Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 962, 963

Files18

Search terms highlighted
Eversource rate increase is on 409 pages across 16 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
44 pages match

Text of OCC-962 Attachment 7.pdf

Extracted from the file · 144 pages · 700,506 characters

Text of OCC-962 Attachment 6.pdf

Extracted from the file · 136 pages · 685,692 characters

Text of OCC-962 Attachment 5.pdf

Extracted from the file · 128 pages · 641,445 characters

Text of OCC-962 Attachment 4.pdf

Extracted from the file · 120 pages · 653,488 characters

41 pages match
  1. Page 99 of 136Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 99 of 136 The weighted average grant-date fair value of RSUs granted for the years ended December 31, 2020, 2019 and 2018 was $88.23, $67.91 and $56.69, respectively. As of December 31, 2020 and 2019, the number and weighted average grant-date fair value of unvested RSUs was 379,258 and $77.13 per share, and 439,293 and $63.06 per share, respectively. During 2020, there were 265,020 RSUs at a weighted average grant-date fair value of $62.99 per share that vested during the year and were either paid or deferred. As of December 31, 2020, 294,960 RSUs were fully vested and deferred and an additional 360,295 are expected to vest. Performance Shares: Eversource granted performance shares under the annual long-term incentive programs that vest based upon the extent to which Company goals are achieved at the end of three-year performance measurement periods. Performance shares are paid in shares, after the performance measurement period. A summary of performance share transactions is as follows: Performance Shares (Units) Weighted Average Grant-Date Fair Value Outstanding as of December 31, 2019 Granted 486,907 211,224 $ $ 60.30 75.36 Shares Issued (249,922) $ 55.72 (404) $ 89.85 447,805 $ 69.93 Forfeited Outstanding as of December 31, 2020 The weighted average grant-date fair value of performance shares granted for the years ended December 31, 2020, 2019 and 2018 was $75.36, $68.33 and $56.77, respectively. As of December 31, 2020 and 2019, the number and weighted average grant-date fair value of unvested performance shares was 404,698 and $70.85 per share, and 427,894 and $60.38 per share, respectively. During 2020, there were 233,426 performance shares at a weighted average grant-date fair value of $55.75 per share that vested during the year and were either paid or deferred. As of December 31, 2020, 43,107 performance shares were fully vested and deferred. Compensation Expense: The total compensation expense and associated future income tax benefits recognized by Eversource, CL&P, NSTAR Electric and PSNH for share-based compensation awards were as follows: Eversource For the Years Ended December 31, 2020 (Millions of Dollars) $ Compensation Expense Future Income Tax Benefit 2019 33.9 8.9 $ 2018 27.3 7.0 $ 21.4 5.4 For the Years Ended December 31, CL&P (Millions of Dollars) Compensation Expense Future Income Tax Benefit $ 10.9 2.9 2020 2019 2018 NSTAR Electric NSTAR Electric NSTAR Electric $ PSNH 11.3 3.0 $ 3.6 1.0 CL&P $ 9.8 2.5 $ 9.7 2.5 PSNH $ 3.3 0.8 CL&P $ 7.8 2.0 $ 7.7 1.9 PSNH $ 2.9 0.7 As of December 31, 2020, there was $19.3 million of total unrecognized compensation expense related to nonvested share-based awards for Eversource, including $3.6 million for CL&P, $5.7 million for NSTAR Electric, and $1.2 million for PSNH. This cost is expected to be recognized ratably over a weighted-average period of 1.74 years for Eversource, CL&P and PSNH, and 1.75 years NSTAR Electric. An income tax rate of 26 percent was used to estimate the tax effect on total share-based payments determined under the fair-value based method for all awards. Beginning in 2019, the Company began issuing treasury shares to settle fully vested RSUs and performance shares under the Company's incentive plans. For the years ended December 31, 2020, 2019 and 2018, excess tax benefits associated with the distribution of stock compensation awards reduced income tax expense by $6.6 million, $1.5 million, and $1.5 million, respectively, which increased cash flows from operating activities on the statements of cash flows. D. Other Retirement Benefits Eversource provides retirement and other benefits for certain current and past company officers. These benefits are accounted for on an accrual basis and expensed over a period equal to the service lives of the employees. The actuarially-determined liability for these benefits is included in Other Current and Long-Term Liabilities on the balance sheets. The related expense, which includes the allocation of expense associated with Eversource's service company officers that support CL&P, NSTAR Electric and PSNH, is included in Operations and Maintenance Expense on the income statements. The liability and expense amounts are as follows: As of and For the Years Ended December 31, Eversource (Millions of Dollars) Actuarially-Determined Liability Other Retirement Benefits Expense 2020 $ 2019 45.7 $ 2018 52.0 3.3 2.7 86 $ 49.1 2.7
