  1. Page 15 of 81

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 15 of 81 DE 24-070 - 15 - adjustment will be excluded in calculating the subsequent year’s earnings share. Hearing Exhibit 9, Bates Pages 1408-1409. In addition to these features, the Company proposed a variable described as “KBar,” which, according to the Company, is intended to provide “supplemental revenue” to support “necessary infrastructure investments over and above the I-X price-cap formula.” Hearing Exhibit 9, Bates Pages 1394-1395. (The Company provided lengthy descriptions of “K-Bar” in its responses to Commission Record Requests 1 and 7). In justifying its request for an alternative regulation framework, including the embedded formula, the Company pointed to its proposed alternative regulation approach as prospectively providing the best way to address the capital needs of the Company’s distribution system, as outlined in the testimony of Eversource’s personnel. Hearing Exhibit 9, Bates Pages 1357-1374; 1962-1967; 1991-2003; 22222237. The Company also pointed to its “Distribution Solutions Plan,” Hearing Exhibit 9, Bates Pages 2013-2207, as further justification for its alternative regulation approach. The Company further stated that “[t]he annual K-bar revenue adjustment within the [alternative regulation] plan provides a measure of revenue support within the [alternative regulation] formula that serves as a substitute for a capital-cost recovery mechanism or step adjustments that adjust rate base, to create administrative efficiency that simultaneously incentivizes cost controls…[t]he [alternative regulation] plan not only creates a four-year stay-out period (with a possibility of an extension), but it would also eliminate step adjustments during that period – there would be no distribution rate proceedings until the end of the [alternative regulation] term.” Hearing Exhibit 9, Bates Pages 1375; 1380-1384; 14281430; 1812; Hearing Exhibit 10, Bates Pages 13; 16-18; 22; 33-34; 1012). As a
  2. Page 16 of 81

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 16 of 81 DE 24-070 - 16 - condition to be bound upon the Company if the Commission approves its alternative regulation proposals, the Company agreed not to file its next distribution rate case until 2029. As part of its proposed alternative regulation framework, the Company proposed the application of a series of performance metrics to monitor the Company’s progress, specifically: the System Average Interruption Duration Index (SAIDI), which is calculated as the System Average Interruption Frequency Index (SAIFI) multiplied by the Customer Average Interruption Index, which relate to customer power outages; Months Between Interruption (MBI), which measures the number of months between when an average customer could expect to experience a sustained power interruption; and a series of Customer Satisfaction indices. Hearing Exhibit 9 at Bates Pages 19251946. As part of its rate case filing, Hearing Exhibit 9, the Company presented a “Distribution Solutions Plan,” Id. at Bates Pages 2013 to 2207, with the accompanying testimony of its executives Mr. Lavelle Freeman, Ms. Jennifer Schilling, Ms. Elli Ntakou, Mr. Gerhard Walker, and Mr. Paul Renaud, Id. at Bates Pages 1949 to 2012, presenting the Company’s internal planning approaches to improving system reliability throughout its several planning regions. Through the Company’s executive, Mr. Horton, and his colleagues, the Company provided updates to its expected capital investment budgets to be subject to the proposed alternative regulation framework, the most up-to-date being presented in Attachment RR-006(b) (REVISED), Page 12, in response to the Commission’s Record Request 6. Mr. Horton confirmed, see 5/6/2025 Hearing Transcript (Tr.) at 218-219, and the Company elucidated in its Closing Argument, that “In its initial filing the
  3. Page 17 of 81

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 17 of 81 DE 24-070 - 17 - Company also proposed to explore and, if appropriate projects were identified, implement company-owned solar and co-optimization projects during the alternative regulation term (Hearing Exhibit 9, Bates Pages 2009-2011). The Company is not seeking approval for either Company-owned solar or co-optimization projects. The Commission will review any Company-owned solar project proposal or co-optimization project in separate proceedings. If approved by the Commission, the Company suggests that the costs of any Company-owned solar or co-optimization project be reflected in the K-bar once a project is complete and found to be used and useful. See Docket Tab #289 at 44. B. Other Parties’ Responses to Eversource’s Proposals; Company Rebuttals Of the various other parties to this proceeding, AARP (Hearing Exhibits 31 and 32); Ms. Mary Ellen O’Brien Kramer (Hearing Exhibit 33); Walmart, Inc. (Hearing Exhibit 34); the DOE (Hearing Exhibits 14 through 21; 40-41); and the OCA (Hearing Exhibits 22-27) filed written testimony. In turn, after the Commission invited all parties to file closing statements summarizing their arguments following our hearings, CLF (Docket Tab #280), AARP (Docket Tab #281), Walmart, Inc. (Docket Tab #282), the OCA (Docket Tab #283), Ms. Kramer (Docket Tab #284), and the DOE (Docket Tab #286), responded and filed such Closing Statements, in advance of the Company filing its own Closing Statement. In the Commission Analysis section below, the Commission will address the arguments and counterarguments of the Company and the other parties, as needed, in our findings of fact and application of law.
  4. Page 18 of 81

