Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 32

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy210 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files210

Search terms highlighted
Eversource rate increase is on 9 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of RSR-032 Attachment 176_Part2.pdf

Extracted from the file · 754 pages · 1,598,897 characters

Text of RSR-032 Attachment 176_Part1.pdf

Extracted from the file · 110 pages · 439,601 characters

Text of RSR-032 Attachment 175_Part7.pdf

Extracted from the file · 275 pages · 622,526 characters

Text of RSR-032 Attachment 175_Part6.pdf

Extracted from the file · 350 pages · 828,421 characters

Text of RSR-032 Attachment 175_Part5.pdf

Extracted from the file · 350 pages · 841,526 characters

Text of RSR-032 Attachment 175_Part4.pdf

Extracted from the file · 350 pages · 529,828 characters

Text of RSR-032 Attachment 175_Part3.pdf

Extracted from the file · 350 pages · 417,827 characters

Text of RSR-032 Attachment 175_Part2.pdf

Extracted from the file · 350 pages · 717,402 characters

Text of RSR-032 Attachment 175_Part1.pdf

Extracted from the file · 350 pages · 426,888 characters

Text of RSR-032 Attachment 174.pdf

Extracted from the file · 2 pages · 3,788 characters

Text of RSR-032 Attachment 173.pdf

Extracted from the file · 9 pages · 19,276 characters

Text of RSR-032 Attachment 172.pdf

Extracted from the file · 2 pages · 5,216 characters

Text of RSR-032 Attachment 171.pdf

Extracted from the file · 2 pages · 7,025 characters

Text of RSR-032 Attachment 170.pdf

Extracted from the file · 4 pages · 596 characters

Text of RSR-032 Attachment 169.pdf

Extracted from the file · 14 pages · 2,105 characters

Text of RSR-032 Attachment 168.pdf

Extracted from the file · 178 pages · 303,260 characters

Text of RSR-032 Attachment 167_Part2.pdf

Extracted from the file · 844 pages · 1,367,165 characters

Text of RSR-032 Attachment 167_Part1.pdf

Extracted from the file · 284 pages · 480,797 characters

Text of RSR-032 Attachment 166.pdf

Extracted from the file · 4 pages · 5,984 characters

Text of RSR-032 Attachment 165_Part 4.pdf

Extracted from the file · 84 pages · 130,960 characters

Text of RSR-032 Attachment 165_Part 3.pdf

Extracted from the file · 482 pages · 674,897 characters

Text of RSR-032 Attachment 165_Part 2.pdf

Extracted from the file · 509 pages · 549,394 characters

Text of RSR-032 Attachment 165_Part 1.pdf

Extracted from the file · 500 pages · 578,799 characters

Text of RSR-032 Attachment 164.pdf

Extracted from the file · 42 pages, 16 without text · 66,266 characters

Text of RSR-032 Attachment 163.pdf

Extracted from the file · 575 pages · 624,136 characters

Text of RSR-032 Attachment 162.pdf

Extracted from the file · 17 pages · 19,879 characters

Text of RSR-032 Attachment 161 _Part2.pdf

Extracted from the file · 609 pages · 625,572 characters

Text of RSR-032 Attachment 161 _Part1.pdf

Extracted from the file · 131 pages · 171,359 characters

Text of RSR-032 Attachment 160.pdf

Extracted from the file · 56 pages · 84,793 characters

Text of RSR-032 Attachment 159.pdf

Extracted from the file · 97 pages · 159,126 characters

Text of RSR-032 Attachment 158.pdf

Extracted from the file · 54 pages · 96,528 characters

Text of RSR-032 Attachment 157.pdf

Extracted from the file · 261 pages · 326,004 characters

Text of RSR-032 Attachment 156.pdf

Extracted from the file · 74 pages · 99,158 characters

Text of RSR-032 Attachment 155.pdf

Extracted from the file · 40 pages · 40,141 characters

Text of RSR-032 Attachment 154.pdf

Extracted from the file · 37 pages · 59,275 characters

Text of RSR-032 Attachment 153.pdf

Extracted from the file · 61 pages · 86,468 characters

Text of RSR-032 Attachment 152.pdf

Extracted from the file · 126 pages · 258,689 characters

Text of RSR-032 Attachment 151.pdf

Extracted from the file · 340 pages · 405,994 characters

Text of RSR-032 Attachment 150.pdf

Extracted from the file · 33 pages · 27,344 characters

Text of RSR-032 Attachment 149.pdf

Extracted from the file · 47 pages · 51,678 characters

Text of RSR-032 Attachment 148.pdf

Extracted from the file · 52 pages · 65,933 characters

Text of RSR-032 Attachment 147.pdf

Extracted from the file · 136 pages · 187,807 characters

Text of RSR-032 Attachment 146.pdf

Extracted from the file · 211 pages · 257,714 characters

Text of RSR-032 Attachment 145.pdf

Extracted from the file · 58 pages · 84,698 characters

Text of RSR-032 Attachment 144.pdf

Extracted from the file · 31 pages · 57,751 characters

Text of RSR-032 Attachment 143.pdf

Extracted from the file · 30 pages · 51,258 characters

Text of RSR-032 Attachment 142.pdf

Extracted from the file · 33 pages · 29,732 characters

Words on different pages
  1. Page 13 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 13 of 578 ANNUAL REPORT Eversource Energy 3.3 AOPEC #4 Remediation As stated in the 2019 Annual Report, remediation of AOPEC #4 was planned for 2020 to address PCB impacts exceeding EPA criteria at one localized area and shallow ETPH impacts exceeding DEEP Remediation Standard Regulations (RSR) Residential Direct Exposure Criteria (RES DEC) and GA Pollutant Mobility Criteria (GA PMC) standards across a larger area of this AOPEC. The PCB excavation was completed as a Performance-Based cleanup in accordance with Title 40 CFR Section 761.61(b) and confirmatory sampling fulfilled the requirements of 40 CFR 761.61 Subpart O This AOPEC is located north of the former vehicle maintenance garage building and along the fence line (See Figure 2). Eversource mobilized Strategic Environmental Services, Inc. of Glastonbury, CT (SES) to perform the remedial activities on November 30, December 1, 2, 3, 4 and 7, 2020. SES’s work was overseen by Weston & Sampson field staff. After the planned excavation limits were achieved, Weston & Sampson collected confirmation samples for analytical testing. Details of the remedial activities by contaminant type including excavation dimensions, confirmatory sampling and analytical results and waste disposal documentation are included in the following sections. Analytical laboratory reports are included in Appendix A and analytical data is summarized in Table 1. 