Interrogatory responses
Answers to questions 888, 889, 890
Files5
OCC-888_Final.pdf
PDF · 101 KB · 1 pageText searchable
Download OCC-888_Final.pdfRead the text of OCC-888_Final.pdf
OCC-888 Attachment 1.pdf
PDF · 1.0 MB · 1 pageText searchable
Download OCC-888 Attachment 1.pdfRead the text of OCC-888 Attachment 1.pdf
OCC-888 Attachment 2.pdf
PDF · 8.4 MB · 297 pagesText searchable
Download OCC-888 Attachment 2.pdfRead the text of OCC-888 Attachment 2.pdf
OCC-889_Final.pdf
PDF · 75 KB · 1 pageText searchable
Download OCC-889_Final.pdfRead the text of OCC-889_Final.pdf
OCC-890_Final.pdf
PDF · 74 KB · 1 pageText searchable
Download OCC-890_Final.pdfRead the text of OCC-890_Final.pdf
Page 76 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 76 of 297 APPENDIX 7 POLE-MOUNTED, THREE-PHASE, GROUP OPERATED SWITCHESPage 77 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 77 of 297 5.15 Disconnect Switches General Description Switches are essential elements of the electrical power distribution systems. They provide positive, visible air gap isolation of equipment and line sections for safe examination, maintenance, and repair. Switches are built in a variety of physical forms to accommodate the various requirements of electrical clearances, operational requirements, and space limitations. They can be divided into three main categories: • Regulator Bypass switches • Disconnect switches • Interrupter switches REGULATOR BYPASS SWITCHES Bypass switches are generally used at regulator installations to provide a quick, reliable means of taking such apparatus in and out of service without de-energizing the feeder circuits and to prevent winding burnouts from open-circuit windings. DISCONNECTS – Single Phase Switches (not including fused cutouts) There are two general classifications for disconnect switches: • Loadbreak and • Non-loadbreak Loadbreak disconnects may be used to make or break current up to the ampere rating of the switch/Load Buster tool combination. Non – Loadbreak disconnects are rated for use as a means to energize or de-energize: • Unloaded bus or bus segments only within the substation • Unloaded circuit breakers, lightning arresters, and other switches. and under certain circumstances, may be used to make or break a parallel connection to another switch. All overhead and some substation disconnects include a loadbreak hooks for use with a loadbreak tool. To open the switch under load, use only an approved loadbreak tool or device designed for use with switches. Follow the instructions provided with the loadbreak tools. See DTR Substation Section 18.41 for the complete list of applications and restrictions for Loadbreak and Non-Loadbreak disconnect switches. Three Phase Disconnect Switches – Gang-Operated Disconnects (GOD) sometimes referred to as Gang-Operated Air Brake (GOAB) Gang-operated disconnects are used where more than one phase of a circuit must be opened simultaneously. The most common gang-Page 78 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 78 of 297 operated disconnect switches are the air-brake type manufactured with up to 1200-ampere ratings in voltage classes up to 46 kV. They are used at substations, switching structures, and on the lines for energizing and de-energizing transformer banks and other apparatus. They are also used for sectionalizing. Although they can be MODs (Motor-Operated Disconnects), they are more commonly provided with a switch handle for hand operation. This type of switch is ideal because it lends itself to operation from the ground, often permitting service to be restored to sections of the circuit without pole climbing. Although there are distinctions between the three categories of switches, for the purpose of simplicity, they will be collectively referred to as “disconnects”, in the remainder of this procedure. Motor Control – Some three phase group-operated disconnects are equipped with electric motors to open or close them. These disconnects may be operated remotely. SCADA – Some disconnect switches are connected to SCADA – an automated system that monitors the switch position, current and voltage and provides the data to a remote location. It also allows for remote operation of the switch if the switch is motor operated. Scadamate – A three phase group-operated disconnect type switch with SCADA capability. NOTE: All specific maintenance requirements that are followed by a triangle symbol “▲” are explained in the Maintenance Basis Documentation section of this chapter. Facilities/Equipment • Line bypass, Disconnect, and Interrupter Switches NOTE: The inspection and maintenance for single phase Pole-top disconnects is the same for “inline suspension” disconnects. 