    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 14 of 34 Distribution Tri-State Capital Project Approval Process uncontrollable change to the project resulting in higher project costs. Indirect rate(s) increase from the full funding estimate. For projects forecasting 5% or greater than their original total full funding authorizations prior to construction should consult with Engineering Project Controls to decide if a pre-construction revised authorization should be pursued. Projects that will exceed their APS-01 tolerances must seek reauthorization, either through the revised PAF or supplement funding depending on the circumstance. Additional requests for a Revised-PAF can be evaluated on a case-by-case basis by the state PAC committee. The justification for all Revised-PAFs is subject to the review and approval of the state PAC committee. 4.8.2 Supplement Authorization Form A SAF should be submitted under one or more of these conditions, given the listed condition(s) is(are) the primary driver for the change after construction work has started: 1. Scope Change [Applicable to all projects] Capital investment for additional units of property that were not previously part of the project scope. Significant change(s) in technical design (i.e. OH vs UG, aerial vs. multi-circuit, etc.). Changes to system topology that impact design of the circuit, ratings, or operational changes shall require a SAF. Indirect rate/Cost Increases. 2. Pre-Construction Update [Applicable to projects yet to begin construction forecasting 15% or greater than their original total full funding authorization] Market conditions cause awarded (or to be awarded) vendor contract amount(s) for labor or material to be higher than the amount(s) for the equivalent labor or material allocation(s) in the approved full funding estimate. An agency, stakeholder, or impacted party external to Eversource causes an uncontrollable change to the project resulting in higher project costs. Indirect rate(s) increase from the full funding estimate. Projects forecasting 15% or greater of their original total full funding authorization prior to construction can be re-estimated and represented at state PAC and resubmitted for DOA approval in PowerPlan. Projects that have started construction and will exceed their APS-01 tolerances must seek reauthorization, via supplemental funding. Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 14
  2. Page 15 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 15 of 34 Distribution Tri-State Capital Project Approval Process A SAF shall be submitted where the project will exceed its APS-01 tolerances in all other cases than those allowing for revised funding. Supplemental authorization requests should be prepared as soon as it is likely that the project cost is expected to increase, and the updated project forecast exceeds the APS01 tolerance for the current authorization. Supplement requests should also be submitted once a scope change is identified. The SAF can be found in the appendix, Attachment G, Supplement Authorization Form. If a supplement is approved by state PAC, the project initiator will submit the approved SAF within the Engineering Project Management Portal, and Investment Planning can submit for Delegation of Authority approvals in PowerPlan. When determining when to submit a supplement, stakeholders should note that attaining full approval in PowerPlan may take up to thirty days and sixty days for projects that will require Delegation of Authority approval by the Eversource Subsidiary Board. 4.9 Project Closeout All project documents will be closed and affected databases updated upon project closeout in accordance with applicable local project closeout processes. 5. Instructions for Planned Projects $499k or less (Annuals) Each year annual distribution line budgets are approved and funded to support the many smaller planned projects that will be completed that year. Per section 3.5.1, planned distribution line, Distributed Generation, CDOT, and New Service projects less than or equal to the state parameters set in section 3.5.1 do not require their own PAFs. 6. Instructions for Work Orders (Wos) that exceed $500k Each year annual distribution line budgets are approved in each region and funded to support the many small projects within that year. A small project, also knows as a work order (WO), has a limit of $499k. In the case of these small projects exceeding $500k, project numbers and PAFs will need to be generated and updated in the Engineering Project Management Portal, presented at the state PAC meetings, and routed in Powerplan for DOA approval. If these small projects are emergent in nature and construction is completed, actual costs are allowed to be used to generate the PAF document for state PAC presentations and DOA approvals. If the work is identified under a category, other than emergent, stakeholder groups should be discussing these Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 15
  3. Page 16 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 16 of 34 Distribution Tri-State Capital Project Approval Process smaller projects and working together to determine if a project number and PAF is needed prior to exceeding the $500k threshold. If a project number and a PAF is created for a WO, than it should be uploaded into the Engineering Project Management Portal, and the project process is followed. The induvial states have the authority to generate PAFs for work under the $500k threshold as they see fit. 7. Definitions & Acronyms Annuals Annuals refers to the annual project budgets that are approved to support small projects and small emergent work projects. APS Eversource Accounting Policy Statement Conceptual Engineering The project design phase required to obtain a project cost estimate accurate to -25%/+50% and to generate an SSF Conceptual Estimate A cost estimate with target accuracy of -25% to +50% Construction The project phase for the implementation of an engineered project DOA Delegation of Authority Detailed Engineering The project phase following conceptual engineering. Emergent Work Refers to work to fix equipment that failed while in-service or is at high risk of imminent failure that needs to be addressed real-time Engineering Estimate A cost estimate with target accuracy of +/-10% Full Funding At this stage, all work orders are written in Maximo and estimated using Maximo estimating units. Technical, financial, and scheduling approval are granted. Therefore the project is considered construction ready and construction can begin, assuming all necessary permits are obtained , material is available, and there are no other hold ups. Initial Funding provides exploratory early development dollars intended to facilitate refinement of the project concept, particularly the project need, justification, and objectives. Project scope and alternatives as well as a resource loaded, project schedule shall be developed. Initial funding can support funding up to Preliminary design if the requested dollars are <$250K (Some exceptions may be Initial Funding Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 16