3.3.1 ETPH Remediation Sampling and Analytical Results Summary Initially, SES saw-cut and removed the asphalt layer within the proposed excavation area and placed the asphalt debris into triaxle dump trucks. The asphalt was transported to Recycled Concrete Products of Connecticut (Broad Brook, CT) where it was recycled. SES used a Hydrema excavator and Bobcat skid steer to conduct the soil excavation and removal work. Soil removed from the excavation was loaded into trucks and roll offs for off-Site disposal. The L-shaped ETPH remediation area measured 180 feet (ft.) long by 20 ft. wide and 3 ft. deep at its longest stretch and 32 ft. long by 22 ft. feet wide by 2 ft. deep for the remaining portion which overlaps the PCB removal areas discussed in Section 3.3.2. Evidence of impacts such as staining or odors was not observed in soils. Based on the size of the excavation, confirmation sidewall and bottom soil samples were generally collected at a frequency of approximately one every 20 ft (Figure 2A). Weston & Sampson collected a total of 37 confirmation soil samples, designated CS-E1 through CS-E29, CS-30, CS-33, CS-39, CS-43, CS-47, and CS-65, including two duplicate samples (DUP-E1 and DUP-E2) for quality assurance quality control (QA/QC) purposes. The letter “E” in the sample nomenclature represents a sample collected from only the ETPH-impacted area of the excavation; the remaining samples without the “E” designation indicate that the sample was collected for a dual purpose to address both ETPH and PCBs. Samples were submitted to Phoenix Environmental Laboratories, Inc. (Phoenix) located in Manchester, CT and analyzed for ETPH via the CT ETPH 8015D method. The open excavation was protected with erosion controls and temporary fencing connected to the existing fencing along the northern boundary of the excavation. ETPH was detected in 5 of the 37 ETPH confirmation soil samples at concentrations ranging from 73 to 180 milligram per kilogram (mg/Kg) which were below the 500 mg/Kg GA PMC and RES DEC. Consequently, the soil excavation successfully met the remedial goal, and no further excavation was needed to address EPTH impacts. 3.3.2 PCB Remediation Sampling Analytical Results Summary Based on the presence of PCBs greater than 1 mg/kg in one soil sample collected from AOPEC #4, a Performance-Based PCB cleanup in accordance with Title 40 CFR Section 761.61(b) was performed westonandsampson.com 3-2
  2. Page 14 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 14 of 578 ANNUAL REPORT Eversource Energy and confirmatory sampling fulfilled the requirements of 40 CFR 761.61 Subpart O. As mentioned previously, the PCB-impacted soil area overlapped a portion of the ETPH-impacted area. This area of the excavation measured 32 ft. long by 22 ft. wide and 2 ft. deep. Following Subpart O requirements, Weston & Sampson collected a total of 56 confirmation soil samples, designated CS-30 to CS-82 including three duplicate samples (DUP-1, DUP-2 and DUP-3) for QA/QC purposes. Sidewall confirmation grab samples were collected at a depth of 1.0 ft bgs and bottom confirmation grab samples were collected at a depth of 2.0 ft bgs. All three blind duplicate samples were consistent with their parent samples (i.e., PCBs < detection limits). Figure 2B depicts the PCB/ETPH remediation area and associated confirmation sample locations. Samples were submitted to and analyzed by Phoenix for PCBs via EPA 8082A with Soxhlet extraction method 3540C and reported using DEEP RCP methods. PCBs were not detected in any of the soil samples above detection limits. Based on these results, no further excavation is needed to address PCB impacts. 3.3.3 Waste Disposal Documentation and Restoration Prior to the remedial excavation, SES prepared and implemented a sampling plan which included test pit excavations within the proposed ETPH and PCB remediation areas for pre-disposal characterization (Appendix B). Two composite soil samples were collected from four test pits in the ETPH area, and one composite sample was collected from two test pits in the PCB area. The analytical results were then used to determine suitable disposal facilities for the soil. Conducting pre-disposal characterization ahead of the remedial work also allowed for the live loading of excavated soil, resulting in a cleaner and more efficient process. After receipt of the pre-disposal analytical data, SES prepared waste profiles for Clean Earth of Connecticut (Plainville, CT) for the disposal of non-PCB impacted soils and US Ecology’s Wayne Landfill (Belleville, MI) for PCB-impacted soils. Twenty-three truckloads of non-PCB impacted soil (564.68 tons) was transported by SES to Clean Earth for disposal. PCB-impacted soils were live loaded into three roll offs (46.16 tons) with one trucked directly to Wayne Landfill. The other two roll offs were transported to Red Technologies in Portland, CT where they were subsequently off-loaded into a railcar and then transported to the Wayne Landfill. Disposal documentation, including waste disposal characterization laboratory analytical data and waste manifests, are provided in Appendix B. Restoration of the Site was performed by SES under the supervision of Eversource and included backfilling and compacting the excavation with certified clean gravel obtained from Wapping Sand & Gravel in Broad Brook, CT and processed stone provided by Herb Holden Trucking from a virgin quarry source in Westfield, MA (Appendix A). The excavation footprint will be repaved in the Spring of 2021. 3.4 Continued Groundwater Monitoring As proposed in the 2019 Annual Report, continued groundwater monitoring was performed in 2020. Groundwater samples were collected for laboratory analysis from 16 monitoring wells during the year. westonandsampson.com 3-3
  3. Page 15 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 15 of 578 ANNUAL REPORT Eversource Energy Monitoring well locations are shown on Figure 3. Groundwater Sampling Data Sheets are included in Appendix C and Laboratory Analytical Reports are included in Appendix D. Modifications to the sampling network were made in 2020 based on a review of 2019 data and included the discontinuation of monitoring of certain wells and the addition of select parameters. These modifications were made on an AOPEC basis to either 1) work toward achieving compliance or 2) continue to track contaminant trends for AOPECs pending remediation. Below is a summary table of the wells included in the current monitoring network, sampling frequency, and COC parameters: 2020 Groundwater Sampling Plan Well ID March June September MW-CCA3 E, P E, P E, P MW-CCA4 E, P MW-CCA5 E MW-TRW1 E MW-4R E, V, P E, V, P, EFP E, V, P MW-2A E MW-11A E MW-6 E E, EFP E MW-10 E MW-T3 E MW-T6 E MW-101 E, V E, V E, V MW-102 E, V E, V E, V MW-202 E MW-203 E MW-310 E V-VOCs, E-ETPH, P-PAHs, EFP–ETPH Fingerprint December E,P E, V, P E E, V E, V Groundwater analytical testing results are discussed by AOPEC below in Section 4.1. 3.5 Groundwater Flow Analysis To determine groundwater flow directions, depth to water measurements were collected in March, June, September, and December 2020. Abnormally dry weather and drought conditions were present during the 3rd and 4th quarters of 2020. Table 3 summarizes groundwater depth to water and calculated groundwater table elevations. Figures 4 and 5 illustrate groundwater flow contour lines and directions based upon the gauging information collected during the March and December 2020 gauging events. In general, groundwater flows in a south-southwesterly direction across the Site, which is consistent with prior flow determinations. 3.6 Product Measurement and Recovery Information No measurable oil (light nonaqueous phase liquid [LNAPL]), was detected with an oil-water interface probe in any of the monitoring wells located at the Site. LNAPL has not been detected in well TRW-1 since 2005, and well MW-T3 since 2009. westonandsampson.com 3-4
