Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 159

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy51 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files51

Search terms highlighted
Eversource rate increase is on 36 pages across 17 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of RRU-159 Attachment 23.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 23.pdf

Extracted from the file · 1,160 pages · 16,330,154 characters

Text of RRU-159 Attachment 22.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 22.pdf

Extracted from the file · 1,203 pages · 14,349,246 characters

Text of RRU-159 Attachment 21.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 21.pdf

Extracted from the file · 1,203 pages · 13,880,364 characters

Text of RRU-159 Attachment 20.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-159 Attachment 20.pdf

Extracted from the file · 16 pages · 151,762 characters

Text of RRU-159 Attachment 19.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-159 Attachment 19.pdf

Extracted from the file · 1 page · 5,328 characters

Text of RRU-159 Attachment 18.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 18.pdf

Extracted from the file · 640 pages · 7,983,236 characters

Text of RRU-159 Attachment 17.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 17.pdf

Extracted from the file · 855 pages · 14,651,941 characters

Text of RRU-159 Attachment 16.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 16.pdf

Extracted from the file · 489 pages · 7,076,557 characters

Text of RRU-159 Attachment 15.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 15.pdf

Extracted from the file · 897 pages · 15,723,777 characters

Text of RRU-159 Attachment 14 .pdf

Extracted from the file · 1 page · 2,589 characters

Text of RRU-159 Attachment 14.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-159 Attachment 13.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-159 Attachment 13.pdf

Extracted from the file · 1 page · 427 characters

Text of RRU-159 Attachment 12.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 12.pdf

Extracted from the file · 802 pages · 14,341,138 characters

Text of RRU-159 Attachment 11.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 11.pdf

Extracted from the file · 858 pages · 15,906,152 characters

Text of RRU-159 Attachment 10.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-159 Attachment 10.pdf

Extracted from the file · 1 page · 822 characters

Text of RRU-159 Attachment 09.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 09.pdf

Extracted from the file · 449 pages · 7,355,312 characters

Text of RRU-159 Attachment 08.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 08.pdf

Extracted from the file · 867 pages · 13,878,236 characters

Text of RRU-159 Attachment 07.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 07.pdf

Extracted from the file · 869 pages · 15,728,932 characters

Text of RRU-159 Attachment 06.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 06.pdf

Extracted from the file · 459 pages · 8,128,897 characters

Text of RRU-159 Attachment 05.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 05.pdf

Extracted from the file · 879 pages · 16,073,548 characters

Text of RRU-159 Attachment 04.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-159 Attachment 04.pdf

Extracted from the file · 5 pages · 20,994 characters

Words on different pages

This spreadsheet is large. Its searchable text keeps the sheet names, column headings and text cells and stops at 300,000 characters, so search may miss words further in. Download the file for every cell and figure.

  1. Part 52 of 77

    4D720220 | CB//MADISON, 75 NEW RD//SVC UPGRADE | CB//MADISON, 75 NEW RD//SVC UPGRADE 200A/RPL SVC W #2TPX IF ITS #4TPX_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2W620005 | PHD Elec Maint Replace/Renewal/Ob | PHD Elec Maint Replace/Renewal/Obsol OH DESG (AROH)_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M723981 | TAP ON TPX SVC TO NEW PARALLEL OWNE | TAP ON TPX SVC TO NEW PARALLEL OWNERS SERVICE RISER, MTR SET REQ'D_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 BERLCIRC | BERLIN CENTRAL SYSTEMS | CT VOICE RADIO SYSTEM PROJECT - BERLIN WAN CIRCUITS | Benefits-B01 5D720552 | DG P#2493 DOW RD PLAINFIELD FRNTR P | DG P#2493 DOW RD PLAINFIELD FRNTR POLE RPLC CLP TO SHIFT_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1B722315 | RSO OXFORD, Oakwood Dr - Digu up - | RSO OXFORD, Oakwood Dr - Digu up - damage done by S+S paving (see T/T)_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2L720676 | KENT,45 KENT CORNWALL RD//RUN NEW O | KENT,45 KENT CORNWALL RD//RUN NEW OH/DB SVC TO BARN FROMP#15464 ON GREENWOOD LN_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 DSN72012 | (50): HVAC system, DSN72012 | Fry Brook 13B - Install an air conditioning unit | Benefits-B01 DSN72013 | (50): A/C Unit with Hydrogen sensin | Tunnel 12S - Install an air condiitoning unit | Benefits-B01 GCFL0011 | Gold Coast - Fleet | Gold Coast Payments - Fleet | Benefits-B01 4N721068 | COMPLETED 6/27 CCC - Fault Locate a | COMPLETED 6/27 CCC - Fault Locate and Repair@ POLE 2986 NO POWER UG_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4E520958 | RA CDOT 163-203 RT 66, Windham - | RA CDOT 163-203 RT 66, Windham - 100% reimburse for TT & access road_x000D_ JE-YWO Variance Job Type Exclusion | Benefits-B01 DSN72045 | Fencing | Enfield 12C - REplace the deteriorated fence | Benefits-B01 4D721781 | PT-2017 Double Poles-Pole# 4149-Old | PT-2017 Double Poles-Pole# 4149-Old Quarry Rd, Guilford CT-Conv# 362600_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3R621050 | CD00471-10 Conversion Work Install | CD00471-10 Conversion Work Install Step Down XF Bennett Rd_x000D_ AP2-YWO Total Cost Variance Met - Variance :-26.4673 MIN.:-40 MAX.:40 | Benefits-B01 LENMIE11 | CA AWO MISC-ALL OTHERS | CA AWO MISC-ALL OTHERS | Benefits-B01 5T721716 | AWC 7/9 EAST WINDSOR OMELIA RD - RE | AWC 7/9 EAST WINDSOR OMELIA RD - REPLACED 3 CUTOUTS P-1792_x000D_ EW-YWO Variance - Emergent Work | Benefits-B01 2M722458 | JC/9A, 5/27 266 Jones Rd, Naugatuck | JC/9A, 5/27 266 Jones Rd, Naugatuck - car vs. pole 6001_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 MADSN001 | Madison AWC Site #67 | Madison AWC Site #67-Rose | Benefits-B01 GUILFORD 29F-REPLACE RECLOSER CONTR | PROPOSED REPLACEMENT OF 4 COOPER RECLOSERS WITH SIEMENS FOR GUILFORD 29F1-2, GUILFORD 29F2-2, MEADOW 28J1-2 AND MEADOW 28J2-2 ______________________________________JEL | Benefits-B01 CTIPAD20 | CT New Apprentices Tablets | This work order is to purchase 30 new ipads for CT new apprentices for an estimated amount of $36,682.5. | Benefits-B01 CTIPAD21 | CT New Apprentices Tablets | This work order is to purchase 56 new ipads for the 2021 CT new apprentices._x000D__x000D_ _x000D__x000D_ Per Jonathan Bradley's email dated 3/17/2021 requesting the purchase of 56 ipad at $1,250.00 per tablet for a total amount of $70,000.00._x000D__x000D_ _x000D__x000D_ Per LIsa's email dated 4/2/2021, requesting to increase the number of iPad for CT to 60 at $1,250/iPad. | Benefits-B01 5T721752 | RSO, 7/15, ENFIELD, ELM STREET, POL | RSO, 7/15, ENFIELD, ELM STREET, POLE 2139, REFER TO AWC TO RPLC 9A_x000D_ AP2-YWO Total Cost Variance Met - Variance :35.4939 MIN.:-50 MAX.:150 | Benefits-B01 2M722664 | JC/RSO 7/22 NAUGATUCK, NEW HAVEN RD | JC/RSO 7/22 NAUGATUCK, NEW HAVEN RD- 9A P3602 - BROKEN POLE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 5T720693 | JV COVENTRY, SOUTH ST - SHIFT FRONT | JV COVENTRY, SOUTH ST - SHIFT FRONTIER POLES 391, 392 AND 393_x000D_
  2. Part 53 of 77

