  1. Page 11 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 11 of 35 Capital Project Approval Process \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. The full responsibilities of the SDC are contained in Attachment A, Solution Design Committee Charter. Once reviewed and approved by the Solution Design Committee, projects will proceed with Preliminary Engineering. Certain Transmission and substation projects do not require review and approval by the SDC such as like-for-like asset replacement projects and individual releases within defined programs with minimal scope variations. Questions regarding the need for a project to visit the SDC can be clarified by contacting [email removed]. Distribution street and line projects without substation components may also require a solution vetting process. The state PAC chairperson may require more complex distribution street and line projects to complete a distribution design review prior to state PAC approval. 4.5 Preliminary Engineering Once the project team has chosen a preferred solution with scope definition, it can proceed with preliminary engineering and development of an updated cost estimate of the preferred solution. In order to receive full funding approval, projects will require planning grade (+/-25%) cost estimates. The cost estimate shall be submitted in the form of the Project Controls work breakdown structure (WBS). The WBS format can be referenced the EPAC PAF template located at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. The project team should request support from the Cost Estimating team to develop the planning grade cost estimate. The project team will work with the affected groups listed in Section 2 to complete more in-depth investigations, develop a mitigation plan for project risks, and refine project strategies For preliminary engineering deliverable requirements refer to procedure M7-EN-2000R0 Engineering Deliverables and a listing of the deliverables found at \\nu.com\data\SharedData\EPAC Project Deliverables. Example preliminary deliverables include: • Constructability Review • ROW Environmental Mapping • Preliminary Three-Line • SS Control Enclosure Layout • UG Plan and Profile If the initial funding is not sufficient to complete preliminary engineering and develop a planning grade cost estimate, then the project team can prepare a PAF and make a request for partial funding at EPAC per Section 3.5. The request should generally be for the budget amount that will be required to fulfill project engineering activities, prepare a full funding request and planning grade cost estimate. For large scale projects multiple partial funding requests may be required. Partial funding may include funds for detailed engineering activities. As with IFRs, partial funding requests may include a budget for internal siting and permitting preparation activities but should not include funding for procurement of any material. The request should also include a listing of required schedule milestones as listed in Attachment G. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 9
  2. Page 12 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 12 of 35 Capital Project Approval Process After a minimum of preliminary engineering is completed, the PAF will be completed and the project will be presented to either the EPAC or the state PAC for full approval and funding authorization. PAFs that will be reviewed at EPAC should be submitted to [email removed] at least seven business days prior to the next scheduled EPAC meeting. For the project types listed in Section 3.4.1, the EPAC will not review full funding requests unless the project has already been approved by the Solution Design Committee. The project checklist, a Constructability Review Form, a copy of the current project schedule, a listing of required schedule milestones as shown in Attachment G and a detailed backup cost estimate in accordance with Attachment D to ISO-NE Planning Procedure 4 (PP4) must accompany the PAF. 4.6 Full Project Authorization 4.6.1 Program Approval EPAC will review and approve Asset Management programs using the Operations Program Level Project Authorization Form. The form can be found at\\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. In addition to the information required on the PAF for a regular project (need, objectives, scope, background/justification, etc.) the Program Level PAF will also require a financial evaluation completed on a unit cost basis so that the capital cost of each application of the program can be fully understood. The unit cost is often based on a similar project that has been completed. A listing of proposed circuits or substations by state that will be included in the scope of the program. • An estimate of the program capital investment value by state. • A proposed schedule for bringing forward and executing the program level releases. • A description of the investigations that will be needed at each location to develop the scope and cost estimate at a specific site. As described in Section 4.1.1 Program Level PAFs may also be combined with an initial funding request at the program level so that the initiator will have funds to develop the scope of the program at specific sites and bring forward full funding program release requests. Partial funding may be obtained for individual program release requests when initial funding is not sufficient to complete preliminary engineering and develop a planning grade cost estimate. • 4.6.2 Program Release Authorization Once the scope, site-specific cost estimate and constructability reviews are completed for a particular location or circuit, a Program Release Form will be submitted for full funding. The Program Release Form can be found at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms\. Each Release will summarize the scope and cost estimate at a specific location and discuss any variances between the scope or cost estimates from the expected unit costs and scope approved in the Program Level PAF. Once an individual program release is approved at EPAC, any initial funding costs that were originally charged at the program level will be journaled to the specific project, which will allow those costs to be capitalized along with the specific project and also make more budget available at the program level to Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 10
