  1. Page 4 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 4 of 35 Capital Project Approval Process 1 Purpose This job aid provides instructions and guidance on the process for initiating and then obtaining technical and financial approval for capital projects within all three states. This job aid will focus on project initiation, solution vetting by the Solution Design Committee (SDC), and approval of the Project Authorization Form (PAF) by the Eversource Project Approval Committee (EPAC) for transmission and substation projects and by each of the state Project Approval Committees (state PACs) for distribution projects. The authorization forms used by each committee can be found at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. Completed samples of each form can be found at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms\Sample Forms\. This job aid supports the guidance contained in Accounting Policy Statement 1 (APS01), Operations Project Authorization, which can be found on the Eversource intranet at https://eversourceenergy.sharepoint.com/sites/Accounting/SitePages/Accounting-Policies-%26Procedures.aspx. 2 Affected Groups As described in Responsibilities and General Instructions, the System Planning, Asset Management, Transmission Interconnections, and Project Management groups, along with the SDC, EPAC, and state PAC committees will have primary responsibility for the project review and approval process. The following general groups will also be affected by this job aid as their participation is critical to the successful initiation, development, review, and approval of capital projects. • • • • • • • • • • • Transmission Line, Substation Design, Substation Technical, Protection and Controls, Grid Modernization and Distribution Engineering Construction Scheduling Licensing and Permitting Environmental Siting and Project Services Procurement Investment Planning Operations Engineering Project Controls Transmission Project Controls Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 2
  2. Page 5 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 5 of 35 Capital Project Approval Process 3 Responsibilities 3.1 Project Initiator In general, Transmission and Substation projects will be initiated by either the System Planning (Reliability, Capacity, Distributed Energy Projects), Asset Management (Asset Condition Projects), Grid Modernization or Transmission Interconnections Department (Interconnection Projects). Distribution street and line projects with no substation scope will be initiated by the Distribution Engineering group. Telecom projects (aside from OPGW projects which will be initiated by the Asset Management group) will be initiated by the Telecommunications Engineering Group. For Transmission and Substation projects, the project initiator is responsible for establishing a project by securing initial (or in some cases partial) funding. The initiator is responsible for development of the establishing document(s), typically an initial funding request (IFR), a program level PAF with initial funding for early program development or a partial funding request in some cases. The project initiator will be responsible for securing funding from state PAC for Distribution line projects. For Transmission and Substation projects, a PM will typically be assigned at the time initial funding is procured. As outlined in section 3.2 the PM assumes responsibility for the project budget and schedule as well as organizing engineering, siting, permitting and outreach activities working with the various departments. If a project manager is assigned, the project initiator will support the PM during the engineering phases and PAF development as needed. For applicable projects (See Section 3.4.1 below for details), the project initiator is responsible for the development of the Solution Selection Form (SSF) and presentation of the project preferred and alternative solutions to the SDC. For projects that do not have a project manager assigned, the project initiator will be responsible for; coordinating conceptual engineering activities and conceptual cost estimates (-25%/+50%) to support alternatives analysis; coordinating preliminary engineering activities and developing an updated +/-25% planning grade cost estimate. The project initiator will then be responsible for updating the PAF and securing full funding from the EPAC or a state PAC. Once a project is fully approved and funded, project ownership transfers to the project manager for the project execution and closeout phases. 3.2 Project Manager (PM) For projects managed by the Transmission Projects organization a PM will typically be assigned at the time initial funding is procured. The PM will own the project budget and schedule from the time of assignment. The PM is also responsible for; coordinating conceptual engineering activities and conceptual cost estimates (-25%/+50%) to support alternatives analysis; coordinating preliminary engineering activities and developing an updated +/-25% planning grade cost estimate by driving collaboration with the various engineering disciplines and affected departments. The project manager is responsible for overseeing the development of partial and full funding requests. PAFs shall include the financial and technical project details, a detailed backup cost estimate, a project checklist, the current Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 3