    AP1-YWO Total Cost Less Than 7K | Benefits-B01 3R620648 | BC- CD00746-03 Inst 333kVA Step Xfm | BC- CD00746-03 Inst 333kVA Step Xfmr Bnk pole 996, Shore Rd_x000D_ CL-YWO Variance - Contractor Labor | Benefits-B01 1B620261 | 44 KENOSIA AVE Elec Maint Trouble C | 44 KENOSIA AVE Elec Maint Trouble Call - Repairs/Obsolescence OH PR2/17/16_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3H622162 | HARTFORD, LYME/ BURNHAM STREET 6373 | HARTFORD, LYME/ BURNHAM STREET 6373_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1S722546 | RL: 20 Edgar Rd:Replace #1 AL prim | RL: 20 Edgar Rd:Replace #1 AL primary, cutout & arrester already replaced_x000D_ AP2-YWO Total Cost Variance Met - Variance :-34.5233 MIN.:-50 MAX.:50 | Benefits-B01 3H721859 | 42 Grassmere Ave., W. Htfd - Instal | 42 Grassmere Ave., W. Htfd - Install new OH/DB svc (single-phase, 120/208)_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1B720430 | BLITZ, NM, OLD PARK LN, POLE #10, E | BLITZ, NM, OLD PARK LN, POLE #10, ES SHIFT TEL HAS SET, DBL POLE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M722408 | WC 7/6 SOUTHINGTON, MINE HOLLOW RD/ | WC 7/6 SOUTHINGTON, MINE HOLLOW RD/LONG BOTTOM - 9A P93393_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 LIDAREVL | LIDAR & ALT TECHNOLOGY | UCONN 2ND AMENDED AND RESTATED RESEARCH PROJECT(S)_x000D__x000D_ MONITORS ROADSIDE VEGETATION AND UTILITY INFRASTRUCTURE. ASSET - POLE STRUCTURE INTEGRITY MODEL | Benefits-B01 1N721713 | RSO; 11/24; BAYBERRY LN WSPT; REFER | RSO; 11/24; BAYBERRY LN WSPT; REFER TO AWC TO REPL #2 SVC_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1N621689 | JDB 18 OX YOKE LN NWLK P9366 EXTEND | JDB 18 OX YOKE LN NWLK P9366 EXTEND PRI INS 50KVA & OH/DB SVC DESG (DN)_x000D_ AP2-YWO Total Cost Variance Met - Variance :-19.5236 MIN.:-40 MAX.:40 | Benefits-B01 4N720196 | GCC / EVERS/INSTALL NEW POLE/PRI RI | GCC / EVERS/INSTALL NEW POLE/PRI RISER TO PAD MTD XFMR_x000D_ NL-YWO Variance - NU Construction Labor | Benefits-B01 4N620638 | PD-Tillley/Green/Pearl NLD/Parking | PD-Tillley/Green/Pearl NLD/Parking lot overhead service refeeds_x000D_ NL-YWO Variance - NU Construction Labor | Benefits-B01 5T720674 | Alice Dr, Coventry. Shift Frontier | Alice Dr, Coventry. Shift Frontier pole sets, Replace open wire sec and XFR'S_x000D_ AP2-YWO Total Cost Variance Met - Variance :-24.9807 MIN.:-50 MAX.:50 | Benefits-B01 CT17D013 | Berlin South Penthouse SiteBoss Ins | Install a SiteBoss alarm panel and remove the old Badger E500 alarm panel. | Benefits-B01 UNCLOC11 | Unc. Line of Credit Expenses | Unc. Line of Credit Expenses-Savage | Benefits-B01 2C720081 | rmv tree guy ins stub pole 1172 col | rmv tree guy ins stub pole 1172 college hill rd_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 EHAMP001 | E Hampton AWC #66 | E Hampton AWC #66-Rose | Benefits-B01 2L720778 | BETHLEHEM,384 MAIN ST. N.//Elec Svc | BETHLEHEM,384 MAIN ST. N.//Elec Svc New Com/Ind IT Meter//FAIRGROUNDS//_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 SERP0011 | Benefits-B01 | SERP0011EMPBENPAY11 | Benefits-B01 4D621442 | PATROL REPAIRS, 11J45 - BRANFORD | PATROL REPAIRS, 11J45 - BRANFORD_x000D_ AP2-YWO Total Cost Variance Met - Variance :11.1984 MIN.:-20 MAX.:20 | Benefits-B01 1S721524 | DL; RIVERBANK RD; REPLACE/RELOCATE | DL; RIVERBANK RD; REPLACE/RELOCATE 2 POLES FOR STAMFORD BRIDGE_x000D_ CL-YWO Variance - Contractor Labor | Benefits-B01 2L620133 | Burlington, Milford St - AWC/ 2/5/ | Burlington, Milford St - AWC/ 2/5/ (9A)_x000D_ AP2-YWO Total Cost Variance Met - Variance :59.231 MIN.:-50 MAX.:150 | Benefits-B01 3H721986 | HARTFORD, ANN ST-C6661 - INSTALL 25 | HARTFORD, ANN ST-C6661 - INSTALL 250W HPS AND RECONNECT UG FEED_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M722399 | WC 7/5 SOUTHINGTON, CAMPGROUND RD - | WC 7/5 SOUTHINGTON, CAMPGROUND RD - REPLACED 50 KVA XFMR / cutout / tbracket_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01
  3. Part 54 of 77