  3. Page 13 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 13 of 35 Capital Project Approval Process develop additional Program Release Forms. Once approved, the approval process for a Program Release Form will be the same as stated above for the full funding PAF. 4.6.3 Delegation of Authority Once approved, the EPAC or state PAC administrator will submit the EPAC-approved PAF to Investment Planning for approvals in PowerPlan in accordance with the company Delegation of Authority Policy (DOA). The DOA specifies the capital authorization level of various company positions (manager, director, vice president, senior vice president / subsidiary president, Executive vice president, etc.). The MS Excel file “Power Plan Project Approval Trees” found at N:\EPAC\Administrative\ lists which specific individuals at each authorization level that will be required to approve projects authorized by EPAC. There are separate approval trees listed for transmission line and substation major projects and distribution substation projects. The full project funding is attained once delegation of authority has been performed through PowerPlan in accordance with APS01. PMs should include up to thirty days in project schedules to complete approvals in PowerPlan and sixty days for projects that will require Delegation of Authority approval by the Eversource Subsidiary Board. Projects must be fully approved in PowerPlan before their scope or cost estimates can be shared publicly. This includes but is not limited to sharing cost estimates with ISO-NE, sharing cost estimates with customers for customer or interconnection projects, filing a siting or permitting application that includes a cost estimate, and conducting project outreach. If a project schedule requires the release of project information prior to full project approval in PowerPlan is possible, then a project team can request approval from EPAC to release the information. If EPAC approval is also not possible, then the project team can seek the SDC’s approval to release the information. 4.7 Detailed Engineering, Siting, and Permitting Once the project is fully authorized in PowerPlan, the project team can proceed with detailed engineering, siting and permitting application filings, project outreach, ordering major material, and other development activities. 4.8 Construction and Construction Variance Monitoring The project manager or lead will manage the project’s execution and construction while monitoring the project’s spend vs. its authorized cost. In cases where the project, totaling greater than $300K for planned work or greater than $500K for emergent work, will exceed its APS-01 tolerances, or there is a significant change to the project’s technical design or a significant change to the project’s scope the project manager shall submit a Revised PAF or Supplemental Request Form (SRF) to the EPAC or state PAC. A Revised PAF can be submitted under one or more of these conditions, given the listed condition(s) is(are) the primary driver for the change: 1. Revised PAF – Scope [Applicable to all projects] • • Capital investment for additional units of property that were not previously part of the project scope. Significant change(s) in technical design (i.e. OH vs UG, air vs. GIS, etc.) Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 11
  4. Page 14 of 35Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 14 of 35 Capital Project Approval Process 2. Revised PAF – Pre-Construction [Applicable to projects yet to begin construction forecasting 5% or greater than their original total full funding authorization] • • • Market conditions cause awarded (or to be awarded) vendor contract amount(s) for labor or material to be higher than the amount(s) for the equivalent labor or material allocation(s) in the approved full funding estimate. An agency, stakeholder or impacted party external to Eversource causes an uncontrollable change to the project resulting in higher project costs. Indirect rate(s) increase from the full funding estimate. Projects forecasting 5% or greater than their original total full funding authorization prior to construction should consult PM management to decide if pre-construction revised authorization should be pursued. Projects forecasting over $5M total cost will require a detailed review by Cost Estimating to corroborate the project forecast’s cost increase drivers match the intent of Pre-Construction re-authorization. Project that will exceed their APS-01 tolerances must seek reauthorization, either revised or supplemental funding depending on the circumstance. Additional requests for a Revised PAF can be evaluated on a case-by-case basis by the EPAC committee. The justification for all Revised PAFs is subject to the review and approval of the EPAC committee. A SRF shall be submitted where the project will exceed its APS-01 tolerances in all other cases than those allowing for revised funding. Supplemental authorization requests should be prepared as soon as it is likely that the project cost is expected to increase and the updated project forecast exceeds the APS01 tolerance for the current authorization. Supplement requests should also be submitted once a scope change is identified. The SRF can be found at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. If a supplement is approved by the EPAC or state PAC, the committee administrator will send the approved SRF to Investment Planning for submittal for Delegation of Authority approvals in PowerPlan. When determining when to submit a supplement, PMs should note that attaining full approval in PowerPlan may take up to thirty days and sixty days for projects that will require Delegation of Authority approval by the Eversource Subsidiary Board. 4.9 Project Closeout All project documents will be closed and affected databases updated upon project closeout in accordance with M6-PM-2001, Project Management Process, or applicable local project closeout process. 5 Instructions for Planned Projects $300K or less (Annuals) including Capital Tools Each year annual transmission and distribution substation budgets are approved and funded to support the many small planned projects that will be completed that year. Per APS01 and Operations executive management, planned transmission and distribution substation projects less than or equal to $300,000 Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 12