  4. Page 17 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 17 of 34 Distribution Tri-State Capital Project Approval Process IFR ISD PAF Partial Funding considered). Initial Funding is not intended to support complete project design and engineering and should not fund the project beyond the Preliminary design phase. The core project team should be assembled using Initial Funding. Initial Funding Request Form required to initiate a project with funding and setup a Work Order, the initiator will complete an IFR and submit it to the EPAC. In-Service Date Project Authorization Form required by Accounting Policy Statement 1 for the purpose of requesting authorization of capital funds for a particular project Partial Funding is intended to fund design/engineering for the project as well as project support including site evaluation/prep activities, siting and outreach plans, early procurement activities (in some cases Limited Notice to Proceed for Long-Lead equipment), site testing, outage planning activities, etc. Partial Funding should not be used to purchase material nor be used for construction activities. Planning Estimate Follow Section 3.5.1 for state specific guidelines for what thresholds require a PAF. Section 6 describes when partial funding needs to be routed in Powerplan. A cost estimate with target accuracy of +/-25% PgM Program Manager Powerplan Eversource financial approval tool Program Level PAF Authorization document for programs. A program is a distribution line need that will be addressed at numerous sites (i.e. Tripsavers, Pole Integrity, etc.) or a line need that will be addressed on numerous circuits (i.e. Structure Replacements, Fiber Optic Expansion, etc.) Authorization form for a specific site or circuit of an approved program. Program Release Form SDC SAF State PAC WO Solution Design Committee is a three-state committee that reviews projects and programs to ensure that the best solution is selected, and standardization is implemented across the company Supplement Authorization Form State Project Approval Committee. There will be three state project approval committees for distribution projects: MPAC, CT PAC, and NH PAC Work Order Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 17
  5. Page 18 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 18 of 34 Distribution Tri-State Capital Project Approval Process 8. Revision History Revision 0 – xx/xx/xxxx Original Issue Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 18
  6. Page 19 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 19 of 34 Distribution Tri-State Capital Project Approval Process Attachment A, Solution Design Committee Charter Purpose The Solution Design Committee (SDC) will serve as solution development approval committee to ensure the best solution is selected, ensure guiding principles are followed, and drive standardization. SDC will review project alternatives, scope, and conceptual grade cost estimates during the solution vetting process. Applicability The SDC is responsible for solution selection review of electrical Distribution projects in all three states of the following types: System Planning – Reliability & Capacity Projects Distribution Engineering - Programs (Pole Integrity, , etc.), Reliability, system performance (capacity, sectionalizing etc.) customer request, line relocations, asset health and aging infrastructure, Program releases with significant scope in addition to the program. Distribution Interconnection Projects – Projects on track to sign Interconnection Agreements may be reviewed by the SDC at the request of the sponsoring engineering director. Like-for-like asset replacement projects and individual releases within defined programs with minimal scope variations will not need to be reviewed or approved by the SDC. PAC member directors will also have discretion to determine whether a specific project will require review and approval by the SDC. Objectives The objectives of the SDC are as follows: 1. Confirm that the right subject matter experts from affected departments were appropriately involved in the conceptual engineering, alternatives analysis, and solution selection. 2. Confirm project teams identified and considered a robust set of alternatives when selecting the best solution. 3. Ensure the development of project solutions and alternatives incorporate standardized design and equipment, where practical/possible. 4. Review initial conceptual engineering, scope, and cost estimates for all potential project alternatives. Cost estimates should be of conceptual grade (-25%/+50%) for the preferred solution and competitive alternatives. 5. Review and confirm that project teams identify project risks for the preferred solution and its alternatives with the appropriate level of detail with respect to constructability, routing, outage planning, siting and permitting, environmental impacts, community and external stakeholder impacts, land rights needs and site control, procurement, etc. Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 19
