Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 162, 165

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy7 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files7

Search terms highlighted
Eversource rate increase is on 12 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
2 pages match

Text of RRU-163 Attachment 2.pdf

Extracted from the file · 7 pages · 46,127 characters

Text of RRU-163 Attachment 2.xlsx

Sheet names, column headings and text cells; numbers left out

7 pages match
  1. Page 75 of 129

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 75 of 129 Eversource Energy 2022 CT Management Audit Set FTI-02 Date Issued December 07, 2022 Q- FTI-300 Page 1 of 1 Date Filed: January 17, 2023 Witness: Munson, Danielle J Request from: F T I Consulting Question: Provide the services, amounts and procedures utilized in relation to all entities within the Eversource corporate structure that currently directly charge or allocate costs to Connecticut utilities; describe the general basis of the allocations and clearly identify each entity with Eversource charging time to the CT Utilities’. Provide copies of the contracts executed between these entities for the last three years. Response: Please refer to FTI-117 for an explanation on cost allocation and time-charging procedures. Please refer to FTI-300, Attachment 1(CLP) Confidential for charges from Eversource affiliates to CL&P for the last three years. Please refer to FTI-300, Attachment 1(YGS) Confidential for charges from Eversource affiliates to YGS for the last three years. Please refer to FTI-300, Attachment 1(AQ) Confidential for charges from Eversource affiliates to AQ for the last three years. Please see FTI-300, Attachment 1(ES) Confidential, FTI-300, Attachment 2(ES) Confidential, and FTI-300, Attachment 3(ES) Confidential for contracts executed between YGS and CL&P for the last three years. Please see FTI-115, Attachment 1(AQ) for the contract between Eversource Energy Service Company and Aquarion Company (AQ parent).
  2. Page 76 of 129

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 76 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-347 Page 1 of 1 Date Filed: February 21, 2023 Witness: Munson, Danielle J, Kirven, Debra Request from: F T I Consulting Question: Referring to the response to FTI-114, Attachment 1 (ES), please provide the following information: A) Please explain the nature of the "one time charge related to the Hingham (Massachusetts water company) sale," in the amount of $11.5 million, including 1) the nature of the costs incurred by EESC and which function in EESC incurred them, and 2) how the $11.5 million amount was calculated, accumulated or determined. B) Please state whether this charge was assigned or allocated to any of Aqauarion's water companies, and if so, which companies and in what amounts. C) If this charge was not allocated, assigned or billed to any of Aqaurion's water companies, please describe how it was treated for accounting purposes by Aquarion. Response: (a) There were no costs incurred by the Eversource Energy Service Company (ESC). The Hingham, MA sale was compelled by the Town of Hingham pursuant to provisions of the historical Town Charter and the sale had to be recorded at fair value. In accordance with Article 2.1(a) of the Hingham Asset Purchase agreement (FTI-347, Attachment 1 (ES) Confidential), a portion of the proceeds from the Hingham sale was recorded as a charitable contribution to fund the Eversource Energy Foundation. This charitable contribution totaled $6.4 million and the remainder was retained by ESC. The Eversource Energy Foundation is an independent, nonprofit philanthropic organization that is funded solely by shareholders from Eversource Energy and is dedicated to supporting our communities and making a positive difference in the lives of our customers. (b) Aquarion Water Company of Massachusetts, Inc. included this charge when calculating the after-tax gain on the sale of the Hingham system of $3.5 million. (c) Not applicable. Please refer to part (b), above.
  3. Page 77 of 129Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 77 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-348 Page 1 of 2 Date Filed: February 21, 2023 Witness: Munson, Danielle J Request from: F T I Consulting Question: Referring to the attachments to FTI-114, specifically, the "footnotes" pages from FERC Form 1 in attachments 1, 2 & 3 (CLP), please explain the following: A) Some of the EESC function categories appear to be functions, as titled, such as "Corporate Relations," "Electric Distribution" and "Information Technology." Others appear to be types of cost, such as "Benefits," "Depreciation" and "Rate of Return." Please explain why cost categories that appear to be types of cost are grouped with what appear to be the costs of specific service company functions. B) Are the expenses in the function "Benefits" the payroll benefits associated with all Eversource employees (utility and service company), or just the service company? Please explain. C) Describe the costs in the "Depreciation" function. Is this depreciation on service company plant investment only? D) Describe the costs in the "Rate of Return" function. Is this a regulated return on investment in service company property? If not, what is it? Why is it charged to umbrella FERC account 401, Operating Expense if it is return on investment? E) In the amounts shown for various functions, over $60 million (in 2019, at least) is recorded as FERC umbrella account 412 - Revenue from Plant Leased to Others. This does not appear to be leased plant revenue. Please explain what it is and what title Eversource gives to FERC account 412. Response: (a) The “footnotes” pages from FERC Form 1 in FTI-114, Attachments 1, 2, 3 (CL&P) for affiliate charges from the Eversource Energy Service Company (ESC) are categorized by service department – function, as required by the FERC Form 1 and 2 instructions. For increased transparency and due to the amounts, Eversource Energy also presents certain costs separately, including “Benefits,” “Depreciation” and “Rate of Return.” (b) The costs represented in the “Benefits” function include ESC employee benefits, as well a certain CL&P Operating Company employee benefits, which were paid through direct charging ESC workorders. The benefit costs were appropriately charged to CL&P and a corresponding intercompany payable established to ESC. (c) Yes, the costs in the “Depreciation” function are for ESC plant investments only. (d) Yes, the costs in the "Rate of Return" function are the ESC return on the capital investment that is made by ESC on behalf of the Operating Companies, primarily relating to shared IT infrastructure. Generally, the Rate of Return applied by ESC in the normal course of business for computing the revenue requirement associated with capital investments made by ESC on behalf of the Operating Companies is derived using: (1) a weighted average of the
  4. Page 78 of 129