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 18 of 81 DE 24-070 - 18 - The Company’s responses to the positions of the various parties can be found in the Company’s written Closing Argument, Docket Tab #289, and in its Rebuttal Testimony, Hearings Exhibit 10. The parties and intervenors rejected the Company's stated need for alternative ratemaking, with the partial exception of CLF, which recommended a “stakeholder process” to evaluate the mechanism and develop appropriate performance metrics. The DOE and the OCA advocated for significantly lower ROE: the OCA recommended an 8.13 percent ROE, while the DOE recommended 9.50 percent ROE. The OCA, AARP, and Ms. Kramer all advocated for a lower fixed customer charge than that proposed by the Company (as discussed below). Furthermore, in the testimonial presentations of its witnesses, including the DOE’s consultant, Ms. Donna Mullinax, see e.g., Hearing Exhibit 41, the DOE recommended a series of Adjustments to reflect recommended disallowances to the Company’s rate-base and O&M accounting, as discussed below. II. COMMISSION ANALYSIS A. Partial Adoption of DOE Recommendations re: Permanent Rates For the various reasons delineated below, the Commission has determined to adopt some aspects of the DOE’s recommendations related to adjustments for the Company’s proposals regarding rate base, O&M expense, ROE, and Eversource’s capital ratio. The Commission carefully considered all the parties' inputs, but applied the DOE’s methodology. Notably, the analysis in this section includes the final Eversource permanent rate request of $102.8 million, originally $182 million, and does not include the $35 million PBR request.
  5. Page 19 of 81Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 19 of 81 DE 24-070 - 19 - 1. Disposition of DOE-Recommended Adjustments to Rate Base, O&M For the test year 2023, the Company first seeks a rate increase using the traditional cost-of-service ratemaking structure, on which the alternative ratemaking structure would then build for rate adjustments in the future. In evaluating the Company’s proposals, related to the inclusion of capital investments in rate base and expenses in O&M accounting, the Commission must balance the Company's commercial interests against those of its customers in paying the lowest reasonable cost for distribution service. See RSA 363:17-a. Aside from this imperative, the standards for determining the Company’s rate base and O&M expenses for inclusion in distribution rates are flexible, subject to pragmatic adjustment 7. Appeal of Conservation Law Foundation of New England, Inc., 27 N.H. 606, 636-639 (1986), citing Power Comm’n v. Hope Gas Co., 320 U.S. 591, 602 (1944) (‘Hope’); Bluefield Co. v. Pub. Serv. Comm., 262 U.S. 679, 690-691 (1923) (‘Bluefield’); New Eng. Tel. & Tel. Co. v. State, 98 N.H. 211, 219 (1953) (other citations omitted). RSA 378:28 establishes that “[t]he [C]ommission shall not include in permanent rates any return on any plant, equipment, or capital improvement which has not first been found by the [C]ommission to be prudent, used, and useful.” RSA 378:28. The New Hampshire 7 The New Hampshire Supreme Court has held: “To summarize the results of the ratemaking process that we have considered significant for this case, we may say that in a proceeding to set rates the [C]ommission must set a reasonable rate of return to be allowed on cost-less-depreciation of used and useful property, provided that cost may not include anything imprudently wasteful. The determinations of reasonable rate of return, prudence, and usefulness alike require the exercise of judgment and discretion in determining the recognition that is appropriately due to the competing interests of the [C]ompany and its investors and of the customers who must pay the rates to provide the revenue permitted. It should now be apparent that a rate or structure of rates charged to customers is reasonable within the meaning of the statute [RSA 378:28] when it will produce an amount of revenue that has been determined, and limited, by balancing or relatively weighing investor and customer interests. The [C]ommission must exercise its judgment in balancing those interests when it determines the allowable extent of operating expenses, when it identified the property whose prudently incurred costs is included in the rate base, and when it sets a reasonable rate of return on that rate base. Thus a reasonable rate is the rate resulting from a process that must consider the competing interests of investor and customer and must determine the appropriate recognition that each deserves.” Appeal of Conservation Law Foundation, 127 N.H. at 638.
  6. Page 20 of 81