    2M722436 | RSO/AWC 7/10 CHESHIRE, W JOHNSON AV | RSO/AWC 7/10 CHESHIRE, W JOHNSON AVE - RECONDUCTERING 250' CONDUIT/CABLE_x000D_ CI-YWO Variance - Contractor Invoice | Benefits-B01 4N621240 | MM SMART SWITCH REPROGRAM RECLOSER | MM SMART SWITCH REPROGRAM RECLOSER POLE 916 JEROME FROM RADIAL TO SECT 1Q01_x000D_ AP2-YWO Total Cost Variance Met - Variance :42.4481 MIN.:-50 MAX.:50 | Benefits-B01 4E720513 | RSO 4/9/17 Jurczyk, Franklin - rep | RSO 4/9/17 Jurczyk, Franklin - replaced arrestors @ 383 & 385, replace OH xfrm_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 MS17M011 | WIND/RAIN OCT 29-30 ALL DIV | WIND/RAIN OCT 29-30 ALL DIV | Benefits-B01 UCONN219 | SS SECURITY 40% DISTRIBUTION | UCONN PROFESSER ON SEBATICAL TO ASSIST EVERSOURCE WITH RESEARCH AND DEVELOPMENT OF SOFTWARE THAT WILL ASSIST WITH CYBER SECURITY FOR EQUIPMENT ON EE SYSTEM. BEGINS SEPT THROUGH YEAR END. | Benefits-B01 5D720575 | RSO, 5/5, STARKWEATHER ROAD, 9A GN | RSO, 5/5, STARKWEATHER ROAD, 9A GNESDA, POLE 430, HBV, SHIFT TO NEW POLE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 RGST0611 | Regulatory Assessments-Retail Trans | Regulatory Assessments-Retail Transmission-Caron | Benefits-B01 LTDB2211 | Long Term Debt2007 Series C | Long Term Debt2007 Series C | Benefits-B01 | 2371B0 1B722785 | BR 38 Twin Oaks Beacon Falls New Re | BR 38 Twin Oaks Beacon Falls New Residential Underground_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1B722786 | BR 76 Fieldstone Ln Beacon Falls Ne | BR 76 Fieldstone Ln Beacon Falls New Residential Underground_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4E721442 | 5 CHILDS RD E HMPTN AT P-2674 INSTA | 5 CHILDS RD E HMPTN AT P-2674 INSTALL OH SVC TO GAS CO POLE, UNMETERED ANTENNA_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 CD252007 | CL&P 900 MHZ Greenwich | CL&P 900 MHZ RADIO PROJECT-Greenwich EQUIP CONTACT: P.SCHUBERTH | Benefits-B01 4E721958 | MN 31, LOT 16 BARBERS WAY HEBRON A | MN 31, LOT 16 BARBERS WAY HEBRON AT HH-417-B INSTALL DB SVC & 200A MTR_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3R720020 | CAL - CD00849-01 - Ckt 21M1 MBI Ini | CAL - CD00849-01 - Ckt 21M1 MBI Initiative Design Work, Westport_x000D_ CL-YWO Variance - Contractor Labor | Benefits-B01 MBLD2011 | Maintain Buildings | Maintain Buildings-Rose | Benefits-B01 1S721655 | DM/7 INDIAN HEAD RD RIVERSIDE: INST | DM/7 INDIAN HEAD RD RIVERSIDE: INST 3" SVC RISER, 350MCM DB SVC, 400AMP_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M721096 | 79-229, Route 71 Meriden, W Main St | 79-229, Route 71 Meriden, W Main St - Rebuild SB254 to MH & Test Pit_x000D_ JE-YWO Variance Job Type Exclusion | Benefits-B01 1N721146 | JES; 269 MILLSTONE RD. WILTON.; REL | JES; 269 MILLSTONE RD. WILTON.; RELOCATE OH SVC. POLE 21268..._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 CT17D040 | Colorado Trucks Lowband Radios | A request has come in to order 25 mobile radios for a new wave of Colorado Pickup trucks transportation ordered. | Benefits-B01 CS000094 | BLACK ROCK 11H-PURCH S/S REMOTE RAC | PURCHASE 29 CBS ARCSAFE REMOTE RACKING UNITS FOR SUBSTATIONS THAT CURRENTLY DO NOT HAVE A SYSTEM THAT WORKS SAFELY __________________________________________CMK | Benefits-B01 3L722822 | LEDYARD POLE 6045 250 HPS COBRA COM | LEDYARD POLE 6045 250 HPS COBRA COMPLETED 10/24 EHA_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 5D621134 | BC - CD00450-08 - Re-cond, Inst/Rmv | BC - CD00450-08 - Re-cond, Inst/Rmv River/RR Xing Structures, Town of Preston_x000D_ CL-YWO Variance - Contractor Labor | Benefits-B01 3R621018 | CD00471-01Elim. 23U Voluntown S/S C | CD00471-01Elim. 23U Voluntown S/S Conversion Work #3_x000D_ CI-YWO Variance - Contractor Invoice | Benefits-B01 3H721776 | 7/9 - HARAWC - WINDSOR, PARK RD - E | 7/9 - HARAWC - WINDSOR, PARK RD - EVERSOURCE POLE 156_x000D_ AP2-YWO Total Cost Variance Met - Variance :69.5323 MIN.:-50 MAX.:150 | Benefits-B01
  4. Part 55 of 77