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 78 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-348 Page 2 of 2 Operating Companies’ most recently authorized ROEs; and (2) ESC's actual capital structure, including the cost of ESC debt. The Rate of Return is charged to FERC Account 401, operating expenses, as it is charged to the affiliates in FERC Account 930.2 "Miscellaneous General Expenses." This accounting was reviewed with FERC Audit Staff in conjunction with Docket No. FA19-8-000. The final report is provided as FTI-240, Attachment 1 (CL&P), and no comments were noted. (e) The amounts presented in FERC Account 412 on the “footnotes” pages to the FERC Form 1 should have been presented as FERC Accounts 107 and 108. This is a presentation item only as the charges were appropriately recorded on CL&P’s balance sheets in FERC Accounts 107 and 108.
  5. Page 79 of 129Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 79 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-349 Page 1 of 2 Date Filed: February 22, 2023 Witness: Munson, Danielle J Request from: F T I Consulting Question: Referring to the attachments to FTI-114, specifically, the "footnotes" pages from FERC Form 1 in attachments 1, 2 & 3 (CLP), please explain the following: A) Why did EESC's depreciation costs charged to CL&P increase 74% between 2019 and 2021, from $21,865,986 to $38,083,220? What is the plant behind the additional $16.2 million in EESC depreciation charged to CL&P in 2021 compared with 2019? B) Why did EESC Engineering and Emergency Prep function costs charged to CL&P increase by 36% between 2019 and 2021, from $18,845,858 in 2019 to $25,558,065 in 2021? What is the additional $6.7 million in Engineering / Emergency Prep function cost charged to CL&P in 2021 compared with 2019? C) Why did Finance and Accounting costs charged by EESC to CL&P increase by 24%, from $14,624,106 in 2020 to $18,100,314 in 2021? WHat comprises the additional $3.5 million in CL&P's share of Finance and Accounting cost in 2021 over the cost in 2020? D) Why did EESC Rate of Return charged to CL&P increase 29%, from $22,214,097 in 2019 to $28,632,315 in 2021? What comprises the additional $6.4 million in Rate of Return charged to CL&P in 2021 over the amount charged in 2019? E) Overall, please explain why EESC costs charged to CL&P increased by 17% between 2019 and 2021, from $329.9 million to $385.7 million, a rate much higher than the rate of inflation for the two year period? Response: (a) The depreciation costs charged to CL&P increased between 2019 and 2021 due to increased asset investments, primarily for IT infrastructure. The plant behind the additional $16.2 million in Eversource Energy Service Company depreciation charged to CL&P in 2021 compared with 2019 primarily relates to the following assets/projects that were placed in service during that time period: Microsoft Office 365, ITSM Suite Upgrade, Digital Strategy – One Company Web, Work & Asset Management (WAM) – Electric Operations, Power Survey Technology, and IT Bill Consolidation. (b) The $6.7 million increase in Engineering and Emergency Prep was primarily driven by higher outside services and higher labor charges. Outside services increased due to engineering contractors hired to perform reliability trends and asset data management. Overall labor increased primarily due to additional employees hired in the Project Controls Engineering group, a new Engineering Rotational program that commenced in 2020, and increased time charged on Telecom Engineering due to additional projects between 2019 and 2021. (c) The $3.5 million increase in Finance and Accounting is primarily due to higher outside services and higher labor charges due to annual merit increases. Certain areas within the Finance
  6. Page 80 of 129Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 80 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-349 Page 2 of 2 organization support the Transmission program. Due to the increased number of capital projects, there has been an increase in contractor labor to provide the level of support required. Additionally, approximately $1 million of the increase is due to certain deferred compensation costs presented in Finance and Accounting in 2021 but reflected within the “Benefits” category in the prior years. (d) The $6.4 million increase in Rate of Return is due to increased asset investments at Eversource Energy Service Company necessitated to: (1) enable business process improvements