    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 1 of 34 Distribution Tri-State Capital Project Approval Process Distribution Tri-State Capital Project Approval Process JA-DE-2026-A, Rev. 0 Process Owner: Effective Date: 05/04/2026 Jeffrey Richard, PMP Jeffrey Richard, PMP Director, Distribution Engineering Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 1
  2. Page 2 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 2 of 34 Distribution Tri-State Capital Project Approval Process Copyright 2026 Eversource Energy Proprietary and Confidential All Rights Reserved 410 Sheldon St Hartford, CT 06106 Phone [phone removed] Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 2
  3. Page 3 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 3 of 34 Distribution Tri-State Capital Project Approval Process Contents Table of Contents 1. Purpose 2. Affected Groups 3. Responsibilities 4 4 5 4. General Instructions 5. Instructions for Planned Projects $499k or less (Annuals) 8 15 6. Instructions for Work Orders (Wos) that exceed $500k 7. Definitions & Acronyms 8. Revision History 15 16 18 Attachment A, Solution Design Committee Charter Attachment B, State Project Approval Committee (State PAC) Charter 19 22 Attachment C, Distribution Tri-State Initial Funding Template Attachment D, Distribution Tri-State Initial Funding Template - Guide Attachment E, Distribution Tri-State Partial/Full Funding Template 27 28 29 Attachment F, Distribution Tri-State Partial/Full Funding Template - Guide Attachment G, Distribution Tri-State Supplement Authorization Form Template 30 31 Attachment H, Distribution Tri-State Capital Project Supplement Process Attachment I, Distribution Project Authorization Checklist Attachment J, Distribution Tri-State Project Approval Process Flow Chart 32 33 34 Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 3
  4. Page 4 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 4 of 34 Distribution Tri-State Capital Project Approval Process 1. Purpose This process provides instructions and guidance on the process for initiating and then obtaining technical and financial approval for Distribution Line (Distribution Work conducted outside of the Substation) capital projects. This job aid will focus on project initiation, solution vetting by the Solution Design Committee (SDC), and approval of the Project Authorization Form (PAF) by each of the state Project Approval Committees (state PACs) for distribution line projects. The authorization forms and guides used for each funding level can be found in the appendix. This process document supports the guidance contained in Accounting Policy Statement 1 (APS01), Operations Project Authorization, which can be found in the appendix. 2. Affected Groups This as described in Responsibilities and General Instructions, Distribution Engineering along with the SDC and state PAC committees will have primary responsibility for the project review and approval process. The following general groups will also be affected by this process as their participation is critical to the successful initiation, development, review, and approval of capital projects. Distribution Engineering, Transmission Line, Substation Design, Substation Technical, Protection and Controls, and Grid Modernization o Note: Substation T&D and Transmission follow JA-AM-2001-A Rev:7 for their Capital Project Approval Process. Construction Scheduling (IP&S) Licensing and Permitting Environmental Siting and Project Services Procurement Investment Planning (IP) Operations Engineering Project Controls Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 4
  5. Page 5 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 5 of 34 Distribution Tri-State Capital Project Approval Process 3. Responsibilities 3.1 Project Initiator In general, for Distribution projects, the project initiator is responsible for establishing a project/program by securing initial funding. The initiator is responsible for development of the establishing document(s), typically an initial funding request (IFR). The project initiator will be responsible for securing funding from state PAC for Distribution line projects. For applicable projects (See Section 3.4.1 below for details), the project initiator is responsible for the development of Partial PAF and presentation of the project’s preferred and alternative solutions to SDC. The project initiator will be responsible for; coordinating conceptual engineering activities and conceptual cost estimates (-25%/+50%) to support alternatives analysis; after detailed engineering activities and developing an updated +/-25% planning grade cost estimate. The project initiator will then be responsible for updating the PAF and securing full funding from the state PAC. Once a project is fully approved and funded, project ownership transfers to the field operations group for project execution and closeout phases. 3.2 Distribution Project Controls Group The Distribution Project Control (DPC) group is responsible for all projects once added to the respective operating company’s Engineering Project Management Portal; The DPC will be assigned based on which operating company is funding the project. The DPC will support the project lifecycle from inception through completion and is also responsible for all project tracking within the respective states’ Engineering Project Management Portal. The DPC will ensure that the funding is reflected in the appropriate year, project members are appropriately listed, the correct Project Type is reflected and agrees with the project information that is inputted in PowerPlan. The DPC is responsible for overseeing the timely flow of capital projects from partial funding authorization through full funding as well as supplemental funding, as needed. Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 5