  2. Page 100 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 100 of 136 As of and For the Years Ended December 31, CL&P (Millions of Dollars) Actuarially-Determined Liability $ 0.2 Other Retirement Benefits Expense 12. 2020 2019 2018 NSTAR Electric NSTAR Electric NSTAR Electric $ PSNH 0.1 1.2 $ CL&P 1.7 1.1 $ 0.2 0.5 $ PSNH 0.1 1.0 $ CL&P 1.7 0.9 $ 0.3 0.4 $ 0.1 1.1 1.1 CL&P PSNH $ 1.7 0.4 INCOME TAXES The components of income tax expense are as follows: For the Years Ended December 31, Eversource (Millions of Dollars) 2020 Current Income Taxes: Federal 2019 $ 73.6 State $ 2018 56.9 $ 106.5 19.1 10.5 10.6 Total Current 92.7 67.4 117.1 Deferred Income Taxes, Net: Federal 173.5 138.4 122.6 83.7 71.4 52.2 257.2 (3.7) 209.8 (3.7) 174.8 (2.9) State Total Deferred Investment Tax Credits, Net $ Income Tax Expense 346.2 $ 273.5 $ 289.0 For the Years Ended December 31, CL&P (Millions of Dollars) Current Income Taxes: Federal $ State Total Current Deferred Income Taxes, Net: Federal State Total Deferred Investment Tax Credits, Net Income Tax Expense $ 12.0 2020 2019 2018 NSTAR Electric NSTAR Electric NSTAR Electric $ 53.9 PSNH $ 20.6 CL&P $ 68.4 $ PSNH 82.6 $ 22.9 $ 54.2 $ 12.2 6.9 3.8 15.4 18.2 2.2 20.9 30.0 (0.5) 5.9 60.8 24.4 83.8 100.8 25.1 75.1 109.3 11.7 101.1 33.8 (1.3) 35.2 0.1 5.8 48.5 27.9 15.4 43.4 38.8 8.6 18.8 27.0 10.1 6.4 13.5 20.5 144.5 (0.7) 72.6 (2.6) 7.3 — 54.0 (0.8) 27.1 (2.6) 15.9 — 54.9 (0.9) 41.4 (1.8) 35.9 — 149.7 $ 130.8 $ 31.7 $ 137.0 $ 125.3 $ 41.0 $ 129.1 For the Years Ended December 31, Eversource (Millions of Dollars, except percentages) Income Before Income Tax Expense 2020 $ Statutory Federal Income Tax Expense at 21% 2019 1,558.9 $ 327.4 2018 1,190.1 $ 1,329.5 249.9 279.2 (30.8) Tax Effect of Differences: Depreciation (11.1) 1.9 Investment Tax Credit Amortization (3.7) (3.7) (2.9) State Income Taxes, Net of Federal Impact 44.9 24.6 44.4 (5.1) Dividends on ESOP (5.1) (5.1) Tax Asset Valuation Allowance/Reserve Adjustments 33.4 40.1 5.2 Excess Stock Benefit (6.6) (1.5) (1.5) EDIT Amortization (48.7) (37.4) (5.0) Other, Net 15.7 4.7 Effective Tax Rate 79.3 (6.1) A reconciliation between income tax expense and the expected tax expense at the statutory rate is as follows: Income Tax Expense $ PSNH $ 346.2 22.2 % 87 $ 273.5 23.0 % 5.5 $ 289.0 21.7 % $ 148.9 $ 47.6
  3. Page 101 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 101 of 136 For the Years Ended December 31, 2020 2019 2018 PSNH (Millions of Dollars, except percentages) CL&P NSTAR Electric PSNH CL&P NSTAR Electric PSNH CL&P NSTAR Electric Income Before Income Tax Expense $ 607.6 $ 575.8 $ 179.0 $ 547.8 $ 557.3 $ 175.0 $ 506.8 $ 532.0 $ 163.5 127.6 120.9 37.6 115.0 117.0 36.8 106.4 111.7 34.3 Depreciation 0.4 (3.7) (1.4) (0.2) (3.0) (0.8) (1.2) (2.8) 0.1 Investment Tax Credit Amortization (0.7) (2.6) — (0.8) (2.6) — (0.9) (1.8) — State Income Taxes, Net of Federal Impact (1.2) 36.0 9.8 2.5 35.7 9.8 14.5 33.2 15.8 Tax Asset Valuation Allowance/Reserve Adjustments 30.7 — — 24.5 — — 7.1 1.2 — Excess Stock Benefit (2.3) (2.3) (0.8) (0.5) (0.5) (0.2) (0.1) (0.1) (0.1) EDIT Amortization (9.0) (20.4) (15.4) (5.8) (22.9) (4.0) — — (4.4) Other, Net 4.2 2.9 1.9 2.3 1.6 (0.6) 3.3 7.5 $ 149.7 $ 130.8 31.7 $ 137.0 $ 125.3 41.0 $ 129.1 $ 148.9 Statutory Federal Income Tax Expense at 21% Tax Effect of Differences: Income Tax Expense Effective Tax Rate 24.6 % $ 22.7 % 17.7 % 25.0 % $ 22.5 % 23.4 % 25.5 % 1.9 $ 28.0 % 47.6 29.1 % Eversource, CL&P, NSTAR Electric and PSNH file a consolidated federal income tax return and unitary, combined and separate state income tax returns. These entities are also parties to a tax allocation agreement under which taxable subsidiaries do not pay any more taxes than they would have otherwise paid had they filed a separate company tax return, and subsidiaries generating tax losses, if any, are paid for their losses when utilized. Deferred tax assets and liabilities are recognized for the future tax effects of temporary differences between the carrying amounts and the tax basis of assets and liabilities. The tax effect of temporary differences is accounted for in accordance with the rate-making treatment of the applicable regulatory commissions and relevant accounting authoritative literature. The tax effects of temporary differences that give rise to the net accumulated deferred income tax obligations are as follows: As of December 31, 2020 (Millions of Dollars) Eversource Deferred Tax Assets: Employee Benefits $ 602.4 CL&P $ 144.5 2019 NSTAR Electric $ 79.8 PSNH $ 56.6 Eversource $ 509.4 NSTAR Electric CL&P $ 125.4 $ 54.8 PSNH $ 46.7 Derivative Liabilities 92.6 91.8 — — 105.0 103.6 — — Regulatory Deferrals - Liabilities 259.8 30.2 161.8 13.4 267.0 37.1 165.7 19.0 Allowance for Uncollectible Accounts 87.5 42.3 20.9 4.6 56.7 25.7 17.7 2.8 Tax Effect - Tax Regulatory Liabilities 810.9 331.4 271.8 105.2 830.4 333.5 280.9 111.3 Net Operating Loss Carryforwards 12.7 — — — 9.1 — — — Purchase Accounting Adjustment 54.5 — — — 58.7 — — — Other 200.3 100.9 14.3 19.8 190.4 92.0 35.8 20.0 2,120.7 48.3 741.1 33.7 548.6 — 199.6 — 2,026.7 43.0 717.3 24.9 554.9 — 199.8 — Total Deferred Tax Assets Less: Valuation Allowance Net Deferred Tax Assets $ 2,072.4 $ Deferred Tax Liabilities: Accelerated Depreciation and Other Plant-Related Differences $ 4,153.6 88.7 Property Tax Accruals 707.4 $ 548.6 $ 199.6 $ 1,983.7 $ $ 1,438.1 $ 1,489.4 $ 453.8 $ 3,901.0 39.0 37.0 5.8 76.8 692.4 $ 554.9 $ 199.8 $ 1,362.2 $ 1,391.9 $ 428.9 36.8 29.0 4.7 Regulatory Amounts: Regulatory Deferrals - Assets 1,376.7 444.8 324.4 263.4 1,155.6 340.7 276.2 260.9 Tax Effect - Tax Regulatory Assets 244.6 174.4 11.3 8.6 238.2 171.7 11.7 8.3 Goodwill Regulatory Asset - 1999 Merger 86.0 — 73.8 — 90.6 — 77.8 — Derivative Assets 17.8 17.8 — — 19.7 19.7 — — Other 200.3 1.6 72.6 5.6 257.6 5.9 125.6 3.2 $ 6,167.7 $ 2,115.7 $ 2,008.5 737.2 $ 5,739.5 $ 1,937.0 $ 1,912.2 Total Deferred Tax Liabilities 88 $ $ 706.0
