Text of OCC-962 Attachment 7.pdf

Extracted from the file · 144 pages · 700,506 characters

Text of OCC-962 Attachment 6.pdf

Extracted from the file · 136 pages · 685,692 characters

Text of OCC-962 Attachment 5.pdf

Extracted from the file · 128 pages · 641,445 characters

Text of OCC-962 Attachment 4.pdf

Extracted from the file · 120 pages · 653,488 characters

41 pages match
  1. Page 105 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 105 of 136 PSNH 2021 (Millions of Dollars) Renewable Energy $ 2022 67.6 $ 2023 68.5 $ 2024 29.7 $ 2025 26.8 $ Thereafter 27.2 $ 323.1 Total $ 542.9 Purchased Power and Capacity 0.5 0.5 0.5 — — — 1.5 Transmission Support Commitments 4.3 3.8 3.8 4.1 4.2 4.2 24.4 Total $ 72.4 $ 72.8 $ 34.0 $ 30.9 $ 31.4 $ 327.3 $ 568.8 Renewable Energy: Renewable energy contracts include non-cancellable commitments under contracts of CL&P, NSTAR Electric and PSNH for the purchase of energy and capacity from renewable energy facilities. Such contracts extend through 2041 for both CL&P and NSTAR Electric and 2033 for PSNH. As required by 2018 regulation, CL&P and UI entered into ten-year contracts to purchase a combined total of approximately 9 million MWh annually from the Millstone Nuclear Power Station generation facility. On March 15, 2019, CL&P and UI each signed a ten-year contract with the owner of Millstone Nuclear Power Station in order to purchase a combined amount of approximately 50 percent of the facility's output (approximately 40 percent by CL&P). The Millstone Nuclear Power Station has a 2,112 MW nameplate capacity. PURA approved the contracts on September 18, 2019. Energy deliveries and payments under these contracts began in the fourth quarter of 2019. CL&P and UI were also required by 2018 regulation to enter into eight-year contracts to purchase a combined amount of approximately 18 percent of the facility's output (approximately 15 percent by CL&P) from the Seabrook Nuclear Power Plant beginning January 1, 2022. The Seabrook Nuclear Power Plant has an approximate 1,250 MW nameplate capacity. On November 22, 2019, CL&P and UI each signed an eight-year contract with the owner of the Seabrook Nuclear Power Plant. PURA approved the contracts on November 27, 2019. The total estimated future cost of the Millstone Nuclear Power Station and Seabrook Nuclear Power Plant energy purchase contracts are $3.6 billion and are reflected in the table above. CL&P sells the energy purchased under these contracts into the market and uses the proceeds from these energy sales to offset the contract costs. As the net costs under these contracts are recovered from customers in future rates, the contracts do not have an impact on the net income of CL&P. These contracts do not meet the definition of a derivative, and accordingly, the costs of these contracts are being accounted for as incurred. Excluded from the table above are long-term commitments of NSTAR Electric pertaining to the Massachusetts Clean Energy 83D contract, for which construction had not commenced by December 31, 2020. Estimated costs under this contract are expected to begin in 2023 and range between $150 million and $415 million per year under a 20-year contract, totaling approximately $6.7 billion. The contractual obligations table above does not include long-term commitments signed by CL&P and NSTAR Electric, as required by the PURA and DPU, respectively, for the purchase of renewable energy and related products that are contingent on the future construction of energy facilities. Natural Gas Procurement: Eversource's natural gas distribution businesses have long-term contracts for the purchase, transportation and storage of natural gas as part of its portfolio of supplies, which extend through 2045. Long-term purchases for natural gas procurement include contracts of EGMA, which was formed as a result of the CMA asset acquisition. Purchased Power and Capacity: These contracts include capacity CfDs of CL&P through 2026, and various IPP contracts or purchase obligations for electricity which extend through 2024 for CL&P, 2031 for NSTAR Electric and 2023 for PSNH. CL&P, along with UI, has three capacity CfDs consisting of two generation units and one demand response project. The combined capacities of these contracts as of December 31, 2020 and 2019 were 675 MW and 676 MW, respectively. The capacity CfDs extend through 2026 and obligate both CL&P and UI to make or receive payments on a monthly basis to or from the generation facilities based on the difference between a set contractual capacity price and the capacity market prices received by the generation facilities in the ISO-NE capacity markets. CL&P has a sharing agreement with UI, whereby UI shares 20 percent of the costs and benefits of these contracts. CL&P's portion of the costs and benefits of these contracts will be paid by, or refunded to, CL&P's customers. The contractual obligations table above does not include CL&P's, NSTAR Electric's or PSNH's standard/basic service contracts for the purchase of energy supply, the amounts of which vary with customers' energy needs. Peaker CfDs: CL&P, along with UI, has three peaker CfDs for a total of approximately 500 MW of peaking capacity through 2042. CL&P has a sharing agreement with UI, whereby CL&P is responsible for 80 percent and UI for 20 percent of the net costs or benefits of these CfDs. The Peaker CfDs pay the generation facility owner the difference between capacity, forward reserve and energy market revenues and a cost-of-service payment stream for 30 years. The ultimate cost or benefit to CL&P under these contracts will depend on the costs of plant operation and the prices that the projects receive for capacity and other products in the ISO-NE markets. CL&P's portion of the amounts paid or received under the Peaker CfDs are recovered from, or refunded to, CL&P's customers. 92