  6. Page 6 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 6 of 34 Distribution Tri-State Capital Project Approval Process 3.3 Project Sponsor Typically, the Project Sponsor will be the director of the project initiator. The Project Sponsor will be responsible for review and approval of project documents before they are submitted to the committees for approval. 3.4 Solution Design Committee (SDC) The SDC will serve as solution development gate keepers to ensure the best solution is selected, ensure guiding principles are followed, and drive standardization. SDC will review project alternatives, scope, and conceptual grade cost estimates during the solution vetting process. More information on solution vetting can be found in Section 4.4 and the full responsibilities of the SDC are contained in Attachment A, Solution Design Committee Charter. 3.4.1 Project Types The SDC will review and approve solutions for the following Distribution project types: • System Planning – Reliability, Resiliency, Regulatory and Capacity Projects Distribution Engineering – Programs (Pole Integrity, , etc.), Reliability, system performance (capacity, sectionalizing etc.) customer request, line relocations, asset health and aging infrastructure, Program releases with significant scope in addition to the program. • Distribution Interconnection Projects – Projects on track to sign Interconnection Agreements may be reviewed by the SDC at the request of the sponsoring engineering director. State PAC member directors will also have discretion to determine whether a specific project or program will require review and approval by the SDC. In cases where there is a quorum of PAC representatives present at the SDC, a partial funding request may be presented and voted on, in conjunction with the same project at SDC. 3.5 State Project Approval Committees (CT PAC, MPAC, and NH PAC) The state PACs will be responsible for the review and approval of the technical and financial merits of Distribution projects. There will be three different project approval committees to review and approve the projects: one from each state (CT PAC, MPAC, and NH PAC). The state PACs will review partial and full funding requests to develop detailed engineering and to support early establishment of projects in Eversource financial and scheduling systems. Regardless of cost, if partial funding requests is required it shall adhere to PAC approval processes and shall include a schedule by which engineering plans to complete detailed engineering, produce a planning grade cost estimate and present for full funding authorization. The state PAC committee chair will track projects that are given approval for Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 6
  7. Page 7 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 7 of 34 Distribution Tri-State Capital Project Approval Process partial funding and ensure timely submission, review, and approval of PAFs for full funding authorization. Distribution projects looking to secure full funding authorization shall develop PAFs containing a planning grade (+/-25%) cost estimate. The full responsibilities of the state PACs are contained in Attachment B, State Project Approval Committee (State PAC) Charter. 3.5.1 Project Types The state PACs will review and approve the following project types: All distribution projects greater than $500,000. Note that per APS01 and Operations executive management, all other underground, overhead, and underground-overhead mixed distribution projects under the dollar thresholds listed below but over $500,000 total cost require PAF documentation. The approving director(s) for each state can use their discretion to require any projects to be reviewed at the state PAC. CT requires new service, CDOT, and DER projects that are >=$250k be required to have a PAF and be presented at CPAC. Depending on project type, projects that are $100K or greater but less than $500K may require PAF documentation at the discretion of the PAC committees, except for emergency projects, which will only require PAFs for projects $500K or greater in all cases. These PAFs will be reviewed, presented, uploaded into the project portal, and approved in PowerPlan. NH Requires all non-emergent work that are >=$250k be required to have a PAF and be presented at NHPAC. Emergency projects, which will only require PAFs for projects $500K or greater in all cases. These PAFs will be reviewed, presented, uploaded into the project portal, and approved in PowerPlan. MA follows APS-01. All projects >=$500k require projects. All WO’s that exceed $500k will require PAFs. These PAFs will be reviewed, presented, uploaded into the project portal, and approved in PowerPlan. Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 7
  8. Page 8 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 8 of 34 Distribution Tri-State Capital Project Approval Process 3.6 Cost Estimating For Distribution projects, partial funding will be estimated using high level estimation units. This estimate will be generated by the engineering team to generate a -25%/+50% grade estimate and it will be presented at SDC and state level PAC meetings. Construction grade estimates will utilize the estimation units from Maximo in conjunction with any additional contractor bids to generate a full funding estimate . A 10% contingency will be added, based on the line-item baseline budget (directs and indirect) to the full funded estimate and will be included in the financial tables within the full funded PAF. Once the estimates from Maximo and the bid results are analyzed the results will be presented at state level PAC meetings for approval. 4. General Instructions The process to proceed with each successive phase of a capital project is designed to ensure that there is a valid need, the right solution alternatives are evaluated, the technical approach is sound, and resources are budgeted and prudently spent. The overall process flow for Distribution projects is depicted in Attachment J, Distribution Project Approval Process Flow Chart. The initiation and major engineering and approval phases of the process flow charts correspond to the sections below. These general instructions are for the project types listed in Sections 3.5.1. Refer to Section 5 for instructions for planned distribution projects less than or equal to $500,000. Refer to Section 6 for instructions for securing approval of emergent work. 4.1 Project Initiation Following the identification of a project need a project number will be assigned. Project initiators can reach out to their supervisor or manager for assistance securing a project number. Project initiators will then complete an Initial Funding Request (IFR) and submit it to the Lead and/or Manager for approval. Refer to appendix, Attachment C, Initial