Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 67, 77, 83

Files14

Search terms highlighted
Eversource rate increase is on 8 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages

Text of RRU-067 Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out

Words on different pages

Text of RRU-067 Attachment 2.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-067 Attachment 3.pdf

Extracted from the file · 1 page · 147 characters

Text of RRU-077_Final.pdf

Extracted from the file · 1 page · 1,339 characters

Words on different pagesRead the text of RRU-077_Final.pdf

Text of RRU-077 Attachment 1.pdf

Extracted from the file · 1 page · 663 characters

Text of RRU-077 Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-077 Attachment 2.pdf

Extracted from the file · 1 page · 2,707 characters

Text of RRU-077 Attachment 2.xlsx

Sheet names, column headings and text cells; numbers left out

Text of RRU-083_Final.pdf

Extracted from the file · 2 pages · 2,447 characters

Words on different pagesRead the text of RRU-083_Final.pdf
8 pages match
  1. Page 13 of 24Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 13 of 24 107 Selden Street, Berlin, CT 06037 P.O. Box 270, Hartford, CT 06141-0270 Vincent P. Pace [phone removed] [email removed] January 31, 2023 Jeffrey R. Gaudiosi, Esq. Executive Secretary Public Utilities Regulatory Authority 10 Franklin Square New Britain, CT 06051 Re: Docket No. 17-10-46, Application Of The Connecticut Light And Power Company D/B/A Eversource Energy To Amend Rate Schedules – Compliance with April 18, 2018 Decision (Orders No. 5, 6 & 7) Dear Mr. Gaudiosi: The Connecticut Light and Power Company dba Eversource Energy (the “Company”) submits this filing in compliance with Orders 5, 6 and 7 of the Public Utilities Regulatory Authority’s (“PURA’s) April 18, 2018 decision in this docket. A. Order No. 5 Order No. 5 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year actuarial minimum pension contribution and provide the amount of actual pension contribution made for the corresponding calendar year. The Company relies on its actuary to project pension funding requirements at the overall plan level and based on applicable IRS rules for determining minimum required contributions. Contributions are generally allocated across entities based on the relative funded status of each entity. In addition, the Company has discretion to increase or decrease allocations among entities based on corporate finance, tax and other considerations. The actuarial firm utilized by Eversource determined that there was no minimum required contribution for 2022 based on funding requirements adopted under the American Rescue Plan Act of 2021 (ARPA). (see attached excerpt in Attachment 1 hereto from 2022 Actuarial Valuation Report). While no minimum contribution was required, $60 million was contributed by Eversource Energy Service Company and $15 million was contributed by NSTAR Electric on a discretionary basis during 2022. Contributions in excess of the minimum required contributions are reflected in
  2. Page 14 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 14 of 24 the prefunding balance; and such excess funding can be used in future years to offset minimum funding requirements at the overall plan level. B. Order No. 6 Order No. 6 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year actuarial minimum FAS 106 contribution and provide the amount of actual pension contribution made for the corresponding calendar year. FAS 106 addresses Post-Retirement Benefits other than Pension (OPEB) Plans. There is no IRS requirement to fund OPEB Plans and no minimum required contribution. During 2022, there were no contributions to the OPEB Plan by the Company. The OPEB Plan continues to be well-funded. C. Order No. 7 Order No. 7 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year contributions to the MedVantage plan. There is no IRS requirement to fund the Med-Vantage plan and no minimum required contribution. During 2022, there was no contribution to the Med-Vantage plan. If you have any questions in connection with this compliance filing, please do not hesitate to contact the undersigned. Sincerely, Vincent P. Pace Vincent P. Pace Assistant General Counsel On behalf of CL&P d/b/a Eversource Energy cc: Service List
  3. Page 15 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 15 of 24 Quarterly Contributions Unless a plan qualifies for an exemption, quarterly installments toward the minimum required contribution are due on April 15, July 15, and October 15 of the plan year, and January 15 of the following plan year. If the quarterly due date falls on a weekend or holiday, it is recommended that the payment be made by the last business day before the weekend or holiday. If the plan does not satisfy these quarterly installment requirements, interest penalties payable to the plan accrue, and plan participants may need to be notified if the contribution is more than 60 days late. In addition, there may be other implications of missed quarterly installments such as a requirement to notify the PBGC and a requirement to file certain information with the PBGC under ERISA section 4010. <> A plan is exempt from the quarterly contribution requirements if it did not have a funding shortfall for the prior plan year. Quarterly requirements may be satisfied by a combination of contributions, and, if eligible, application of funding balances. 2022 Quarterly Contribution Exemption The plan did not have a funding shortfall for the 2021 plan year, so quarterly contributions are not required for the 2022 plan year. 2023 Quarterly Contribution Exemption The plan does not have a funding shortfall for the 2022 plan year, so quarterly contributions are not required for the 2023 plan year.