  4. Page 16 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 16 of 578 ANNUAL REPORT Eversource Energy 4.0 AOPEC UPDATE AND PROPOSED ACTIVITIES No further soil investigations are planned in 2021. Groundwater sampling is expected to continue at AOPECs #2A, #2B, #3B, #3C, #3D, #3F, #3G and #5 for DEEP Remediation Standard Regulations (RSR) compliance demonstration or contaminant trend purposes. Post-remediation groundwater monitoring is planned for AOPEC #4. Soil and groundwater investigations are considered complete and no further action is required at AOPECs #1A, #7A, #7B, #7C, #8, and #9. A Final Site Investigation Report and Completion of Investigation Transmittal Form for these AOPECs were previously submitted to the DEEP in February 2015. Soil and groundwater investigations at AOPECs #3E, #6A, and #10 are also considered complete and no further action is required. A Final Site Investigation Report and Completion of Investigation Transmittal Form were prepared for these AOPECs and submitted to the DEEP in December 2018. Based upon review of recent and historical results, soil and groundwater investigations at AOPEC #3A is considered complete and no further action is required. A Final Site Investigation Report and Completion of Investigation Transmittal Form will be prepared for this AOPEC and submitted to the DEEP in 2021. The following presents the status and proposed 2021 activities for each of the following AOPECs. 4.1 Status Summary and Proposed Actions 4.1.1 AOPEC #1B and #1C: Septic Leach Field AOPEC #1B: This AOPEC is located north of the former vehicle maintenance garage and serves the same building. The Phase II ESA investigation included the analysis of two soil samples (CCA5 and TP2) from this area. No detections of COCs were found in these samples. However, Weston & Sampson determined that additional testing was needed, as this septic system continued to be used after the previous testing was completed in 2001. Two borings (B313 and B316) were completed in this AOPEC and converted into groundwater monitoring wells (MW-200 and MW-201) in 2017 (Figure 7). Boring B313 (MW-200) is located on the upgradient side of the septic leach field and boring B316 (MW-201) is located on the downgradient side. A calibrated PID was used to screen soil for the presence of VOCs in each of the borings, and no VOC readings above background were noted. One soil sample was collected from each boring at 8 to 10 ft bgs, which matched the previous testing depth completed by CCA in 2001. This depth is believed to be just below the septic system elevation. The samples were tested for PCBs, ETPH and VOCs. The analytical results revealed no detections of COCs above laboratory detection limits. Based on these findings, no further soil investigations are planned for this AOPEC at this time. The new monitoring wells (MW-200 and MW-201) and existing well (MW-CCA5) were sampled in May 2017 to document water quality in and downgradient of the septic leach field. Groundwater samples were analyzed for PCBs, ETPH, and VOCs. No COCs were detected above laboratory reporting limits. Based on the initial data, groundwater quality in this area appeared to have not been impacted by releases from the septic system. However, to meet RSR compliance, these monitoring wells were westonandsampson.com 4-1
  5. Page 17 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 17 of 578 ANNUAL REPORT Eversource Energy sampled during each quarter of 2018 and analyzed for the same COCs. PCBs and VOCs were not detected throughout the four quarters. ETPH was detected in each of the wells for two or more quarters at concentrations ranging from 0.084 mg/L to 0.21 mg/L. None of the detected ETPH concentrations exceed the RSR Groundwater Protection Criteria (GWPC) or Surface Water Protection Criteria (SWPC). Based on the 2017 and 2018 results, sampling for PCBs and VOCs was discontinued at these three wells. One additional round of quarterly groundwater samples from wells MW-200, MW-201 and MW-CCA5 was collected on March 2019 to monitor for ETPH. Results revealed that ETPH was not detected above laboratory detection limits in any of the groundwater samples (see Table 2A). Based on these results, combined with four previous rounds of groundwater sampling from these wells, groundwater compliance has been achieved and further groundwater monitoring is not deemed necessary at this time. However, formal closure of this AOPEC cannot be achieved until the system is no longer in use. Once the system is no longer in use and either removed/abandoned in place, final assessment can be conducted to assess for closure. AOPEC #1C: This AOPEC is located south of the former Substation Maintenance (SSM) building and the Construction, Testing, and Maintenance (CT&M) building, and serves both buildings. The Phase II ESA investigation analyzed two soil samples (CCA2 and TP-1) from this AOPEC. No detections of COCs were found in these samples. Additional testing was needed because the septic system continued to be used after the previous testing was completed in 2001. Two borings (B331 and B332) were advanced on the upgradient and downgradient sides of this AOPEC in 2017. A calibrated PID was used to screen soil for the presence of VOCs, and no readings above background were noted. One soil sample was collected from each boring at 8 to 10 ft bgs, which matched the previous testing depth completed in 2001 and is believed to be just below the septic system elevation. Soil samples were tested for PCBs, ETPH and VOCs. The analytical results revealed no detections of COCs above laboratory detection limits. Based on these findings, no further soil investigations are planned for this AOPEC at this time. During 2017, existing monitoring wells MW-CCA2, MW-15, and MW-16 were sampled in May and July to document water quality within and downgradient of this septic leach field. Groundwater samples were analyzed for PCBs, ETPH, and VOCs. VOCs and PCBs were not detected above laboratory reporting limits in any of the wells during May or July. ETPH was detected in each of the wells during the May event at a concentration below applicable RSR criteria. ETPH was not detected during the July sampling event. To meet RSR compliance requirements, these wells were sampled during each quarter of 2018 and analyzed for the same COCs. PCBs and VOCs were not detected throughout the four quarters. ETPH was detected in each of the wells for two or more quarters at concentrations ranging from 0.078 mg/L to 0.16 mg/L. None of the detected ETPH concentrations exceed the GWPC or SWPC. Based on the 2017 and 2018 results, sampling for PCBs and VOCs was discontinued at these wells. One additional round of quarterly groundwater samples from wells MW-15, MW-16 and MW-CCA2 was collected in March 2019 to monitor for ETPH. Results revealed that ETPH was not detected above laboratory detection limits in any of the groundwater samples (see Table 2B). westonandsampson.com 4-2
