  1. Page 96 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 96 of 297 (Note 2) Infrared surveys are performed on Regulators in accordance with the requirements of EMP Chapter 5.22 – Infrared Inspections. Refer to EMP Chapter 5.22 – Infrared Inspections for inspection requirements and the interval at which inspections are to be performed. (Note 3) The time interval between maintenance activities will depend upon frequency of tap-changer operation and the load on the regulator. Regulators subjected to numerous overloads and a high load factor may require more frequent inspections than those carrying normal loads. The initial maintenance interval will be as listed above, and will be adjusted in the future, based on collected performance data In Table 1, the intersection of the row and column indicates the inspection or maintenance interval for the equipment under the column heading. For example, the interval for Major Maintenance on a Regulator is A/R (or As Required). The abbreviations used for the intervals are: M = Month, i.e. 1M = 1 Month Y = Year, i.e. 2Y = 2 Years A/R = As Required 5.01.2 Maintenance Activities See EMP Instruction 6.01 for details on performing the following maintenance tasks. TIME-DIRECTED 5.01.2.1 Routine Inspection – Energized 5.01.2.2 Oil Top-Off – De-Energized 5.01.2.3 Oil Sampling – Energized or De-Energized CONDITION-BASED 5.01.2.4 Major Maintenance – De-Energized 5.01.2.5 Return to Service 5.01.2.6 Infrared Survey (See EMP Chapter 5.22 – Infrared Inspection.) 5.01.3 Failure finding Failures of Voltage Regulators shall be documented in the equipment failure reporting system used by your region (EFRS, UPER, or Cascade, as appropriate) and placed in “To Eng” status for review. Analysis of a failed Regulator may be performed as deemed necessary. 5.01.4 Regulator Maintenance Basis Documentation Requirement 1Y Inspection interval Basis The regulators manufacturer’s maintenance manuals do not specify a time interval for inspection and oil sampling. They state that inspection and oil sampling functions are conditionbased, and are dependent upon the frequency of tap-changer operation and the load on the regulator. Industry experience with Automatic Voltage
  2. Page 97 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 97 of 297 5Y Substation Oil Sample interval Infrared Inspection Regulator performance testing as listed in: • Council Controls Working Group (WG) Recommendations Policy • U.S. Department of the Interior Bureau of Reclamation Denver,Colorado • US Navy -Publication Number: TM 5684/NAVFAC MO 200/AFJMAN 32-1082 Recommends an annual inspection. Note: The EMP, based on the Work Practice #M4WP-3018 Rev. 1, recommends a 6-month inspection interval, but company experience has proven that a 1-year interval is sufficient for keeping the equipment reliable. Industry experience with Automatic Voltage Regulator performance testing as listed in: Council Controls Working Group (WG) Recommendations Policy U.S. Department of the Interior Bureau of Reclamation Denver, Colorado US Navy -Publication Number: TM 5-684/NAVFAC MO 200/AFJMAN32-1082 Recommends a 5-year oil sampling frequency. The maintenance practice of many other utilities as it pertained to step voltage regulators were examined to determine the frequency of their oil sampling. The examination revealed that some utilities perform an oil sample every two years, other never performed oil sampling. The manufacturer’s instruction states that their regulator are design for many years of trouble free operation, without the need for any maintenance, and that maintenance is condition based. One manufacturer went as far as to say their regulator could possibly function for 20 years without any maintenance. Several manufacturers suggest operation counts in the 100,000 count range as a basis for performing Major Maintenance. Although each manufacturer states that they do not anticipate the need for frequency maintenance, periodic inspection including oil sampling would help to assure continuity of service. Based on these recommendations and of a review of NU regulator failure reports, in which no noticeable failures were observed over a five year period; the 5Y or 50,000 operations count (based on application) oil sampling interval is being established on a regulators. This replaces the previous 2-year oil sample interval. As data is collected, and examined, this interval may be adjusted. Infrared inspection is a proven technique for locating “hot spots” on equipment and connections in order to identify conditions that can be corrected before they become serious problems.
  3. Page 98 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 98 of 297 6.01 Voltage Regulator Maintenance Instructions Before You Begin 1. Ensure that all employees are properly trained and qualified to perform this work; and all appropriate PPE and safety requirements are met, including but not limited to those defined within the following documents: •TD 211, “When to Wear FR Clothing” •Eversource Employee Safety & Health Handbook Procedure Routine Inspection – Energized Substation and Pole-Top 1. Perform touch potential testing on any metal surface that may be accessible to the public. 2. Verify the condition of the primary taps. 3. Verify the bushing conditions. 4. Verify the Regulator tank is in satisfactory condition. 5. Check the regulator for any oil leaks or foreign material in the area. 6. Visually check to ensure grounding is properly installed and in good condition. 7. Check the condition of the control cabinet for moisture or other problems. 8. Measure regulated voltage at the test terminals to verify correct bandwidth. 9. Check for proper operation of the raise and lower controls. • If the regulator will not operate properly, try using a substitute control before removing the unit from service. • Refer to the manufacturer’s instruction manual for the proper procedures on removing and replacing the control. 10. Verify the tap operations counter is working. 11. Verify and record the tap operations counter and tap indictor readings. 12. If applicable, then verify the Reverse Flow indicator is on. 13. If applicable, then verify the Reverse Flow indicator is operational. 14. Verify the Neutral indicator light is operational. 15. Ensure that all switches are in their normal positions. 16. Reset the Drag Arms. 17. Check to ensure animal guards are present, correctly installed, and in good condition. 18. Properly secure and lock the control cabinet. 19. Use binoculars to view the oil level window, if possible.
