  1. Page 16 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 16 of 35 Capital Project Approval Process Initial Funding Estimate (+/-10%). See M7-EN-2000R0 Engineering Deliverables for further details. • Initial Funding provides exploratory early development dollars intended to facilitate refinement of the project concept, particularly the project need, justification and objectives. • Project scope and alternatives as well as a resource loaded, project schedule shall be developed. • Initial funding can support funding up to Preliminary design if the requested dollars are <$250K (Some exceptions may be considered). • Initial Funding is not intended to support complete project design and engineering and should not fund the project beyond the Preliminary design phase. • The core project team should be assembled using Initial Funding. IFR Initial Funding Request Form required to initiate a project with funding and setup a Work Order, the initiator will complete an IFR and submit it to the EPAC. ISD In-Service Date ISO-NE The independent operator of New England’s bulk electric power system and transmission lines. ISO-NE manages a comprehensive regional planning process. M2-TP-2018 The Project Alternative Strategy procedure document published by the System Planning organization. M6-PM-2001 The Project Management Process procedure document M6-PM-2012 Constructability Review procedure document M7-EN-2000R0 Engineering Deliverables procedure document PAF Project Authorization Form required by Accounting Policy Statement 2 for the purpose of requesting authorization of capital funds for a particular project Partial Funding • • • Partial Funding is intended to fund design/engineering for the project as well as project support including site evaluation/prep activities, siting and outreach plans, early procurement activities (in some cases Limited Notice to Proceed for Long-Lead equipment), site testing, outage planning activities, etc. Partial Funding should not be used to purchase material nor be used for construction activities. Since Partial Funding typically requests >$250K, a PAF should be completed. Planned Annual Scheduled capital work costing $300K or less that is not to fix equipment that failed while in-service that needs to be addressed real-time Planning Estimate A cost estimate with target accuracy of +/-25% Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 14
  2. Page 17 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 17 of 35 Capital Project Approval Process PM Project Manager PowerPlan Eversource financial approval tool PP4 ISO-NE Planning Procedure 4 Preliminary Engineering The project phase for the engineering needed to obtain a project cost estimate accurate to ± 25% and to generate a PAF Program Level PAF Authorization document for programs. A program is a substation need that will be addressed at numerous sites (i.e. Oil Circuit Breaker Replacements, Relay Replacements, etc.) or a line need that will be addressed on numerous circuits (i.e. Structure Replacements, Fiber Optic Expansion, etc.) Program Release Form Authorization form for a specific site or circuit of an approved program. SCLL Single Contingency Loss of Load SDC Solution Design Committee is a three-state committee that reviews substation and transmission projects and programs to ensure that the best solution is selected and standardization is implemented across the company SSF Solution Selection Form – Document that the SDC will review and approve SRF Supplement Request Form State PAC State Project Approval Committee. There will be three state project approval committees for distribution projects: MPAC, CT PAC, and NH PAC WBS Work Breakdown Structure WO Work Order Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 15
  3. Page 18 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 18 of 35 Capital Project Approval Process 8 Revision History Revision 7 – June 1, 2022 • Updated Attachment G project milestones required • Added Revised PAF – pre-construction definition to section 4.8 • Updates section 3.6, PAC Project Types • Other minor updates Revision 6 – January 1, 2022 • Updated dollar threshold requirements in accordance with Jan 1 2022 APS01 update • Updated section 5 to reflect modified annuals process • Updated section 3.6 to include updated state PAC instructions • Update section 3.7 Cost Estimating instructions • Updated sections 4.1, 4.3, 4.6 to add schedule milestone requirements • Added attachment G, PAF Schedule Milestone Requirements • Added definitions for initial funding and partial funding • Added IFC Engineering to Attachment D and E • Other minor updates Revision 5 – June 1, 2020 • Added Sections 4.1.1, 4.5.1, and 4.5.2 containing description and instructions for initiating programs, Program Level PAFs, and Program Release Forms • Added Sections 4.5.3 to add additional description of Delegation of Authority Policy • Added Sections 5 and 6 to include instructions for securing authorization for emergent work and annual projects • All Sections: Added detail and instructions for distribution line projects, distributed generation interconnection projects, and communications engineering projects. • Other minor updates Revision 4 – November 2, 2018 • Updated all sections to align with updated project lifecycle including new Project Initiation Process and Solution Design Committee Process Revision 3 • Minor updates Revision 2 – October 27, 2017 • All Sections: Changed from TRC and CPAC to EPAC and state PACs Revision 1 – December 7, 2016 • 4 General Instructions – Added location of forms • 4.2 Detailed Engineering Approval – Added requirement to complete TAF Transmission Checklist Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 16
  4. Page 19 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 19 of 35 Capital Project Approval Process • • • 5 Definitions and Acronyms – Added acronyms used in Attachment F 6 Summary of Changes – Added section Added Attachment F, TAF Transmission Checklist and Instructions Revision 0 – August 28, 2016 • Original issue Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 17