  6. Page 18 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 18 of 578 ANNUAL REPORT Eversource Energy Based on these results, combined with four previous rounds of groundwater sampling from these wells, detected concentrations of ETPH are below the GWPC. However, formal closure of this AOPEC cannot be achieved until the system is no longer in use. Once the system is no longer in use and either removed/abandoned in place, final assessment can be conducted to assess for closure. 4.1.2 AOPEC #2A and #2B: Hydraulic Lifts (existing and former) AOPEC #2A: This AOPEC includes existing hydraulic lifts located inside the former vehicle maintenance garage. The Phase II ESA investigation included soil samples obtained from borings B-6, B-7, and B-8. An ETPH detection of 1,500 mg/kg at 8 to 12 ft bgs from boring B-6 prompted further investigated in 2017 and 2018. In 2017, six interior borings were advanced proximal to boring B-6 (B301 through B305, and B6A), and five additional borings (B313, and B316 through B319) were advanced outside of the garage to define the nature and extent of ETPH impacts in this AOPEC. Multi-depth sampling was performed at B6A to vertically profile the ETPH impacts previously identified at boring B-6. One soil sample was analyzed from borings B301 through B305, generally targeting the 8 to 12-foot depth interval where ETPH had previously been identified in 2001. The results identified ETPH in four samples, but at concentrations below RSR criteria. Select soil samples were also tested for PCBs. No PCBs were detected in these samples. In 2018, additional borings were advanced at and east of boring B-301, in which ETPH was previously detected at 500 mg/kg (equivalent to the RSR Residential Direct Exposure Criteria [RES DEC]), to fully assess the nature and extent of impacts in this area. Borings were also advanced within a former chemical storage room that was not previously investigated prior to Eversource vacating the building. Multi-depth soil sampling was completed at borings B601, B606 and B607 (vehicle lift area) and at borings B602 through B605 (chemical storage area) to identify potential releases. The samples collected near the former in-ground lifts were submitted for ETPH and PCB analysis. PCBs were not detected in any of the samples. ETPH was detected in samples from boring B601 and B606. The detected ETPH concentration in sample B606A from 8 to 10 ft bgs was 520 mg/kg, which exceeds the RES DEC and GA Pollutant Mobility Criteria (GA PMC). ETPH was detected at a concentration below RSR criteria from a deeper sample collected from boring B-606 at 10 to 12 ft bgs (B-606B). Samples collected from the four borings within the former chemical storage area were analyzed for PCBs, VOCs, SVOCs, ETPH and Total RCRA 8 metals. PCBs were not detected in any of these samples. VOCs, SVOCs, ETPH and some total metals were detected throughout the samples, but at concentrations that do not exceed applicable RSR criteria. Groundwater samples collected from monitoring wells MW-202 and MW-203 were analyzed for ETPH in May 2017 to document water quality cross gradient and downgradient of the hydraulic lifts, respectively. ETPH was not detected above laboratory reporting limits. ETPH was also not detected in upgradient wells MW-200 and MW-201. To meet RSR compliance, MW-202 (cross gradient) and MW-203 (downgradient), along with MWCCA5 (located upgradient of this AOPEC) were sampled during each quarter of 2018 and analyzed for ETPH. ETPH was detected in each sample at concentrations ranging from 0.091 mg/L to 0.30 mg/L. Only the ETPH concentration of 0.30 mg/L in well MW-202 from March 2018 exceeded the GWPC and SWPC. Groundwater samples were also analyzed for PCBs at MW-CCA5 all four quarters, at MW-202 westonandsampson.com 4-3
  7. Page 19 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 19 of 578 ANNUAL REPORT Eversource Energy during the second quarter (June), and at MW-203 during the first quarter (March). PCBs were not detected in any of the sampling events. To meet quarterly monitoring requirements, MW-203 was sampled in each quarter in 2019 and analyzed for PCBs. PCBs were not detected above laboratory detection limits in any of the samples. Based on the planned remediation in this AOPEC, monitoring wells MW-202, MW-203 and MW-CCA5 were sampled in March 2019 to track ETPH concentrations until remediation is performed. ETPH was not detected above laboratory detection limits in samples MW-202 and MW-CCA5, but was detected in sample MW-203 at a concentration of 0.22 mg/L. The detected ETPH concentration does not exceed the GWPC or SWPC. These wells were additionally sampled in March 2020 to continue tracking ETPH concentrations. ETPH was not detected in any of these three wells (see Table 2C). In 2021, Weston & Sampson proposes collecting one round of groundwater samples in March for ETPH at monitoring wells MW-CCA5, MW-202 and MW-203 to continue tracking ETPH concentration trends. AOPEC #2B: This AOPEC includes former hydraulic lifts located inside the Substation Maintenance (SSM) building. The Phase II ESA investigation included one sample from each of four borings (B-1, B2, B-3, and B-4). ETPH was detected at 1,900 mg/kg in boring B-3 from 8 to 12 ft bgs, warranting further investigation. In 2017, six interior borings (B306 through B310, and B310A) were advanced proximal to boring B-3. Multi-depth sampling was performed at boring B310A to vertically profile the ETPH impact previously identified in boring B-3. One soil sample was analyzed from borings B303 through B310, generally targeting the 8 to 12-foot depth interval where the ETPH impacts had been identified in 2001. All soil samples were tested for ETPH, with select soil samples also tested for PCBs. ETPH was detected in six soil samples collected from two-foot intervals between 6 and 12 ft bgs in borings B307, B308, B310, and B310A. ETPH concentrations at two locations (B310 at 8 to 10 ft, and B310A at 6 to 8 ft) exceeded RSR criteria. PCBs were not detected in any of the soil samples analyzed. A fingerprint analysis was performed on the 6 to 8-foot soil sample from boring B310A to determine the type of petroleum hydrocarbon present. The fingerprint indicated a transformer oil profile. AOPEC 3B, which abuts this AOPEC to the east, is associated with past transformer oil releases from USTs that are located adjacent to and upgradient of the SSM building. Existing monitoring wells MW-6 and MW-T3 were sampled in May 2017 to document groundwater quality in the vicinity of the former hydraulic lifts. An additional well, MW-310, was installed and sampled in September 2017. Groundwater samples were analyzed for ETPH. ETPH was not detected above laboratory reporting limits in MW-6. However, concentrations of ETPH detected in MW-T3 and MW-310 exceeded the SWPC. Groundwater monitoring was performed in 2018 to continue to track natural attenuation of ETPH in AOPEC #2B. MW-6, MW-310 and MW-T3 samples were analyzed for ETPH in the first quarter only. Monitoring well MW-6 was additionally analyzed for PCBs in the first quarter. PCBs were not detected in any of the samples analyzed. ETPH was detected in each of the samples, with concentrations in MW-310 and MW-T3 from March 2018 continuing to exceed RSR criteria. westonandsampson.com 4-4
