  1. Page 21 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 21 of 35 Capital Project Approval Process Membership SDC shall consist of an executive sponsor, a chairperson, voting members, an administrator, and nonvoting attendees as shown on the below table. The chairperson may designate additional voting members, if required. SDC Membership List SDC Role Executive Sponsor Co-Chairperson Co-Chairperson Administrator(s) Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Company Position VP, Substation and Transmission Engineering Director, Substation Design Engineering Director, Substation Protection and Controls As appointed by the Chairperson Director, Transmission Business and Quality Assurance Director(s), System Planning Director, Transmission Line Engineering Director, Substation Technical Engineering Director, Distribution Technical Engineering Director, Engineering Capital Projects Director, Project Performance Director(s), Transmission Project Management Director, Transmission Siting and Project Services Director(s), Station Operations Director, Transmission Project Controls Director, Engineering Project Controls Manager of Project Solutions Manager of Siting Manager of Project Services Manager of Estimating Manager of Asset Management Manager(s) of Substation Engineering Manager(s) of Protection and Controls Manager(s)/Lead(s) of Transmission Line and Civil Eng. Manager(s) of Substation Technical Engineering Manager(s) of System Planning Manager of Licensing and Permitting Manager(s) of Environmental Affairs Manager(s) of Procurement Supervisor(s)/Manager(s) of Outage and Ops Planning Manager of Generation Interconnections Manager of Operational Compliance Manager(s) of Transmission Line Operations Manager(s) of Station Operations/ Field Engineering/ System Dispatch Manager(s) of Systems Engineering Manager of ISO Policy and Economic Analysis Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 19
  2. Page 22 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 22 of 35 Capital Project Approval Process Roles and Responsibilities Executive Sponsor • Provide senior management vision, direction and feedback to the SDC • Appoint the Chairperson(s) Chairperson(s) • Preside at SDC meetings • Designate a Voting Member as an alternate to preside at meetings in his/her absence • Solicit Voting Member appointments • Appoint a SDC administrator • Determine the meeting schedule and location(s) • Approve meeting agendas • Review meeting materials on the agenda prior to the SDC meeting • Hold votes as required • Participate in discussions and votes to meet the SDC objectives • Initiate the biennial review of the SDC process in coordination with EPAC • Create subcommittees as required Voting Member • If required, designate a manager in the same organization as a voting alternate to participate in the SDC • Review meeting materials on the agenda prior to the SDC meeting • Participate in discussions and votes to meet the SDC objectives • Participate in the biennial review of the SDC process as required Administrator • Schedule meetings • Prepare draft meeting agendas • Quality Screening of Project Documentation • Distribute meeting materials to attendees five working days prior to a scheduled SDC meeting • Record the result of any votes • Prepare and distribute meeting notes • Record Solution Select Forms presented and their attachments and meeting results • Attend to and manage the [email removed] email inbox Project Lead/Initiator • Complete a Solution Selection Form (including statement of need, project objectives, alternatives analysis, and scope for preferred solution) for any proposed capital project that meets the applicability criteria described above • Ensure that SDC objectives listed above are fully met, and that subject matter experts from affected departments were included in the alternatives analysis. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 20
  3. Page 23 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 23 of 35 Capital Project Approval Process • • • Submit the Solution Selection Form to the SDC administrator via [email removed] at least five working days prior to the next scheduled SDC meeting (ensures document screening and review by committee members) Attend the SDC meeting and present the Solution Selection Form to SDC members Revise the Solution Selection Form and/or respond to comments from the SDC as required Quorum The Chairperson(s) (or alternate) plus a minimum of four Voting Members (or alternates) shall constitute a quorum for voting purposes if all appropriate disciplines are present to challenge the merits of the project(s). Meeting Schedule and Location The SDC shall schedule meetings twice monthly. The Chairperson(s) may cancel a meeting or require more frequent meetings from time to time as required. The location of the SDC meeting will rotate between MA, CT, and NH. Voting The Voting Members and the Chairpersons, or their designated alternates, are eligible to vote. A vote is carried by a simple majority. Each person has one vote. Subcommittees The Chairperson may establish standing or ad hoc subcommittees as required to meet the objectives of the SDC. Subcommittees shall be chaired by a voting member of the SDC or their designated alternate. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 21