  5. Page 20 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 20 of 35 Capital Project Approval Process Attachment A, Solution Design Committee Charter Purpose The Solution Design Committee (SDC) will serve as solution development approval committee to ensure the best solution is selected, ensure guiding principles are followed, and drive standardization. SDC will review project alternatives, scope, and conceptual grade cost estimates during the solution vetting process. Applicability The SDC is responsible for solution selection review of electrical Transmission and Substation projects in all three states of the following types: • • • System Planning – Reliability & Capacity Projects Asset Management – Programs (OPGW Programs, Breaker Programs, etc.), Rebuilds, Conductor/Cable Replacements, Program releases with significant scope in addition to the program. Transmission Interconnection Projects – Projects on track to sign Interconnection Agreements may be reviewed by the SDC at the request of the sponsoring engineering director. Like-for-like asset replacement projects and individual releases within defined programs with minimal scope variations will not need to be reviewed or approved by the SDC. EPAC member directors will also have discretion to determine whether a specific project will require review and approval by the SDC. Objectives The objectives of the SDC are as follows: 1. Confirm that the right subject matter experts from affected departments were appropriately involved in the conceptual engineering, alternatives analysis, and solution selection. 2. Confirm project teams identified and considered a robust set of alternatives when selecting the best solution in accordance with M2-TP-2018 Project Alternative Process. 3. Ensure the development of project solutions and alternatives incorporate standardized design and equipment, where practical/possible. 4. Review initial conceptual engineering, scope, and cost estimates for all potential project alternatives. Cost estimates should be of conceptual grade (-25%/+50%) for the preferred solution and competitive alternatives. 5. Review and confirm that project teams identify project risks for the preferred solution and its alternatives with the appropriate level of detail with respect to constructability, routing, outage planning, possible SCLLs, siting and permitting, environmental impacts, community and external stakeholder impacts, land rights needs and site control, procurement, etc. 6. Review and confirm project team’s alternatives analyses and choice for preferred solutions and ensure the rationale is appropriately documented. 7. Coordinate with EPAC to initiate any needed process changes on at least a biennial basis. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 18
  6. Page 21 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 21 of 35 Capital Project Approval Process Membership SDC shall consist of an executive sponsor, a chairperson, voting members, an administrator, and nonvoting attendees as shown on the below table. The chairperson may designate additional voting members, if required. SDC Membership List SDC Role Executive Sponsor Co-Chairperson Co-Chairperson Administrator(s) Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Company Position VP, Substation and Transmission Engineering Director, Substation Design Engineering Director, Substation Protection and Controls As appointed by the Chairperson Director, Transmission Business and Quality Assurance Director(s), System Planning Director, Transmission Line Engineering Director, Substation Technical Engineering Director, Distribution Technical Engineering Director, Engineering Capital Projects Director, Project Performance Director(s), Transmission Project Management Director, Transmission Siting and Project Services Director(s), Station Operations Director, Transmission Project Controls Director, Engineering Project Controls Manager of Project Solutions Manager of Siting Manager of Project Services Manager of Estimating Manager of Asset Management Manager(s) of Substation Engineering Manager(s) of Protection and Controls Manager(s)/Lead(s) of Transmission Line and Civil Eng. Manager(s) of Substation Technical Engineering Manager(s) of System Planning Manager of Licensing and Permitting Manager(s) of Environmental Affairs Manager(s) of Procurement Supervisor(s)/Manager(s) of Outage and Ops Planning Manager of Generation Interconnections Manager of Operational Compliance Manager(s) of Transmission Line Operations Manager(s) of Station Operations/ Field Engineering/ System Dispatch Manager(s) of Systems Engineering Manager of ISO Policy and Economic Analysis Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 19
  7. Page 22 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 22 of 35 Capital Project Approval Process Roles and Responsibilities Executive Sponsor • Provide senior management vision, direction and feedback to the SDC • Appoint the Chairperson(s) Chairperson(s) • Preside at SDC meetings • Designate a Voting Member as an alternate to preside at meetings in his/her absence • Solicit Voting Member appointments • Appoint a SDC administrator • Determine the meeting schedule and location(s) • Approve meeting agendas • Review meeting materials on the agenda prior to the SDC meeting • Hold votes as required • Participate in discussions and votes to meet the SDC objectives • Initiate the biennial review of the SDC process in coordination with EPAC • Create subcommittees as required Voting Member • If required, designate a manager in the same organization as a voting alternate to participate in the SDC • Review meeting materials on the agenda prior to the SDC meeting • Participate in discussions and votes to meet the SDC objectives • Participate in the biennial review of the SDC process as required Administrator • Schedule meetings • Prepare draft meeting agendas • Quality Screening of Project Documentation • Distribute meeting materials to attendees five working days prior to a scheduled SDC meeting • Record the result of any votes • Prepare and distribute meeting notes • Record Solution Select Forms presented and their attachments and meeting results • Attend to and manage the [email removed] email inbox Project Lead/Initiator • Complete a Solution Selection Form (including statement of need, project objectives, alternatives analysis, and scope for preferred solution) for any proposed capital project that meets the applicability criteria described above • Ensure that SDC objectives listed above are fully met, and that subject matter experts from affected departments were included in the alternatives analysis. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 20