  7. Page 20 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 20 of 34 Distribution Tri-State Capital Project Approval Process 6. Review and confirm project team’s alternatives analyses and choice for preferred solutions and ensure the rationale is appropriately documented. Membership SDC shall consist of an executive sponsor, a chairperson(s), voting members, an administrator, and non- voting attendees as shown on the below table. The chairperson may designate additional voting members, if required. SDC Membership List SDC Role Executive Sponsor Co-Chairperson – Voting Member Administrator(s) Voting Member(s) Voting Member Voting Member Voting Member Voting Member As-Required Voting Member Attendee Attendee Attendee Company Position VP, Distribution Engineering Director(s), Distribution Engineering As appointed by the Chairperson Manager(s), Distribution Engineering Operations Representative Investment Planning Representative IP&S Representative Engineering Leads Distributed Generation Representative Distribution Engineers Standards Representative Operations Supervisor(s) Roles and Responsibilities Executive Sponsor Provide senior management vision, direction, and feedback to the SDC Appoint the Chairperson(s) Chairperson(s) Preside and facilitate SDC meetings Designate a Voting Member as an alternate to preside at meetings in his/her absence Solicit Voting Member appointments Appoint a SDC administrator Determine the meeting schedule and location(s) Approve meeting agendas Review meeting materials on the agenda prior to the SDC meeting Hold votes as required Participate in discussions and votes to meet the SDC objectives Initiate the biennial review of the SDC process in coordination with EPAC Create subcommittees as required Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 20
  8. Page 21 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 21 of 34 Distribution Tri-State Capital Project Approval Process Voting Member If required, designate a manager in the same organization as a voting alternate to participate in the SDC Review meeting materials on the agenda prior to the SDC meeting Participate in discussions and votes to meet the SDC objectives Participate in the biennial review of the SDC process as required Administrator Schedule meetings Prepare draft meeting agendas Quality Screening of Project Documentation Distribute meeting materials to attendees five working days prior to a scheduled SDC meeting Record the result of any votes Prepare and distribute meeting notes Record Solution Select Forms presented and their attachments and meeting results Project Lead/Initiator Quorum Complete a Partial PAF document (including statement of need, project objectives, alternatives analysis, and scope for preferred solution) for any proposed capital project that meets the applicability criteria described above Ensure that SDC objectives listed above are fully met, and that subject matter experts from affected departments were included in the alternatives analysis. Attend the SDC meeting and present the Solution Selection Form to SDC members Revise the Solution Selection Form and/or respond to comments from the SDC as required The Chairperson(s) (or alternate) plus a minimum of four Voting Members (or alternates) shall constitute a quorum for voting purposes if all appropriate disciplines are present to challenge the merits of the project(s). Meeting Schedule and Location The SDC shall schedule meetings twice monthly. The Chairperson(s) may cancel a meeting or require more frequent meetings from time to time as required. Voting The Voting Members and the Chairpersons, or their designated alternates, are eligible to vote. A vote is carried by a Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 21
  9. Page 22 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 22 of 34 Distribution Tri-State Capital Project Approval Process simple majority. Each person has one vote. Subcommittees The Chairperson may establish standing or ad hoc subcommittees as required to meet the objectives of the SDC. Subcommittees shall be chaired by a voting member of the SDC or their designated alternate. Attachment B, State Project Approval Committee (State PAC) Charter Purpose Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 22
  10. Page 23 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 1 Page 23 of 34 Distribution Tri-State Capital Project Approval Process The state Project Authorization Committee (PAC) reviews and approves the technical and financial merits of Distribution projects, including the selection of preferred solutions that are consistent with Eversource priorities (e.g. safety, reliability, cost efficiency). The state PAC authorizes, monitors, and adjusts capital expenditure and resources for projects; prioritizes projects for the capital program and defers projects based on budget and resource availability. Applicability The state PAC is responsible for the technical review and financial approval of electrical Distribution projects in all three states. Objectives The objectives of the state PAC are as follows: 1. Receive, review, and approve Partial and Full Funding Request Forms a. Review the need and confirm that a capital project is needed to address the need. b. Review and approve the project’s objectives. c. Ensure the funding request amount, planned development activities, and schedule are appropriate. 2. Receive, review, and approve PAFs for all projects that meet the Accounting Policy Statement No. 1 threshold. A lower threshold may be imposed by the state PAC, if desired. a. Ensure that the PAF justification is valid. b. Review and approve the project’s technical merits. c. Ensure that all reasonable alternatives were evaluated and appropriately rejected. d. Ensure the scope and cost estimates are reasonable to ± 25% for projects seeking full authorization. e. The committee has the ability to review engineering designs, ensuring the proposed work is in accordance with Eversource Standards, evaluate load implications, assess root cause / reliability and vet out all possible alternatives. f. Not all projects presented are requesting funding and require a vote – these projects will be noted “FOR DISCUSSION ONLY”. g. Ensure the Project Authorization checklist is complete. h. Ensure the financial analysis is reasonable to the accuracy appropriate to the project phase. i. Ensure the project schedule is achievable and reasonable to the accuracy appropriate to the project phase j. Ensure risks and mitigation plans are identified. 3. Evaluate project funding and priorities relative to the five-year capital plan. 4. Ensure project approval statuses and DOA progress are reviewed at least monthly. 5. Prioritize projects for deferment or cancellation. 6. Review EPAC process performance and lessons learned and coordinate with the state PACs to initiate any needed changes on at least a biennial basis. Distribution Capital Project Approval Process JA-DE-2026-A, Rev.0 23
1 page match

Text of OCC-927_Final.pdf

Extracted from the file · 4 pages · 12,932 characters

Words on different pagesRead the text of OCC-927_Final.pdf

As listed on the current system

Question(s) Answered 923, 925, 927 (The Connecticut Light and Power Company) Date Filed: 10/20/2026

This filing on the current system (opens in a new tab)