  4. Page 24 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 24 of 35 Capital Project Approval Process Attachment B, Eversource Project Authorization Committee Charter Purpose The Eversource Project Authorization Committee (EPAC) reviews and approves the technical and financial merits of Transmission and Substation projects, including the selection of preferred solutions that are consistent with Eversource priorities (e.g. safety, reliability, cost efficiency). The EPAC authorizes, monitors and adjusts capital expenditure and resources for projects; prioritizes projects for the capital program and defers projects based on budget and resource availability. Applicability The EPAC is responsible for the technical review and financial approval of electrical Transmission and Substation projects in all three states. Objectives The objectives of the EPAC are as follows: 1. Receive, review, and approve Initial Funding Request Forms a. Review the need and confirm that a capital project is needed to address the need. b. Review and approve the project’s objectives. c. Ensure the funding request amount, planned development activities, and schedule are appropriate. 2. Receive, review, and approve PAFs for all projects that meet the Accounting Policy Statement No. 1 threshold. A lower threshold may be imposed by the EPAC, if desired. a. Ensure that the PAF justification is valid. b. Review and approve the project’s technical merits. c. Ensure that all reasonable alternatives were evaluated and appropriately rejected. d. Ensure the scope and cost estimates are reasonable to ± 25% for projects seeking full authorization. e. The committee has the ability to review engineering designs, ensuring the proposed work is in accordance with Eversource Standards, evaluate load implications, assess root cause / reliability and vet out all possible alternatives. f. Not all projects presented are requesting funding and require a vote – these projects will be noted “FOR DISCUSSION ONLY”. g. Ensure the PAF project checklist is complete. h. Ensure the Constructability Review Form is complete i. Ensure the financial analysis is reasonable to the accuracy appropriate to the project phase. j. Ensure the project schedule is achievable and reasonable to the accuracy appropriate to the project phase k. Ensure risks and mitigation plans are identified. 3. Evaluate project funding and priorities relative to the five-year capital plan. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 22
  5. Page 25 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 25 of 35 Capital Project Approval Process 4. Ensure project approval statuses and DOA progress are reviewed at least monthly. 5. Prioritize projects for deferment or cancellation. 6. Review EPAC process performance and lessons learned and coordinate with the state PACs to initiate any needed changes on at least a biennial basis. Membership EPAC shall consist of an executive sponsor, a chairperson, voting member directors, an administrator, and non-voting attendees as shown on the below table. The chairperson may designate additional voting member directors, if required. EPAC Membership List EPAC Role Executive Sponsor Co-Chairperson Co-Chairperson Administrator Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Member Director Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Company Position VP, Transmission Projects Director, Transmission Project Controls Director, Transmission Business and Quality Assurance EPAC Program Manager Director(s), Transmission Project Management Director, Transmission Line Engineering Director, Substation Design Engineering Director, Substation Technical Engineering Director, Substation Protection and Controls Director, Distribution System Planning Director, Transmission System Planning Director, Siting and Project Services Director(s), Investment Planning Director, Sustainability and Environmental Affairs Director, Reliability, Compliance and Implementation Director(s), Transmission/System Ops Director, System Operations Director(s), Field Operations Lines Director(s), Field Operations Substations Director(s), Field Engineering Director, Engineering Project Controls Director, Engineering Capital Projects Director, Project Performance Manager of Project Solutions Manager of Transmission Siting Manager of Project Services Manager of Transmission Cost Estimating Manager of Licensing and Permitting Manager(s) of Procurement Manager(s) of Substation Engineering Manager(s) of Protection and Controls Manager(s)/Lead(s) of Transmission Line and Civil Eng. Program Manager- Transmission Capital Program Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 23