and new business capabilities via the implementation of new technology solutions; (2) improve customer interaction capabilities; (3) standardize collaboration and service technologies across the enterprise; and (4) maintain secure and supported technology solutions. (e) Overall, costs increased from 2019 to 2021 primarily due to the above mentioned variances. In addition, the variance also includes higher medical and other benefits, including merit increases; an increase in overall labor charges due to an increase in full-time employees hired in the Transmission organization; and, higher costs for outside services related to information technology infrastructure and application maintenance/support.
  7. Page 81 of 129Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 81 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-350 Page 1 of 2 Date Filed: February 22, 2023 Witness: Munson, Danielle J Request from: F T I Consulting Question: Referring to the attachments to FTI-114, specifically, the "footnotes" pages from FERC Form 2 in attachments 1, 2 & 3 (YGS), please explain the following: A) Why did EESC's depreciation costs charged to Yankee Gas increase 58% between 2019 and 2020, from $5,714,824 to $9,017,288? What is the plant behind the additional $3.3 million in EESC depreciation charged to Yankee in 2020 compared with 2019? B) Why did EESC Benefits costs charged to Yankee Gas increase by 21%, from $19,189,946 to $23,257,244 between 2019 and 2021? What comprises the additional $$4.1 million in Benefits costs charged to Yankee in 2021 compared with 2019? C) Why did Operations Administration costs charged by EESC to Yankee Gas increase by 24%, from $12,150,626 in 2019 to $15,055,015 in 2020? What comprises the additional $2.9 million in Yankee Gas's share of EESC Operations Administration cost in 2020 over the cost in 2019? D) Why did EESC Rate of Return charged to Yankee Gas increase 33%, from $5,397,911 in 2019 to $7,177,834 in 2020? What comprises the additional $1.8 million in Rate of Return charged to Yankee Gas in 2020 over the amount charged in 2019? E) Overall, please explain why EESC costs charged to Yankee Gas increased by 13% in one year from 2019 to 2020, from $68.7 million to $77.6 million, a rate much higher than the rate of inflation for the one year period? Response: (a) The depreciation costs charged to YGS increased between 2019 and 2020 due to increased asset investments, primarily for IT infrastructure. The plant behind the additional $3.3 million in EESC depreciation charged to YGS in 2020 compared with 2019 primarily relates to the following assets/projects that were placed in service during that time period: Work and Asset Management (WAM) – Gas mobile, Microsoft Office 365, ITSM Suite Upgrade, and IT Bill Consolidation. (b) The $4.1 million increase in Eversource Energy Service Company (ESC) benefits costs to YGS in 2021 compared to 2019 is primarily due to higher medical and prescription benefits and higher post-retirement benefits. Approximately $2.4 million of this increase relates to higher medical and prescription benefit charges for YGS employees that were paid using a direct charging ESC workorder. The benefit costs were appropriately charged to YGS and a corresponding intercompany payable established to ESC.
  8. Page 82 of 129Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 82 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-350 Page 2 of 2 (c) The $2.9 million increase in Operations Administration is primarily driven by higher labor charges due to new employees hired into the Management Gas Control, Project Engineering and Quality Assurance organizations as well as higher outside services for Engineering Design Services. (d) The $1.8 million increase in Rate of Return charged to YGS is due to increased asset investments at ESC necessitated to: (1) enable business process improvements and new business capabilities via the implementation of new technology solutions; (2) improve customer interaction capabilities; (3) standardize collaboration and service technologies across the enterprise; and (4) maintain secure and supported technology solutions. (e) Overall, costs increased from 2019 to 2020 primarily due to the above-mentioned variances. In addition, the variance for the one-year period includes the impact of COVID 19 related costs and higher costs for outside services related to information technology infrastructure and application support/maintenance.
  9. Page 83 of 129