  2. Page 106 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 106 of 136 Transmission Support Commitments: Along with other New England utilities, CL&P, NSTAR Electric and PSNH entered into a series of agreements in the 1980’s to support the costs of, and receive rights to use, transmission and terminal facilities that were built to import electricity from the Hydro-Québec system in Canada. CL&P, NSTAR Electric and PSNH were obligated to pay, over a 30-year period ending in 2020, their proportionate shares of the annual operation and maintenance expenses and capital costs of those facilities. On December 18, 2020, the parties to these agreements submitted to FERC an offer of settlement and amendments to these agreements implementing the terms of an extension for an additional 20-year period. The parties have requested these terms to be placed in effect as of January 1, 2021 or such other date as authorized by FERC. The estimated future annual costs included in the contractual obligations table above, are subject to the approval of these amendments by FERC and can vary as a result. The total costs incurred under these agreements were as follows: Eversource For the Years Ended December 31, 2020 (Millions of Dollars) $ Renewable Energy 2019 584.2 $ 2018 320.8 $ 218.5 Natural Gas Procurement 453.4 448.5 432.4 Purchased Power and Capacity 62.7 62.1 72.0 Peaker CfDs 22.7 13.0 20.9 Transmission Support Commitments 22.1 21.8 23.4 For the Years Ended December 31, CL&P (Millions of Dollars) Renewable Energy $ 426.3 $ 2020 2019 2018 NSTAR Electric NSTAR Electric NSTAR Electric 88.8 PSNH $ 69.1 CL&P $ 160.6 $ 89.9 PSNH $ 70.3 CL&P $ 63.2 $ 89.8 PSNH $ 65.5 Purchased Power and Capacity 59.3 3.1 0.3 50.4 5.1 6.6 49.4 4.4 Peaker CfDs 22.7 — — 13.0 — — 20.9 — 18.2 — Transmission Support Commitments 8.7 8.7 4.7 8.6 8.6 4.6 9.2 9.2 5.0 C. Spent Nuclear Fuel Obligations - Yankee Companies CL&P, NSTAR Electric and PSNH have plant closure and fuel storage cost obligations to the Yankee Companies, which have each completed the physical decommissioning of their respective nuclear power facilities and are now engaged in the long-term storage of their spent fuel. The Yankee Companies fund these costs through litigation proceeds received from the DOE and, to the extent necessary, through wholesale, FERCapproved rates charged under power purchase agreements with several New England utilities, including CL&P, NSTAR Electric and PSNH. CL&P, NSTAR Electric and PSNH, in turn recover these costs from their customers through state regulatory commission-approved retail rates. The Yankee Companies collect amounts that management believes are adequate to recover the remaining plant closure and fuel storage cost estimates for the respective plants. Management believes CL&P and NSTAR Electric will recover their shares of these obligations from their customers. PSNH has recovered its total share of these costs from its customers. Spent Nuclear Fuel Litigation: The Yankee Companies have filed complaints against the DOE in the Court of Federal Claims seeking monetary damages resulting from the DOE's failure to accept delivery of, and provide for a permanent facility to store, spent nuclear fuel pursuant to the terms of the 1983 spent fuel and highlevel waste disposal contracts between the Yankee Companies and the DOE. The court previously awarded the Yankee Companies damages for Phases I, II and III of litigation resulting from the DOE's failure to meet its contractual obligations. These Phases covered damages incurred in the years 1998 through 2012, and the awarded damages have been received by the Yankee Companies with certain amounts of the damages refunded to their customers. DOE Phase IV Damages - On May 22, 2017, each of the Yankee Companies filed a fourth set of lawsuits against the DOE in the Court of Federal Claims. The Yankee Companies sought monetary damages totaling $104.4 million for CYAPC, YAEC and MYAPC, resulting from the DOE's failure to begin accepting spent nuclear fuel for disposal covering the years from 2013 to 2016 (DOE Phase IV). On February 21, 2019, the Yankee Companies received a partial summary judgment and partial final judgment in their favor for the undisputed amount of monetary damages of $103.2 million. The court awarded CYAPC, YAEC and MYAPC damages of $40.7 million, $28.1 million and $34.4 million, respectively. The DOE did not appeal the court's judgment and the decision became final on April 23, 2019. On June 12, 2019, each of the Yankee Companies received the damages proceeds. On June 12, 2019, the court accepted an offer of judgment in the amount of $0.5 million to settle the disputed amount of approximately $1 million in Phase IV contested damages. The Yankee Companies received the $0.5 million payment in July 2019. In September 2019, the Yankee Companies made a required informational filing with FERC as to the use of proceeds, for which approval was received in the fourth quarter of 2019. In December 2019, YAEC and MYAPC returned proceeds of $5.4 million and $21.0 million, respectively, to its member companies, of which the Eversource utilities (CL&P, NSTAR Electric and PSNH) received a total of $2.8 million from YAEC and $5.0 million from MYAPC. The Eversource utilities refund these amounts received to their utility customers. Also, in December 2019, CYAPC paid $29.0 million to the DOE to partially settle its pre-1983 spent nuclear fuel obligation. 93
  3. Page 107 of 136Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 107 of 136 D. Guarantees and Indemnifications In the normal course of business, Eversource parent provides credit assurances on behalf of its subsidiaries, including CL&P, NSTAR Electric and PSNH, in the form of guarantees. Management does not anticipate a material impact to net income or cash flows as a result of these various guarantees and indemnifications. Guarantees issued on behalf of unconsolidated entities, including equity method offshore wind investments, for which Eversource parent is the guarantor, are recorded at fair value as a liability on the balance sheet at the inception of the guarantee. Eversource regularly reviews performance risk under these guarantee arrangements, and in the event it becomes probable that Eversource parent will be required to perform under the guarantee, the amount of probable payment will be recorded. The fair value of