    3H722155 | JWL @ 877-879 CAPITOL AVE replace | JWL @ 877-879 CAPITOL AVE replace svc from sb3177._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3H722156 | 8/18 - RSO/HAROH - EAST HARTFORD, | 8/18 - RSO/HAROH - EAST HARTFORD, SEDGEWICK RD, P2646, 9A_x000D_ AP2-YWO Total Cost Variance Met - Variance :73.2456 MIN.:-50 MAX.:150 | Benefits-B01 5T721250 | 5/16 RSO & ESO PUCKER ST,COVENTRY 9 | 5/16 RSO & ESO PUCKER ST,COVENTRY 9A_x000D_ EW-YWO Variance - Emergent Work | Benefits-B01 3H721937 | AWC 7/24 MANCHESTER HARTFORD RD 9A | AWC 7/24 MANCHESTER HARTFORD RD 9A - REPLACED QUAD SERVICE FROM P-4700_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4D721830 | COMP 12/30 CCC-Municipal Light Faul | COMP 12/30 CCC-Municipal Light Fault Locate and Repair@ POLE 93 NO VOLTAGE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 5D720743 | RSO 6/2 GRISWOLD, BITGOOD RD- 9A P1 | RSO 6/2 GRISWOLD, BITGOOD RD- 9A P1789 - WEBB/GEMBEL/CIVARDI , NOT COMP_x000D_ AP2-YWO Total Cost Variance Met - Variance :85.6143 MIN.:-50 MAX.:150 | Benefits-B01 4N721464 | PD-44 Indianola Rd Niantic/Replace | PD-44 Indianola Rd Niantic/Replace OH svc drop_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3H720698 | WETHERSFIELD, BERLIN TPKE, 9A REPLA | WETHERSFIELD, BERLIN TPKE, 9A REPLACE P1738 45/2_x000D_ AP2-YWO Total Cost Variance Met - Variance :-47.6215 MIN.:-50 MAX.:50 | Benefits-B01 3H721728 | RSO/AWC, 7/3, WEST HARTFORD, CONCOR | RSO/AWC, 7/3, WEST HARTFORD, CONCORD STREET REPLACED 150' SEC WITH 4/0_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1N621292 | JES; WILLARD RD. NWLK.; IR INSP. - | JES; WILLARD RD. NWLK.; IR INSP. - Minor DESG (IFOH) - POLE 13273_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 ASEE0011 | AS&E | ASEE0011ALLOCCLEARING11 | Benefits-B01 4N721497 | GCC / REMOVE AND INSTALL OVERHEAD S | GCC / REMOVE AND INSTALL OVERHEAD SERVICE TO HOME_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 CTCART25 | Blanket Cart for CT Dielectric Lab | This rubber blanket cart will be in the Berlin dielectric lab to maneuver rubber blankets around the lab. _x000D__x000D_ _x000D__x000D_ Per Teams call with Matthew Chamberlain 10-10-2025, the estimated cost is $3,705.00. This is from EverGreen Sheet Metal, Inc. The vendor is fabricating a blanket cart from stainless steel. | Benefits-B01 3H721029 | EJL - 270 Wetherell St.Manch.Reloca | EJL - 270 Wetherell St.Manch.Relocate 25KVA/Pri./Remove tree guy/P-5188_x000D_ AP2-YWO Total Cost Variance Met - Variance :113.508 MIN.:-50 MAX.:150 | Benefits-B01 2M622924 | Waterbury Rd Prospect 9A - (POST CO | Waterbury Rd Prospect 9A - (POST CONSTRUCTION)_x000D_ AP2-YWO Total Cost Variance Met - Variance :-26.9179 MIN.:-40 MAX.:40 | Benefits-B01 3H721751 | 7/5 - AWC - WETHERSFIELD, OLD PEPPE | 7/5 - AWC - WETHERSFIELD, OLD PEPPERIDGE LA - REPLACED CUTOUT/TERM/RISER_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4E720228 | (CH) HH#313A: NEED TO CHG COVER_HH# | (CH) HH#313A: NEED TO CHG COVER_HH#311G: COMP'D_FAULT LOCATED/RPR'D/CHG'D_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 5T621064 | Shenipsit Lake Rd, Tolland. BBA P-3 | Shenipsit Lake Rd, Tolland. BBA P-35 all work done in field_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 DNLTW1DC | DANIELSON TOWER REPLACEMENT | DANIELSON TOWER REPLACEMENT - CL&P | Benefits-B01 4N621217 | ESO 9A - 08/15/16 GREEN HAVEN STONI | ESO 9A - 08/15/16 GREEN HAVEN STONINGTON car v pole 6781_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4D721230 | cb//branford, farm river rd//rpl li | cb//branford, farm river rd//rpl light head p 38780R w full cutoff, shield_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1S721343 | DM/DAVIS & LE GRANDE AVE GRN: P.679 | DM/DAVIS & LE GRANDE AVE GRN: P.67972 REPLACE XARMS_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 PW1N0011 | Private Work | Private Work | Benefits-B01
  5. Part 56 of 77

    3H723179 | 12/2 - RSO - HARTFORD, ELLIOT ST - | 12/2 - RSO - HARTFORD, ELLIOT ST - NEED TO REPLACE 150W C9116_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 5D720811 | DG P#2456 1 BEATTIE AVE THOMPSON FR | DG P#2456 1 BEATTIE AVE THOMPSON FRNTR POLE RPLC, 25 KVA, OH SVC_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4D720334 | NS- Maple Ave, OS- Mittigate Outage | NS- Maple Ave, OS- Mittigate Outages- Ins COs on XFMRs Downstream P 596_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1B720145 | CDOT 34-313 Danbury - CIS#2 - relo | CDOT 34-313 Danbury - CIS#2 - reloc service to Wells Fargo_x000D_ JE-YWO Variance Job Type Exclusion | Benefits-B01 1S721069 | PH; 51 LENOX AVE; Replace OH Servic | PH; 51 LENOX AVE; Replace OH Service_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2C720133 | ins new db svc to beckley furnace l | ins new db svc to beckley furnace lower rd north canaan_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M722088 | Municipal Light Fault Locate and Re | Municipal Light Fault Locate and Repair@ POLE 3 - COMP 7-6-17 CCC_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M721945 | ESO/AWC 5/26 WATERBURY, MERIDEN RD | ESO/AWC 5/26 WATERBURY, MERIDEN RD - 9A P 9259_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1S720200 | DM/461 STANWICH RD GREENWICH: CAR V | DM/461 STANWICH RD GREENWICH: CAR VS POLE 73690-S_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M622249 | EJC 718 West Main St, Waterbury P#1 | EJC 718 West Main St, Waterbury P#121 Repl Alum Stlt Pole and Heads_x000D_ AP2-YWO Total Cost Variance Met - Variance :-11.0863 MIN.:-50 MAX.:50 | Benefits-B01 1N621850 | RM -CD00667, Recloser @ P-4977 Knap | RM -CD00667, Recloser @ P-4977 Knapp St - Norwalk_x000D_ AP2-YWO Total Cost Variance Met - Variance :23.7919 MIN.:-30 MAX.:30 | Benefits-B01 4E721884 | MN 426 CABIN RD COLCH AT P-2297 RE | MN 426 CABIN RD COLCH AT P-2297 REPLACE OH SVC, MIDSPAN,10 FT OFF OF POLE._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4N621769 | MM ALL WORK COMPLETE GORTON ST,POLE | MM ALL WORK COMPLETE GORTON ST,POLE 1740 - REPLACED 70' 2 STRAND SERVICE_x000D_ | Benefits-B01 1G520706 | DM/6 Grove ST COS COB: PRIORITY DE | DM/6 Grove ST COS COB: PRIORITY DESG (IFOH) - POLE#119_x000D_ CL-YWO Variance - Contractor Labor | Benefits-B01 2M722933 | DM/ESO 9A 6/10/17 - CHESHIRE - P#85 | DM/ESO 9A 6/10/17 - CHESHIRE - P#853 RESAG OH SVC 1308 S MERIDEN RD_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4E720266 | (CH) HH#204A: CHG HDP TO POLYCRETE_ | (CH) HH#204A: CHG HDP TO POLYCRETE_DISC/RE-CONN SVC FOR SOCKET CHANGE-OUT._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M721636 | Jpt-Terryville Ave BRI (Frnt)P6309 | Jpt-Terryville Ave BRI (Frnt)P6309 - 9a - DUMP TRUCK BROUGHT POLE & WIRE DOWN_x000D_ AP2-YWO Total Cost Variance Met - Variance :29.3622 MIN.:-50 MAX.:50 | Benefits-B01 1B721855 | 36 HAYES LN relocate to mid-span E | 36 HAYES LN relocate to mid-span Existing Residential Overhead_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M720867 | RTM-SMITHFIELD AVE, MERIDEN. POLE 8 | RTM-SMITHFIELD AVE, MERIDEN. POLE 80551_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4E620324 | 491 COOK HILL RD LEB REPL 4 POLES, | 491 COOK HILL RD LEB REPL 4 POLES, 3 SPANS OF, INS STUB POLE & ANC, SHIFT FAC's_x000D_ CL-YWO Variance - Contractor Labor | Benefits-B01 MDEC0011 | Misc. Dist expense (small tools) | MDEC0011ALLOCCLEARING11 | Benefits-B01 RENTIL11 | CA AWO RENT - INTERNAL | CA AWO RENT - INTERNAL | Benefits-B01 | 93111X HUNTBRK1 | Montville Hunts Brook Fly Ash | Montville Hunts Brook Fly Ash - Environmental Reserve. Had to re-create becuase he it didn't come over in the conversaion. | Benefits-B01 4N621470 | MM STUB POLE, 95s ANCHOR, SPAN GUY, | MM STUB POLE, 95s ANCHOR, SPAN GUY, SDWLK GUY COLMANST NEW LONDON notif #490181_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01
  6. Part 57 of 77