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 83 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-351 Page 1 of 2 Date Filed: February 22, 2023 Witness: Munson, Danielle J Request from: F T I Consulting Question: Referring to the response to FTI-114, Attachment 2 (CLP), please: A) Identify the storm event or events responsible for most or all of the $19.2 million in "storm outage support" provided by NSTAR Electric and Public Service New Hampshire to CL&P, as shown on page 429 of FERC Form 1 for 2020. B) Identify the month or months in 2020 in which most of the support was provided to CL&P, and the approximate number of NSTAR and PSNH employees whose time was charged to CL&P. If the outage support was something other than employee labor, please describe it. C) Please describe the $4,006,888 in meters transferred by CL&P to NSTAR Electric in 2020. Specifically, how many meters were transferred, why did CL&P have so many spare meters, why were they needed by NSTAR, and what was the pricing basis for the meters transferred? D) Please describe the $6,741,305 in transmission system modifications CL&P made on behalf of NSTAR Electric in 2020. Specifically, 1) was this CL&P employee labor, and if so, how may employees were involved? 2) If it was not employee labor, what was the nature of the cost and how was the transfer price established. Response: (a) and (b) The $19.2 million in outage support was caused by Tropical Storm Isaias in early August 2020; a thunderstorm event in late August 2020; and a rain/wind event in November 2020. The number of NSTAR and PSNH employees supporting the Tropical Storm Isaias response in Connecticut in early August 2020 was 789 and 416, respectively. The number of NSTAR and PSNH employees supporting the thunderstorm event in late August 2020 was 106 and 89, respectively. The number of NSTAR and PSNH employees supporting the rain/wind event in November 2020 was 72 and 64, respectively. (c) There were 28,318 meters transferred in the amount of $3,449,896 to NSTAR Electric. There were excess meters at CL&P as a result of PURA’s initiation of an AMI proceeding in 2019, in Docket No. 17-12-03RE02, and the impact of the COVID-19 pandemic, which reduced the amount of meter exchanges conducted in 2020 in CT. To put the meters to use, the meters were transferred to Eastern Massachusetts for use in that service territory. The service territory in Western Massachusetts does not have a meter lab. Therefore, the meters are received in and stored in the closest meter lab to that service territory, which is New Britain, CT. When meters are shipped to Western Massachusetts, they are then transferred to individual area work centers for deployment. The remaining $556,992 relates to 3,508 meters that were inadvertently paid for by CL&P due to an incorrect paying entity in the source system. When this transaction was paid, an
  10. Page 84 of 129

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 23, 2026 RRU-163 Attachment 3 Page 84 of 129 Eversource Energy 2022 CT Management Audit Set FTI-03 Date Issued February 01, 2023 Q- FTI-351 Page 2 of 2 intercompany receivable was established at CL&P and NSTAR Electric received the charge and established an intercompany payable to CL&P. The intercompany payable and receivable were settled in cash in the following month. The meters were transferred at book cost. (d) The majority of the costs charged to NSTAR Electric in the amount of $6,726,533 was for materials issued from a CT storeroom for projects in the Western Massachusetts service territory. The remaining charges were due to labor, employee expenses and vehicle charges incurred by employee personnel to manage and transport the materials. There is no mark-up on costs for services or materials charged by affiliates.

Text of RRU-165_Final.pdf

Extracted from the file · 1 page · 575 characters

Words on different pagesRead the text of RRU-165_Final.pdf

As listed on the current system

Question(s) Answered 162, 165 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 11/06/2026

This filing on the current system (opens in a new tab)