  4. Page 102 of 136Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 102 of 136 2020 Federal Legislation: On March 27, 2020, President Trump signed the $2.2 trillion bipartisan Coronavirus Aid, Relief, and Economic Security (CARES) Act. Among other provisions, the CARES Act provides for loans and other benefits to small and large businesses, expanded unemployment insurance, direct payments to those with wages middle-income and below, new appropriations funding for health care and other priorities, and tax changes like deferrals of employer payroll tax liabilities coupled with an employee retention tax credit and rollbacks of Tax Cuts and Jobs Act of 2017 limitations on net operating losses and certain business interest limitation. For the year ended December 31, 2020, we have recorded a tax liability of approximately $39 million related to the deferral of employer payroll tax liability provision. Fifty percent of the deferral of employer payroll tax liability must be paid by December 31, 2021 and the remaining amount by December 31, 2022. Other than the cash flow benefit described, the CARES Act did not have a material impact. On December 27, 2020, President Trump signed into law H.R. 133, the “Consolidated Appropriations Act, 2021.” The House of Representatives and Senate previously passed the bill with overwhelming support. The legislation includes tax extenders as part of Division EE, the “Taxpayer Certainty and Disaster Tax Relief Act of 2020.” The provisions within the law include the extension of the Investment Tax Credit (ITC) for solar at 26 percent for facilities the construction of which begins through the end of 2022, at 22 percent for facilities the construction of which begins in 2023, and postponement of the date after which solar facilities placed in service receive only a 10 percent ITC to December 31, 2025, the extension of the ITC at 30 percent (with no phase-down) to offshore wind if construction begins by December 31, 2025 (qualifying offshore wind includes facilities located in the inland navigable waters or in the coastal waters of the U.S.), and the extension and expansion of the CARES Act employee retention tax credit for the period from January 1, 2021 through June 30, 2021, including increasing the credit rate from 50 percent to 70 percent of qualified wages, and increasing the per-employee creditable wages limit from $10,000 per year to $10,000 for each quarter. The tax credit provision impacts to Eversource are still being evaluated but are a significant positive development for the Company and provides the opportunity to generate additional tax credits in its renewable energy projects when the projects become operational. Carryforwards: The following table provides the amounts and expiration dates of state tax credit and loss carryforwards and federal tax credit and net operating loss carryforwards: As of December 31, 2020 (Millions of Dollars) Eversource Federal Net Operating Loss State Net Operating Loss $ — CL&P $ — 2019 NSTAR Electric $ — Expiration Range PSNH $ Eversource $ 19.8 CL&P $ — NSTAR Electric $ — Expiration Range PSNH — — — 2033 - 2037 183.4 — — — 2021 - 2040 65.5 — — $ — 2020 - 2038 State Tax Credit 186.6 133.4 — — 2020 - 2025 168.1 122.3 — — 2019 - 2024 State Charitable Contribution 10.2 — — — 2020 - 2024 9.9 — — — 2019 - 2023 In 2020, the company increased its valuation allowance reserve for state credits by $10.3 million ($8.8 million for CL&P), net of tax, to reflect an update for expiring tax credits. In 2019, the Company increased its valuation allowance reserve for state credits by $18.5 million ($14.2 million for CL&P), net of tax, to reflect an update for expiring tax credits. For 2020 and 2019, state credit and state loss carryforwards have been partially reserved by a valuation allowance of $48.3 million and $43.0 million (net of tax), respectively. Unrecognized Tax Benefits: A reconciliation of the activity in unrecognized tax benefits, all of which would impact the effective tax rate if recognized, is as follows: Eversource (Millions of Dollars) Balance as of January 1, 2018 $ 51.7 CL&P $ 18.1 Gross Increases - Current Year 9.2 3.2 Gross Decreases - Prior Year (6.5) (0.9) Lapse of Statute of Limitations (8.5) (2.2) Balance as of December 31, 2018 Gross Increases - Current Year 45.9 18.2 12.1 4.0 Gross Increases - Prior Year 3.4 3.3 Lapse of Statute of Limitations (6.4) (2.4) Balance as of December 31, 2019 Gross Increases - Current Year 55.0 11.9 23.1 4.6 Gross Increases - Prior Year 1.4 0.7 Lapse of Statute of Limitations (6.5) (2.6) Balance as of December 31, 2020 $ 61.8 $ 25.8 89
  5. Page 103 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 103 of 136 Interest and Penalties: Interest on uncertain tax positions is recorded and generally classified as a component of Other Interest Expense on the statements of income. However, when resolution of uncertainties results in the Company receiving interest income, any related interest benefit is recorded in Other Income, Net on the statements of income. No penalties have been recorded. The amount of interest expense/(income) on uncertain tax positions recognized and the related accrued interest payable/(receivable) are as follows: Other Interest Income Accrued Interest Expense For the Years Ended December 31, 2020 (Millions of Dollars) Eversource $ 2019 — $ As of December 31, 2018 — $ 2020 (1.7) $ 2019 0.1 $ 0.1 Tax Positions: During 2020 and 2019, Eversource did not resolve any of its uncertain tax positions. Open Tax Years: The following table summarizes Eversource, CL&P, NSTAR Electric, and PSNH's tax years that remain subject to examination by major tax jurisdictions as of December 31, 2020: Description Tax Years Federal Connecticut 2020 2017 - 2020 Massachusetts 2017 - 2020 New Hampshire 2017 - 2020 Eversource does not estimate to have an earnings impact related to unrecognized tax benefits during the next twelve months. 