  4. Page 16 of 24Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 16 of 24 107 Selden Street, Berlin, CT 06037 P.O. Box 270, Hartford, CT 06141-0270 Vincent P. Pace [phone removed] [email removed] January 30, 2024 Jeffrey R. Gaudiosi, Esq. Executive Secretary Public Utilities Regulatory Authority 10 Franklin Square New Britain, CT 06051 Re: Docket No. 17-10-46, Application Of The Connecticut Light And Power Company D/B/A Eversource Energy To Amend Rate Schedules – Compliance with April 18, 2018 Decision (Orders No. 5, 6 & 7) Dear Mr. Gaudiosi: The Connecticut Light and Power Company dba Eversource Energy (the “Company”) submits this filing in compliance with Orders 5, 6 and 7 of the Public Utilities Regulatory Authority’s (“PURA’s) April 18, 2018 decision in this docket. A. Order No. 5 Order No. 5 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year actuarial minimum pension contribution and provide the amount of actual pension contribution made for the corresponding calendar year. The Company relies on its actuary to project pension funding requirements at the overall plan level and based on applicable IRS rules for determining minimum required contributions. Contributions are generally allocated across entities based on the relative funded status of each entity. In addition, the Company has discretion to increase or decrease allocations among entities based on corporate finance, tax and other considerations. The actuarial firm utilized by Eversource determined that there was no minimum required contribution for 2023 based on funding requirements adopted under the American Rescue Plan Act of 2021 (ARPA). (see attached excerpt in Attachment 1 hereto from 2023 Actuarial Valuation Report). The Company did not make any discretionary contributions to the plan during 2023. Contributions in excess of the minimum required contributions are reflected in the prefunding balance; and such excess funding can be used in future years to offset minimum funding requirements at the overall plan level.
  5. Page 17 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 17 of 24 B. Order No. 6 Order No. 6 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year actuarial minimum FAS 106 contribution and provide the amount of actual pension contribution made for the corresponding calendar year. FAS 106 addresses Post-Retirement Benefits other than Pension (OPEB) Plans. There is no IRS requirement to fund OPEB Plans and no minimum required contribution. During 2023, there were no contributions to the OPEB Plan by the Company. The OPEB Plan continues to be well-funded. C. Order No. 7 Order No. 7 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year contributions to the MedVantage plan. There is no IRS requirement to fund the Med-Vantage plan and no minimum required contribution. During 2023, there was no contribution to the Med-Vantage plan. If you have any questions in connection with this compliance filing, please do not hesitate to contact the undersigned. Sincerely, Vincent P. Pace Vincent P. Pace Assistant General Counsel On behalf of CL&P d/b/a Eversource Energy cc: Service List
  6. Page 18 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 18 of 24 Quarterly Contributions Unless a plan qualifies for an exemption, quarterly installments toward the minimum required contribution are due on April 15, July 15, and October 15 of the plan year, and January 15 of the following plan year. If the quarterly due date falls on a weekend or holiday, it is recommended that the payment be made by the last business day before the weekend or holiday. If the plan does not satisfy these quarterly installment requirements, interest penalties payable to the plan accrue, and plan participants may need to be notified if the contribution is more than 60 days late. In addition, there may be other implications of missed quarterly installments such as a requirement to notify the PBGC and a requirement to file certain information with the PBGC under ERISA section 4010. <> A plan is exempt from the quarterly contribution requirements if it did not have a funding shortfall for the prior plan year. Quarterly requirements may be satisfied by a combination of contributions, and, if eligible, application of funding balances. 2023 Quarterly Contribution Exemption The plan did not have a funding shortfall for the 2022 plan year, so quarterly contributions are not required for the 2023 plan year. 2024 Quarterly Contribution Exemption The plan does not have a funding shortfall for the 2023 plan year, so quarterly contributions are not required for the 2024 plan year.
  7. Page 19 of 24Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 19 of 24 107 Selden Street, Berlin, CT 06037 P.O. Box 270, Hartford, CT 06141-0270 Vincent P. Pace [phone removed] [email removed] January 31, 2025 Jeffrey R. Gaudiosi, Esq. Executive Secretary Public Utilities Regulatory Authority 10 Franklin Square New Britain, CT 06051 Re: Docket No. 17-10-46, Application Of The Connecticut Light And Power Company D/B/A Eversource Energy To Amend Rate Schedules – Compliance with April 18, 2018 Decision (Orders No. 5, 6 & 7) Dear Mr. Gaudiosi: The Connecticut Light and Power Company dba Eversource Energy (the “Company”) submits this filing in compliance with Orders 5, 6 and 7 of the Public Utilities Regulatory Authority’s (“PURA’s”) April 18, 2018 decision in this docket. A. Order No. 5 Order No. 5 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year actuarial minimum pension contribution and provide the amount of actual pension contribution made for the corresponding calendar year. The Company relies on its actuary to project pension funding requirements at the overall plan level and based on applicable IRS rules for determining minimum required contributions. Contributions are generally allocated across entities based on the relative funded status of each entity. In addition, the Company has discretion to increase or decrease allocations among entities based on corporate finance, tax and other considerations. The actuarial firm utilized by Eversource determined that there was no minimum required contribution for 2024 based on funding requirements adopted under the American Rescue Plan Act of 2021 (ARPA). (see attached excerpt in Attachment 1 hereto from 2024 Actuarial Valuation Report). The Company did not make any discretionary contributions to the plan during 2024. Contributions in excess of the minimum required contributions are reflected in the prefunding balance; and such excess funding can be used in future years to offset minimum funding requirements at the overall plan level.
  8. Page 20 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 20 of 24 B. Order No. 6 Order No. 6 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year actuarial minimum FAS 106 contribution and provide the amount of actual pension contribution made for the corresponding calendar year. FAS 106 addresses Post-Retirement Benefits other than Pension (OPEB) Plans. There is no IRS requirement to fund OPEB Plans and no minimum required contribution. During 2024, there were no contributions to the OPEB Plan by the Company. The OPEB Plan continues to be well-funded. C. Order No. 7 Order No. 7 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year contributions to the MedVantage plan. There is no IRS requirement to fund the Med-Vantage plan and no minimum required contribution. During 2024, there was no contribution to the Med-Vantage plan. If you have any questions in connection with this compliance filing, please do not hesitate to contact the undersigned. Sincerely, Vincent P. Pace Vincent P. Pace Assistant General Counsel On behalf of CL&P d/b/a Eversource Energy cc: Service List
  9. Page 21 of 24