5.15.1 Inspection and Maintenance Schedules 5.15.1.1 Table 1 – Disconnect Switch Maintenance Intervals Disconnect Switch Interval Maintenance Schedule PM Task Condition Monitoring Motor Operated Drives/Control A/R Time-Directed Maintenance Infrared Inspection (GODs & S/S) – Energized ▲ 1Y Infrared Inspection – Vertical Pole Top and Inline Suspension Single Phase Disconnects (Note 2) 1YPage 79 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 79 of 297 Visual Inspection (In Substations) – Energized 1M Visual as part of the Overhead Plan Inspection 1Y Motor Control Visual Inspection/Battery Replacement (Note 1) 3Y Condition-Based Maintenance (CBM) Infrared Inspection – Vertical Pole Top and Inline Suspension Single Phase Disconnects (Note 2) A/R Visual Inspection (“outside of the fence”) – Energized (Note 3) A/R Major Inspection (Note 4) A/R Major Maintenance (Substation – “within the fence”) (Note 5) A/R Major Maintenance (Pole-Top GOD / GOAB– “outside of the fence”) A/R Major Maintenance – De-Energized (Lines – “outside of the fence”) A/R Replace Braids A/R Any Visual Findings A/R Operational Test (Note 6) A/R In Table 1, the type of maintenance is listed in the left column and the interval required for that type of maintenance is listed in the right column. For example, the interval for an Infrared Inspection of a Disconnect Switch is 1Y (or 1 Year). The abbreviations used for the intervals are: Y = Year, i.e. 2Y = 2 Years N/A = Not Applicable M = Month, i.e. 1M = 1 Month A/R = As Required S/S = Substation Within the Fence refers to those components within the substation. Outside of the Fence refers to those components beginning on the first Distribution pole outside of the substation. (Note 1) = Routine Switch Controller maintenance consists of replacing the battery packs. The frequency of replacement depends on designed battery life, ambient temperature, float charge voltage and frequency of discharge. Industry experience has shown that batteries should be replaced every two years for hot environments and three years for colder environments. (Note 2) = Infrared surveys are performed on Disconnect Switches in accordance with EMP Chapter 5.22 – Infrared Inspections. Refer to Chapter 5.22 – Infrared Inspections for inspection requirements and the interval at which inspections are to be performed. (Note 3) = Visual Inspection of Disconnects (“outside the fence”) shall be performed prior to every manual operation. This inspection may be performed either from a bucket or from the ground. (Note 4) = A Major Inspection is performed for those Substation Disconnects that are not practical to de-energize, even when the associated equipment is being maintained and is out of service. Those units that fail this inspection are replaced. (Note 5) = Major Maintenance – De-Energized for Substation DisconnectsPage 80 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 80 of 297 (those that can be de-energized) is performed when the equipment to which it is associated is being maintained and is out of service. (Note 6) = The Operational Test is performed at the time of Major Maintenance. See EMP Instructions 6.15A for details on performing maintenance on 3-Phase Overhead disconnects and 6.15B for performing maintenance on Substation disconnects. 5.15.2 Disconnect Switch Maintenance Categories See EMP Instructions 6.15A and 6.15B for details on performing the following maintenance activities for Overhead Disconnects and Substation Disconnects respectively. TIME-DIRECTED 5.15.2.1 Visual Inspection – In Substations – Energized 5.15.2.2 Major Inspection – Energized 5.15.2.3 Motor Control Visual Inspection / Battery Replacement CONDITION-BASED 5.15.2.4 Major Maintenance – De-Energized 5.15.2.5 Operational Test 5.15.2.6 Visual Inspection – “Outside the Fence” 5.15.2.7 Infrared Inspection – Energized NOTE: Due to operating criteria and mounting configurations, pole-top and inline suspension switches are not readily serviced or required to be serviced at frequent intervals. However, inspection and annual infrared scanning are recommended. Refer to EMP Chapter 5.22 – Infrared Inspection. 5.15.3 Failure Finding Failures of major disconnect switches shall be documented in the equipment failure reporting system used by your region (EFRS, UPER, or Cascade, as appropriate). Analysis of disconnect switch failures should be performed when deemed necessary by Distribution Standards.Page 81 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 81 of 297 5.15.4 Disconnect Switch Maintenance Basis Documentation The maintenance activities and their schedules are based on industry experience, manufacturer’s recommendations, feedback from the service technicians, and the subject matter expert, who in this case, is an engineer for Distribution Engineering and Design. Requirement Infrared (IR) Inspection – 1Y • Pole Mounted (3 phase and single phase) • Substation Visual Inspection – 1M • In Substation Visual Inspection – A/R • “Outside the Fence” Major Maintenance – DeEnergized • 3 Phase Pole Top – A/R • Substation – W hen associated equipment is taken out of service. Major Inspection – Energized • Substation – W hen associated equipment is taken out of service. Operational Test Basis Infrared inspection is a proven technique for locating “hot spots” on equipment and connections in order to identify conditions that can be corrected before they become serious problems. Following a review of the recommendations contained within IEEE Std C37.35-1995 by the WG on 5/22/12, the WG determined that the existing practice of Infrared inspection of single phase disconnect switches along