  3. Page 6 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 6 of 35 Capital Project Approval Process project schedule, a listing of required schedule milestones as shown in Attachment G, and a Constructability Review (CR) Form (CR form required for full funding requests) at least seven working days prior to the next scheduled EPAC meeting for Transmission and Substation projects or three working days prior to the next scheduled state PAC meeting for Distribution projects. For transmission projects, the detailed cost estimate must be in accordance with Attachment D to PP4 (ISO-New England Planning Procedure 4). The estimate should be formatting in-line with Transmission Project Control’s Work Breakdown Structure (WBS). The PM will also be responsible for any required supplemental approval with support from the project initiator, if necessary. 3.3 Project Sponsor Typically, the Project Sponsor will be the director of the project initiator. The Project Sponsor will be responsible for review and approval of project documents before they are submitted to the committees for approval. 3.4 Solution Design Committee (SDC) The SDC will serve as solution development gate keepers to ensure the best solution is selected, ensure guiding principles are followed, and drive standardization. SDC will review project alternatives, scope, and conceptual grade cost estimates during the solution vetting process. The SDC administrators will use the email address [email removed] to communicate with project initiators and for all committee communications. More information on solution vetting can be found in Section 4.4 and the full responsibilities of the SDC are contained in Attachment A, Solution Design Committee Charter. 3.4.1 Project Types The SDC will review and approve solutions for the following Transmission and Substation project types: • • • • System Planning – Reliability and Capacity Projects Asset Management – Programs (OPGW Programs, Breaker Programs, etc.), Rebuilds, Conductor/Cable Replacements, Program releases with significant scope in addition to the program. Transmission Interconnection Projects – Projects on track to sign Interconnection Agreements may be reviewed by the SDC at the request of the sponsoring engineering director. Other Telecom projects and programs Like-for-like asset replacement projects and individual releases within defined programs with minimal scope variations will not need to be reviewed or approved by the SDC. EPAC member directors will also have discretion to determine whether a specific project or program will require review and approval by the SDC. In certain cases where there is a quorum of EPAC representatives present at the SDC, an initial or partial funding request may be presented in conjunction with an SSF for the same project at the SDC. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 4
  4. Page 7 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 7 of 35 Capital Project Approval Process 3.5 Eversource Project Approval Committee (EPAC) The EPAC will be responsible for the review and approval of the technical and financial merits of transmission and substation projects. For project and program initiations, the EPAC will review and authorize Initial Funding Request Forms (IFRs) typically up to $250,000, including Program Level PAFs with initial funding. The EPAC may also review requests for initial funding beyond $250,000 if a larger funding amount is required to complete preliminary engineering activities. For previously initiated projects and programs, the EPAC will review partial and full funding PAFs, Program Level PAFs, and Program Release Forms. The EPAC will review conceptual grade cost estimates (-25%/+50%) for projects looking to secure partial funding and will review planning grade cost estimates (+/-25%) for projects looking to secure full funding authorization. The EPAC administrators will use the email address [email removed] to communicate with project teams and for all committee communications The full responsibilities of the EPAC are contained in Attachment B, Eversource Project Authorization Committee Charter. 3.5.1 Project Types The EPAC will review and approve the following project types: • • • • • • • • Planned Transmission line and/or substation projects (Transmission and Distribution substation over $300,000 total cost) Transmission line and/or substation programs (OPGW Programs, Breaker Programs, etc.) Telecom projects that impact transmission lines and/or substations New or reconfiguration of a distribution substation (regardless of voltage level) Substation projects with transmission and distribution components will be reviewed as a package, only by the EPAC Customer interconnection requests that require transmission or substation work Emergency projects greater than $500,000 total cost (refer to section 6 for further details) Any other project per the discretion of the EPAC chairperson(s) All other distribution projects will be reviewed and approved by the state PAC (see section 3.6.1). See Section 5 for review process for transmission and substation projects less than or equal to $300,000 total cost. 3.6 State Project Approval Committees (CT PAC, MPAC, and NH PAC) The state PACs will be responsible for the review and approval of the technical and financial merits of Distribution projects. There will be three different project approval committees to review and approve the projects; one from each state (CT PAC, MPAC, and NH PAC). The state PACs will review initial funding requests to develop detailed engineering and to support early establishment of projects in Eversource financial and scheduling systems. Regardless of cost, initial funding requests shall adhere to PAC approval processes and shall include a schedule by which engineering plans to complete detailed engineering, produce a planning grade cost estimate and present for full funding authorization. The state PAC committee chair will track projects that are given Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 5