Funding Request Template and Attachment D, Initial Funding Request Form – Guide. The initiator will be required to state the project need and objectives and include an explanation of the funding request amount. The IFR should not include funding for detailed engineering. The regional manager may decide to approve the request directly or may request that the initiator present the request for input and feedback to the state SDC or PAC meeting. Once an IFR is approved, the project initiator will upload the approved Initial Funding Request in the Engineering Project Management Portal and Investment Planning will be notified to submit it for delegation of authority (DOA) approvals in PowerPlan, the Eversource software tool for financial approval. The initial funding is obtained once delegation of authority has been performed through PowerPlan in accordance with APS01 (See Section 4.6.3 for more information on Delegation of Authority Policy). The DPC will be notified by the Engineering Project Management Portal when the DOA’s are completed in PowerPlan. Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 8
  9. Page 9 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 9 of 34 Distribution Tri-State Capital Project Approval Process 4.2 Project Initiation for Programs Initial funding can also be requested at the program level using the Partial/Full Project Authorization Form, found in the appendix. The funding can be used to advance specific project scope under an approved program. Sections 4.6.1 and 4.6.2 contain more information on full approval of programs and program level releases. 4.3 Conceptual Engineering The project initiator should develop the preferred and alternates for the project during this stage. Incorporate designs from standards library and develop scope and major equipment lists for all alternatives under consideration. Conceptual engineering of all competitive alternatives including early field review and desktop analysis. Identification of key project risks with the appropriate level of detail with respect to constructability, routing, outage planning, and applicable mitigation actions, siting and permitting, environmental impacts, community and external stakeholder impacts, site control, procurement, etc. Identification of any land right’s needs. Develop project strategies to mitigate identified risks. Non-Wire Alternatives (NWA) solutions should be evaluated and estimated where applicable by state regulations. Conceptual grade cost estimates (-25%/+50%) for all competitive alternatives (at least the preferred solution and leading alternative). Order of magnitude cost estimates (-50%/+200) should be provided for alternatives that are not competitive with the preferred solution. The project initiator will then recommend a preferred solution and document the rationale for the choice of preferred solution and present at SDC and then at the state PAC meeting. Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 9
  10. Page 10 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 10 of 34 Distribution Tri-State Capital Project Approval Process 4.4 Solution Vetting (SDC) Prior to proceeding with detailed engineering of the preferred solution, more comprehensive projects and asset condition projects at the program level will need to be reviewed and approved. The project initiator will present the preferred solution and the alternatives at SDC. The SDC will review the Partial PAF and confirm that the project initiator has selected the best solution. The Partial PAF will require a statement of the project need and objectives, documentation of the alternatives analysis, scope and major equipment list for the preferred solution, and a conceptual grade cost estimates for the preferred solution and any competitive alternatives. The form can be found in the appendix. The full responsibilities of the SDC are contained in Attachment A, Solution Design Committee Charter. Once reviewed and approved by the Solution Design Committee, the project initiator will proceed with updating the Partial PAF document and proceed to obtain State PAC committee solution approval. 4.5 PAC Design Approval Once the project initiator has addressed all comments from SDC, the Lead and/or Manager will review and approve, then the project is ready to be presented at state PAC for PAC Design Approval. The Partial/Full Funding Template, Attachment E, will be updated based on the comments from SDC. Follow Attachment B, State Project Approval Committee (State PAC) Charter for formal approval process. Once all voting members agree of the parameters of the project/program, PAC Design Approval is granted within the Engineering Project Management Portal. If additional funds are required outside of what is being funded initially to procure land, Environmental permits (typically ROW work), Environmental studies, and order any additional special material not typically stocked than the PAF must be approved for Partial Funding and then routed in Powerplan for DOA approval. In most cases, Powerplan routing is not needed, however, if pre-construction costs are expected to exceed $500k and be charged to the project, Powerplan routing is required. PAC Design Approval may be granted in a single meeting that combines the SDC and PAC Design Approval, or the two components may be addressed in separate meetings. This decision depends on several factors, including—but not limited to—the number of projects on the agenda and the availability of voting members. Once the PAC Design Approval is approved, the project initiator will upload the approved Partial Funding Request in the Engineering Project Management Portal. If timing is a concern, PAC Design Approval can be granted by the voting members via email, and the Engineering Management Project Poral can be updated, in lieu of waiting until the next state PAC meeting. PAC Design Approval is needed before detailed design can start. Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 10
1 page match

Text of OCC-927_Final.pdf

Extracted from the file · 4 pages · 12,932 characters

Words on different pagesRead the text of OCC-927_Final.pdf

As listed on the current system

Question(s) Answered 923, 925, 927 (The Connecticut Light and Power Company) Date Filed: 10/20/2026

This filing on the current system (opens in a new tab)