  4. Page 99 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 99 of 297 Warning: Siemens MJ-XL controls manufactured prior to August 2005 may have a defect that allows the control to indicate a false position reading. For example, the control may indicate that the switch is in a “manual” position when in reality it is still in “auto” mode. This concerns only the MJ-XL control and not the MJ-X control. Follow the instructions on page 7 of this section when servicing a regulator equipped with the MJ-XL control. 20. Inspect the bypass arrester, if present. Oil Sample – Substation Only Perform this step once every 5 years for Substation regulators. NOTE: Only take an oil sample from those regulators that are equipped with an oil level sight gauge and a drain valve. 1. 2. Check the oil level sight gauge and add oil as necessary so that an oil sample can be taken without leaving the regulator oil level too low. When performing this step, be sure to maintain safe working clearances from conductors and other electrical equipment or de- energize and ground the regulator. • If it is necessary to add oil before taking a sample, use the pressure relief valve to vent the regulator of positive or negative pressure. Take an oil sample to submit for testing in accordance with TD 202 to ensure compliance with ChemLab requirements. • Use the pressure relief valve to vent the regulator of positive or negative pressure before taking the oil sample. • If the dielectric strength is found to be below 24kv, de- energize the regulator, filter or replace the oil, and perform dissolved gas analysis testing to determine the oil’s integrity. Major Maintenance De - Energized NOTE: Prior to beginning maintenance, a clearance must be obtained and the respective equipment must be de-energized and grounded in accordance with the applicable company procedure(s): 1. TD 703 – Temporary Protective Grounds for Personnel in Substations 2. TD 855 – Grounding for Personal Protection on Overhead Lines 3. TD 856 – Temporary Protective Grounding for Personal Protection on Overhead Lines, 69 kV and Above. (Regulator Bypassed) Warning: High pressure or mechanical failure due to improper bypass operation can cause death, severe injury or damage. To prevent these consequences, bypass the regulator only with the regulator on the neutral tap position.
  5. Page 100 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 100 of 297 To ensure the regulator is in neutral: 1. 2. Place the volt meter leads into the appropriate receptacles and observe the voltage readings. Observe the voltage readings as you operate the Raise or Lower switch. Operate the regulator until the Indicating gauge reads neutral, while ensuring the voltage reading is still at appropriate levels. • If the control has a Neutral Light, ensure it turns on when the gauge is on neutral. If the light does not turn on, check the bulb and replace it if necessary. At this point, the indicator position should read neutral and the neutral indicator light should be on. If both of these conditions are not met, then use an approved regulator neutral tester (SC0188570) as an additional means of neutral verification. See Over & Under Issue # 64, dated June ’09 or PSNH Procedure CO-1040 for details on using this tool. PSNH Procedure CO-1040 and Over &Under Issue # 64 are appended to the end of this instruction. Until there are at least two indications of neutral, DO NOT ATTEMPT to bypass the unit. In such event, de-energize the regulator to remove it from service. 1. De – energize the regulator 2. Remove the voltage regulator from the pole or pad/platform to perform de-energized maintenance. CAUTION: W hen untanking the regulator, be sure to use the proper lifting point, NOT the regulator cover. NOTE: • All Pole-Top regulators will receive their Major Maintenance at the shop. • Substation regulators receive their Major Maintenance at the shop except for those units too large to move. U • Untanking the regulator is not to be performed in the field, except for those Substation regulators which are not practical to move due to their size. 3 . n 3. Untank the regulator. NOTE: Avoid removing the main core-and-coil assembly from the oil, except when a winding failure occurs. Use blocking between the cover and tank lip to suspend the core and coil assembly within the oil until inspection of the tap changer or other maintenance is complete. If it is necessary to expose the main core and coil to air, follow the manufacturer’s instructions before returning the unit to service. 4. Make a thorough inspection of all internal components – particularly noting contact wear, springs, and chain • Determine the remaining contact life by noting the amount of contact erosion which has occurred as compared to the amount of arcing material remaining.