  6. Page 26 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 26 of 35 Capital Project Approval Process Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Attendee Supervisor(s)/Manager(s) of Outage and Ops Planning Manager of Standards Manager of Budget and Investment Manager of Generation Interconnections Manager of Asset Management Manager of Operational Compliance Manager(s) of Line Operations Manager(s) of Substation Technical Engineering Manager(s) of System Planning Roles and Responsibilities Executive Sponsor • Provide senior management vision, direction and feedback to the EPAC • Appoint the Chairperson(s) Chairperson(s) • Preside at EPAC meetings • Designate a Member Director as an alternate to preside at meetings in his/her absence • Solicit Member Director appointments from the leadership team • Appoint a EPAC administrator • Determine the meeting schedule and location(s) • Approve meeting agendas • Review meeting materials on the agenda prior to the EPAC meeting • Hold votes as required • Participate in discussions and votes to meet the EPAC objectives • Initiate the biennial review of the EPAC process in coordination with the other EPACs • Create subcommittees as required Member Director • If required, designate a manager in the same organization as a voting alternate to participate in the EPAC • Review meeting materials on the agenda prior to the EPAC meeting • Participate in discussions and votes to meet the EPAC objectives • Participate in the biennial review of the EPAC process as required Administrator • Schedule meetings • Prepare draft meeting agendas • Quality Screening and Quality Measurement of Project Documentation. • Distribute meeting materials to attendees three working days prior to a scheduled EPAC meeting Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 24
  7. Page 27 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 27 of 35 Capital Project Approval Process • • • • • Record the result of any votes Prepare and distribute meeting notes Record PAFs and SRFs presented and meeting results Submit PAFs and SRFs approved to Investment Planning for Delegation of Authority approvals in PowerPlan Attend to and manage the [email removed] email inbox Project Lead/Initiator • Complete a PAF (including financial and technical details, cost estimate, project checklist, and Constructability Review Form) for any proposed capital project or change, ensuring that EPAC objective one items are fully met, and obtain any necessary reviews and approvals prior to submittal to the EPAC • Submit the PAF to the EPAC administrator via [email removed] at least seven working days prior to the next scheduled EPAC meeting for engineering approval (ensures document screening and review by committee members) • Attend the EPAC meeting and present the PAF to EPAC members • Revise the PAF and/or respond to comments from the EPAC as required Quorum The Chairperson(s) (or alternate) plus a minimum of four Member Directors (or alternates) shall constitute a quorum for voting purposes if all appropriate disciplines are present to challenge the merits of the project(s). Meeting Schedule and Location The EPAC shall schedule meetings twice monthly. The Chairperson(s) may cancel a meeting or require more frequent meetings from time to time as required. Voting The Member Directors and the Chairpersons, or their designated alternates, are eligible to vote. A vote is carried by a simple majority. Each person has one vote. Subcommittees The Chairperson may establish standing or ad hoc subcommittees as required to meet the objectives of the EPAC. Subcommittees shall be chaired by a voting member of the EPAC or their designated alternate. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 25
  8. Page 28 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 28 of 35 Capital Project Approval Process Attachment C, State Project Approval Committee (State PAC) Charter Purpose The State Project Approval Committees (State PACs) review and challenge the technical merit of proposed distribution projects, and approve them as consistent with Eversource priorities (e.g. safety, reliability, cost efficiency). Applicability This charter applies to the three state PACs in Connecticut, Massachusetts and New Hampshire that are responsible for all Eversource electrical distribution projects originating in their respective states. Objectives The objectives of a state PAC are as follows: 1. Receive, review and approve Project Authorization Forms (PAFs) for all projects that meet the Accounting Policy Statement No. 1 threshold. A lower threshold may be imposed by the state PAC, if desired. a. Ensure that the PAF justification is valid. b. Review and approve the project’s technical merits. c. Ensure the scope and cost estimates are reasonable to ± 25% for projects seeking full authorization and to -25%/+50% for projects seeking initial funding. d. Ensure that all reasonable alternatives were evaluated and appropriately rejected. e. The committee has the ability to review detailed engineering designs, ensuring the proposed work is in accordance with our Standards, evaluate load implications, assess root cause / reliability and vet out all possible alternatives. f. Not all projects presented are requesting funding and require a vote – these projects will be noted “FOR DISCUSSION ONLY”. g. Ensure risks and mitigation plans are identified. h. Ensure the PAF project checklist is complete. i. Ensure the Constructability Review Form is complete. j. Ensure the financial analysis is reasonable to the accuracy appropriate to the project phase. k. Ensure the project schedule is achievable and reasonable to the accuracy appropriate to the project phase. l. If CEO or subsidiary board approval is required, ensure project and cost analysis has been reviewed by the Enterprise Risk Management and Financial Planning & Analysis departments. 2. Release engineering labor and funds for detailed engineering on approved PAFs. 3. Review projects authorized for detailed engineering at least monthly to control engineering spend. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 26