  5. Page 8 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 8 of 35 Capital Project Approval Process approval for initial funding and ensure timely submission, review and approval of PAFs for full funding authorization. Distribution projects looking to secure full funding authorization shall develop PAFs containing a planning grade (+/-25%) cost estimate. The full responsibilities of the state PACs are contained in Attachment C, State Project Approval Committee (State PAC) Charter. 3.6.1 Project Types The state PACs will review and approve the following project types: • • • • Overhead distribution projects greater than $300,000. Underground distribution and combined overhead-underground distribution projects greater than $1 million. Customer interconnection requests with total cost estimates (including indirect costs) greater than $1 million. Customer interconnection projects less than $1 million are reviewed and approved in PowerPlan and typically will not require review and approval by the state PAC. DG interconnection request without substation scope that require a new feeder (regardless of cost) or with total cost estimate greater than $500,000. Note that DG interconnection projects with substation scope will be reviewed by EPAC as described in Section 3.5.1.) Note that per APS01 and Operations executive management, all other underground, overhead, and underground-overhead mixed distribution projects under the dollar thresholds listed above but over $500,000 total cost require PAF documentation. Projects $300K or greater but less than $500K may require PAF documentation at the discretion of the PAC committees, except for emergency projects and standard distribution underground interconnections in EMA, both of which will only require PAFs for projects $500K or greater in all cases. These PAFs will be reviewed and approved directly in PowerPlan. The approving director can use his/her discretion to require any of these projects to be reviewed at the state PAC. All other transmission and substation projects will be reviewed and approved by the EPAC (see section 3.5.1). 3.7 Cost Estimating The Transmission Cost Estimating team will support development of project cost estimates for Transmission and Substation projects. Depending on the complexity of the project, the approximate cost, and other factors the level of support provided by the Cost Estimating team may range from taking the lead in developing the estimate to reviewing an estimate prepared by the project team. To request support from the Cost Estimating team, project teams should complete the Estimate Request Form which can be found at \\nu.com\data\SharedData\Estimating-Shared\2) Estimate Templates\1) Est Request form\Current\ and submit to [email removed] Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 6
  6. Page 9 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 9 of 35 Capital Project Approval Process 4 General Instructions The process to proceed with each successive phase of a capital project is designed to ensure that there is a valid need, the right solution alternatives are evaluated, the technical approach is sound, and resources are budgeted and prudently spent. The overall process flow for Transmission and Substation projects is depicted in Attachment D, Transmission and Substation Project Approval Process Flow Charts. Attachment E, Transmission and Substation Project Approval Process Detailed Flow Chart is a 17”x11” flowchart with more detailed descriptions. The overall process flow for Distribution projects is depicted in Attachment F, Distribution Project Approval Process Flow Chart. The initiation and major engineering and approval phases of the process flow charts correspond to the sections below. These general instructions are for the project types listed in Sections 3.5.1 and 0. Refer to Section 5 for instructions for planned transmission and substation projects less than or equal to $300,000. Refer to Section 6 for instructions for securing approval of emergent work. 4.1 Project Initiation Following the identification of a project need the initiator will secure a project number. Project initiators can email [email removed] for assistance securing a project number. Project initiators will then complete an IFR and submit it to EPAC via [email removed]. The IFR may be used to request funding per Section 3.5. The form can be found at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms\. The initiator will be required to state the project need and objectives and include an explanation of the funding request amount, including a budget for conceptual and preliminary engineering activities and the required schedule milestones as shown in attachment G. The IFR may include a budget for initial internal siting and permitting preparation activities. The IFR should not include funding for detailed engineering or procurement of any material. The EPAC chairman may decide to approve the request directly or may request that the initiator present the request for input and feedback to the EPAC. Once an IFR is approved, the EPAC administrator will send the approved form to Investment Planning to create a project and submit it for Delegation of Authority approvals in PowerPlan, the Eversource software tool for financial approval. The initial funding is obtained once delegation of authority has been performed through PowerPlan in accordance with APS01 (See Section 4.5.3 for more information on Delegation of Authority Policy). Once fully approved in PowerPlan a Work Order (WO) will be assigned. The EPAC administer will copy the Project Management on the submittal to Investment Planning so that a Project Manager can be assigned as appropriate. The Project Manager should work with their Investment Planning contact to determine the work order setup best suited for the management and execution of the project. For some projects the Project Manager role may remain with the Project Initiator, be assigned to a lead engineer, or be assigned to an individual in Maintenance and Operations. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 7
  7. Page 10 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 10 of 35 Capital Project Approval Process 4.2 Project Initiation for Programs Initial funding can also be requested at the program level using the Program Level Project Authorization Form. The form can be found at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. The funding can be used to advance specific project scope under an approved program. Sections 4.5.1 and 4.5.2 contains more information on full approval of programs and program level releases. 