  8. Page 20 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 20 of 578 ANNUAL REPORT Eversource Energy In 2019, additional soil sampling was performed in this AOPEC to further delineate ETPH impacts in an effort to help refine soil volume estimates in advance of anticipated remedial activities. Two exterior borings were advanced adjacent to this AOPEC west (B39A) and north (B310N) of existing boring B310, which exhibited elevated ETPH detections from the 8 to 10 ft bgs sampling interval. Two sampling intervals (8 to 10 and 10 to 12 ft bgs) were collected from each boring. ETPH was not detected above laboratory detection limits in either boring from the 8 to 10 ft bgs interval. ETPH was detected in each of the 10 - 12 ft bgs sampling intervals at concentrations of 16 mg/kg and 98 mg/kg. However, neither detection exceeds the RES DEC or GA PMC. Based on the planned remediation in this AOPEC, monitoring wells MW-6, MW-T3, and MW-310 were sampled in the March 2019 sampling quarter to track ETPH concentrations until remediation is performed. A blind duplicate sample (DUP-1) of MW-6 was also collected for quality assurance/quality control (QA/QC) purposes. ETPH was detected above laboratory detection limits in each of the samples. The detected ETPH concentrations in MW-6 (0.52 mg/L), DUP-1 (9.1 mg/L), MW-310 (0.35 mg/L), and MW-T3 (3.9 mg/L) exceed the GWPC and SWPC. These three wells were additionally sampled in March 2020 to continue tracking ETPH concentrations. Monitoring well MW-6 was also sampled in June, September, and December 2020 for ETPH. A blind duplicate sample (DUP-1) of MW6 was also collected for QA/QC purposes in December. ETPH was detected in the September sampling round at MW-6 (0.45 mg/L) and in both MW-310 (7.7 mg/L) and MW-T3 (3.4 mg/L) in March. Each of the detected ETPH concentrations exceed the GWPC and SWPC (see Table 2D). In 2021, Weston & Sampson proposes collecting one round of groundwater samples in March for ETPH at monitoring wells MW-6, MW-310, and MW-T3 to continue tracking ETPH concentration trends. 4.1.3 AOPEC #3A, #3B, #3D, #3F and 3G: Former USTs AOPEC #3A: This AOPEC comprises former underground storage tanks (USTs) A1 and A1R1, which were reported to have contained heating oil/diesel fuel. Soil testing within this AOPEC was not completed after the tanks were removed, and the Phase II ESA Report documents the collection and analysis of one groundwater sample. As such, additional testing was needed to properly close this AOPEC for LEP verification. In 2017, two soil borings (B314 and B315) were completed within the footprint of this AOPEC, with one soil sample collected and analyzed from each boring. The sampling interval targeted the bottom depth of the USTs, which was estimated at 11 to 13 ft bgs. Soil samples were tested for VOCs, SVOCs and ETPH. The analytical results revealed no detections of any compounds. No groundwater sampling was conducted in 2017 at MW-A1R1, as prior favorable groundwater data for the primary COCs (ETPH and VOCs) from four sampling events over a two-year period exists for this AOPEC. However, historical sampling did not include SVOCs as a COC. Therefore, four quarters of groundwater monitoring was conducted at well MW-A1R1 in 2018. Due to low water table conditions, a sample could not be retrieved during the September quarterly event. The March, June and December samples were submitted for SVOC analysis. No SVOCs were not detected for any of the sampling quarters. In 2019, monitoring well MW-A1R1 was sampled one additional quarter (March) for polycyclic westonandsampson.com 4-5
  9. Page 21 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 21 of 578 ANNUAL REPORT Eversource Energy aromatic hydrocarbons (PAHs). Results revealed that PAHs were not detected above laboratory detection limits (see Table 2E). Based on the 2018 through 2019 results, in combination with the lack of any contaminants detected in groundwater from this AOPEC in the Phase II ESA, additional monitoring is not considered necessary for AOPEC #3A. It is the opinion of the LEP that the investigation of this AOPEC is now complete and a Final Investigation Report and Completion of Investigation Transmittal Form is anticipated to be prepared and submitted to DEEP in 2021. AOPEC #3B: This AOPEC comprises former USTs J-10, J-11, J-12, and K-13. These USTs were located side by side in subsurface concrete block vaults east of the Substation Maintenance Building. Three of the USTs contained non-PCB transformer oil and one UST contained waste oil. Soil and groundwater impacts were identified at this AOPEC following removal of these tanks. Historical groundwater data at monitoring well MW-T3 and recovery well TRW-1 exhibited intermittent thin layers of LNAPL in 2003, 2004, 2005, 2007, and 2009. LNAPL was not detected at either well during 2006, 2008, and 2010 through 2020. Additional testing has been needed to demonstrate compliance with the RSRs for LEP verification. Six soil borings (B325 through B330) were completed within the footprint of this AOPEC in 2017. One soil sample was analyzed from each of the borings, with the sampling interval generally targeting the depth of the former USTs (estimated at 6 to 10 ft bgs). The soil samples were tested for PCBs, VOCs, ETPH, and total RCRA 8 metals. Analytical results revealed PCBs and VOCs were not detected above laboratory detection limits. Select total metals were detected at concentrations that do not exceed applicable RSR criteria. ETPH was detected in each of the soil samples at concentrations ranging from 26 mg/kg to 1,000 mg/kg. ETPH in samples B328 (9-11 ft bgs) and B330 (9-11 ft bgs) exceed RSR criteria (GA PMC and RES DEC). Similar to AOPEC #2B, additional soil sampling was performed for this AOPEC in 2019 to further delineate ETPH impacts and refine soil volume estimates in advance of anticipated future remedial activities. A groundwater sample was collected from monitoring well MW-6, downgradient of AOPEC #3B in May 2017 and analyzed for ETPH. ETPH was not detected above laboratory reporting limits. However, following a review of AOPEC #3B data prior to the 2018 sampling year, it was determined that a groundwater data gap existed for this AOPEC. Therefore, wells MW-T6 and, MW-TRW1 within AOPEC 3B, and MW-6 and MW-CCA4 located downgradient and upgradient of the AOPEC, respectively, were monitored to track attenuation of ETPH in this area. In 2018, one quarter of groundwater samples was collected from MW-T6, MW-6, and MW-TRW1 in March, and four quarters of samples were collected from MW-CCA4, upgradient of this AOPEC. Samples were analyzed for ETPH, PCBs, VOCs, SVOCs and/or RCRA 8 metals. PCBs, VOCs and SVOCs were not detected in any of the samples. Total chromium was detected in sample MW-6 at a concentration that does not exceed the GWPC. ETPH was detected in samples collected from each of the wells at concentrations ranging from 0.081 mg/L to 4.7 mg/L. ETPH detected in samples from wells MW-T3 (4.7 mg/L) and MW-TRW1 (1.2 mg/L) from the March event exceeded the GPWC and SWPC. In 2019, additional soil sampling was performed in this AOPEC to further delineate ETPH impacts in efforts to help refine soil volume estimates in advance of anticipated future remedial activities. Six borings (B325A through B330A) were advanced adjacent to existing borings to obtain additional vertical samples (Figure 3). Four additional borings (B328E, B328S, B328W, and B330W) were westonandsampson.com 4-6
  10. Page 22 of 578