guarantees issued on behalf of unconsolidated entities are recorded within Other Long-Term Liabilities on the balance sheet, and was $0.5 million as of December 31, 2020. The following table summarizes Eversource parent's exposure to guarantees and indemnifications of its subsidiaries and affiliates to external parties as of December 31, 2020: Company (Obligor) Maximum Exposure (in millions) Description North East Offshore LLC Construction-related purchase agreements with third-party contractors Eversource Investment LLC Funding and indemnification obligations of North East Offshore LLC (1) (2) $ Expiration Dates 30.5 (1) — (2) Sunrise Wind LLC OREC capacity production (3) 2.2 (3) South Fork Wind, LLC Transmission interconnection 1.7 — Bay State Wind LLC Real estate purchase 2.5 2021 Various Surety bonds (4) 56.6 2021 - 2023 Rocky River Realty Company and Eversource Service Lease payments for real estate 5.2 2024 (1) Eversource parent issued guarantees on behalf of its 50 percent-owned affiliate, North East Offshore LLC (NEO), under which Eversource parent agreed to guarantee 50 percent of NEO’s performance of obligations under certain purchase agreements with third-party contactors, in an amount not to exceed $1.3 billion with an expiration date in 2025. Eversource parent also issued a separate guarantee to Ørsted on behalf of NEO, under which Eversource parent agreed to guarantee 50 percent of NEO’s payment obligations under certain offshore wind project construction-related agreements with Ørsted in an aggregate amount not to exceed $62.5 million. Any amounts paid under this guarantee to Ørsted will count toward, but not increase, the maximum amount of the Funding Guarantee described in Note 2, below. The guarantee expires upon the full performance of the guaranteed obligations. (2) Eversource parent issued a guarantee (Funding Guarantee) on behalf of Eversource Investment LLC (EI), its wholly-owned subsidiary that holds a 50 percent ownership interest in NEO, under which Eversource parent agreed to guarantee certain funding obligations and certain indemnification payments of EI under the Amended and Restated Limited Liability Company Operating Agreement of NEO, in an amount not to exceed $910 million. The guaranteed obligations include payment of EI's funding obligations during the construction phase of NEO’s underlying offshore wind projects and indemnification obligations associated with third party credit support for its investment in NEO. Eversource parent’s obligations under the Funding Guarantee expire upon the full performance of the guaranteed obligations. (3) On October 25, 2019, Eversource parent issued a guarantee on behalf of its 50 percent-owned affiliate, Sunrise Wind LLC, whereby Eversource parent will guarantee Sunrise Wind LLC's performance of certain obligations, in an amount not to exceed $15.4 million, under the Offshore Wind Renewable Energy Certificate Purchase and Sale Agreement (the Agreement). The Agreement was executed on October 23, 2019, by and between the New York State Energy Research and Development Authority (NYSERDA) and Sunrise Wind LLC. The guarantee expires upon the full performance of the guaranteed obligations. (4) Surety bond expiration dates reflect termination dates, the majority of which will be renewed or extended. Certain surety bonds contain credit ratings triggers that would require Eversource parent to post collateral in the event that the unsecured debt credit ratings of Eversource parent are downgraded. Letter of Credit: On September 16, 2020, Eversource parent entered into a guarantee on behalf of Eversource Investment LLC, which holds Eversource's investments in offshore wind-related equity method investments, under which Eversource parent would guarantee Eversource Investment LLC's obligations under a letter of credit facility with a financial institution that Eversource Investment LLC may request in an aggregate amount of up to approximately $25 million. E. FERC ROE Complaints Four separate complaints were filed at the FERC by combinations of New England state attorneys general, state regulatory commissions, consumer advocates, consumer groups, municipal parties and other parties (collectively, the Complainants). In each of the first three complaints, filed on October 1, 2011, December 27, 2012, and July 31, 2014, respectively, the Complainants challenged the NETOs' base ROE of 11.14 percent that had been utilized since 2005 and sought an order to reduce it prospectively from the date of the final FERC order and for the separate 15-month complaint periods. In the fourth complaint, filed April 29, 2016, the Complainants challenged the NETOs' base ROE billed of 10.57 percent and the maximum ROE for transmission incentive (incentive cap) of 11.74 percent, asserting that these ROEs were unjust and unreasonable. 94
  4. Page 108 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 108 of 136 The ROE originally billed during the period October 1, 2011 (beginning of the first complaint period) through October 15, 2014 consisted of a base ROE of 11.14 percent and incentives up to 13.1 percent. On October 16, 2014, the FERC set the base ROE at 10.57 percent and the incentive cap at 11.74 percent for the first complaint period. This was also effective for all prospective billings to customers beginning October 16, 2014. This FERC order was vacated on April 14, 2017 by the U.S. Court of Appeals for the D.C. Circuit (the Court). All amounts associated with the first complaint period have been refunded, which totaled $38.9 million (pre-tax and excluding interest) at Eversource and reflected both the base ROE and incentive cap prescribed by the FERC order. The refund consisted of $22.4 million for CL&P, $13.7 million for NSTAR Electric and $2.8 million for PSNH. Eversource has recorded a reserve of $39.1 million (pre-tax and excluding interest) for the second complaint period as of both December 31, 2020 and 2019. This reserve represents the difference between the billed rates during the second complaint period and a 10.57 percent base ROE and 11.74 percent incentive cap. The reserve consisted