    2M723013 | Jpt-RSO-518 Jerome Ave BRI P2073 - | Jpt-RSO-518 Jerome Ave BRI P2073 - RAN NEW 100' #2 SVS MIDSPANNED_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1B722524 | TB 154 ENTERPRISE DR INSTALL NEW PR | TB 154 ENTERPRISE DR INSTALL NEW PRIMARY SVC AND 300 KVA XFMR_x000D_ AP2-YWO Total Cost Variance Met - Variance :49.4991 MIN.:-50 MAX.:50 | Benefits-B01 3H720736 | RSO 3/23 -- WEST HARTFORD, 134 OAKW | RSO 3/23 -- WEST HARTFORD, 134 OAKWOOD AVE- POLE # 1082 - 9A_x000D_ AP2-YWO Total Cost Variance Met - Variance :-11.2451 MIN.:-50 MAX.:50 | Benefits-B01 5T721678 | Sandy Beach 130, Ellington. Upgrade | Sandy Beach 130, Ellington. Upgrade 15 KVA to 25 KVA for solar project. P-2353_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 CT16D027 | BERLIN SOUTH CAMPUS FIBER RUNS | Pull fiber from Berlin OBA communications room to Berlin South Main communications room. Fiber to be pulled from East Building communications room to Berlin South Bldg. | Benefits-B01 CT16D028 | TOLLAND AWC MW UPGRADE W/USED EQUIP | The OC3 microwave equipment that was removed from service between Mt Tom GS and Hadley area work center will be moved from the books to the new locations Tolland and Bolton. This work order is for equipment to be located at Tolland AWC. | Benefits-B01 2M720949 | RTM-220 Berlin Tpke, Ber. Relocate | RTM-220 Berlin Tpke, Ber. Relocate P#99264 & P#4728 100% Reimbursable_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 PTRACK13 | PURCHASE RADIO RECEIVER CARDS | PURCHASE RADIO RECEIVER CARDS 2013 | Benefits-B01 RGST0411 | Regulatory Assessments | Regulatory Assessments | Benefits-B01 BORDE011 | Borderline Purchases | Borderline Purchases | Benefits-B01 3H722164 | 8/17 RSO-AWC, WHARTFORD, SEQUIN RD | 8/17 RSO-AWC, WHARTFORD, SEQUIN RD 9A - REPLACED POLE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 NWKTW101 | TOWER REPLACEMENT-NORWALK | TOWER REPLACEMENT-NORWALK PROJECT: NWKTW1DC1 CONTACT: STEVE FLORIO | Benefits-B01 4D721307 | cb//branford, 15 pawson rd//oh svc | cb//branford, 15 pawson rd//oh svc upgrade_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4E621328 | BC - CDOT 41-118 - Relocate facilit | BC - CDOT 41-118 - Relocate facilities on RT 66 for bridge replacement STAGE 1_x000D_ JE-YWO Variance Job Type Exclusion | Benefits-B01 2M722162 | Municipal Light Fault Locate and Re | Municipal Light Fault Locate and Repair@ POLE 3758 - COMP 6/17 CCC_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M722853 | AMM 32 DEPOT PL, FARMINGTON. REPLA | AMM 32 DEPOT PL, FARMINGTON. REPLACED 3 PH BANK ON POLE 2350 & ADDED 3 CUTOUTS._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4E720474 | (CH) P#2427: RPL EXIST'G OH/DB SVC | (CH) P#2427: RPL EXIST'G OH/DB SVC WITH NEW 4/0 OH/DB SVC_85'_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M722550 | Nelson Ave,Wtby. Make upgrades on p | Nelson Ave,Wtby. Make upgrades on pole 6791, 6789 & 6787 for animal protection._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4D621494 | S Main St, Deep River/TL-ESO - 9A - | S Main St, Deep River/TL-ESO - 9A - 10/12 Car vs Pole 337_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1S720461 | RL:11 Watch Hill Dr:Elec Existing R | RL:11 Watch Hill Dr:Elec Existing Residential OH/DB Remove span Tpx & OH service_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2L720762 | TORRINGTON - FRANKLIN ST / ADD LIGH | TORRINGTON - FRANKLIN ST / ADD LIGHTS BEHIND SLOVAK CLUB_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4N720646 | MM NEW MID SPAN SERVICE POLE 1200 H | MM NEW MID SPAN SERVICE POLE 1200 HOUSE 213 SHORE RD MLC METER SER TO SET METER_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4N621416 | PD-187 West Main St East Lyme/Car V | PD-187 West Main St East Lyme/Car VS P# 1224_x000D_ NL-YWO Variance - NU Construction Labor | Benefits-B01 3R621017 | CD00471-01Elim. 23U Voluntown S/S C | CD00471-01Elim. 23U Voluntown S/S Conversion Work #2_x000D_
  7. Part 58 of 77