with the existing work practice of multiple operations meetings the guideline. In addition the WG expressed the opinion that additional periodic maintenance beyond this was not warranted based on the observed failure rates and potential cost and operational impact such activities would entail. This inspection is performed to look for conditions that may require immediate attention or unplanned maintenance. This interval has proven effective in detecting problems that could impact equipment performance. This inspection is performed to look for conditions that may require immediate attention or unplanned maintenance. This interval has proven effective in detecting problems that could impact equipment performance. De-Energized Major Maintenance is performed on Pole Top disconnects on an as needed basis, based upon visual and IR findings. Substation disconnects are difficult to de-energize and therefore receive Major Maintenance only when its associated equipment is taken out of service for maintenance. This is an energized inspection for Substation disconnects. It is used to determine the overall condition of the disconnect and if the disconnect requires replacement. Recommended by IEEE STD C.37.35-1995, SME Tino Dangelo and manufacturer S&C.Page 82 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 82 of 297 6.15A Switches, Disconnect – Three Phase Overhead GOAB – Maintenance Instructions. Before You Begin 1. Ensure that all employees are properly trained and qualified to perform this work; and all appropriate PPE and safety requirements are met, including but not limited to those defined within the following documents: • TD 211, “When to Wear FR Clothing” • Eversource System Employee Safety & Health Handbook Procedure Visual Inspection – All 3 Phase Disconnects – Energized 1. Visually inspect the three phase disconnect switch for the following: • Insulators - damage • Frayed or broken flexible connections • Taps - from switch to line conductors • Overheating (visual) • Condition of operating mechanism • Alignment of blades and proper contact • Signs of abnormal discharge, alignment and tripping linkage on load breaking devices • Operating rod insulator for damage and proper position, or missing insulator • Mechanical condition of frame • Condition or pitting of arcing horns, if applicable • Condition of grounds and ground attachments • Obstructions / Tree Branches that might obstruct operation or create a contact hazard • Debris - bird nests, kite string, etc. on switch • Squirrel Guards - missing or damaged, if applicable • Confirm all switch numbers and phase markings are installed, where applicable. • Visually check the condition of the Lightning Arresters, if applicable. • Condition of the motor operator, if applicable. Ensure that the condensation heaters are operational and the control box is free of debris or foreign objects. 2. Record any conditions that require follow-up repair onto EMP Form 6.15A.Follow-up repairs require the initiation of a corrective work order / request. NOTE: This use of this form is optional and it is intended for use as a Worker’s aid – not for use as a permanent record.Page 83 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 83 of 297 Major Maintenance – Energized 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Perform touch potential testing on all components that may be accessible to the public. Ensure that the switch is bypassed or transfer the load before performing this inspection. Check the structural grounds for mechanical security. Inspect the flexible braids or slipping contacts used for grounding the operating handle. Replace any braids showing signs of corrosion, wear, or having broken strands. Examine the structure, mechanism enclosure and linkage for general condition Ensure mechanical locking devices are secure and in good operating condition Operate all switches several times. Check the switch for smooth operation. Ensure the open and close mechanical indicators are working. Ensure that all Motor Operated Drive (MOD) control switches are in their normal position or are properly tagged, if applicable. Check MOD red and green indicating lights, if applicable. NOTE: The S&C disconnect switches require inspection / adjustment to ensure proper blade alignment. See the section “Alignment Procedure – S&C” following the Operational Test section for instructions on adjusting the S&C Disconnect Switches. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. Verify that rotating blades are fully seated and rotated, if applicable. Visually check the alignment of the blade and jaw on each pole and verify the blades are latched, if applicable. Check the insulator for chipped or cracked porcelain, and the accumulation of dirt or other contamination deposits (bird nest, strings, etc.). Check the condition of arcing horns and / or whips for pitting, burning and missing parts, if applicable. Verify the operation of heaters and proper operation of the thermostats, if applicable. Note the position of the safety relief valve and check the indicator on switches using a vacuum or gas interrupting unit, if applicable. Visually check all electrical and mechanical connections for tightness and unusual wear. Check for proper pressure and air leaks on switches employing an Air Blast attachment. Check for the condition and presence of all signage and phase designations, where applicable. Record any conditions that require follow-up repair onto EMP Form 6.15A. Follow-up repairs require the initiation of a corrective work order /request. NOTE: The use of EMP Form 6.15A is optional and is a worker’s aid only and not a permanent record.Page 84 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 84 of 297 Major Maintenance – De-Energized 1. 