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 141 Page 22 of 578 ANNUAL REPORT Eversource Energy advanced to obtain both horizontal and vertical samples to delineate ETPH impacts detected in original borings B328 and B330. Analytical results revealed elevated ETPH concentrations in samples collected from borings B326A, B329A, B330A, and B330W at the northern portion of this AOPEC. Two additional sampling intervals were collected from boring B326A to assess soils deeper than the 6 to 8 ft bgs sample from the original B326 boring. ETPH was detected at 18 mg/kg from 8 to10 ft bgs, and 700 mg/kg from 10 to 12 ft bgs. Two additional sampling intervals were collected from boring B329A to assess soils deeper than the 8 to 10 ft bgs sample from the original B329 boring. ETPH was detected at 11,000 mg/kg from 10 to 12 ft bgs, and 71 mg/kg from 12 to 14 ft bgs. Two additional sampling intervals were collected from boring B330A to assess soils above and below the 9 to 11 ft bgs sample from the original B330 boring. ETPH was detected at 100 mg/kg from 6 to 8 ft bgs, and 1,400 mg/kg from 12 to 14 ft bgs. Three sampling intervals were collected from boring B330W to delineate horizontal and vertical impacts west of original boring B330. ETPH was detected at 14,000 mg/kg from 8 to 10 ft bgs, 5,800 mg/kg from 10 to 12 ft bgs, and 25 mg/kg from 12 to 14 ft bgs. The detected ETPH concentrations in samples B326A (10-12 ft), B329A (10-12 ft), B330A (12-14 ft), B330W (8-10 ft), and B330W (10-12 ft) exceed the RES DES, I/C DEC and/or GA PMC. The remaining detected ETPH concentrations do not exceed criteria. Based on the planned remediation in this AOPEC, monitoring wells MW-6, MW-T3, MW-T6, and MWTRW-1 were sampled in March 2019 to track ETPH concentrations until remediation is performed. A blind duplicate sample (DUP-1) of MW-6 was also collected for QA/QC purposes. ETPH was detected above laboratory detection limits in each of the samples. The detected ETPH concentrations in DUP1 (9.1 mg/L), MW-T3 (3.9 mg/L), and MW-T3 (3.9 mg/L) exceed the GWPC and SWPC. These wells were additionally sampled in 2020 for ETPH in March. Monitoring well MW-6 was also sampled in June, September, and December 2020 for ETPH. A blind duplicate sample (DUP-1) of MW-6 was also collected for QA/QC purposes in December. ETPH was detected in the September sampling round from MW-6 (0.45 mg/L) and in MW-T3 (3.4 mg/L) at concentrations that exceed the GWPC and SWPC. ETPH wat not detected in monitoring well MW-T6 (see Table 2F). In 2021, Weston & Sampson proposes collecting one round of groundwater samples (March) for ETPH at monitoring wells MW-6, MW-T3, MW-T6, and MW-TRW-1 to continue tracking ETPH concentration trends pending remediation. AOPEC #3C: This AOPEC comprises former UST F-6, which is reported to have contained waste oil. The Phase II ESA Report documents two soil samples collected from one boring in this AOPEC, which were submitted for analysis of VOCs, PCBs, ETPH, and SPLP RCRA 8 metals. Based on the Phase II ESA Report, none of the selected compounds were detected above regulatory criteria. In 2019, additional soil and groundwater investigations were performed for this AOPEC to support the findings of the Phase II ESA. A soil sample from boring B-701 was collected from 8 to 10 ft bgs at the presumed bottom depth of the former UST. PCBs, VOCs, SVOCs, ETPH and TPH were not detected above laboratory detection limits. Three total and two leachable metals were detected at concentrations that do not exceed the RES DEC or GA PMC. Based on these soil results, further soil assessment is not needed. westonandsampson.com 4-7