13. COMMITMENTS AND CONTINGENCIES A. Environmental Matters Eversource, CL&P, NSTAR Electric and PSNH are subject to environmental laws and regulations intended to mitigate or remove the effect of past operations and improve or maintain the quality of the environment. These laws and regulations require the removal or the remedy of the effect on the environment of the disposal or release of certain specified hazardous substances at current and former operating sites. Eversource, CL&P, NSTAR Electric and PSNH have an active environmental auditing and training program and each believes it is substantially in compliance with all enacted laws and regulations. Environmental reserves are accrued when assessments indicate it is probable that a liability has been incurred and an amount can be reasonably estimated. The approach used estimates the liability based on the most likely action plan from a variety of available remediation options, including no action required or several different remedies ranging from establishing institutional controls to full site remediation and monitoring. These liabilities are estimated on an undiscounted basis and do not assume that the amounts are recoverable from insurance companies or other third parties. The environmental reserves include sites at different stages of discovery and remediation and do not include any unasserted claims. These reserve estimates are subjective in nature as they take into consideration several different remediation options at each specific site. The reliability and precision of these estimates can be affected by several factors, including new information concerning either the level of contamination at the site, the extent of Eversource's, CL&P's, NSTAR Electric's and PSNH's responsibility for remediation or the extent of remediation required, recently enacted laws and regulations or changes in cost estimates due to certain economic factors. It is possible that new information or future developments could require a reassessment of the potential exposure to required environmental remediation. As this information becomes available, management will continue to assess the potential exposure and adjust the reserves accordingly. The amounts recorded as environmental reserves are included in Other Current Liabilities and Other Long-Term Liabilities on the balance sheets and represent management's best estimate of the liability for environmental costs, and take into consideration site assessment, remediation and long-term monitoring costs. The environmental reserves also take into account recurring costs of managing hazardous substances and pollutants, mandated expenditures to remediate contaminated sites and any other infrequent and non-recurring clean-up costs. A reconciliation of the activity in the environmental reserves is as follows: Eversource (Millions of Dollars) Balance as of January 1, 2019 Additions $ 64.7 CL&P $ NSTAR Electric 5.4 $ 10.9 PSNH $ 5.4 26.5 7.0 0.5 2.8 Payments/Reductions (10.2) (1.0) (3.4) (0.7) Balance as of December 31, 2019 Increase Due to CMA Asset Acquisition 81.0 22.9 11.4 — 8.0 — 7.5 — Additions 8.4 4.2 0.7 — Payments/Reductions (9.9) (3.3) (4.0) (0.4) Balance as of December 31, 2020 $ 102.4 $ 90 12.3 $ 4.7 $ 7.1
  6. Page 104 of 136Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 104 of 136 The number of environmental sites for which remediation or long-term monitoring, preliminary site work or site assessment is being performed are as follows: Eversource CL&P NSTAR Electric 63 57 2020 2019 15 15 PSNH 12 15 9 9 The increase in the reserve balance was due primarily to the addition of nine MGP sites at the EGMA natural gas business resulting from the CMA acquisition and changes in cost estimates at the natural gas companies MGP sites and at CL&P for which additional remediation will be required. Included in the number of sites and reserve amounts above are former MGP sites that were operated several decades ago and manufactured natural gas from coal and other processes, which resulted in certain by-products remaining in the environment that may pose a potential risk to human health and the environment, for which Eversource may have potential liability. The reserve balances related to these former MGP sites were $92.2 million and $67.9 million as of December 31, 2020 and 2019, respectively, and related primarily to the natural gas business segment. As of December 31, 2020, for 6 environmental sites (1 for CL&P) that are included in the Company's reserve for environmental costs, the information known and the nature of the remediation options allow for the Company to estimate the range of losses for environmental costs. As of December 31, 2020, $41.7 million (including $0.9 million for CL&P) had been accrued as a liability for these sites, which represents the low end of the range of the liabilities for environmental costs. Management believes that additional losses of up to approximately $33 million ($0.5 million at CL&P) may be incurred in executing current remediation plans for these sites. As of December 31, 2020, for 15 environmental sites (7 for CL&P and 2 for NSTAR Electric) that are included in the Company's reserve for environmental costs, management cannot reasonably estimate the exposure to loss in excess of the reserve, or range of loss, as these sites are under investigation and/or there is significant uncertainty as to what remedial actions, if any, the Company may be required to undertake. As of December 31, 2020, $17.5 million (including $2.6 million for CL&P and $0.4 million for NSTAR Electric) had been accrued as a liability for these sites. As of December 31, 2020, for the remaining 42 environmental sites (including 7 for CL&P, 10 for NSTAR Electric and 9 for PSNH) that are included in the Company's reserve for environmental costs, the $43.2 million accrual (including $8.8 million for CL&P, $4.3 million for NSTAR Electric and $7.1 million for PSNH) represents management's best estimate of the probable liability and no additional loss is anticipated at this time. PSNH, NSTAR Gas, EGMA and Yankee Gas have rate recovery mechanisms for MGP related environmental costs, therefore, changes in their respective environmental reserves do not impact Net Income. CL&P is allowed to defer certain environmental costs for future recovery. NSTAR Electric does not have a separate environmental cost recovery regulatory mechanism. B. Long-Term Contractual Arrangements Estimated Future Annual Costs: The estimated future annual costs of significant executed, non-cancelable, long-term contractual arrangements in effect as of December 31, 2020 are as follows: Eversource 2021 (Millions of Dollars) Renewable Energy $ 2022 650.0 $ 2023 716.8 $ 2024 652.3 $ 2025 648.8 $ Thereafter 651.5 $ Total 