2. 3. Disconnect the switch from all electric power sources before servicing. Check for broken plastic cams on the blades. Inspect the insulators for breaks, cracks, burns, or cement deterioration. • Clean the insulators particularly where abnormal conditions such as salt deposits, cement dust, or acid fumes exist. This is important as it will minimize the possibility of flashover resulting from the accumulation of foreign substances on the insulator surfaces. • Replace any broken or defective insulators immediately. NOTE: The S&C disconnect switches require inspection / adjustment to ensure proper blade alignment. See the section “Alignment Procedure – S&C” following the Operational Test section for instructions on adjusting the S&C Disconnect Switches. 4. Check the switch for alignment, contact pressure, eroded contacts, corrosion, and mechanical malfunction. NOTE: S&C Omni-Rupter® Switch blade contacts are greaseless and selflubricating. Do not apply lubricant to the blade contacts. Replace damaged or badly eroded components. If contact pitting is of a minor nature, smooth the surface with clean, fine emery cloth or as the manufacturer recommends. NOTE: Scotch Brite works well on silver contacts when a wire brush cannot be used. • Lubricate the contacts with a thin film of manufacturerrecommended, non-oxide grease for non-self lubricating contacts only. Lubricate the bearings, if applicable. Check the blade latch for adjustment. Ensure the blades move freely and still are rigid enough for proper alignment with contacts. Inspect all live parts for scarring, gouging, or sharp points that could contribute to excessive radio noise and corona. Inspect inter-phase linkages, operating rods, levers, bearings, etc., to ensure that adjustments are correct, all joints are tight, and pipes are not bent or cracked. • Clean and lubricate the switch parts, as required. • Check for simultaneous closing of all blades and for proper seating in the closed position. Check the gear boxes for moisture that could cause damage due to corrosion or ice formation, if possible. Ensure all nuts and bolts are tight, including the piercing bolts on the operating shaft. Inspect the flexible braids or slip-ring contacts used for grounding the operating handle and replace those showing signs of corrosion, wear, or having broken strands. • • 5. 6. 7. 8. 9. 10. 11.Page 85 of 297
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 85 of 297 12. Power-operating mechanisms for switches are usually of the motordriven type. Follow the switch manufacturer's instructions for maintaining each mechanism. Check the limit switch including external switches for: •Poor contacts •Burned out coils •Adequacy of supply voltage •Any other conditions that might prevent the proper functioning of the complete switch assembly. 13. Inspect the overall switch and working condition of operating mechanism: •Check that the bolts, nuts, washers, cotter pins, and terminal connectors are in place and in good condition. •Replace items showing excessive wear or corrosion. •Inspect all bus cable connections for signs of overheating or looseness. 14. Inspect and check all safety interlocks while testing for proper operation. 15. Check the switch to ensure equal pole closing and opening. 16. Operate the switch to ensure its smooth operation. Listen for grinding noises or other signs of wear or malfunction. 17. Record any conditions that require follow-up repair onto EMP Form 6.15A. Follow-up repairs require the initiation of a corrective work order /request. NOTE: The use of EMP Form 6.15A is optional and is a worker’s aid only and not a permanent record. Motor Control Visual Inspection / Battery Replacement 1. Visually inspect the switch-control unit for the following: • Condition of the control cable • Condition of the control cabinet • Compartment heater condition • Condition of the indicating lights 2. Check the battery date and replace the battery if it has expired or will expire within the next three (3) years. 3. Record any conditions that require follow-up repair onto EMP Form 6.15A. Follow-up repairs require the initiation of a corrective work order / request. NOTE: The use of EMP Form 6.15A is optional and is a worker’s aid only and not a permanent record. Battery Replacement Instructions Before you begin: 1. Notify Dispatch before beginning work.
Text of OCC-890_Final.pdf
Extracted from the file · 1 page · 553 characters
As listed on the current system
Question(s) Answered 888, 889, 890 (The Connecticut Light and Power Company) Date Filed: 10/09/2026