4.3 Conceptual Engineering The project initiator should follow the Project Alternative Process in procedure M2-TP-2018 for the identification, development and selection of project alternatives. As described in detail in M2-TP-2018, the project manager with support from the project initiator will coordinate the following activities with input from affected departments: • • • • • • Incorporate designs from standards library and develop scope and major equipment lists for all alternatives under consideration. Conceptual engineering of all competitive alternatives including early field review and desktop analysis. Identification of key project risks with the appropriate level of detail with respect to constructability, routing, outage planning, possible Single Contingency Loss of Load (SCLL) conditions and applicable mitigation actions, siting and permitting, environmental impacts, community and external stakeholder impacts, site control, procurement, etc. Identification of any land rights needs. Develop project strategies to mitigate identified risks. Conceptual grade cost estimates (-25%/+50%) for all competitive alternatives (at least the preferred solution and leading alternative). Order of magnitude cost estimates (-50%/+200) should be provided for alternatives that are not competitive with the preferred solution. The project team should request support from the Cost Estimating team for all estimates. The project team will then recommend a preferred solution and document the rationale for the choice of preferred solution. For conceptual engineering deliverable requirements refer to procedure M7-EN2000R0 Engineering Deliverables and a listing of the deliverables found at \\nu.com\data\SharedData\EPAC Project Deliverables. 4.4 Solution Vetting Prior to proceeding with Preliminary Engineering of the preferred solution, more comprehensive projects and asset condition projects at the program level will need to be reviewed and approved by the SDC (See Section 3.4.1 for list of project types the SDC will review). The project team will submit a Solution Selection Forms (SSF) to the SDC via [email removed] at least seven business days prior to the next scheduled SDC meeting. The SDC will review the SSF and confirm that the project team has selected the best solution. The SSF will require a statement of the project need and objectives, documentation of the alternatives analysis, scope and major equipment list for the preferred solution, and a conceptual grade cost estimates for the preferred solution and any competitive alternatives. The form can be found at Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 8
  8. Page 11 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 11 of 35 Capital Project Approval Process \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. The full responsibilities of the SDC are contained in Attachment A, Solution Design Committee Charter. Once reviewed and approved by the Solution Design Committee, projects will proceed with Preliminary Engineering. Certain Transmission and substation projects do not require review and approval by the SDC such as like-for-like asset replacement projects and individual releases within defined programs with minimal scope variations. Questions regarding the need for a project to visit the SDC can be clarified by contacting [email removed]. Distribution street and line projects without substation components may also require a solution vetting process. The state PAC chairperson may require more complex distribution street and line projects to complete a distribution design review prior to state PAC approval. 4.5 Preliminary Engineering Once the project team has chosen a preferred solution with scope definition, it can proceed with preliminary engineering and development of an updated cost estimate of the preferred solution. In order to receive full funding approval, projects will require planning grade (+/-25%) cost estimates. The cost estimate shall be submitted in the form of the Project Controls work breakdown structure (WBS). The WBS format can be referenced the EPAC PAF template located at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. The project team should request support from the Cost Estimating team to develop the planning grade cost estimate. The project team will work with the affected groups listed in Section 2 to complete more in-depth investigations, develop a mitigation plan for project risks, and refine project strategies For preliminary engineering deliverable requirements refer to procedure M7-EN-2000R0 Engineering Deliverables and a listing of the deliverables found at \\nu.com\data\SharedData\EPAC Project Deliverables. Example preliminary deliverables include: • Constructability Review • ROW Environmental Mapping • Preliminary Three-Line • SS Control Enclosure Layout • UG Plan and Profile If the initial funding is not sufficient to complete preliminary engineering and develop a planning grade cost estimate, then the project team can prepare a PAF and make a request for partial funding at EPAC per Section 3.5. The request should generally be for the budget amount that will be required to fulfill project engineering activities, prepare a full funding request and planning grade cost estimate. For large scale projects multiple partial funding requests may be required. Partial funding may include funds for detailed engineering activities. As with IFRs, partial funding requests may include a budget for internal siting and permitting preparation activities but should not include funding for procurement of any material. The request should also include a listing of required schedule milestones as listed in Attachment G. Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 9