    AP2-YWO Total Cost Variance Met - Variance :-28.5624 MIN.:-30 MAX.:30 | Benefits-B01 4D720251 | CB//MADISON, HULL RD//RELOCATE SECO | CB//MADISON, HULL RD//RELOCATE SECONDARY,XF (EXISTING CROSS FUSE)_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M724513 | Jpt-7 Pickett Ln Farm (Frnt)P6024 - | Jpt-7 Pickett Ln Farm (Frnt)P6024 - Existing Residential Overhead - MLC_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4E620817 | Elec Maint Trouble Call - Repairs/O | Elec Maint Trouble Call - Repairs/Obsolescence OH (AROH)_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M722602 | WC-RSO 7/21 SOUTHINGTON, WEST ST - | WC-RSO 7/21 SOUTHINGTON, WEST ST - 9A P92660 PICK UP SNAGGED WIRE - REPLD SVC_x000D_ | Benefits-B01 3H721767 | 7/8 RSO, WINDSOR COLONIAL DR - 9A T | 7/8 RSO, WINDSOR COLONIAL DR - 9A TRUCK TOOK DOWN WIRES - RAN 125' SERVICE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M720552 | Municipal Light Fault Locate and Re | Municipal Light Fault Locate and Repair@ POLE 4 - COMP 4/11 CCC_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2L721541 | SW CDOT 086-091 BRIDGE REPL RT# 109 | SW CDOT 086-091 BRIDGE REPL RT# 109 (THOMASTON RD) MORRIS (Inst Primary/Neutral)_x000D_ JE-YWO Variance Job Type Exclusion | Benefits-B01 HVDCGRID | HVDC GRID HARDENING | UCONN 2ND AMENDED AND RESTATED RESEARCH PROJECT(S)_x000D__x000D_ HARDENING OF EE HVDC SYSTEMS AGAINST GEOMAGNETIC DISTURBANCE AND MONOPOLE OPERATION OF THE HVDC SYSTEM. ASSET - MODEL HVDC SYSTEMS INCLUDING HVDC CONVERTER STATION, REACTIVE POWER COMPENSATION DEVICES, CONVERTER TRANSFORMERS AND HVDC OH LINE OR CABLE | Benefits-B01 3R620120 | BW 2015 SR Highway Crossing, Locati | BW 2015 SR Highway Crossing, LocationID46668676, Pole 3472 & 3473_x000D_ CI-YWO Variance - Contractor Invoice | Benefits-B01 2M722455 | WC 7/11 SOUTHINGTON, MAIN ST - REPL | WC 7/11 SOUTHINGTON, MAIN ST - REPLACED 3 PH BANK & 2 CUTOUTS P86145_x000D_ AP2-YWO Total Cost Variance Met - Variance :20.4912 MIN.:-50 MAX.:50 | Benefits-B01 1S721431 | RL:1 Lillian Ter: Replace OH Servic | RL:1 Lillian Ter: Replace OH Service 110' #2 Tpx_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1N721672 | AJC 54 WILTON RD WSPT REPLACE POLE | AJC 54 WILTON RD WSPT REPLACE POLE 1205 INSTALL P RISER & PAD REM P DB PRI & DH_x000D_ | Benefits-B01 3H622080 | HTFD 3080 MAIN STREET City to repla | HTFD 3080 MAIN STREET City to replace pole CH8668_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 DCDW0011 | DISTRIBUTION CLEARANCE ADMIN/WRITER | DCDW0011OPSNTRELEXPENSES11_x000D__x000D_ work order to be used by Distribution Clearance Administrator and Distribution Clearance Writer under CT Grid management | Benefits-B01 4N820210 | MM REPLACE DAMAGED SERVICE WIRE FRO | MM REPLACE DAMAGED SERVICE WIRE FROM POLE 1517TO HOUSE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3L722875 | PLYMOUTH POLE 1711 150 HPS PTT FIXT | PLYMOUTH POLE 1711 150 HPS PTT FIXTURE IS WORKING 03/01 NTW_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M721806 | AMM RED OAK HILL RD,FARMINGTON. SH | AMM RED OAK HILL RD,FARMINGTON. SHIFT FRONTIER POLE 360._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M820194 | AMM 12 GILLETTE WAY FARM. Municipa | AMM 12 GILLETTE WAY FARM. Municipal Light Fault Locate and Repair@ POLE 2926._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M820195 | AMM 12 GILLETTE WAY,FARM. Municipa | AMM 12 GILLETTE WAY,FARM. Municipal Light Fault Locate and Repair@ POLE 2927._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 PSTK1811 | Preferred Stock | Preferred StockNT011 | Benefits-B01 PSTK0311 | Preferred Stock | Preferred StockDIST11 | Benefits-B01 4N720274 | PD-9 Fairhaven Rd East Lyme/Disconn | PD-9 Fairhaven Rd East Lyme/Disconnect-reconnect OH svc for upgrade._x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 PSTK0111 | Preferred Stock | Preferred StockDIST11 | Benefits-B01
  8. Part 59 of 77