of $21.4 million for CL&P, $14.6 million for NSTAR Electric and $3.1 million for PSNH as of both December 31, 2020 and 2019. On October 16, 2018, FERC issued an order on all four complaints describing how it intends to address the issues that were remanded by the Court. FERC proposed a new framework to determine (1) whether an existing ROE is unjust and unreasonable and, if so, (2) how to calculate a replacement ROE. Initial briefs were filed by the NETOs, Complainants and FERC Trial Staff on January 11, 2019 and reply briefs were filed on March 8, 2019. The NETOs' brief was supportive of the overall ROE methodology determined in the October 16, 2018 order provided the FERC does not change the proposed methodology or alter its implementation in a manner that has a material impact on the results. The FERC order included illustrative calculations for the first complaint using FERC's proposed frameworks with financial data from that complaint. Those illustrative calculations indicated that for the first complaint period, for the NETOs, which FERC concludes are of average financial risk, the preliminary just and reasonable base ROE is 10.41 percent and the preliminary incentive cap on total ROE is 13.08 percent. If the results of the illustrative calculations were included in a final FERC order for each of the complaint periods, then a 10.41 percent base ROE and a 13.08 percent incentive cap would not have a significant impact on our financial statements for all of the complaint periods. These preliminary calculations are not binding and do not represent what we believe to be the most likely outcome of a final FERC order. On November 21, 2019, FERC issued Opinion No. 569 affecting the two pending transmission ROE complaints against the Midcontinent ISO (MISO) transmission owners, in which FERC adopted a new methodology for determining base ROEs. Various parties sought rehearing. On December 23, 2019, the NETOs filed supplementary materials in the NETOs' four pending cases to respond to this new methodology because of the uncertainty of the applicability to the NETOs' cases. On May 21, 2020, the FERC issued its order in Opinion No. 569-A on the rehearing of the MISO transmission owners' cases, in which FERC again changed its methodology for determining the MISO transmission owners' base ROEs. Various parties appealed the MISO transmission owners' opinion. On November 19, 2020, the FERC issued Opinion No. 569-B denying rehearing of Opinion No. 569-A and reaffirmed the methodology previously adopted in Opinion No. 569-A. The new methodology differs significantly from the methodology proposed by FERC in its October 16, 2018 order to determine the NETOs' base ROEs in its four pending cases. Given the significant uncertainty regarding the applicability of the FERC opinions in the MISO transmission owners' two complaint cases to the NETOs' pending four complaint cases, Eversource concluded that there is no reasonable basis for a change to the reserve or recognized ROEs for any of the complaint periods at this time. As well, Eversource cannot reasonably estimate a range of any gain or loss for any of the four complaint proceedings at this time. Eversource, CL&P, NSTAR Electric and PSNH currently record revenues at the 10.57 percent base ROE and incentive cap at 11.74 percent established in the October 16, 2014 FERC order. A change of 10 basis points to the base ROE used to establish the reserves would impact Eversource’s after-tax earnings by an average of approximately $3 million for each of the four 15-month complaint periods. F. Eversource and NSTAR Electric Boston Harbor Civil Action In 2016, the United States Attorney on behalf of the United States Army Corps of Engineers filed a civil action in the United States District Court for the District of Massachusetts against NSTAR Electric, HEEC, and the Massachusetts Water Resources Authority (together with NSTAR Electric and HEEC, the "Defendants"). The action alleged that the Defendants failed to comply with certain permitting requirements related to the placement of the HEEC-owned electric distribution cable beneath Boston Harbor. The parties reached a settlement pursuant to which HEEC agreed to install a new 115kV distribution cable across Boston Harbor to Deer Island, utilizing a different route, and remove portions of the existing cable. Construction of the new distribution cable was completed in August 2019 and removal of the portions of the existing cable was completed in January 2020. All issues surrounding the current permit from the United States Army Corps of Engineers are expected to be resolved, and subsequently, such litigation then dismissed with prejudice. NSTAR Electric agreed to provide a rate base credit of $17.5 million to the Massachusetts Water Resources Authority for the new cable. This negotiated credit resulted in the initial $17.5 million of construction costs on the new cable being expensed as incurred, all of which was fully expensed in 2018. In connection with the new cable that was placed into service, a corresponding ARO was recognized for approximately $32 million within Other Long-Term Liabilities on the Eversource and NSTAR Electric balance sheets as of December 31, 2019. 95