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 21 of 24 15 15 15 15 60 4010 2024 2023 2024 2025 2024 2025
  10. Page 22 of 24Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 25, 2026 RRU-083 Attachment 1 Page 22 of 24 107 Selden Street, Berlin, CT 06037 P.O. Box 270, Hartford, CT 06141-0270 Vincent P. Pace [phone removed] [email removed] January 31, 2026 Jeffrey R. Gaudiosi, Esq. Executive Secretary Public Utilities Regulatory Authority 10 Franklin Square New Britain, CT 06051 Re: Docket No. 17-10-46, Application Of The Connecticut Light And Power Company D/B/A Eversource Energy To Amend Rate Schedules – Compliance with April 18, 2018 Decision (Orders No. 5, 6 & 7) Dear Mr. Gaudiosi: The Connecticut Light and Power Company dba Eversource Energy (the “Company”) submits this filing in compliance with Orders 5, 6 and 7 of the Public Utilities Regulatory Authority’s (“PURA’s”) April 18, 2018 decision in this docket. A. Order No. 5 Order No. 5 states: No later than January 31, 2019, and annually thereafter until the next general rate proceeding, the Company shall provide its calendar year actuarial minimum pension contribution and provide the amount of actual pension contribution made for the corresponding calendar year. The Company relies on its actuary to project pension funding requirements at the overall plan level and based on applicable IRS rules for determining minimum required contributions. Contributions are generally allocated across entities based on the relative funded status of each entity. In addition, the Company has discretion to increase or decrease allocations among entities based on corporate finance, tax and other considerations. The actuarial firm utilized by Eversource determined that there was no minimum required contribution for 2025 based on funding requirements adopted under the American Rescue Plan Act of 2021 (ARPA). (see attached excerpt in Attachment 1 hereto from 2025 Actuarial Valuation Report). The Company did not make any discretionary contributions to the plan during 2025. Contributions in excess of the minimum required contributions are reflected in the prefunding balance; and such excess funding can be used in future years to offset minimum funding requirements at the overall plan level.

Text of RRU-083 Attachment 2.pdf

Extracted from the file · 160 pages · 784,587 characters

As listed on the current system

Question(s) Answered 67, 77, 83 (CL&P dba Eversource Energy) Date Filed: 10/11/2026

This filing on the current system (opens in a new tab)