    3R621059 | CD00471-01 Elim. 23U S/S & Inst. Te | CD00471-01 Elim. 23U S/S & Inst. Temp. 500KVA Step XF's for Conversion_x000D_ AP2-YWO Total Cost Variance Met - Variance :-19.1314 MIN.:-30 MAX.:30 | Benefits-B01 2L721475 | Hartland--Center St. (157) 4154 Run | Hartland--Center St. (157) 4154 Run new oh svc & set meter_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 CT17D022 | SOAPSTONE TO LONG HILL MICROW UPGRA | Upgrade the microwave equipment from DS3 to OC3 capacity to provide sufficient backhaul to enable microwave to be an alternate path from fiber and increase capacity. | Benefits-B01 5T820043 | COMP 3/2 CCC - ENFIELD THE MEADOWS | COMP 3/2 CCC - ENFIELD THE MEADOWS P#18 - RPL BLK FG POLE & PTT 150HPS_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3L722556 | BLOOMFIELD POLE 5616 100 HPS PTT & | BLOOMFIELD POLE 5616 100 HPS PTT & BROWN SQUARE POLE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3R620095 | CD00103-13 11M3 seg 13 resiliency p | CD00103-13 11M3 seg 13 resiliency part 1_x000D_ AP2-YWO Total Cost Variance Met - Variance :8.3386 MIN.:-30 MAX.:30 | Benefits-B01 1N721075 | JDB 144 MAIN ST, NORWALK- BAD DB PR | JDB 144 MAIN ST, NORWALK- BAD DB PRIM P#20241 07/19/17_x000D_ AP2-YWO Total Cost Variance Met - Variance :6.2892 MIN.:-50 MAX.:50 | Benefits-B01 ACTP0011 | Accounts Payable offset | Accounts Payable offset-Ouimette | Benefits-B01 DSN72033 | (50): Miscellaneous | Southington 4C - Refurbish the switchgear enclosure | Benefits-B01 DSN72016 | (50): Miscellaneous; Refurbishment | Prospect Street 22E - REfurbish the switchgear enclosure - ROOF REPLACEMENT | Benefits-B01 DSN72017 | (50): Miscellaneous, Refurbishment | Byram 13C - Refurbish the switchgear enclosure | Benefits-B01 4N721319 | PD-7/28 INST. NEW XFORMER AND 3/CUT | PD-7/28 INST. NEW XFORMER AND 3/CUT OUTS ON 7057_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 DSN82001 | (50): A/C Unit DSN82001 | Rocky Hill 3R - Replace failing A/C Unit and Install Hydrogen Detection System | Benefits-B01 2W620247 | PHD JC/ POLE 9436 FRONTIER SHIFT | PHD JC/ POLE 9436 FRONTIER SHIFT_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3L722823 | LEDYARD POLE 96 50 HPS COBRA COMPLE | LEDYARD POLE 96 50 HPS COBRA COMPLETED 10/24 EHA_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1N522133 | AJC 128 MATHER ST WLTN INSTALL RISE | AJC 128 MATHER ST WLTN INSTALL RISER FOR 480V 3PH DELTA SERVICE P24555_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 4N721153 | PD-27 Lincoln Rd WTFD/Disconnect-re | PD-27 Lincoln Rd WTFD/Disconnect-reconnect for svc upgrade/Net meter_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M621311 | (DF) (R/I) PTT Light pole 1586 - -6 | (DF) (R/I) PTT Light pole 1586 - -6/11 ESO 9A - Car v light pole- COMP 12/28 CCC_x000D_ CL-YWO Variance - Contractor Labor | Benefits-B01 1B622120 | 8-13 PRINCESS PINE LN Electric Ser | 8-13 PRINCESS PINE LN Electric Service New UG Residential Meter Dept Set_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 5W120380 | PR 103752, seg01, UCONN East Bldg, | PR 103752, seg01, UCONN East Bldg, U.G., Mansfield_x000D_ | Benefits-B01 STRM1D6Y | WO CREATED TO RECORD INVOICES FROM | WORK ORDER TO BE USED TO RECORD THE INVOICES RECEIVED FROM CONTRACTORS FOR STORM REST- ORATION WORK. COSTS CLEARED OUT TO WORK ORDER SET UP FOR EACH SPECIFIC STORM WHEN INVOICE | Benefits-B01 UNINTENTIONAL ISLAND & FREQ | RELEASE 4 OF PO - UCONN Unintentional islanding & frequency response analysis Eversource Distribution Systems under various weather conditions | Benefits-B01 EE Ground Lidar Project | RELEASE 5 OF PO - UCONN EE Ground Lidar Project (technology) Eversource Distribution Systems under various weather conditions | Benefits-B01 CT17D048 | Berlin OpenSky Router Replacement | This WO is to replace the EOL cisco 2800 series router used by OpenSky on site. | Benefits-B01
  9. Part 60 of 77

    11MEYE21 | CT Elec Fleet Cap Purch - Mobileye | CT Elec Fleet Capital Purchase - Mobileye $208,078.47_x000D__x000D_ Mobileye Safety Mechanism hardware & installation 153 Units | Benefits-B01 2L620240 | SW CDOT 086-091 BRIDGE REPL RT# 109 | SW CDOT 086-091 BRIDGE REPL RT# 109 (THOMASTON RD) MORRIS (Rem Primary/Neutral)_x000D_ JE-YWO Variance Job Type Exclusion | Benefits-B01 DSQ72015 | (50): Miscellaneous replacement of | Cos Cob 11R - Replace the failed HMI system | Benefits-B01 MBLD0311 | Maintain Buildings | MBLD0311NT011 | Benefits-B01 11ENSTAP | CL&P EE Expense | 11ENSTAP11RES | Benefits-B01 TRAF0011 | POLICE/TRAFFIC CONTROL | POLICE/TRAFFIC CONTROL | Benefits-B01 2M622292 | WC-39 Luke St,Propsect. Car v Pole | WC-39 Luke St,Propsect. Car v Pole 2507_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 1N721556 | RM - CDOT173-415, test-pits, RT 57 | RM - CDOT173-415, test-pits, RT 57 BRIDGE REPAIR - WESTON_x000D_ JE-YWO Variance Job Type Exclusion | Benefits-B01 BORXE011 | WME BORD GRANVILL & SOUTWICK JAN 13 | BORXE011NT011 | Benefits-B01 | 55501X LTDB0611 | Long Term Debt2004 Series A | Long Term Debt2004 Series A | Benefits-B01 | 237CD0 PSTK1311 | Preferred Stock | Preferred StockDIST11 | Benefits-B01 GXC18W01 | WILLIAMS - Transformer Testers | WILLIAMS - Transformer Testers | Benefits-B01 GXC18W81 | Printer M426FDW | Printer M426FDW | Benefits-B01 APAY0011 | Accounts Payable Processing | Accounts Payable Processing | Benefits-B01 3R420243 | CD00316-02; 11C14 Resiliency; Recon | CD00316-02; 11C14 Resiliency; Recon. RT 81 w 336 TW pole 602 to 637; WO 3 of 3_x000D_ AP2-YWO Total Cost Variance Met - Variance :-6.1021 MIN.:-20 MAX.:20 | Benefits-B01 3L820579 | STAMFORD POLE 16917 250 HPS COBRA C | STAMFORD POLE 16917 250 HPS COBRA COMPLETED 12/20 NTW_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 CS000212 | Torr Term 8A S/S Lighting Upgrades | Install and/or upgrade S/S lighting fixtures and additional 120VAC outlets at various CL&P Substations. All fixtures will be ordered & stocked at BCS and s/b charged to the appropriate WO # when they are picked up at the warehouse. | Benefits-B01 CS002788 | THOMASTON 2B SWITCHGEAR | Refurbish switchgear body, excludes roof. Refurbish roof after moratorium | Benefits-B01 GX170017 | NPT Threading Machine Die Head | Universal NPT Threading Machine Die Head Model # 26152 | Benefits-B01 GX170023 | Two SF6 Multi Analyzers & Adapters | Two - Dilo SF6 Multi Analyzer (Dilo Item # 3-038R-R303V0 Model Q-23398) and Two adapter Kits Accessories plus misc accessories (heater blankets, scale, etc) | Benefits-B01 GX170024 | Milwaukee Cable Cutter and Crimper | One Each Milwaukee M18 FORCE LOGIC 12 ton Crimper (Cat # 2778-22) and M18 FORCE LOGIC 1590 ACSR Cable Cutter (Cat # 2777-21) | Benefits-B01 GX170025 | Western Div Wireless Phasing Meters | Three phasing meters for Western AWCs - Norwalk, Torrington, Stamford. Hastings Phase-Tell III wireless Phasing Meter | Benefits-B01 GX170027 | DMA-35CRT Hydrometer - Data Logging | ALBER DMA35-CRT Hydrometer with data logging | Benefits-B01 GX170029 | Snowblowers | Three Snowblowers for Construction Group | Benefits-B01 BORXR011 | ICB Borderline Revs elim | ICB Borderline Revs elim | Benefits-B01 | 44711X CT17D021 | LONG HILL TO SOAPSTONE MICROW UPGRA | Upgrade the microwave equipment from DS3 to OC3 capacity to provide sufficient backhaul to enable microwave to be an alternate path from fiber and increase capacity. | Benefits-B01 2M721153 | CAR VS SVC; RPL TPX SVC TO COMM REP | CAR VS SVC; RPL TPX SVC TO COMM REPAIR/UPGRADE FROM POLE 61693_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 2M723162 | WC-9/3 RSO P#1468 INSTLLD, CO NEED | WC-9/3 RSO P#1468 INSTLLD, CO NEED RHANG TPX TO NEW POLE + HANG SRV TO HOUSE_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 3H620959 | Elliot St Htfd C9103 City Pole 9a | Elliot St Htfd C9103 City Pole 9a Replace 250W head_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01
  10. Part 61 of 77