  9. Page 12 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 12 of 35 Capital Project Approval Process After a minimum of preliminary engineering is completed, the PAF will be completed and the project will be presented to either the EPAC or the state PAC for full approval and funding authorization. PAFs that will be reviewed at EPAC should be submitted to [email removed] at least seven business days prior to the next scheduled EPAC meeting. For the project types listed in Section 3.4.1, the EPAC will not review full funding requests unless the project has already been approved by the Solution Design Committee. The project checklist, a Constructability Review Form, a copy of the current project schedule, a listing of required schedule milestones as shown in Attachment G and a detailed backup cost estimate in accordance with Attachment D to ISO-NE Planning Procedure 4 (PP4) must accompany the PAF. 4.6 Full Project Authorization 4.6.1 Program Approval EPAC will review and approve Asset Management programs using the Operations Program Level Project Authorization Form. The form can be found at\\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms. In addition to the information required on the PAF for a regular project (need, objectives, scope, background/justification, etc.) the Program Level PAF will also require a financial evaluation completed on a unit cost basis so that the capital cost of each application of the program can be fully understood. The unit cost is often based on a similar project that has been completed. A listing of proposed circuits or substations by state that will be included in the scope of the program. • An estimate of the program capital investment value by state. • A proposed schedule for bringing forward and executing the program level releases. • A description of the investigations that will be needed at each location to develop the scope and cost estimate at a specific site. As described in Section 4.1.1 Program Level PAFs may also be combined with an initial funding request at the program level so that the initiator will have funds to develop the scope of the program at specific sites and bring forward full funding program release requests. Partial funding may be obtained for individual program release requests when initial funding is not sufficient to complete preliminary engineering and develop a planning grade cost estimate. • 4.6.2 Program Release Authorization Once the scope, site-specific cost estimate and constructability reviews are completed for a particular location or circuit, a Program Release Form will be submitted for full funding. The Program Release Form can be found at \\nu.com\data\SharedData\EPAC\Administrative\EPAC Forms\. Each Release will summarize the scope and cost estimate at a specific location and discuss any variances between the scope or cost estimates from the expected unit costs and scope approved in the Program Level PAF. Once an individual program release is approved at EPAC, any initial funding costs that were originally charged at the program level will be journaled to the specific project, which will allow those costs to be capitalized along with the specific project and also make more budget available at the program level to Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 10
  10. Page 13 of 35

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 5, 2026 OCC-925 Attachment 2 Page 13 of 35 Capital Project Approval Process develop additional Program Release Forms. Once approved, the approval process for a Program Release Form will be the same as stated above for the full funding PAF. 4.6.3 Delegation of Authority Once approved, the EPAC or state PAC administrator will submit the EPAC-approved PAF to Investment Planning for approvals in PowerPlan in accordance with the company Delegation of Authority Policy (DOA). The DOA specifies the capital authorization level of various company positions (manager, director, vice president, senior vice president / subsidiary president, Executive vice president, etc.). The MS Excel file “Power Plan Project Approval Trees” found at N:\EPAC\Administrative\ lists which specific individuals at each authorization level that will be required to approve projects authorized by EPAC. There are separate approval trees listed for transmission line and substation major projects and distribution substation projects. The full project funding is attained once delegation of authority has been performed through PowerPlan in accordance with APS01. PMs should include up to thirty days in project schedules to complete approvals in PowerPlan and sixty days for projects that will require Delegation of Authority approval by the Eversource Subsidiary Board. Projects must be fully approved in PowerPlan before their scope or cost estimates can be shared publicly. This includes but is not limited to sharing cost estimates with ISO-NE, sharing cost estimates with customers for customer or interconnection projects, filing a siting or permitting application that includes a cost estimate, and conducting project outreach. If a project schedule requires the release of project information prior to full project approval in PowerPlan is possible, then a project team can request approval from EPAC to release the information. If EPAC approval is also not possible, then the project team can seek the SDC’s approval to release the information. 4.7 Detailed Engineering, Siting, and Permitting Once the project is fully authorized in PowerPlan, the project team can proceed with detailed engineering, siting and permitting application filings, project outreach, ordering major material, and other development activities. 4.8 Construction and Construction Variance Monitoring The project manager or lead will manage the project’s execution and construction while monitoring the project’s spend vs. its authorized cost. In cases where the project, totaling greater than $300K for planned work or greater than $500K for emergent work, will exceed its APS-01 tolerances, or there is a significant change to the project’s technical design or a significant change to the project’s scope the project manager shall submit a Revised PAF or Supplemental Request Form (SRF) to the EPAC or state PAC. A Revised PAF can be submitted under one or more of these conditions, given the listed condition(s) is(are) the primary driver for the change: 1. Revised PAF – Scope [Applicable to all projects] • • Capital investment for additional units of property that were not previously part of the project scope. Significant change(s) in technical design (i.e. OH vs UG, air vs. GIS, etc.) Capital Project Approval Process - JA-AM-2001-A, Rev. 7 Page 11

Text of OCC-927_Final.pdf

Extracted from the file · 4 pages · 12,932 characters

Words on different pagesRead the text of OCC-927_Final.pdf

As listed on the current system

Question(s) Answered 923, 925, 927 (The Connecticut Light and Power Company) Date Filed: 10/20/2026

This filing on the current system (opens in a new tab)