  5. Page 109 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 109 of 136 G. Litigation and Legal Proceedings Eversource, including CL&P, NSTAR Electric and PSNH, are involved in legal, tax and regulatory proceedings regarding matters arising in the ordinary course of business, which involve management's assessment to determine the probability of whether a loss will occur and, if probable, its best estimate of probable loss. The Company records and discloses losses when these losses are probable and reasonably estimable, and discloses matters when losses are probable but not estimable or when losses are reasonably possible. Legal costs related to the defense of loss contingencies are expensed as incurred. 14. LEASES Eversource, including CL&P, NSTAR Electric and PSNH, has entered into lease agreements as a lessee for the use of land, office space, service centers, vehicles, information technology, and equipment. These lease agreements are classified as either finance or operating leases and the liability and right-of-use asset are recognized on the balance sheet at lease commencement. Leases with an initial term of 12 months or less are not recorded on the balance sheet and are recognized as lease expense on a straight-line basis over the lease term. Eversource determines whether or not a contract contains a lease based on whether or not it provides Eversource with the use of a specifically identified asset for a period of time, as well as both the right to direct the use of that asset and receive the significant economic benefits of the asset. Eversource has elected the practical expedient to not separate non-lease components from lease components and instead to account for both as a single lease component, with the exception of the information technology asset class where the lease and non-lease components are separated. The provisions of Eversource, CL&P, NSTAR Electric and PSNH lease agreements contain renewal options. The renewal options range from one year to twenty years. The renewal period is included in the measurement of the lease liability if it is reasonably certain that Eversource will exercise these renewal options. For leases entered into or modified after the January 1, 2019 implementation date, the discount rate utilized for classification and measurement purposes as of the inception date of the lease is based on each company's collateralized incremental interest rate to borrow over a comparable term for an individual lease because the rate implicit in the lease is not determinable. CL&P and PSNH entered into certain contracts for the purchase of energy that qualify as leases. These contracts do not have minimum lease payments and therefore are not recognized as a lease liability on the balance sheet and are not reflected in the future minimum lease payments table below. Expense related to these contracts is included as variable lease cost in the table below. The expense and long-term obligation for these contracts are also included in Note 13B, "Commitments and Contingencies - Long-Term Contractual Arrangements," to the financial statements. The components of lease cost, prior to amounts capitalized, are as follows: For the Years Ended December 31, 2020 (Millions of Dollars) Eversource Financing Lease Cost: Amortization of Right-of-use-Assets $ 2.6 Interest on Lease Liabilities Total Finance Lease Cost Operating Lease Cost Variable Lease Cost Total Lease Cost CL&P $ 0.7 $ 0.2 PSNH $ Eversource 0.1 $ 1.7 NSTAR Electric CL&P $ 0.7 $ 0.2 PSNH $ 0.1 1.4 0.3 0.6 — 1.2 0.6 0.6 — 4.0 11.1 1.0 0.6 0.8 2.1 0.1 0.1 2.9 11.7 1.3 0.5 0.8 3.4 0.1 0.1 57.8 $ 2019 NSTAR Electric 72.9 12.2 $ 13.8 — $ 2.9 45.6 $ 45.8 60.5 $ 75.1 13.3 $ 15.1 — $ 4.2 47.2 $ 47.4 Operating lease rental payments charged to expense in 2018 (which exclude CL&P's and PSNH's energy purchase contracts) were as follows: (Millions of Dollars) Eversource 2018 $ 10.8 NSTAR Electric CL&P $ 10.9 $ 11.8 PSNH $ 2.5 Operating lease cost, net of the capitalized portion, is included in Operations and Maintenance (or Purchased Power, Fuel and Transmission expense for transmission segment leases) on the statements of income. Amortization of finance lease assets is included in Depreciation on the statements of income. Interest expense on finance leases is included in Interest Expense on the statements of income. 96
  6. Page 110 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 110 of 136 Supplemental balance sheet information related to leases is as follows: As of December 31, 2020 (Millions of Dollars) Eversource Balance Sheet Classification CL&P NSTAR Electric PSNH Operating Leases: Operating Lease Right-of-use-Assets, Net Other Long-Term Assets $ Operating Lease Liabilities - Current Portion Other Current Liabilities $ Operating Lease Liabilities - Long-Term Other Long-Term Liabilities 55.2 $ 0.3 $ 9.5 $ 0.2 $ 23.6 $ 0.7 $ 0.3 Operating Lease Liabilities 45.7 0.1 — 22.9 0.3 $ 55.2 $ 0.3 $ 23.6 $ 0.3 Property, Plant and Equipment, Net $ 60.5 $ 0.7 $ 3.5 $ 0.8 Finance Lease Liabilities - Current Portion Other Current Liabilities $ 5.0 $ 1.4 $ — $ 0.1 Finance Lease Liabilities - Long-Term Other Long-Term Liabilities Total Operating Lease Liabilities Finance Leases: Finance Lease Right-of-use-Assets, Net Finance Lease Liabilities 57.6 $ Total Finance Lease Liabilities — 62.6 $ 4.8 1.4 $ 4.8 0.7 $ 0.8 As of December 31, 2019 (Millions of Dollars) Operating Leases: Operating Lease Right-of-use-Assets, Net Eversource Balance Sheet Classification Other Long-Term Assets $ Operating Lease Liabilities - Current Portion Other Current Liabilities $ Operating Lease Liabilities - Long-Term Other Long-Term Liabilities CL&P NSTAR Electric 49.9 $ 0.7 $ 8.6 $ 0.5 $ PSNH 24.2 $ 0.4 0.7 $ 0.1 Operating Lease Liabilities 41.3 0.2 23.5 0.3 $ 49.9 $ 0.7 $ 24.2 $ 0.4 Property, Plant and Equipment, Net $ 8.2 $ 1.9 $ 3.3 $ 0.9 Finance Lease Liabilities - Current Portion Other Current Liabilities $ 2.4 $ 1.6 $ — $ 0.1 Finance Lease Liabilities - Long-Term Other Long-Term Liabilities Total Operating Lease Liabilities Finance Leases: Finance Lease Right-of-use-Assets, Net Finance Lease Liabilities 8.1 $ Total Finance Lease Liabilities 1.4 10.5 $ 4.4 3.0 $ 4.4 0.8 $ 0.9 The finance lease payments that NSTAR Electric will make over the next twelve months are entirely interest-related, due to escalating payments. As such, none of the finance lease payments over the next twelve months will reduce the finance lease liability. Other information related to leases is as follows (in millions of dollars, unless otherwise noted): As of December 31, 2020 Eversource 2019 NSTAR Electric CL&P PSNH Eversource NSTAR Electric CL&P PSNH Weighted-Average Remaining Lease Term (Years): Operating Leases 10 3 19 8 12 2 20 9 Finance Leases 17 1 21 8 12 2 22 9 Weighted-Average Discount Rate (Percentage): Operating Leases 4.0 % 2.4 % 4.1 % 3.7 % 3.9 % 2.5 % 4.1 % 3.7 % Finance Leases 2.9 % 10.5 % 2.9 % 3.5 % 4.0 % 10.5 % 2.9 % 3.5 % Eversource CL&P NSTAR Electric PSNH For the Year Ended December 31, 2020 Cash Paid for Amounts Included in the Measurement of Lease Liabilities: Operating Cash Flows from Operating Leases $ 10.9 $ 0.6 $ 1.8 $ 0.1 Operating Cash Flows from Finance Leases 1.7 0.3 0.6 — Financing Cash Flows from Finance Leases 2.8 1.6 — 0.1 Right-of-use-Assets Obtained in Exchange for New Operating Lease Liabilities 0.6 0.1 0.2 — Right-of-use-Assets Obtained in Exchange for New Finance Lease Liabilities 0.7 — 0.3 — Supplemental Non-Cash Information on Lease Liabilities: 97