Text of RSR-032 Attachment 140.pdf

Extracted from the file · 26 pages · 45,518 characters

Text of RSR-032 Attachment 139.pdf

Extracted from the file · 29 pages · 58,671 characters

Text of RSR-032 Attachment 138.pdf

Extracted from the file · 24 pages · 44,766 characters

Text of RSR-032 Attachment 137.pdf

Extracted from the file · 54 pages · 85,922 characters

Text of RSR-032 Attachment 136.pdf

Extracted from the file · 618 pages · 1,036,591 characters

Text of RSR-032 Attachment 135.pdf

Extracted from the file · 52 pages · 107,952 characters

Text of RSR-032 Attachment 134.pdf

Extracted from the file · 57 pages · 119,843 characters

Text of RSR-032 Attachment 133.pdf

Extracted from the file · 82 pages · 196,725 characters

Text of RSR-032 Attachment 132.pdf

Extracted from the file · 137 pages · 251,594 characters

Text of RSR-032 Attachment 131.pdf

Extracted from the file · 7 pages · 1,043 characters

Text of RSR-032 Attachment 130.pdf

Extracted from the file · 847 pages · 1,478,588 characters

Text of RSR-032 Attachment 129.pdf

Extracted from the file · 124 pages · 255,121 characters

Text of RSR-032 Attachment 128.pdf

Extracted from the file · 104 pages · 208,223 characters

Text of RSR-032 Attachment 127.pdf

Extracted from the file · 125 pages · 243,340 characters

Text of RSR-032 Attachment 126.pdf

Extracted from the file · 128 pages · 264,919 characters

Text of RSR-032 Attachment 125.pdf

Extracted from the file · 824 pages · 1,180,085 characters

Text of RSR-032 Attachment 124.pdf

Extracted from the file · 28 pages · 47,835 characters

Text of RSR-032 Attachment 123.pdf

Extracted from the file · 29 pages · 4,370 characters

Text of RSR-032 Attachment 122.pdf

Extracted from the file · 29 pages · 4,370 characters

Text of RSR-032 Attachment 121.pdf

Extracted from the file · 50 pages · 7,541 characters

Text of RSR-032 Attachment 120.PDF

Extracted from the file · 2 pages · 3,192 characters

Text of RSR-032 Attachment 119_Part3.pdf

Extracted from the file · 105 pages · 238,387 characters

Text of RSR-032 Attachment 119_Part2.pdf

Extracted from the file · 169 pages · 372,755 characters

Text of RSR-032 Attachment 119_Part1.pdf

Extracted from the file · 51 pages · 61,331 characters

Text of RSR-032 Attachment 118_Part6.pdf

Extracted from the file · 54 pages · 47,246 characters

Text of RSR-032 Attachment 118_Part5.pdf

Extracted from the file · 254 pages · 39,246 characters

Text of RSR-032 Attachment 118_Part4.pdf

Extracted from the file · 378 pages · 97,273 characters

Text of RSR-032 Attachment 118_Part3.pdf

Extracted from the file · 218 pages · 519,182 characters

Text of RSR-032 Attachment 118_Part2.pdf

Extracted from the file · 334 pages · 879,939 characters

Text of RSR-032 Attachment 118_Part1.pdf

Extracted from the file · 164 pages · 353,286 characters

Text of RSR-032 Attachment 117.pdf

Extracted from the file · 55 pages · 49,861 characters

Text of RSR-032 Attachment 116.pdf

Extracted from the file · 2 pages · 5,651 characters

Text of RSR-032 Attachment 115.pdf

Extracted from the file · 135 pages · 191,165 characters

Text of RSR-032 Attachment 114.pdf

Extracted from the file · 123 pages · 185,862 characters

Text of RSR-032 Attachment 113.pdf

Extracted from the file · 4 pages · 596 characters

Text of RSR-032 Attachment 112.pdf

Extracted from the file · 2 pages · 298 characters

Text of RSR-032 Attachment 111.pdf

Extracted from the file · 42 pages · 123,247 characters

Text of RSR-032 Attachment 110.pdf

Extracted from the file · 38 pages · 8,159 characters

Text of RSR-032 Attachment 109.pdf

Extracted from the file · 1 page · 149 characters

Text of RSR-032 Attachment 108.pdf

Extracted from the file · 23 pages · 27,882 characters

Text of RSR-032 Attachment 107.pdf

Extracted from the file · 1 page · 243 characters

Text of RSR-032 Attachment 106.pdf

Extracted from the file · 1 page · 321 characters

Text of RSR-032 Attachment 105.pdf

Extracted from the file · 493 pages · 1,262,208 characters

Text of RSR-032 Attachment 104.pdf

Extracted from the file · 628 pages · 1,570,354 characters

Text of RSR-032 Attachment 103.pdf

Extracted from the file · 40 pages · 129,345 characters

Text of RSR-032 Attachment 102.pdf

Extracted from the file · 2 pages · 298 characters

Text of RSR-032 Attachment 101.pdf

Extracted from the file · 186 pages · 437,630 characters

Text of RSR-032 Attachment 100.pdf

Extracted from the file · 244 pages · 509,938 characters

Text of RSR-032 Attachment 99.pdf

Extracted from the file · 193 pages · 412,257 characters

Text of RSR-032 Attachment 98.pdf

Extracted from the file · 2,201 pages · 3,529,384 characters

Text of RSR-032 Attachment 97.pdf

Extracted from the file · 2 pages · 2,870 characters

Text of RSR-032 Attachment 96.pdf

Extracted from the file · 2 pages · 296 characters

Text of RSR-032 Attachment 95.pdf

Extracted from the file · 27 pages · 8,963 characters

Text of RSR-032 Attachment 94.pdf

Extracted from the file · 3 pages · 5,367 characters

Text of RSR-032 Attachment 93.pdf

Extracted from the file · 3 pages · 5,315 characters

Text of RSR-032 Attachment 92.pdf

Extracted from the file · 3 pages · 5,225 characters

Text of RSR-032 Attachment 91.pdf

Extracted from the file · 2 pages · 2,709 characters

Text of RSR-032 Attachment 90.pdf

Extracted from the file · 2 pages · 2,630 characters

Text of RSR-032 Attachment 89.pdf

Extracted from the file · 2 pages · 2,615 characters

Text of RSR-032 Attachment 88.pdf

Extracted from the file · 2 pages · 2,771 characters

Text of RSR-032 Attachment 87.pdf

Extracted from the file · 2 pages · 2,948 characters

Text of RSR-032 Attachment 86.pdf

Extracted from the file · 2 pages · 2,772 characters

Text of RSR-032 Attachment 85.pdf

Extracted from the file · 2 pages · 2,764 characters

Text of RSR-032 Attachment 84.pdf

Extracted from the file · 2 pages · 2,999 characters

Text of RSR-032 Attachment 83.pdf

Extracted from the file · 2 pages · 2,995 characters

Text of RSR-032 Attachment 82.pdf

Extracted from the file · 2 pages · 2,968 characters

Text of RSR-032 Attachment 81.pdf

Extracted from the file · 2 pages · 2,973 characters

Text of RSR-032 Attachment 80.pdf

Extracted from the file · 2 pages · 296 characters

Text of RSR-032 Attachment 79.pdf

Extracted from the file · 2 pages · 2,694 characters

Text of RSR-032 Attachment 78.pdf

Extracted from the file · 3 pages · 3,876 characters

Text of RSR-032 Attachment 77.pdf

Extracted from the file · 3 pages · 3,646 characters

Text of RSR-032 Attachment 76.pdf

Extracted from the file · 3 pages · 3,805 characters

Text of RSR-032 Attachment 75.pdf

Extracted from the file · 9 pages · 13,840 characters

Text of RSR-032 Attachment 74.pdf

Extracted from the file · 3 pages · 3,990 characters

Text of RSR-032 Attachment 73.pdf

Extracted from the file · 3 pages · 4,170 characters

Text of RSR-032 Attachment 72.pdf

Extracted from the file · 3 pages · 3,957 characters

Text of RSR-032 Attachment 71.pdf

Extracted from the file · 3 pages · 3,642 characters

Text of RSR-032 Attachment 70.pdf

Extracted from the file · 2 pages · 2,078 characters

Text of RSR-032 Attachment 69.pdf

Extracted from the file · 3 pages · 4,357 characters

Text of RSR-032 Attachment 68.pdf

Extracted from the file · 3 pages · 3,165 characters

Text of RSR-032 Attachment 67.pdf

Extracted from the file · 4 pages · 3,715 characters