3,490.7 $ 6,810.1 Natural Gas Procurement 558.9 374.1 292.0 263.1 260.2 1,825.8 3,574.1 Purchased Power and Capacity 69.4 75.5 86.8 79.6 60.3 13.2 384.8 Peaker CfDs 30.0 34.2 46.9 41.6 31.3 102.4 286.4 Transmission Support Commitments 20.5 18.0 18.1 19.2 19.7 19.7 Total $ 1,328.8 $ 1,218.6 $ 1,096.1 $ 1,052.3 $ 1,023.0 $ 115.2 5,451.8 $ 11,170.6 CL&P 2021 (Millions of Dollars) $ Renewable Energy 2022 484.4 $ 2023 548.3 $ 2024 547.2 $ 2025 549.1 $ Thereafter 551.2 $ Total 2,645.5 $ 5,325.7 Purchased Power and Capacity 65.8 71.9 83.3 76.6 57.4 0.1 355.1 Peaker CfDs 30.0 34.2 46.9 41.6 31.3 102.4 286.4 Transmission Support Commitments 8.1 7.1 7.2 7.6 7.8 7.8 $ Total 588.3 $ 661.5 $ 684.6 $ 674.9 $ 647.7 $ 45.6 2,755.8 $ 6,012.8 NSTAR Electric 2021 (Millions of Dollars) Renewable Energy $ 2022 98.0 $ 2023 100.0 $ 2024 75.4 $ 2025 72.9 $ Thereafter 73.1 $ 522.1 Purchased Power and Capacity 3.1 3.1 3.0 3.0 2.9 13.1 Transmission Support Commitments 8.1 7.1 7.1 7.5 7.7 7.7 Total $ 109.2 $ 110.2 $ 85.5 91 $ 83.4 $ 83.7 $ 542.9 Total $ 941.5 28.2 45.2 $ 1,014.9
  7. Page 105 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 105 of 136 PSNH 2021 (Millions of Dollars) Renewable Energy $ 2022 67.6 $ 2023 68.5 $ 2024 29.7 $ 2025 26.8 $ Thereafter 27.2 $ 323.1 Total $ 542.9 Purchased Power and Capacity 0.5 0.5 0.5 — — — 1.5 Transmission Support Commitments 4.3 3.8 3.8 4.1 4.2 4.2 24.4 Total $ 72.4 $ 72.8 $ 34.0 $ 30.9 $ 31.4 $ 327.3 $ 568.8 Renewable Energy: Renewable energy contracts include non-cancellable commitments under contracts of CL&P, NSTAR Electric and PSNH for the purchase of energy and capacity from renewable energy facilities. Such contracts extend through 2041 for both CL&P and NSTAR Electric and 2033 for PSNH. As required by 2018 regulation, CL&P and UI entered into ten-year contracts to purchase a combined total of approximately 9 million MWh annually from the Millstone Nuclear Power Station generation facility. On March 15, 2019, CL&P and UI each signed a ten-year contract with the owner of Millstone Nuclear Power Station in order to purchase a combined amount of approximately 50 percent of the facility's output (approximately 40 percent by CL&P). The Millstone Nuclear Power Station has a 2,112 MW nameplate capacity. PURA approved the contracts on September 18, 2019. Energy deliveries and payments under these contracts began in the fourth quarter of 2019. CL&P and UI were also required by 2018 regulation to enter into eight-year contracts to purchase a combined amount of approximately 18 percent of the facility's output (approximately 15 percent by CL&P) from the Seabrook Nuclear Power Plant beginning January 1, 2022. The Seabrook Nuclear Power Plant has an approximate 1,250 MW nameplate capacity. On November 22, 2019, CL&P and UI each signed an eight-year contract with the owner of the Seabrook Nuclear Power Plant. PURA approved the contracts on November 27, 2019. The total estimated future cost of the Millstone Nuclear Power Station and Seabrook Nuclear Power Plant energy purchase contracts are $3.6 billion and are reflected in the table above. CL&P sells the energy purchased under these contracts into the market and uses the proceeds from these energy sales to offset the contract costs. As the net costs under these contracts are recovered from customers in future rates, the contracts do not have an impact on the net income of CL&P. These contracts do not meet the definition of a derivative, and accordingly, the costs of these contracts are being accounted for as incurred. Excluded from the table above are long-term commitments of NSTAR Electric pertaining to the Massachusetts Clean Energy 83D contract, for which construction had not commenced by December 31, 2020. Estimated costs under this contract are expected to begin in 2023 and range between $150 million and $415 million per year under a 20-year contract, totaling approximately $6.7 billion. The contractual obligations table above does not include long-term commitments signed by CL&P and NSTAR Electric, as required by the PURA and DPU, respectively, for the purchase of renewable energy and related products that are contingent on the future construction of energy facilities. Natural Gas Procurement: Eversource's natural gas distribution businesses have long-term contracts for the purchase, transportation and storage of natural gas as part of its portfolio of supplies, which extend through 2045. Long-term purchases for natural gas procurement include contracts of EGMA, which was formed as a result of the CMA asset acquisition. Purchased Power and Capacity: These contracts include capacity CfDs of CL&P through 2026, and various IPP contracts or purchase obligations for electricity which extend through 2024 for CL&P, 2031 for NSTAR Electric and 2023 for PSNH. CL&P, along with UI, has three capacity CfDs consisting of two generation units and one demand response project. The combined capacities of these contracts as of December 31, 2020 and 2019 were 675 MW and 676 MW, respectively. The capacity CfDs extend through 2026 and obligate both CL&P and UI to make or receive payments on a monthly basis to or from the generation facilities based on the difference between a set contractual capacity price and the capacity market prices received by the generation facilities in the ISO-NE capacity markets. CL&P has a sharing agreement with UI, whereby UI shares 20 percent of the costs and benefits of these contracts. CL&P's portion of the costs and benefits of these contracts will be paid by, or refunded to, CL&P's customers. The contractual obligations table above does not include CL&P's, NSTAR Electric's or PSNH's standard/basic service contracts for the purchase of energy supply, the amounts of which vary with customers' energy needs. Peaker CfDs: CL&P, along with UI, has three peaker CfDs for a total of approximately 500 MW of peaking capacity through 2042. CL&P has a sharing agreement with UI, whereby CL&P is responsible for 80 percent and UI for 20 percent of the net costs or benefits of these CfDs. The Peaker CfDs pay the generation facility owner the difference between capacity, forward reserve and energy market revenues and a cost-of-service payment stream for 30 years. The ultimate cost or benefit to CL&P under these contracts will depend on the costs of plant operation and the prices that the projects receive for capacity and other products in the ISO-NE markets. CL&P's portion of the amounts paid or received under the Peaker CfDs are recovered from, or refunded to, CL&P's customers. 92