  5. Page 15 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 15 of 35 Capital Project Approval Process total cost and emergency projects less than or equal to $500,000 total cost do not require their own PAFs. Planned annuals require the initiator to document the work scope, justification, estimated cost and inservice date(ISD). To create a work order that will charge against one of these annual budgets for a small planned transmission or distribution substation project, the project initiator must follow the Capital Annuals Process found at \\nu.com\data\SharedData\EPAC\Administrative. The EPAC Annuals administrative team can be contacted at [email removed]. 6 Instructions for Emergent Work Each year annual transmission and distribution substation budgets are approved in each region and funded to support the many small projects that classify as emergent work within that year. In the case of emergency projects to fix equipment that failed while in-service or is at high risk of imminent failure that needs to be addressed real-time not allowing for fully planned project development, only those emergency projects exceeding $500,000 total cost will require a PAF. Emergent annuals require the initiator to document the work scope and justification. To create a work order that will charge against one of these annual budgets for an emergency transmission or distribution substation project, the project lead must follow the Capital Annuals Process found at \\nu.com\data\SharedData\EPAC\Administrative. The EPAC Annuals administrative team can be contacted at [email removed]. 7 Definitions & Acronyms Annuals Annuals refers to the annual project budgets that are approved to support small projects and small emergent work projects. APS Eversource Accounting Policy Statement Conceptual Engineering The project design phase required to obtain a project cost estimate accurate to -25%/+50% and to generate an SSF Conceptual Estimate A cost estimate with target accuracy of -25% to +50% Construction The project phase for the implementation of an engineered project DOA Delegation of Authority Detailed Engineering The project phase following preliminary engineering. See M7-EN-2000R0 Engineering Deliverables for further details. Emergent Work Refers to work to fix equipment that failed while in-service or is at high risk of imminent failure that needs to be addressed real-time Engineering Estimate A cost estimate with target accuracy of +/-10% EPAC Eversource Project Approval Committee IFC Engineering Issue for Construction Engineering phase follows detailed engineering. IFC engineering completion is typically required to support an Engineering Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 13
  6. Page 16 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 16 of 35 Capital Project Approval Process Initial Funding Estimate (+/-10%). See M7-EN-2000R0 Engineering Deliverables for further details. • Initial Funding provides exploratory early development dollars intended to facilitate refinement of the project concept, particularly the project need, justification and objectives. • Project scope and alternatives as well as a resource loaded, project schedule shall be developed. • Initial funding can support funding up to Preliminary design if the requested dollars are <$250K (Some exceptions may be considered). • Initial Funding is not intended to support complete project design and engineering and should not fund the project beyond the Preliminary design phase. • The core project team should be assembled using Initial Funding. IFR Initial Funding Request Form required to initiate a project with funding and setup a Work Order, the initiator will complete an IFR and submit it to the EPAC. ISD In-Service Date ISO-NE The independent operator of New England’s bulk electric power system and transmission lines. ISO-NE manages a comprehensive regional planning process. M2-TP-2018 The Project Alternative Strategy procedure document published by the System Planning organization. M6-PM-2001 The Project Management Process procedure document M6-PM-2012 Constructability Review procedure document M7-EN-2000R0 Engineering Deliverables procedure document PAF Project Authorization Form required by Accounting Policy Statement 2 for the purpose of requesting authorization of capital funds for a particular project Partial Funding • • • Partial Funding is intended to fund design/engineering for the project as well as project support including site evaluation/prep activities, siting and outreach plans, early procurement activities (in some cases Limited Notice to Proceed for Long-Lead equipment), site testing, outage planning activities, etc. Partial Funding should not be used to purchase material nor be used for construction activities. Since Partial Funding typically requests >$250K, a PAF should be completed. Planned Annual Scheduled capital work costing $300K or less that is not to fix equipment that failed while in-service that needs to be addressed real-time Planning Estimate A cost estimate with target accuracy of +/-25% Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 14