Text of RSR-032 Attachment 66.pdf

Extracted from the file · 3 pages · 3,168 characters

Text of RSR-032 Attachment 65.pdf

Extracted from the file · 3 pages · 444 characters

Text of RSR-032 Attachment 64.pdf

Extracted from the file · 2 pages · 2,099 characters

Text of RSR-032 Attachment 63.pdf

Extracted from the file · 2 pages · 2,062 characters

Text of RSR-032 Attachment 62.pdf

Extracted from the file · 7 pages · 5,200 characters

Text of RSR-032 Attachment 61.pdf

Extracted from the file · 5 pages · 10,643 characters

Text of RSR-032 Attachment 60.pdf

Extracted from the file · 2 pages · 296 characters

Text of RSR-032 Attachment 59.pdf

Extracted from the file · 2 pages · 4,147 characters

Text of RSR-032 Attachment 58.pdf

Extracted from the file · 1 page · 2,448 characters

Text of RSR-032 Attachment 57.pdf

Extracted from the file · 2 pages · 296 characters

Text of RSR-032 Attachment 56.pdf

Extracted from the file · 10 pages · 1,491 characters

Text of RSR-032 Attachment 55_Part10.pdf

Extracted from the file · 286 pages · 344,076 characters

Text of RSR-032 Attachment 55_Part9.pdf

Extracted from the file · 500 pages · 957,292 characters

Text of RSR-032 Attachment 55_Part8.pdf

Extracted from the file · 500 pages · 874,750 characters

Text of RSR-032 Attachment 55_Part7.pdf

Extracted from the file · 500 pages · 470,022 characters

Text of RSR-032 Attachment 55_Part6.pdf

Extracted from the file · 500 pages · 494,317 characters

Text of RSR-032 Attachment 55_Part5.pdf

Extracted from the file · 500 pages · 461,760 characters

Text of RSR-032 Attachment 55_Part4.pdf

Extracted from the file · 500 pages · 492,694 characters

Text of RSR-032 Attachment 55_Part3.pdf

Extracted from the file · 500 pages · 580,603 characters

Text of RSR-032 Attachment 55_Part2.pdf

Extracted from the file · 500 pages · 483,371 characters

Text of RSR-032 Attachment 55_Part1.pdf

Extracted from the file · 500 pages · 881,595 characters

Text of RSR-032 Attachment 54.pdf

Extracted from the file · 121 pages · 447,477 characters

Text of RSR-032 Attachment 53.pdf

Extracted from the file · 204 pages · 625,248 characters

Text of RSR-032 Attachment 52.pdf

Extracted from the file · 130 pages · 298,641 characters

Text of RSR-032 Attachment 51.pdf

Extracted from the file · 57 pages · 123,610 characters

Text of RSR-032 Attachment 50.pdf

Extracted from the file · 6 pages · 8,050 characters

Text of RSR-032 Attachment 49.pdf

Extracted from the file · 83 pages · 194,182 characters

Text of RSR-032 Attachment 48.pdf

Extracted from the file · 3 pages · 8,556 characters

Text of RSR-032 Attachment 47.pdf

Extracted from the file · 10 pages · 14,266 characters

Text of RSR-032 Attachment 46.pdf

Extracted from the file · 7 pages · 10,783 characters

Text of RSR-032 Attachment 45.pdf

Extracted from the file · 373 pages · 490,688 characters

Text of RSR-032 Attachment 44.pdf

Extracted from the file · 38 pages · 6,799 characters

Text of RSR-032 Attachment 43.pdf

Extracted from the file · 49 pages · 83,514 characters

Text of RSR-032 Attachment 42.pdf

Extracted from the file · 25 pages, 14 without text · 13,836 characters

Text of RSR-032 Attachment 41.pdf

Extracted from the file · 3 pages · 5,506 characters

Text of RSR-032 Attachment 40.pdf

Extracted from the file · 1 page · 1,448 characters

Text of RSR-032 Attachment 39.pdf

Extracted from the file · 14 pages · 17,145 characters

Text of RSR-032 Attachment 38.pdf

Extracted from the file · 12 pages · 14,555 characters

Text of RSR-032 Attachment 37.pdf

Extracted from the file · 12 pages · 14,398 characters

Text of RSR-032 Attachment 36.pdf

Extracted from the file · 12 pages · 15,426 characters

Text of RSR-032 Attachment 35.pdf

Extracted from the file · 38 pages · 61,388 characters

Text of RSR-032 Attachment 34.pdf

Extracted from the file · 13 pages · 12,161 characters

Text of RSR-032 Attachment 33.pdf

Extracted from the file · 11 pages · 7,928 characters

Text of RSR-032 Attachment 32.pdf

Extracted from the file · 3 pages · 444 characters

Text of RSR-032 Attachment 31.pdf

Extracted from the file · 26 pages · 3,891 characters

Text of RSR-032 Attachment 30.pdf

Extracted from the file · 18 pages · 2,691 characters

Text of RSR-032 Attachment 29.pdf

Extracted from the file · 9 pages · 10,238 characters

Text of RSR-032 Attachment 28.pdf

Extracted from the file · 127 pages · 218,825 characters

Text of RSR-032 Attachment 27.pdf

Extracted from the file · 12 pages · 12,858 characters

Text of RSR-032 Attachment 26.pdf

Extracted from the file · 12 pages · 14,742 characters

Text of RSR-032 Attachment 25.pdf

Extracted from the file · 14 pages · 16,968 characters

Text of RSR-032 Attachment 24.pdf

Extracted from the file · 13 pages · 16,061 characters

Text of RSR-032 Attachment 23.pdf

Extracted from the file · 19 pages · 8,357 characters

Text of RSR-032 Attachment 22.pdf

Extracted from the file · 1,282 pages · 3,304,505 characters

Text of RSR-032 Attachment 21.pdf

Extracted from the file · 1,005 pages · 2,609,640 characters

Text of RSR-032 Attachment 20_Part2.pdf

Extracted from the file · 109 pages · 16,568 characters

Text of RSR-032 Attachment 20_Part1.pdf

Extracted from the file · 150 pages · 190,904 characters

Text of RSR-032 Attachment 19.pdf

Extracted from the file · 23 pages · 39,103 characters

Text of RSR-032 Attachment 18.pdf

Extracted from the file · 8 pages · 12,671 characters

Text of RSR-032 Attachment 17_Part3.pdf

Extracted from the file · 282 pages · 740,441 characters

Text of RSR-032 Attachment 17_Part2.pdf

Extracted from the file · 500 pages · 1,293,274 characters

Text of RSR-032 Attachment 17_Part1.pdf

Extracted from the file · 500 pages · 1,270,790 characters

Text of RSR-032 Attachment 16.pdf

Extracted from the file · 46 pages · 130,280 characters

Text of RSR-032 Attachment 15.pdf

Extracted from the file · 17 pages · 25,967 characters

Text of RSR-032 Attachment 14.pdf

Extracted from the file · 10 pages · 15,944 characters

Text of RSR-032 Attachment 13.pdf

Extracted from the file · 17 pages · 29,849 characters

Text of RSR-032 Attachment 12.pdf

Extracted from the file · 12 pages · 20,731 characters

Text of RSR-032 Attachment 11.pdf

Extracted from the file · 15 pages · 23,899 characters

Text of RSR-032 Attachment 10.pdf

Extracted from the file · 145 pages · 332,684 characters

Text of RSR-032 Attachment 9.pdf

Extracted from the file · 897 pages · 1,943,866 characters

Text of RSR-032 Attachment 8.pdf

Extracted from the file · 203 pages · 512,054 characters

Text of RSR-032 Attachment 7.pdf

Extracted from the file · 12 pages · 13,977 characters

Text of RSR-032 Attachment 6.pdf

Extracted from the file · 335 pages · 685,056 characters

Text of RSR-032 Attachment 5.pdf

Extracted from the file · 65 pages · 194,221 characters

Text of RSR-032 Attachment 4.pdf

Extracted from the file · 570 pages · 1,357,502 characters

Text of RSR-032 Attachment 3.pdf

Extracted from the file · 8 pages · 15,762 characters

Text of RSR-032 Attachment 2.pdf

Extracted from the file · 26 pages · 3,865 characters

Text of RSR-032 Attachment 1.pdf

Extracted from the file · 18 pages · 2,673 characters

As listed on the current system

Question(s) Answered 32 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/30/2026

This filing on the current system (opens in a new tab)