  8. Page 106 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 106 of 136 Transmission Support Commitments: Along with other New England utilities, CL&P, NSTAR Electric and PSNH entered into a series of agreements in the 1980’s to support the costs of, and receive rights to use, transmission and terminal facilities that were built to import electricity from the Hydro-Québec system in Canada. CL&P, NSTAR Electric and PSNH were obligated to pay, over a 30-year period ending in 2020, their proportionate shares of the annual operation and maintenance expenses and capital costs of those facilities. On December 18, 2020, the parties to these agreements submitted to FERC an offer of settlement and amendments to these agreements implementing the terms of an extension for an additional 20-year period. The parties have requested these terms to be placed in effect as of January 1, 2021 or such other date as authorized by FERC. The estimated future annual costs included in the contractual obligations table above, are subject to the approval of these amendments by FERC and can vary as a result. The total costs incurred under these agreements were as follows: Eversource For the Years Ended December 31, 2020 (Millions of Dollars) $ Renewable Energy 2019 584.2 $ 2018 320.8 $ 218.5 Natural Gas Procurement 453.4 448.5 432.4 Purchased Power and Capacity 62.7 62.1 72.0 Peaker CfDs 22.7 13.0 20.9 Transmission Support Commitments 22.1 21.8 23.4 For the Years Ended December 31, CL&P (Millions of Dollars) Renewable Energy $ 426.3 $ 2020 2019 2018 NSTAR Electric NSTAR Electric NSTAR Electric 88.8 PSNH $ 69.1 CL&P $ 160.6 $ 89.9 PSNH $ 70.3 CL&P $ 63.2 $ 89.8 PSNH $ 65.5 Purchased Power and Capacity 59.3 3.1 0.3 50.4 5.1 6.6 49.4 4.4 Peaker CfDs 22.7 — — 13.0 — — 20.9 — 18.2 — Transmission Support Commitments 8.7 8.7 4.7 8.6 8.6 4.6 9.2 9.2 5.0 C. Spent Nuclear Fuel Obligations - Yankee Companies CL&P, NSTAR Electric and PSNH have plant closure and fuel storage cost obligations to the Yankee Companies, which have each completed the physical decommissioning of their respective nuclear power facilities and are now engaged in the long-term storage of their spent fuel. The Yankee Companies fund these costs through litigation proceeds received from the DOE and, to the extent necessary, through wholesale, FERCapproved rates charged under power purchase agreements with several New England utilities, including CL&P, NSTAR Electric and PSNH. CL&P, NSTAR Electric and PSNH, in turn recover these costs from their customers through state regulatory commission-approved retail rates. The Yankee Companies collect amounts that management believes are adequate to recover the remaining plant closure and fuel storage cost estimates for the respective plants. Management believes CL&P and NSTAR Electric will recover their shares of these obligations from their customers. PSNH has recovered its total share of these costs from its customers. Spent Nuclear Fuel Litigation: The Yankee Companies have filed complaints against the DOE in the Court of Federal Claims seeking monetary damages resulting from the DOE's failure to accept delivery of, and provide for a permanent facility to store, spent nuclear fuel pursuant to the terms of the 1983 spent fuel and highlevel waste disposal contracts between the Yankee Companies and the DOE. The court previously awarded the Yankee Companies damages for Phases I, II and III of litigation resulting from the DOE's failure to meet its contractual obligations. These Phases covered damages incurred in the years 1998 through 2012, and the awarded damages have been received by the Yankee Companies with certain amounts of the damages refunded to their customers. DOE Phase IV Damages - On May 22, 2017, each of the Yankee Companies filed a fourth set of lawsuits against the DOE in the Court of Federal Claims. The Yankee Companies sought monetary damages totaling $104.4 million for CYAPC, YAEC and MYAPC, resulting from the DOE's failure to begin accepting spent nuclear fuel for disposal covering the years from 2013 to 2016 (DOE Phase IV). On February 21, 2019, the Yankee Companies received a partial summary judgment and partial final judgment in their favor for the undisputed amount of monetary damages of $103.2 million. The court awarded CYAPC, YAEC and MYAPC damages of $40.7 million, $28.1 million and $34.4 million, respectively. The DOE did not appeal the court's judgment and the decision became final on April 23, 2019. On June 12, 2019, each of the Yankee Companies received the damages proceeds. On June 12, 2019, the court accepted an offer of judgment in the amount of $0.5 million to settle the disputed amount of approximately $1 million in Phase IV contested damages. The Yankee Companies received the $0.5 million payment in July 2019. In September 2019, the Yankee Companies made a required informational filing with FERC as to the use of proceeds, for which approval was received in the fourth quarter of 2019. In December 2019, YAEC and MYAPC returned proceeds of $5.4 million and $21.0 million, respectively, to its member companies, of which the Eversource utilities (CL&P, NSTAR Electric and PSNH) received a total of $2.8 million from YAEC and $5.0 million from MYAPC. The Eversource utilities refund these amounts received to their utility customers. Also, in December 2019, CYAPC paid $29.0 million to the DOE to partially settle its pre-1983 spent nuclear fuel obligation. 93
