatures; corrective action must be taken at relatively low magnitudes of temperature rise for these components.
  8. Page 293 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 293 of 297 5.22.1 Facilities and Equipment An Infrared Survey is performed on all Distribution three-phase overhead backbone circuitry, Distribution substation equipment, and other equipment deemed necessary. • Three-phase overhead circuitry for distribution backbone and Transmission circuitry, which includes: Capacitors (Pole-top) Disconnect Switches Lightning Arresters Overhead Plant Potential Transformers Reclosers Regulators Transformers (Pole-top) • Substation equipment, which includes: Capacitors (Substation) Capacitor Switches (Vacuum) Circuit Switchers Disconnect Switches Lightning Arresters Load Tap Changers Oil Circuit Breakers Potential Transformers Regulators Transformers (Substation) • Other equipment (as deemed necessary), which includes: Air Circuit Breakers Pad-Mounted Switchgear SF6 Gas Circuit Breakers Underground Cables Underground Switches Underground Transformers Vacuum Circuit Breakers Other DB Equipment Survey Findings The findings are classified as “Minor”, “Serious”, and “Emergency“ in increasing order of severity. Refer to TD 853 “Infrared Thermographic Inspections” for details. This TD has been endorsed by all three operating companies.
  9. Page 294 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 294 of 297 5.22.2 Inspection and Maintenance Activity Schedules Table 1 – Infrared Survey Intervals Infrared Survey Interval PM Task Condition Monitoring Time-Directed N/A Infrared Survey – Distribution Substation 1Y (Note 1) Infrared Survey – Distribution Three-Phase Overhead Backbone 1Y (Note 1) Infrared Survey – Three Phase Transmission Overhead 1Y Condition-Based Perform follow-up based on analysis of IR surveys. A/R Failure Finding Report Emergency level findings immediately to the appropriate AWC personnel. A/R The abbreviations used for the intervals are: A/R = As Required N/A = Not Applicable Y = Year, i.e. 5Y = 5 Years Note 1 = An infrared inspection is required at least once per year and may be performed twice per year at the discretion of each Operating Company. Note 2 = Infrared inspections of three phase OH backbone on right-of ways is NOT performed unless other conditions identified during the routine visual inspection warrant further investigation. 5.22.3 Maintenance Categories Condition Monitoring Not Applicable.
  10. Page 295 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 295 of 297 TIME-DIRECTED 5.22.3.1 Routine Inspection 1. Perform infrared surveys on all Distribution overhead three-phase Backbone, Transmission overhead circuits and Distribution substation equipment. 2. Analyze the findings of the surveys, prioritize the actions to be taken, and distribute reports in accordance with TD 853 “Infrared Thermographic Inspections”. 3. If deemed necessary, an oil sample can be taken to confirm an abnormally high and unacceptable temperature. 4. Priority and response recommendations provided by the Thermographer are based solely on evaluated equipment condition, and may be adjusted by maintenance management and/or work management personnel as necessary to accommodate scheduling concerns. CONDITION-BASED 5.22.3.2 Actions Based on Findings: Infrared surveys may find temperatures that indicate minor to serious conditions that require action ranging from more frequent inspection to immediate repair or replacement of the component. 5.22.4 References: • TD 853 “Infrared Thermographic Inspections” • Appendix 19, EMP 5.22 Infrared Surveys, DPUC Docket “Electric Utility Line Maintenance Plan Pursuant to Section 16-32g of the General Statutes of Connecticut and Section 16-32g-1 of the Regulations of Connecticut State Agencies” 2010 Filing, January 1, 2010. • Eversource Maintenance Program (EMP) Manual, Preventive Maintenance Frequencies, dated January 1, 2002. • PSNH Document ED3017 • ASTM E 1934-99a “Standard Guide for Examining Electrical and Mechanical Equipment with Infrared Thermography”
Words on different pages

Text of OCC-890_Final.pdf

Extracted from the file · 1 page · 553 characters

Words on different pagesRead the text of OCC-890_Final.pdf

As listed on the current system

Question(s) Answered 888, 889, 890 (The Connecticut Light and Power Company) Date Filed: 10/09/2026

This filing on the current system (opens in a new tab)