  7. Page 111 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 111 of 136 Eversource also acquired $14.7 million of right-of-use assets in exchange for the assumption of new operating lease liabilities and $54.2 million of right-of-use assets in exchange for the assumption of new finance lease liabilities as a result of the CMA asset acquisition. Eversource CL&P NSTAR Electric PSNH For the Year Ended December 31, 2019 Cash Paid for Amounts Included in the Measurement of Lease Liabilities: Operating Cash Flows from Operating Leases $ 11.4 $ 0.4 $ 1.6 $ 0.1 Operating Cash Flows from Finance Leases 1.2 0.6 0.6 — Financing Cash Flows from Finance Leases 2.6 1.4 — 0.1 Right-of-use-Assets Obtained in Exchange for New Operating Lease Liabilities 2.9 1.0 0.1 0.2 Right-of-use-Assets Obtained in Exchange for New Finance Lease Liabilities 2.0 — — — Supplemental Non-Cash Information on Lease Liabilities: Future minimum lease payments, excluding variable costs, under long-term leases, as of December 31, 2020 are as follows: Operating Leases (Millions of Dollars) Eversource Year Ending December 31, 2021 $ 11.4 CL&P $ 0.2 Finance Leases NSTAR Electric $ 1.6 PSNH $ Eversource 0.1 $ 7.2 NSTAR Electric CL&P $ 1.5 $ PSNH 0.6 $ 0.1 2022 9.0 0.1 1.6 0.1 5.7 — 0.6 0.1 2023 6.4 — 1.6 0.1 4.9 — 0.6 0.1 2024 4.5 — 1.7 — 4.8 — 0.7 0.1 2025 3.4 — 1.7 — 4.7 — 0.7 0.1 Thereafter 36.2 — 27.0 0.1 60.7 — 13.0 0.4 Future lease payments Less amount representing interest 70.9 15.7 0.3 — 35.2 11.6 0.4 0.1 88.0 25.4 1.5 0.1 16.2 11.4 0.9 0.1 Present value of future minimum lease payments 15. $ 55.2 $ 0.3 $ 23.6 $ 0.3 $ 62.6 $ 1.4 $ 4.8 $ 0.8 FAIR VALUE OF FINANCIAL INSTRUMENTS The following methods and assumptions were used to estimate the fair value of each of the following financial instruments: Preferred Stock, Long-Term Debt and Rate Reduction Bonds: The fair value of CL&P's and NSTAR Electric's preferred stock is based upon pricing models that incorporate interest rates and other market factors, valuations or trades of similar securities and cash flow projections. The fair value of long-term debt and RRB debt securities is based upon pricing models that incorporate quoted market prices for those issues or similar issues adjusted for market conditions, credit ratings of the respective companies and treasury benchmark yields. The fair values provided in the table below are classified as Level 2 within the fair value hierarchy. Carrying amounts and estimated fair values are as follows: Eversource Carrying Amount Preferred Stock Not Subject to Mandatory Redemption Long-Term Debt CL&P NSTAR Electric Fair Value Fair Value $ 155.6 $ 169.1 $ 116.2 $ 123.4 $ 16,179.1 18,420.1 3,914.8 4,800.9 3,643.2 4,294.0 1,099.1 1,207.0 540.1 603.4 — — — — 540.1 603.4 Preferred Stock Not Subject to Mandatory Redemption $ 155.6 $ 162.0 $ 116.2 $ 117.8 $ Long-Term Debt 14,098.2 15,170.2 3,518.1 4,058.0 3,342.1 3,659.9 951.6 1,005.7 583.3 625.9 — — — — 583.3 625.9 (Millions of Dollars) Carrying Amount Fair Value PSNH Carrying Amount Carrying Amount Fair Value As of December 31, 2020: Rate Reduction Bonds 43.0 $ 45.7 $ — $ — As of December 31, 2019: Rate Reduction Bonds 43.0 $ 44.2 $ — $ — Derivative Instruments and Marketable Securities: Derivative instruments and investments in marketable securities are carried at fair value. For further information, see Note 4, "Derivative Instruments," and Note 5, "Marketable Securities," to the financial statements. See Note 1I, "Summary of Significant Accounting Policies – Fair Value Measurements," for the fair value measurement policy and the fair value hierarchy. 98
  8. Page 112 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 112 of 136 16. ACCUMULATED OTHER COMPREHENSIVE INCOME/(LOSS) The changes in accumulated other comprehensive income/(loss) by component, net of tax, are as follows: For the Year Ended December 31, 2020 Eversource (Millions of Dollars) Qualified Cash Flow Hedging Instruments Unrealized Gains on Marketable Securities Balance as of January 1st $ $ (3.0) 0.7 Defined Benefit Plans $ For the Year Ended December 31, 2019 Total (62.8) $ (65.1) Qualified Cash Flow Hedging Instruments Unrealized Gains/(Losses) on Marketable Securities $ $ (4.4) (0.5) Defined Benefit Plans $ (55.1) Total $ (60.0) OCI Before Reclassifications — 0.4 (19.6) (19.2) — 1.2 (13.3) Amounts Reclassified from AOCI 1.6 — 6.3 7.9 1.4 — 5.6 7.0 Net OCI 1.6 0.4 (13.3) (11.3) 1.4 1.2 (7.7) (5.1) Balance as of December 31st $ (1.4) $ 1.1 $ (76.1) $ (76.4) $ (3.0) $ 0.7 $ (62.8) (12.1) $ (65.1) Defined benefit plan OCI amounts before reclassifications relate to actuarial gains and losses that arose during the year and were recognized in AOCI. The unamortized actuarial gains and losses and prior service costs on the defined benefit plans are amortized from AOCI into Other Income, Net over the average future employee service period, and are reflected in amounts reclassified from AOCI. The related tax effects of the defined benefit plan OCI amounts before reclassifications recognized in AOCI were net deferred tax assets of $6.0 million and $4.4 million in 2020 and 2019, respectively, and deferred tax liabilities of $0.2 million in 2018. The following table sets forth the amounts reclassified from AOCI by component and the impacted line item on the statements of income: Amounts Reclassified from AOCI For the Years Ended December 31, Eversource (Millions of Dollars) 2020 2019 (2.5) $ Statements of Income Line Item Impacted 2018 Qualified Cash Flow Hedging Instruments Tax Effect $ Qualified Cash Flow Hedging Instruments, Net of Tax $ (1.6) $ (1.4) $ (1.8) Defined Benefit Plan Costs: Amortization of Actuarial Losses $ (8.1) $ (5.7) $ 0.9 Amortization of Prior Service Cost Total Defined Benefit Plan Costs Tax Effect (2.5) $ 1.1 (2.8) Interest Expense 1.0 Income Tax Expense (6.0) Other Income, Net (1) (0.3) (1.8) (0.4) Other Income, Net (1) (8.4) (7.5) (6.4) 2.1 1.9 1.6 Defined Benefit Plan Costs, Net of Tax $ (6.3) $ (5.6) $ (4.8) Total Amounts Reclassified from AOCI, Net of Tax $ (7.9) $ (7.0) $ (6.6) (1) Income Tax Expense These amounts are included in the computation of net periodic Pension, SERP and PBOP costs. See Note 1M, "Summary of Significant Accounting Policies – Other Income, Net" and Note 11A, "Employee Benefits – Pension Benefits and Postretirement Benefits Other Than Pension," for further information. As of December 31, 2020, it is estimated that a pre-tax amount of $1.8 million ($0.5 million for NSTAR Electric and $1.3 million for PSNH) will be reclassified from AOCI as a decrease to Net Income over the next 12 months as a result of the amortization of the interest rate swap agreements which have been settled. 17. DIVIDEND RESTRICTIONS Eversource parent's ability to pay dividends may be affected by certain state statutes, the ability of its subsidiaries to pay common dividends and the leverage restriction tied to its consolidated total debt to total capitalization ratio requirement in its revolving credit agreements. Pursuant to the joint revolving credit agreement of Eversource, CL&P, PSNH, NSTAR Gas, Yankee Gas and Aquarion Water Company of Connecticut, the joint revolving credit agreement of Eversource and EGMA, and to the NSTAR Electric revolving credit agreement, each company is required to maintain consolidated total indebtedness to total capitalization ratio of no greater than 65 percent at the end of each fiscal quarter. As of December 31, 2020, all companies were in compliance with such covenant and in compliance with all such provisions of the revolving credit agreements that may restrict the payment of dividends as of December 31, 2020. The Retained Earnings balances subject to dividend restrictions were $4.61 billion for Eversource, $2.17 billion for CL&P, $2.53 billion for NSTAR Electric and $615.0 million for PSNH as of December 31, 2020. CL&P, NSTAR Electric and PSNH are subject to Section 305 of the Federal Power Act that makes it unlawful for a public utility to make or pay a dividend from any funds "properly included in its capital account." Management believes that this Federal Power Act restriction, as applied to CL&P, NSTAR Electric and PSNH, would not be construed or applied by the FERC to prohibit the payment of dividends from retained earnings for lawful and legitimate business purposes. In addition, certain state statutes may impose additional limitations on such companies and on NSTAR Gas, Yankee Gas, EGMA, Aquarion Water Company of Connecticut, Aquarion Water Company of Massachusetts and Aquarion Water Company of New Hampshire. Such state law restrictions do not restrict the payment of dividends from retained earnings or net income. 99
  9. Page 113 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 113 of 136 18. COMMON SHARES The following table sets forth the Eversource parent common shares and the shares of common stock of CL&P, NSTAR Electric and PSNH that were authorized and issued, as well as the respective per share par values: Shares Authorized as of December 31, 2020 and 2019 Par Value Eversource CL&P $ 5 $ NSTAR Electric $ PSNH $ Issued as of December 31, 2020 2019 380,000,000 357,818,402 345,858,402 10 24,500,000 6,035,205 6,035,205 1 100,000,000 200 200 1 100,000,000 301 301 Common Share Issuances and 2019 Forward Sale Agreement: On June 15, 2020, Eversource completed an equity offering of 6,000,000 common shares at a price per share of $86.26. Eversource used the net proceeds of this offering to fund a portion of the purchase of the assets of CMA that closed on October 9, 2020. The issuance of these common shares resulted in proceeds of $509.2 million, net of issuance costs. In June 2019, Eversource completed an equity offering consisting of 5,980,000 common shares issued directly by the Company and 11,960,000 common shares issuable pursuant to a forward sale agreement with an investment bank. Under the forward sale agreement, 11,960,000 common shares were borrowed from third parties and sold by the underwriters. The forward sale agreement allowed Eversource, at its election and prior to May 29, 2020, to physically settle the forward sale agreement by issuing common shares in exchange for net proceeds at the then-applicable forward sale price specified by the agreement (initially, $71.48 per share) or, alternatively, to settle the forward sale agreement in whole or in part through the delivery or receipt of shares or cash. The forward sale price was subject to adjustment daily based on a floating interest rate factor and would decrease in respect of certain fixed amounts specified in the agreement, such as dividends. Eversource issued 6,000,000 common shares under the forward sale agreement in December 2019. On March 23, 2020, Eversource physically settled a portion of the forward sale agreement by delivering 1,500,000 common shares in exchange for net proceeds of $105.7 million. Subsequently, on March 26, 2020, Eversource physically settled the remaining portion of the forward sale agreement by delivering 4,460,000 common shares in exchange for net proceeds of $314.1 million. The forward sale price used to determine the cash proceeds received by Eversource was calculated based on the initial forward sale price, as adjusted in accordance with the forward sale agreement. The March and June 2020 common share issuances of 5,960,000 and 6,000,000, respectively, resulted in total proceeds of $929.0 million, net of issuance costs. The June and December 2019 common share issuances of 5,980,000 and 6,000,000, respectively, resulted in total proceeds of $852.3 million. These issuances were reflected in shareholders’ equity and as financing activities on the statements of cash flows. Issuances of shares under the forward sale agreement were classified as equity