  7. Page 17 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 17 of 35 Capital Project Approval Process PM Project Manager PowerPlan Eversource financial approval tool PP4 ISO-NE Planning Procedure 4 Preliminary Engineering The project phase for the engineering needed to obtain a project cost estimate accurate to ± 25% and to generate a PAF Program Level PAF Authorization document for programs. A program is a substation need that will be addressed at numerous sites (i.e. Oil Circuit Breaker Replacements, Relay Replacements, etc.) or a line need that will be addressed on numerous circuits (i.e. Structure Replacements, Fiber Optic Expansion, etc.) Program Release Form Authorization form for a specific site or circuit of an approved program. SCLL Single Contingency Loss of Load SDC Solution Design Committee is a three-state committee that reviews substation and transmission projects and programs to ensure that the best solution is selected and standardization is implemented across the company SSF Solution Selection Form – Document that the SDC will review and approve SRF Supplement Request Form State PAC State Project Approval Committee. There will be three state project approval committees for distribution projects: MPAC, CT PAC, and NH PAC WBS Work Breakdown Structure WO Work Order Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 15
  8. Page 18 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 18 of 35 Capital Project Approval Process 8 Revision History Revision 7 – June 1, 2022 • Updated Attachment G project milestones required • Added Revised PAF – pre-construction definition to section 4.8 • Updates section 3.6, PAC Project Types • Other minor updates Revision 6 – January 1, 2022 • Updated dollar threshold requirements in accordance with Jan 1 2022 APS01 update • Updated section 5 to reflect modified annuals process • Updated section 3.6 to include updated state PAC instructions • Update section 3.7 Cost Estimating instructions • Updated sections 4.1, 4.3, 4.6 to add schedule milestone requirements • Added attachment G, PAF Schedule Milestone Requirements • Added definitions for initial funding and partial funding • Added IFC Engineering to Attachment D and E • Other minor updates Revision 5 – June 1, 2020 • Added Sections 4.1.1, 4.5.1, and 4.5.2 containing description and instructions for initiating programs, Program Level PAFs, and Program Release Forms • Added Sections 4.5.3 to add additional description of Delegation of Authority Policy • Added Sections 5 and 6 to include instructions for securing authorization for emergent work and annual projects • All Sections: Added detail and instructions for distribution line projects, distributed generation interconnection projects, and communications engineering projects. • Other minor updates Revision 4 – November 2, 2018 • Updated all sections to align with updated project lifecycle including new Project Initiation Process and Solution Design Committee Process Revision 3 • Minor updates Revision 2 – October 27, 2017 • All Sections: Changed from TRC and CPAC to EPAC and state PACs Revision 1 – December 7, 2016 • 4 General Instructions – Added location of forms • 4.2 Detailed Engineering Approval – Added requirement to complete TAF Transmission Checklist Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 16
  9. Page 19 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 19 of 35 Capital Project Approval Process • • • 5 Definitions and Acronyms – Added acronyms used in Attachment F 6 Summary of Changes – Added section Added Attachment F, TAF Transmission Checklist and Instructions Revision 0 – August 28, 2016 • Original issue Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 17
  10. Page 20 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 20 of 35 Capital Project Approval Process Attachment A, Solution Design Committee Charter Purpose The Solution Design Committee (SDC) will serve as solution development approval committee to ensure the best solution is selected, ensure guiding principles are followed, and drive standardization. SDC will review project alternatives, scope, and conceptual grade cost estimates during the solution vetting process. Applicability The SDC is responsible for solution selection review of electrical Transmission and Substation projects in all three states of the following types: • • • System Planning – Reliability & Capacity Projects Asset Management – Programs (OPGW Programs, Breaker Programs, etc.), Rebuilds, Conductor/Cable Replacements, Program releases with significant scope in addition to the program. Transmission Interconnection Projects – Projects on track to sign Interconnection Agreements may be reviewed by the SDC at the request of the sponsoring engineering director. Like-for-like asset replacement projects and individual releases within defined programs with minimal scope variations will not need to be reviewed or approved by the SDC. EPAC member directors will also have discretion to determine whether a specific project will require review and approval by the SDC. Objectives The objectives of the SDC are as follows: 1. Confirm that the right subject matter experts from affected departments were appropriately involved in the conceptual engineering, alternatives analysis, and solution selection. 2. Confirm project teams identified and considered a robust set of alternatives when selecting the best solution in accordance with M2-TP-2018 Project Alternative Process. 3. Ensure the development of project solutions and alternatives incorporate standardized design and equipment, where practical/possible. 4. Review initial conceptual engineering, scope, and cost estimates for all potential project alternatives. Cost estimates should be of conceptual grade (-25%/+50%) for the preferred solution and competitive alternatives. 5. Review and confirm that project teams identify project risks for the preferred solution and its alternatives with the appropriate level of detail with respect to constructability, routing, outage planning, possible SCLLs, siting and permitting, environmental impacts, community and external stakeholder impacts, land rights needs and site control, procurement, etc. 6. Review and confirm project team’s alternatives analyses and choice for preferred solutions and ensure the rationale is appropriately documented. 7. Coordinate with EPAC to initiate any needed process changes on at least a biennial basis. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 18

Text of OCC-927_Final.pdf

Extracted from the file · 4 pages · 12,932 characters

Words on different pagesRead the text of OCC-927_Final.pdf

As listed on the current system

Question(s) Answered 923, 925, 927 (The Connecticut Light and Power Company) Date Filed: 10/20/2026

This filing on the current system (opens in a new tab)