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 20 of 81 DE 24-070 - 20 - Supreme Court has elaborated that, when the Commission is analyzing the question of prudence, “[i]f the entire investment in a given asset was foreseeably wasteful, the entire investment must be excluded; if only some of the constituent costs attributable to a given asset were foreseeably wasteful, the value for rate base purposes of the investment in this asset must be reduced accordingly,” with exclusion from rate base of costs that the Company should have foreseen as wasteful. Appeal of Conservation Law Foundation, 27 N.H. at 637. For the question of expenditures and investments meeting the “used and useful” standard of RSA 378:28, New Hampshire case law has invested the Commission with flexibility in determining what may qualify as used and useful, “thus necessarily providing scope for policy judgments.” Id. The New Hampshire Supreme Court grants broad discretion to the Commission in its approach to these responsibilities. Id. at 615-616, citing LUCC v. Public Serv. Co. of N.H., 119 N.H. 332, 340 (1979) (citations omitted). See also Appeal of Morin, 140 N.H. 515, 517518 (N.H. Compensation Appeals Board has ‘broad discretion over the conduct of its proceedings, including its hearings,’ and ‘[o]rders or decisions of the [B]oard shall not be set aside or vacated except for errors of law, unless the [Supreme Court] is satisfied, by a clear preponderance of the evidence before it, that such order is unjust or unreasonable.’), citations omitted. For our assessment of the Company’s proposals, we turn to the parties’ and intervenors’ proposals, with particular attention paid to the DOE’s recommended adjustments to the Company’s revenue requirement and the supplemental testimony of the DOE’s witness, Ms. Mullinax. See, e.g., Hearing Exhibit 41. We address each recommendation in turn below.
  7. Page 21 of 81

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 21 of 81 DE 24-070 - 21 - In general, as summarized in Ms. Mullinax’s testimony, Hearing Exhibit 41, the Company eventually presented a requested revenue requirement (deficiency) of $102,823,201 (as presented in Hearing Exhibit 39), a reduction from the Company’s originally stated revenue deficiency of $181,898,881. This reduction resulted primarily from the Company’s removal of storm costs and 2024 capital investments, as recommended by the DOE, for consideration in future proceedings. Notably, this analysis does not include the additional $35 million requested by the Company for PBR associated with the years 2024 and 2025. The DOE requested additional adjustments, further reducing the Company’s revenue requirement by $42,889,149, for a DOE-recommended revenue requirement of $59,934,052. Hearing Exhibit 41 at Bates Page 4. Ostensibly, 19 discrete adjustments are being presented for the Commission’s consideration by the DOE. However, upon inspection, there is one “Adjustment” (Adjustment 16), that is illustrative, insofar as the matter being addressed by the DOE (Unrecovered Storm Costs), that was deferred by the Commission for a future phase of this proceeding, one “Adjustment” (Adjustment 7) is a blank space in Ms. Mullinax’s list, labeled, “No Adjustment,” and one “Adjustment” (Adjustment 4) has been withdrawn by the DOE, after the Company had accepted the crux of the recommendation. The original list of these Adjustments was presented by the DOE, for the most part, in Ms. Mullinax’s original direct testimony, Hearing Exhibit 19, while the weather normalization of Test-Year Billing Determinants, discussed in Adjustment 6, was addressed by Mr. Clark’s direct testimony on behalf of the DOE, Hearing Exhibit 14, and incorporated by reference in the Joint Testimony of Messrs. Dudley, Willoughby, and DeVirgilio, Hearing Exhibit 17. Furthermore, the Disallowed Plant in Service
  8. Page 22 of 81