  8. Page 23 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 23 of 35 Capital Project Approval Process • • • Submit the Solution Selection Form to the SDC administrator via [email removed] at least five working days prior to the next scheduled SDC meeting (ensures document screening and review by committee members) Attend the SDC meeting and present the Solution Selection Form to SDC members Revise the Solution Selection Form and/or respond to comments from the SDC as required Quorum The Chairperson(s) (or alternate) plus a minimum of four Voting Members (or alternates) shall constitute a quorum for voting purposes if all appropriate disciplines are present to challenge the merits of the project(s). Meeting Schedule and Location The SDC shall schedule meetings twice monthly. The Chairperson(s) may cancel a meeting or require more frequent meetings from time to time as required. The location of the SDC meeting will rotate between MA, CT, and NH. Voting The Voting Members and the Chairpersons, or their designated alternates, are eligible to vote. A vote is carried by a simple majority. Each person has one vote. Subcommittees The Chairperson may establish standing or ad hoc subcommittees as required to meet the objectives of the SDC. Subcommittees shall be chaired by a voting member of the SDC or their designated alternate. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 21
  9. Page 24 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 24 of 35 Capital Project Approval Process Attachment B, Eversource Project Authorization Committee Charter Purpose The Eversource Project Authorization Committee (EPAC) reviews and approves the technical and financial merits of Transmission and Substation projects, including the selection of preferred solutions that are consistent with Eversource priorities (e.g. safety, reliability, cost efficiency). The EPAC authorizes, monitors and adjusts capital expenditure and resources for projects; prioritizes projects for the capital program and defers projects based on budget and resource availability. Applicability The EPAC is responsible for the technical review and financial approval of electrical Transmission and Substation projects in all three states. Objectives The objectives of the EPAC are as follows: 1. Receive, review, and approve Initial Funding Request Forms a. Review the need and confirm that a capital project is needed to address the need. b. Review and approve the project’s objectives. c. Ensure the funding request amount, planned development activities, and schedule are appropriate. 2. Receive, review, and approve PAFs for all projects that meet the Accounting Policy Statement No. 1 threshold. A lower threshold may be imposed by the EPAC, if desired. a. Ensure that the PAF justification is valid. b. Review and approve the project’s technical merits. c. Ensure that all reasonable alternatives were evaluated and appropriately rejected. d. Ensure the scope and cost estimates are reasonable to ± 25% for projects seeking full authorization. e. The committee has the ability to review engineering designs, ensuring the proposed work is in accordance with Eversource Standards, evaluate load implications, assess root cause / reliability and vet out all possible alternatives. f. Not all projects presented are requesting funding and require a vote – these projects will be noted “FOR DISCUSSION ONLY”. g. Ensure the PAF project checklist is complete. h. Ensure the Constructability Review Form is complete i. Ensure the financial analysis is reasonable to the accuracy appropriate to the project phase. j. Ensure the project schedule is achievable and reasonable to the accuracy appropriate to the project phase k. Ensure risks and mitigation plans are identified. 3. Evaluate project funding and priorities relative to the five-year capital plan. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 22
  10. Page 25 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 25 of 35 Capital Project Approval Process 4. Ensure project approval statuses and DOA progress are reviewed at least monthly. 5. Prioritize projects for deferment or cancellation. 6. Review EPAC process performance and lessons learned and coordinate with the state PACs to initiate any needed changes on at least a biennial basis. Membership EPAC shall consist of an executive sponsor, a chairperson, voting member directors, an administrator, and non-voting attendees as shown on the below table. The chairperson may designate additional voting member directors, if required. EPAC Membership List EPAC Role Executive Sponsor Co-Chairperson Co-Chairperson Administrator Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Company Position VP, Transmission Projects Director, Transmission Project Controls Director, Transmission Business and Quality Assurance EPAC Program Manager Director(s), Transmission Project Management Director, Transmission Line Engineering Director, Substation Design Engineering Director, Substation Technical Engineering Director, Substation Protection and Controls Director, Distribution System Planning Director, Transmission System Planning Director, Siting and Project Services Director(s), Investment Planning Director, Sustainability and Environmental Affairs Director, Reliability, Compliance and Implementation Director(s), Transmission/System Ops Director, System Operations Director(s), Field Operations Lines Director(s), Field Operations Substations Director(s), Field Engineering Director, Engineering Project Controls Director, Engineering Capital Projects Director, Project Performance Manager of Project Solutions Manager of Transmission Siting Manager of Project Services Manager of Transmission Cost Estimating Manager of Licensing and Permitting Manager(s) of Procurement Manager(s) of Substation Engineering Manager(s) of Protection and Controls Manager(s)/Lead(s) of Transmission Line and Civil Eng. Program Manager- Transmission Capital Program Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 23

Text of OCC-927_Final.pdf

Extracted from the file · 4 pages · 12,932 characters

Words on different pagesRead the text of OCC-927_Final.pdf

As listed on the current system

Question(s) Answered 923, 925, 927 (The Connecticut Light and Power Company) Date Filed: 10/20/2026

This filing on the current system (opens in a new tab)