transactions. Accordingly, no amounts relating to the forward sale agreement were recorded in the financial statements until settlements took place. Prior to any settlements, the only impact of the forward sale agreement to the financial statements was the inclusion of incremental shares within the calculation of diluted EPS using the treasury stock method. See Note 21, "Earnings Per Share," to the financial statements for information on the forward sale agreement’s impact on the calculation of diluted EPS. Eversource used the net proceeds received from the direct issuance of common shares and the net proceeds received from settlement of the forward sale agreement to repay short-term debt under the commercial paper program, to partially fund the purchase of the assets of CMA, to fund capital spending and clean energy initiatives, and for general corporate purposes. Treasury Shares: As of December 31, 2020 and 2019, there were 14,864,379 and 15,977,757 Eversource common shares held as treasury shares, respectively. As of December 31, 2020 and 2019, there were 342,954,023 and 329,880,645 Eversource common shares outstanding, respectively. Eversource issues treasury shares to satisfy awards under the Company's incentive plans, shares issued under the dividend reinvestment and share purchase plan, and matching contributions under the Eversource 401k Plan. The issuance of treasury shares represents a non-cash transaction, as the treasury shares were used to fulfill Eversource's obligations that require the issuance of common shares. 19. PREFERRED STOCK NOT SUBJECT TO MANDATORY REDEMPTION The CL&P and NSTAR Electric preferred stock is not subject to mandatory redemption and is presented as a noncontrolling interest of a subsidiary in Eversource's financial statements. CL&P is authorized to issue up to 9,000,000 shares of preferred stock, par value $50 per share, and NSTAR Electric is authorized to issue 2,890,000 shares of preferred stock, par value $100 per share. Holders of preferred stock of CL&P and NSTAR Electric are entitled to receive cumulative dividends in preference to any payment of dividends on the common stock. Upon liquidation, holders of preferred stock of CL&P and NSTAR Electric are entitled to receive a liquidation preference before any distribution to holders of common stock in an amount equal to the par value of the preferred stock plus accrued and unpaid dividends. If the net assets were to be insufficient to pay the liquidation preference in full, then the net assets would be distributed ratably to all holders of preferred stock. The preferred stock of CL&P and NSTAR Electric is subject to optional redemption by the CL&P and NSTAR Electric Boards of Directors at any time. 100
  10. Page 114 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 114 of 136 Details of preferred stock not subject to mandatory redemption are as follows (in millions, except in redemption price and shares): Redemption Price Per Share Series Shares Outstanding as of December 31, 2020 As of December 31, 2019 2020 2019 CL&P $1.90 Series of 1947 $ 52.50 163,912 163,912 $2.00 Series of 1947 $ 54.00 336,088 336,088 $ 8.2 $ $2.04 Series of 1949 $ 52.00 100,000 100,000 5.0 5.0 $2.20 Series of 1949 $ 52.50 200,000 200,000 10.0 10.0 3.90% Series of 1949 $ 50.50 160,000 160,000 8.0 8.0 $2.06 Series E of 1954 $ 51.00 200,000 200,000 10.0 10.0 16.8 8.2 16.8 $2.09 Series F of 1955 $ 51.00 100,000 100,000 5.0 5.0 4.50% Series of 1956 $ 50.75 104,000 104,000 5.2 5.2 4.96% Series of 1958 $ 50.50 100,000 100,000 5.0 5.0 4.50% Series of 1963 $ 50.50 160,000 160,000 8.0 8.0 5.28% Series of 1967 $ 51.43 200,000 200,000 10.0 10.0 $3.24 Series G of 1968 $ 51.84 300,000 300,000 15.0 15.0 6.56% Series of 1968 $ 51.44 200,000 200,000 10.0 2,324,000 2,324,000 $ 116.2 $ 116.2 $ 18.0 $ 18.0 Total CL&P 10.0 NSTAR Electric 4.25% Series of 1956 $ 103.625 180,000 180,000 4.78% Series of 1958 $ 102.80 250,000 250,000 430,000 430,000 Total NSTAR Electric 25.0 $ 43.0 25.0 $ (3.6) Fair Value Adjustment due to Merger with NSTAR 43.0 (3.6) Other 6.00% Series of 1958 $ 100.00 23 Total Eversource - Noncontrolling Interest - Preferred Stock of Subsidiaries 20. 23 $ — $ — $ 155.6 $ 155.6 COMMON SHAREHOLDERS' EQUITY AND NONCONTROLLING INTERESTS Dividends on the preferred stock of CL&P and NSTAR Electric totaled $7.5 million for each of the years ended December 31, 2020, 2019 and 2018. These dividends were presented as Net Income Attributable to Noncontrolling Interests on the Eversource statements of income. Noncontrolling Interest – Preferred Stock of Subsidiaries on the Eversource balance sheets totaled $155.6 million as of December 31, 2020 and 2019. On the Eversource balance sheets, Common Shareholders' Equity was fully attributable to Eversource parent and Noncontrolling Interest – Preferred Stock of Subsidiaries was fully attributable to the noncontrolling interest. For the years ended December 31, 2020, 2019 and 2018, there was no change in ownership of the common equity of CL&P and NSTAR Electric. 101

Text of OCC-962 Attachment 2.pdf

Extracted from the file · 128 pages · 591,550 characters

Text of OCC-962 Attachment 1.pdf

Extracted from the file · 136 pages · 612,504 characters

Text of OCC-963 Attachment 8.pdf

Extracted from the file · 96 pages · 352,588 characters

Text of OCC-963 Attachment 7.pdf

Extracted from the file · 105 pages · 381,994 characters

Text of OCC-963 Attachment 6.pdf

Extracted from the file · 101 pages · 366,377 characters

Text of OCC-963 Attachment 5.pdf

Extracted from the file · 105 pages · 393,802 characters

Text of OCC-963 Attachment 4.pdf

Extracted from the file · 88 pages · 321,021 characters

Text of OCC-963 Attachment 3.pdf

Extracted from the file · 86 pages · 305,704 characters

Text of OCC-963 Attachment 2.pdf

Extracted from the file · 77 pages · 270,743 characters

Text of OCC-963 Attachment 1.pdf

Extracted from the file · 76 pages · 279,055 characters

As listed on the current system

Question(s) Answered 962, 963 (The Connecticut Light and Power Company) Date Filed: 10/20/2026

This filing on the current system (opens in a new tab)