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 22 of 81 DE 24-070 - 22 - matters were primarily addressed in the Dudley-Willoughby-DeVirgilio Testimony, hearing Exhibit 17, and in the Joint Testimony of Ms. Nixon and Ms. Trottier, Hearing Exhibit 21. Adjustment 1: Disallowed Plant in Service The DOE recommended disallowances to the Company’s rate base for the Commission’s consideration, see Docket Tab #286 at 29-45. The Commission will address those recommendations in turn. The DOE recommended that the Company’s Project DG9R, involving “field design and construction to accommodate customer installation of Distributed Energy Resource (DER) (e.g. solar) funded by customer or developer,” amounting to $650,000, be disallowed from rate base, as the Company’s Project Costs Summary shows that all project costs would be reimbursed by the customer in question, in accordance with the Company’s Tariff. Hearing Exhibit 10 at Bates Pages 771-772, 775. In response, the Company argued that some portion of unspecified “non-reimbursable” costs for this project could still exist. Docket Tab #289 at 90-92. Having reviewed these arguments, the Commission CONCURS with the DOE that this project should not be allowed in rate base, due to the costs of the project having been reimbursed by the customer installing the distributed energy resource(s). The DOE further advocated for the elimination of an entire category of capital projects that the DOE characterized as “incomplete,” totaling $27,858,763, also described as “multi-year projects.” Hearing Exhibit 17 at Bates Page 24. Likewise, the DOE recommends exclusion of $3,635,185 of ongoing project costs associated with projects that were the subject of past step adjustments approved by the Commission for the Company, arguing that the “complete” status of these projects at the time that
  9. Page 23 of 81Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 23 of 81 DE 24-070 - 23 - the step increases were approved serves as a bar on ongoing inclusion of incremental costs in the Company’s rate base. Hearing Exhibit 17 at Bates Pages 29-31. The Company argued that these costs constituted “carry-over” costs, that extend through multiple years, for which recovery was appropriate by the Company. Docket Tab #289 at 87-90. Having reviewed these arguments, the Commission agrees with the Company that the DOE’s arguments against those projects, including those projects subject to past step adjustment reimbursements in the rate base, are not compelling; therefore, we REJECT those recommended disallowances by the DOE. The DOE further recommended disallowance of $311,739 for eight Electric Vehicle (EV) charging stations at the Company’s properties in Portsmouth and Nashua (with four chargers installed at each location), arguing that the Company failed to show any customer benefit for these EV stations from its expenditure. See Hearing Exhibit 10 at Bates Pages 227-229. DOE recommended disallowance insofar as the stations are not accessible to the public, nor did the Company provide any evidence of its assertions that the EV stations were necessary to provide safe and reliable services for the benefit of its customers, and enabled the attraction and retention of qualified employees. Id. The Company argued in response that the DOE’s definition of customer benefit was too narrow and that the expenditure was prudent. Docket Tab #289 at 9596. Having reviewed the record and these arguments, we CONCUR with the DOE that the Company has failed to meet the burden to justify this expense; therefore, we adopt this disallowance recommendation. The DOE made another recommendation on EV Make-Ready infrastructure at the Monadnock Community Market Cooperative in Keene, amounting to $139,786 in costs, which the DOE argued would be covered by the customer as a line-extension
  10. Page 24 of 81

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 2, 2026 OCC-905 Attachment 2 Page 24 of 81 DE 24-070 - 24 - cost under the Company’s Tariff. Docket Tab #286 at 39-40; see Hearing Exhibit 10 at Bates Pages 242-244; 796-811; Hearing Exhibit 17 at Bates Page 542. In response, the Company asserted that these costs were part of the scope of the settlement agreement approved by the Commission in Docket No. DE 21-078. Docket Tab #289 at 103-105. Having reviewed the record and these arguments, we CONCUR with the DOE that, as the customer should cover these costs under the Company’s Tariff, they should not be included in the rate base. The DOE further recommended another disallowance from rate base related to the Company’s expenditure of approximately $1.8 million ($1,247,000 in 2022 and $607,773 in 2023) for diesel trucks with a battery-power capability. Docket Tab #286 at 43; Hearing Exhibit 17 at Bates Pages 60-61. The DOE argued that the Company was under no mandate to acquire this equipment or to abide by New Hampshire’s anti-idling rules, and failed to produce adequate evidence to support its assertions of cost savings associated with it; therefore, the $1,854,773 associated with this investment should be disallowed. In response, the Company argued that this investment did reflect New Hampshire’s policy against idling and offered $52,000 in benefits attributable to annual fuel savings. Hearing Exhibit 10 at Bates Page 258; Docket Tab #289 at 106-107; 5/23/25 Tr. at 27. Having reviewed the record before us and these arguments, we CONCUR with the DOE that the $52,000 in cost savings pointed to by the Company, compared to the more than $1.8 million in outlay, do not justify this investment in the absence of a New Hampshire EV mandate, therefore, we ACCEPT the DOE’s recommendation for this disallowance of imprudent investment. The DOE further argues that for the Company’s investment in the PowerClerk computer program (Project #IT224477), the costs presented by the Company of

Text of OCC-905 Attachment 3.pdf

Extracted from the file · 26 pages · 51,406 characters

Text of OCC-905 Attachment 4.pdf

Extracted from the file · 128 pages · 333,681 characters

As listed on the current system

Question(s) Answered 902, 905 (The Connecticut Light and Power Company) Date Filed: 10/21/2026