  6. Page 101 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 101 of 297 When inspecting contact wear, inspect both stationary and movable contacts. • Refer to manufacturer’s instruction manual for contact wear guidance. • Be especially watchful for inadequate contact pressure, unequal pressure on both sides of contacts, contact alignment and carbon formation on any portion of all contact structures. Check for signs of oil leaking from any seal or gasket. Check all chain and gear parts carefully for chipped or broken teeth or excess backlash in its operation. Check all connections for tightness and overheating. Operate the mechanism through its entire range to ensure there is no mechanical interference and that contact alignment is proper on all steps. Adjust the tap changer to ensure it goes through the neutral position. Operate the regulation equipment to the fully raised and the fully lowered positions to check the upper and lower limit switch operation. Ensure the drive mechanism stops properly on position. Check the counter for proper operation. Use cleaning insulating oil with the proper dielectric strength to refill the regulator. Perform a power factor test (Doble) to determine the insulation integrity of the regulator. Perform an insulation resistance test (megohmmeter). Perform a Transformer Turns Ration Test. Check internal and external motor capacitors. Return the regulator to CMS/DERF Shop for a more thorough repair or disposal if it cannot be made to function within specification. • 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. When the inspection is complete, the unit is ready for service. Return to Service The return to service procedure is essentially the reverse of the procedure used to remove the regulator from service. Energize the regulator only with regulator on neutral tap position. See the appended procedure, co-1040 for details. Siemens MJ-X└ Controls Use the following procedure when placing and MJ-X└ equipped regulator into or out of service. Note that these steps are only for placing the regulator into or out of service. You must still perform the inspection steps, such as the power factor test, TTR, insulation test, etc. that are in the previous section.
  7. Page 102 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 102 of 297 Placing the regulator into service: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Place the Auto/Manual switch in the Bypass position. Place the Raise/Lower switch in “off”. Make certain the regulator is in the Neutral (N) position. Turn the voltage Power Source switch to “off”. Remove the control power fuse. Close, sequentially, the source and the load switches. Open the bypass switch. Visually observe that the bypass circuit has opened. Replace the control power fuse. Place the voltage power source switch to “Normal”. Removing the regulator from service: 1. Place the Auto/Manual switch in the Bypass position. 2. Place the Raise/Lower switch in “Off”. 3. Make certain the regulator is in the Neutral (N) position. If independent checks of the position indicator and the neutral light indicator do not confirm the neutral position, bypassing must not be attempted. In such an event, de-energize the system to remove the regulator from service. 4. Turn the voltage power source switch to “off”. 5. Remove the control power fuse. 6. After ensuring the regulator is in Neutral (N), close the bypass switch. 7. Open sequentially, the load and source switches. 8. Perform the applicable action: • For single phase or grounded wye connection, make sure the high voltage disconnect switches are opened. • For closed delta connection, ensure all regulators in the bank are bypassed and isolated. 9. Exercise appropriate care in the removal of the regulator. High voltage will still be present at the bypass switch and the source and load switch terminals. Remove the ground connection last.
  8. Page 103 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 103 of 297 APPENDIX 9 RECLOSERS AND SECTIONALIZERS
  9. Page 104 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 104 of 297 5.44 Automatic Circuit Reclosers (ACR) & Sectionalizers General Description Reclosers sense and interrupt fault currents and automatically restore service after momentary outages. The automatic circuit recloser is essentially a self- contained device with the necessary intelligence to sense over currents, to time and interrupt fault currents, and to re-energize the line by reclosing automatically. If a fault is permanent, the recloser locks open after a preset number of operations, isolating the faulted section from the main part of the system. Automatic circuit reclosers installed at Northeast Utilities: • Can be either Single-phase or Three-phase • Can have either Oil or Vacuum Interrupters • Can have either Hydraulic or Electronic Controls • Can be either Oil or Epoxy Insulated Single-phase reclosers are used to protect single-phase lines such as branches or taps of a three-phase feeder. They can also be used on three-phase circuits where the load is predominantly single phase. Single phase reclosers installed at Northeast Utilities include (not a complete list) Type H, 4H, V4H, L, V4L, VXE15, D, E, 4E, V4E, and DV. (See Appendix 2.) Three phase reclosers are used in multiple applications: As main feeder breakers at the substation source, as sectionalizing and tie devices with over current protection within auto loops; and for over current protection on major three phase laterals. Reclosers within auto loops operate based on local current and voltage sensing to resectionalize circuits to limit the number of customers interrupted by a fault on a circuit backbone. The majority of three phase reclosers are monitored as part of the DSCADA System, providing remote control and data acquisition capability. Three phase reclosers installed at Northeast Utilities include (not a complete list) Type 6H, V6H, W, WE, VWE, WVE27, VWVE27, NOVA27, WVE38X, VWVE38X, VSO12, and NOVA38. (See Appendix 2.) Recloser Controls provide the intelligence that enables a recloser to sense overcurrents, select timing operation, time the tripping and reclosing functions, and finally lockout the circuit when required. There are two basic types of controls used: an integral hydraulic control or an electronic control located in a separate cabinet. • Hydraulic recloser controls are used in most single-phase reclosers and in threephase recloser types 6H, V6H, and W. The controls are an integral part of the recloser. With this type of control, an over-current is sensed by a trip coil that is connected in series with the line. • Electronic recloser controls are used in most three-phase reclosers and in the single-phase Cooper recloser types VXE and NOVA.
  10. Page 105 of 297