  9. Page 29 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 29 of 35 Capital Project Approval Process 4. Review state PAC process performance and lessons learned and coordinate with the other state PACs and the EPAC to initiate any needed changes on at least a biennial basis. 5. Provide a forum for design review for more complex distribution street and line projects. The state PAC chairperson will use their judgement to determine which projects require distribution design review prior to state PAC approval. Membership Each state PAC shall consist of an executive sponsor, a chairperson, voting member directors, an administrator and non-voting attendees as shown in the below table. The chairperson may designate additional voting member directors, if required. State PAC Membership List State PAC Role Executive Sponsor Chairperson Administrator Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Voting Member Attendee Company Position VP, Engineering Director, Distribution Engineering Appointed by Chairperson Manager, Distribution Engineering Manager, Investment Planning Manager, Distributed Generation Manager/Supervisor, Field Engineering Manager, Integrated Planning, Scheduling Manager, System Operations Manager, Field Operations Manager, Substation Technical Engineering Manager, Engineering Standards Project Manager(s) Roles and Responsibilities Executive Sponsor • Provide senior management vision, direction and feedback to the state PAC • Appoint the Chairperson Chairperson • Preside at state PAC meetings • Designate a Member Director as an alternate to preside at meetings in his/her absence • Solicit Member Director appointments from the leadership team • Appoint a state PAC administrator • Determine the meeting schedule and location(s) • Approve meeting agendas • Review meeting materials on the agenda prior to the state PAC meeting Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 27
  10. Page 30 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 30 of 35 Capital Project Approval Process • • • • • • Hold votes as required Participate in discussions and votes to meet the state PAC objectives Release funds on approved PAFs for detailed engineering Initiate the biennial review of the state PAC process in coordination with the other state PACs Create subcommittees as required Determine which projects should complete a design review prior to state PAC approval Voting Member • If required, designate a voting alternate to participate in the state PAC • Review meeting materials on the agenda prior to the state PAC meeting • Participate in discussions and votes to meet the state PAC objectives • Participate in the biennial review of the state PAC process as required Administrator • Schedule meetings • Prepare draft meeting agendas • Distribute meeting materials to attendees three days prior to a scheduled state PAC meeting • Record the result of any votes • Prepare and distribute meeting notes • Record PAFs presented and meeting results in the capital project database Project Initiator (typically engineer level) • Complete a PAF for any proposed capital project, ensuring that state PAC objective 1 items are fully met, and obtain any necessary reviews and approvals prior to submittal to the state PAC • Submit the PAF to the state PAC administrator at least three working days prior to the next scheduled state PAC meeting for engineering approval • Attend the state PAC meeting and present the PAF to state PAC members • Revise the PAF and/or respond to comments from the state PAC as required • Once fully authorized, if costs exceed the approved PAF levels by more than the amounts shown in Accounting Policy Statement No. 1, create a SRF, attach to the previously approved PAF, and resubmit for review and approval. Quorum The Chairperson(s) (or alternate) plus a minimum of two Member Directors (or alternates) shall constitute a quorum for voting purposes if all appropriate disciplines are present to challenge the merits of the project(s). Meeting Schedule Each of the state PACs shall schedule meetings at least bimonthly. The Chairperson may cancel a meeting or require more frequent meetings from time to time as required. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 28

Text of OCC-927_Final.pdf

Extracted from the file · 4 pages · 12,932 characters

Words on different pagesRead the text of OCC-927_Final.pdf

As listed on the current system

Question(s) Answered 923, 925, 927 (The Connecticut Light and Power Company) Date Filed: 10/20/2026

This filing on the current system (opens in a new tab)