  9. Page 107 of 136Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 107 of 136 D. Guarantees and Indemnifications In the normal course of business, Eversource parent provides credit assurances on behalf of its subsidiaries, including CL&P, NSTAR Electric and PSNH, in the form of guarantees. Management does not anticipate a material impact to net income or cash flows as a result of these various guarantees and indemnifications. Guarantees issued on behalf of unconsolidated entities, including equity method offshore wind investments, for which Eversource parent is the guarantor, are recorded at fair value as a liability on the balance sheet at the inception of the guarantee. Eversource regularly reviews performance risk under these guarantee arrangements, and in the event it becomes probable that Eversource parent will be required to perform under the guarantee, the amount of probable payment will be recorded. The fair value of guarantees issued on behalf of unconsolidated entities are recorded within Other Long-Term Liabilities on the balance sheet, and was $0.5 million as of December 31, 2020. The following table summarizes Eversource parent's exposure to guarantees and indemnifications of its subsidiaries and affiliates to external parties as of December 31, 2020: Company (Obligor) Maximum Exposure (in millions) Description North East Offshore LLC Construction-related purchase agreements with third-party contractors Eversource Investment LLC Funding and indemnification obligations of North East Offshore LLC (1) (2) $ Expiration Dates 30.5 (1) — (2) Sunrise Wind LLC OREC capacity production (3) 2.2 (3) South Fork Wind, LLC Transmission interconnection 1.7 — Bay State Wind LLC Real estate purchase 2.5 2021 Various Surety bonds (4) 56.6 2021 - 2023 Rocky River Realty Company and Eversource Service Lease payments for real estate 5.2 2024 (1) Eversource parent issued guarantees on behalf of its 50 percent-owned affiliate, North East Offshore LLC (NEO), under which Eversource parent agreed to guarantee 50 percent of NEO’s performance of obligations under certain purchase agreements with third-party contactors, in an amount not to exceed $1.3 billion with an expiration date in 2025. Eversource parent also issued a separate guarantee to Ørsted on behalf of NEO, under which Eversource parent agreed to guarantee 50 percent of NEO’s payment obligations under certain offshore wind project construction-related agreements with Ørsted in an aggregate amount not to exceed $62.5 million. Any amounts paid under this guarantee to Ørsted will count toward, but not increase, the maximum amount of the Funding Guarantee described in Note 2, below. The guarantee expires upon the full performance of the guaranteed obligations. (2) Eversource parent issued a guarantee (Funding Guarantee) on behalf of Eversource Investment LLC (EI), its wholly-owned subsidiary that holds a 50 percent ownership interest in NEO, under which Eversource parent agreed to guarantee certain funding obligations and certain indemnification payments of EI under the Amended and Restated Limited Liability Company Operating Agreement of NEO, in an amount not to exceed $910 million. The guaranteed obligations include payment of EI's funding obligations during the construction phase of NEO’s underlying offshore wind projects and indemnification obligations associated with third party credit support for its investment in NEO. Eversource parent’s obligations under the Funding Guarantee expire upon the full performance of the guaranteed obligations. (3) On October 25, 2019, Eversource parent issued a guarantee on behalf of its 50 percent-owned affiliate, Sunrise Wind LLC, whereby Eversource parent will guarantee Sunrise Wind LLC's performance of certain obligations, in an amount not to exceed $15.4 million, under the Offshore Wind Renewable Energy Certificate Purchase and Sale Agreement (the Agreement). The Agreement was executed on October 23, 2019, by and between the New York State Energy Research and Development Authority (NYSERDA) and Sunrise Wind LLC. The guarantee expires upon the full performance of the guaranteed obligations. (4) Surety bond expiration dates reflect termination dates, the majority of which will be renewed or extended. Certain surety bonds contain credit ratings triggers that would require Eversource parent to post collateral in the event that the unsecured debt credit ratings of Eversource parent are downgraded. Letter of Credit: On September 16, 2020, Eversource parent entered into a guarantee on behalf of Eversource Investment LLC, which holds Eversource's investments in offshore wind-related equity method investments, under which Eversource parent would guarantee Eversource Investment LLC's obligations under a letter of credit facility with a financial institution that Eversource Investment LLC may request in an aggregate amount of up to approximately $25 million. E. FERC ROE Complaints Four separate complaints were filed at the FERC by combinations of New England state attorneys general, state regulatory commissions, consumer advocates, consumer groups, municipal parties and other parties (collectively, the Complainants). In each of the first three complaints, filed on October 1, 2011, December 27, 2012, and July 31, 2014, respectively, the Complainants challenged the NETOs' base ROE of 11.14 percent that had been utilized since 2005 and sought an order to reduce it prospectively from the date of the final FERC order and for the separate 15-month complaint periods. In the fourth complaint, filed April 29, 2016, the Complainants challenged the NETOs' base ROE billed of 10.57 percent and the maximum ROE for transmission incentive (incentive cap) of 11.74 percent, asserting that these ROEs were unjust and unreasonable. 94
  10. Page 108 of 136