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 28, 2026 OCC- 888 Attachment 2 Page 105 of 297 5.44.1 Inspection and Maintenance Schedules Table 1 –Recloser Maintenance Intervals Recloser Contacts in Vacuum Contacts in Oil Check – Energized S/S 1M 1M Check – Energized (SCADA) – Pole Top (Note 1) 1Y 1Y Check – Energized (Non-SCADA) Pole-Top Electronic 2M 2M Check – Energized Pole-Top Hydraulic 1Y 1Y Inspection – Energized (Infrared) 1Y 1Y Major Maintenance – De-Energized N/A 12Y Major Maintenance – Triggered by Contact Life or Duty Cycle. (Note 2) <95% < 95% Major Maintenance – Triggered by Fault Operations 200 N/A Major Maintenance Evaluation– Triggered by Operations Count. (Note 3) N/A 100 Maintenance Schedule Time-Directed Maintenance Condition-Based Maintenance Scheduling Requirements Schedule maintenance of the attached Potential Transformer at the same time as the recloser, if applicable. In Table 1, the type of maintenance is listed in the left column and the interval required for that type of maintenance is listed in the right column. For example, the interval for an Energized Check for Substations is 1M (or 1 month). The abbreviations used for the intervals are: A/R = As Required M = Month, i.e. 1M = 1 Month Y = Year, i.e. 2Y = 2 Years Note 1 – SCADA Pole Top reclosers are monitored continuously and do not require the monthly checks. They will be inspected for physical damage on an annual basis. Note 2: Duty cycle is calculated based on the number and magnitude of fault interruptions. The duty cycle is calculated and monitored by all electronic controllers (except Form 3A). This is equivalent to remaining contact life. Note 3: Use the operations count for Hydraulic controls and Form 3A controls. Note 4: Scheduled Major Maintenance for oil filled Reclosers may be deferred if a capital replacement project has been formally established and is being implemented on a 12 year replacement plan
Words on different pages

Text of OCC-890_Final.pdf

Extracted from the file · 1 page · 553 characters

Words on different pagesRead the text of OCC-890_Final.pdf

As listed on the current system

Question(s) Answered 888, 889, 890 (The Connecticut Light and Power Company) Date Filed: 10/09/2026

This filing on the current system (opens in a new tab)