    CT17D028 | North Stonington Paging Base | The existing equipment is at the end of its useful life. New equipment including a superior timing mechanism are proposed. No Stonington Radio Tower Site | Benefits-B01 3L820837 | FARMINGTON POLE 1076 70 HPS COBRA - | FARMINGTON POLE 1076 70 HPS COBRA - COMP 2/3/18 TOL_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 RESILEVL | RESILIENCY PROG FUNDING LEVELS | UCONN 2ND AMENDED AND RESTATED RESEARCH PROJECT(S)_x000D__x000D_ IDENTIFY WHICH PROGRAMS TO CONTINUE & FUNDING LEVELS OF RESILIENCY PROGRAMS BEYOND 2017_x000D__x000D_ Asset - STOCHASTIC DYNAMIC PROGRAMMING MODEL | Benefits-B01 1B722973 | JS - Larson Dr, Danb, Rem OH Neut, | JS - Larson Dr, Danb, Rem OH Neut, Inst OH Sec (28M13)_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 CS000711 | Remove Substation | Greens Farms 22W - Remove all equipment, foundations, fence and trap rocks. All equipment will be scrapped except for the transformers (22W-1X, 22W-2X and 22W-3X). All three transformers will be evaluated for possible use as system spare and it is likely that we keep one. The substation site should be cleared and turned over to Real Estate for sale. | Benefits-B01 FM1CNWSN | FARMINGTON 1C NW SENSOR RELAY | Farmington 1C NETWORK PROTECTOR SENSOR PART OF THE DIGITAL GRID RELAY PROJECT - FARMINGTON 1C SS THE SENSORS ARE BEING ADDED TO THE NW PROTECTOR RELAYS BEING INSTALLED THROUGHOUT CONNECTICUT. SENSORS CANNOT OPERATE WITHOUT THE NW PROTECTOR RELAYS_x000D__x000D_ Work order is to be used to capture costs for retrofitting relays for network protectors | Benefits-B01 4D720314 | S Cove Rd II, #34 Old Saybrook/TL-I | S Cove Rd II, #34 Old Saybrook/TL-INST 4/03CT OH-DB SVC@P#576 *FLOOD PLAIN INST*_x000D_ | Benefits-B01 2M721951 | EJC 116 South Mountain Dr, New Brit | EJC 116 South Mountain Dr, New Britain P#98992 Repl Svc to Midspan per T-Ticket_x000D_ AP1-YWO Total Cost Less Than 7K | Benefits-B01 CS000701 | Naugstuck 19K-Remove Substation | Naugatuck 19K - Remove all equipment, foundations, fence and trap rocks. All equipment will be scrapped except for the transformer (19K-1X) which will be evaluated for possible use as system spare. The substation site should be cleared and turned over to Real Estate for sale. | Benefits-B01 4N621319 | Elec Svc New Com/Ind DESG (DN) | Elec Svc New Com/Ind DESG (DN)_x000D_ | Benefits-B01 DSN82002 | (50): Activate 24A19 Feeder Positio | Flax Hill 24A - Activate 24A19 Feeder Position | Benefits-B01 2M821305 | CDOT 17-186 - RTE 6 Bristol Road Wi | CDOT 17-186 - RTE 6 Bristol Road Widening - Additional Pole Sets to New Depth_x000D_ JE-YWO Variance Job Type Exclusion | Benefits-B01 ILP611C1 | 2016 LC - Network 4500 Switch-ES CT | 4500 Switch Replacements - IT 2016 Lifecycle - ES CT | Benefits-B01 CS001941 | Jewett City 21D-Remove Substation | Jewett City 21D - Remove the substation. All of the equipment will be removed, including the foundations, fence and trap rock. The transformer will be sold for scrap and the site will be turned over to Real Estate for sale. An easement must be maintained becuase overhead lines will continue to cross the site. | Benefits-B01 4E721709 | Elec Maint Trouble Call - Repairs/O | Elec Maint Trouble Call - Repairs/Obsolescence OH (AROH)_x000D_ AP2-YWO Total Cost Variance Met - Variance :-1.0265 MIN.:-50 MAX.:50 | Benefits-B01 CT17D032 | Berlin paging network materials | This work order covers equipment needed in Berlin to improve the contention mechanism for holding off paging and RCLMS transmitter controllers. | Benefits-B01 GXC18C29 | Utility Light (1) Begley 2AD | 2AD - Milwaukee Utility Light Model 2122-21HD (1) $745 | Benefits-B01 GXC18C30 | Climbing Hooks (1) 2NR | 2EK - Climbing Hooks (1) Hydron Inc. TOTAL: $1306.67 | Benefits-B01 GXC18C31 | LED Stand Light Kit (1) 2NR Engel | 2NR - M18LED HP Stand Light Kit - (1) TOTAL $1,250 ENGEL | Benefits-B01

Text of RRU-159 Attachment 03.pdf

Extracted from the file · 840 pages · 14,413,580 characters

Text of RRU-159 Attachment 02.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of RRU-159 Attachment 02.pdf

Extracted from the file · 1,137 pages · 16,605,462 characters

Text of RRU-159 Attachment 01.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-159 Attachment 01.pdf

Extracted from the file · 1 page · 1,403 characters

As listed on the current system

Question(s) Answered 159 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 11/06/2026

This filing on the current system (opens in a new tab)