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 8, 2026 OCC-962, Attachment 3 Page 108 of 136 The ROE originally billed during the period October 1, 2011 (beginning of the first complaint period) through October 15, 2014 consisted of a base ROE of 11.14 percent and incentives up to 13.1 percent. On October 16, 2014, the FERC set the base ROE at 10.57 percent and the incentive cap at 11.74 percent for the first complaint period. This was also effective for all prospective billings to customers beginning October 16, 2014. This FERC order was vacated on April 14, 2017 by the U.S. Court of Appeals for the D.C. Circuit (the Court). All amounts associated with the first complaint period have been refunded, which totaled $38.9 million (pre-tax and excluding interest) at Eversource and reflected both the base ROE and incentive cap prescribed by the FERC order. The refund consisted of $22.4 million for CL&P, $13.7 million for NSTAR Electric and $2.8 million for PSNH. Eversource has recorded a reserve of $39.1 million (pre-tax and excluding interest) for the second complaint period as of both December 31, 2020 and 2019. This reserve represents the difference between the billed rates during the second complaint period and a 10.57 percent base ROE and 11.74 percent incentive cap. The reserve consisted of $21.4 million for CL&P, $14.6 million for NSTAR Electric and $3.1 million for PSNH as of both December 31, 2020 and 2019. On October 16, 2018, FERC issued an order on all four complaints describing how it intends to address the issues that were remanded by the Court. FERC proposed a new framework to determine (1) whether an existing ROE is unjust and unreasonable and, if so, (2) how to calculate a replacement ROE. Initial briefs were filed by the NETOs, Complainants and FERC Trial Staff on January 11, 2019 and reply briefs were filed on March 8, 2019. The NETOs' brief was supportive of the overall ROE methodology determined in the October 16, 2018 order provided the FERC does not change the proposed methodology or alter its implementation in a manner that has a material impact on the results. The FERC order included illustrative calculations for the first complaint using FERC's proposed frameworks with financial data from that complaint. Those illustrative calculations indicated that for the first complaint period, for the NETOs, which FERC concludes are of average financial risk, the preliminary just and reasonable base ROE is 10.41 percent and the preliminary incentive cap on total ROE is 13.08 percent. If the results of the illustrative calculations were included in a final FERC order for each of the complaint periods, then a 10.41 percent base ROE and a 13.08 percent incentive cap would not have a significant impact on our financial statements for all of the complaint periods. These preliminary calculations are not binding and do not represent what we believe to be the most likely outcome of a final FERC order. On November 21, 2019, FERC issued Opinion No. 569 affecting the two pending transmission ROE complaints against the Midcontinent ISO (MISO) transmission owners, in which FERC adopted a new methodology for determining base ROEs. Various parties sought rehearing. On December 23, 2019, the NETOs filed supplementary materials in the NETOs' four pending cases to respond to this new methodology because of the uncertainty of the applicability to the NETOs' cases. On May 21, 2020, the FERC issued its order in Opinion No. 569-A on the rehearing of the MISO transmission owners' cases, in which FERC again changed its methodology for determining the MISO transmission owners' base ROEs. Various parties appealed the MISO transmission owners' opinion. On November 19, 2020, the FERC issued Opinion No. 569-B denying rehearing of Opinion No. 569-A and reaffirmed the methodology previously adopted in Opinion No. 569-A. The new methodology differs significantly from the methodology proposed by FERC in its October 16, 2018 order to determine the NETOs' base ROEs in its four pending cases. Given the significant uncertainty regarding the applicability of the FERC opinions in the MISO transmission owners' two complaint cases to the NETOs' pending four complaint cases, Eversource concluded that there is no reasonable basis for a change to the reserve or recognized ROEs for any of the complaint periods at this time. As well, Eversource cannot reasonably estimate a range of any gain or loss for any of the four complaint proceedings at this time. Eversource, CL&P, NSTAR Electric and PSNH currently record revenues at the 10.57 percent base ROE and incentive cap at 11.74 percent established in the October 16, 2014 FERC order. A change of 10 basis points to the base ROE used to establish the reserves would impact Eversource’s after-tax earnings by an average of approximately $3 million for each of the four 15-month complaint periods. F. Eversource and NSTAR Electric Boston Harbor Civil Action In 2016, the United States Attorney on behalf of the United States Army Corps of Engineers filed a civil action in the United States District Court for the District of Massachusetts against NSTAR Electric, HEEC, and the Massachusetts Water Resources Authority (together with NSTAR Electric and HEEC, the "Defendants"). The action alleged that the Defendants failed to comply with certain permitting requirements related to the placement of the HEEC-owned electric distribution cable beneath Boston Harbor. The parties reached a settlement pursuant to which HEEC agreed to install a new 115kV distribution cable across Boston Harbor to Deer Island, utilizing a different route, and remove portions of the existing cable. Construction of the new distribution cable was completed in August 2019 and removal of the portions of the existing cable was completed in January 2020. All issues surrounding the current permit from the United States Army Corps of Engineers are expected to be resolved, and subsequently, such litigation then dismissed with prejudice. NSTAR Electric agreed to provide a rate base credit of $17.5 million to the Massachusetts Water Resources Authority for the new cable. This negotiated credit resulted in the initial $17.5 million of construction costs on the new cable being expensed as incurred, all of which was fully expensed in 2018. In connection with the new cable that was placed into service, a corresponding ARO was recognized for approximately $32 million within Other Long-Term Liabilities on the Eversource and NSTAR Electric balance sheets as of December 31, 2019. 95

Text of OCC-962 Attachment 2.pdf

Extracted from the file · 128 pages · 591,550 characters

Text of OCC-962 Attachment 1.pdf

Extracted from the file · 136 pages · 612,504 characters

Text of OCC-963 Attachment 8.pdf

Extracted from the file · 96 pages · 352,588 characters

Text of OCC-963 Attachment 7.pdf

Extracted from the file · 105 pages · 381,994 characters

Text of OCC-963 Attachment 6.pdf

Extracted from the file · 101 pages · 366,377 characters

Text of OCC-963 Attachment 5.pdf

Extracted from the file · 105 pages · 393,802 characters

Text of OCC-963 Attachment 4.pdf

Extracted from the file · 88 pages · 321,021 characters

Text of OCC-963 Attachment 3.pdf

Extracted from the file · 86 pages · 305,704 characters

Text of OCC-963 Attachment 2.pdf

Extracted from the file · 77 pages · 270,743 characters

Text of OCC-963 Attachment 1.pdf

Extracted from the file · 76 pages · 279,055 characters

As listed on the current system

Question(s) Answered 962, 963 (The Connecticut Light and Power Company) Date Filed: 10/20/2026

This filing on the current system (opens in a new tab)