Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 32

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy210 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files210

Search terms highlighted
Eversource rate increase is on 9 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of RSR-032 Attachment 176_Part2.pdf

Extracted from the file · 754 pages · 1,598,897 characters

Text of RSR-032 Attachment 176_Part1.pdf

Extracted from the file · 110 pages · 439,601 characters

Text of RSR-032 Attachment 175_Part7.pdf

Extracted from the file · 275 pages · 622,526 characters

Text of RSR-032 Attachment 175_Part6.pdf

Extracted from the file · 350 pages · 828,421 characters

Text of RSR-032 Attachment 175_Part5.pdf

Extracted from the file · 350 pages · 841,526 characters

Text of RSR-032 Attachment 175_Part4.pdf

Extracted from the file · 350 pages · 529,828 characters

Text of RSR-032 Attachment 175_Part3.pdf

Extracted from the file · 350 pages · 417,827 characters

Text of RSR-032 Attachment 175_Part2.pdf

Extracted from the file · 350 pages · 717,402 characters

Text of RSR-032 Attachment 175_Part1.pdf

Extracted from the file · 350 pages · 426,888 characters

Text of RSR-032 Attachment 174.pdf

Extracted from the file · 2 pages · 3,788 characters

Text of RSR-032 Attachment 173.pdf

Extracted from the file · 9 pages · 19,276 characters

Text of RSR-032 Attachment 172.pdf

Extracted from the file · 2 pages · 5,216 characters

Text of RSR-032 Attachment 171.pdf

Extracted from the file · 2 pages · 7,025 characters

Text of RSR-032 Attachment 170.pdf

Extracted from the file · 4 pages · 596 characters

Text of RSR-032 Attachment 169.pdf

Extracted from the file · 14 pages · 2,105 characters

Text of RSR-032 Attachment 168.pdf

Extracted from the file · 178 pages · 303,260 characters

Text of RSR-032 Attachment 167_Part2.pdf

Extracted from the file · 844 pages · 1,367,165 characters

Text of RSR-032 Attachment 167_Part1.pdf

Extracted from the file · 284 pages · 480,797 characters

Text of RSR-032 Attachment 166.pdf

Extracted from the file · 4 pages · 5,984 characters

Text of RSR-032 Attachment 165_Part 4.pdf

Extracted from the file · 84 pages · 130,960 characters

Text of RSR-032 Attachment 165_Part 3.pdf

Extracted from the file · 482 pages · 674,897 characters

Text of RSR-032 Attachment 165_Part 2.pdf

Extracted from the file · 509 pages · 549,394 characters

Text of RSR-032 Attachment 165_Part 1.pdf

Extracted from the file · 500 pages · 578,799 characters

Text of RSR-032 Attachment 164.pdf

Extracted from the file · 42 pages, 16 without text · 66,266 characters

Text of RSR-032 Attachment 163.pdf

Extracted from the file · 575 pages · 624,136 characters

Text of RSR-032 Attachment 162.pdf

Extracted from the file · 17 pages · 19,879 characters

Text of RSR-032 Attachment 161 _Part2.pdf

Extracted from the file · 609 pages · 625,572 characters

Text of RSR-032 Attachment 161 _Part1.pdf

Extracted from the file · 131 pages · 171,359 characters

Text of RSR-032 Attachment 160.pdf

Extracted from the file · 56 pages · 84,793 characters

Text of RSR-032 Attachment 159.pdf

Extracted from the file · 97 pages · 159,126 characters

Text of RSR-032 Attachment 158.pdf

Extracted from the file · 54 pages · 96,528 characters

Text of RSR-032 Attachment 157.pdf

Extracted from the file · 261 pages · 326,004 characters

Text of RSR-032 Attachment 156.pdf

Extracted from the file · 74 pages · 99,158 characters

Text of RSR-032 Attachment 155.pdf

Extracted from the file · 40 pages · 40,141 characters

Text of RSR-032 Attachment 154.pdf

Extracted from the file · 37 pages · 59,275 characters

Text of RSR-032 Attachment 153.pdf

Extracted from the file · 61 pages · 86,468 characters

Text of RSR-032 Attachment 152.pdf

Extracted from the file · 126 pages · 258,689 characters

Text of RSR-032 Attachment 151.pdf

Extracted from the file · 340 pages · 405,994 characters

Text of RSR-032 Attachment 150.pdf

Extracted from the file · 33 pages · 27,344 characters

Text of RSR-032 Attachment 149.pdf

Extracted from the file · 47 pages · 51,678 characters

Text of RSR-032 Attachment 148.pdf

Extracted from the file · 52 pages · 65,933 characters

Text of RSR-032 Attachment 147.pdf

Extracted from the file · 136 pages · 187,807 characters

Text of RSR-032 Attachment 146.pdf

Extracted from the file · 211 pages · 257,714 characters

Text of RSR-032 Attachment 145.pdf

Extracted from the file · 58 pages · 84,698 characters

Text of RSR-032 Attachment 144.pdf

Extracted from the file · 31 pages · 57,751 characters

Text of RSR-032 Attachment 143.pdf

Extracted from the file · 30 pages · 51,258 characters

Text of RSR-032 Attachment 142.pdf

Extracted from the file · 33 pages · 29,732 characters

Text of RSR-032 Attachment 141.pdf

Extracted from the file · 578 pages · 899,265 characters

Text of RSR-032 Attachment 140.pdf

Extracted from the file · 26 pages · 45,518 characters

Text of RSR-032 Attachment 139.pdf

Extracted from the file · 29 pages · 58,671 characters

Text of RSR-032 Attachment 138.pdf

Extracted from the file · 24 pages · 44,766 characters

Text of RSR-032 Attachment 137.pdf

Extracted from the file · 54 pages · 85,922 characters

Text of RSR-032 Attachment 136.pdf

Extracted from the file · 618 pages · 1,036,591 characters

Text of RSR-032 Attachment 135.pdf

Extracted from the file · 52 pages · 107,952 characters

Text of RSR-032 Attachment 134.pdf

Extracted from the file · 57 pages · 119,843 characters

Text of RSR-032 Attachment 133.pdf

Extracted from the file · 82 pages · 196,725 characters

Text of RSR-032 Attachment 132.pdf

Extracted from the file · 137 pages · 251,594 characters

Text of RSR-032 Attachment 131.pdf

Extracted from the file · 7 pages · 1,043 characters

Text of RSR-032 Attachment 130.pdf

Extracted from the file · 847 pages · 1,478,588 characters

Text of RSR-032 Attachment 129.pdf

Extracted from the file · 124 pages · 255,121 characters

Text of RSR-032 Attachment 128.pdf

Extracted from the file · 104 pages · 208,223 characters

Text of RSR-032 Attachment 127.pdf

Extracted from the file · 125 pages · 243,340 characters

Text of RSR-032 Attachment 126.pdf

Extracted from the file · 128 pages · 264,919 characters

Text of RSR-032 Attachment 125.pdf

Extracted from the file · 824 pages · 1,180,085 characters

Text of RSR-032 Attachment 124.pdf

Extracted from the file · 28 pages · 47,835 characters

Text of RSR-032 Attachment 123.pdf

Extracted from the file · 29 pages · 4,370 characters

Text of RSR-032 Attachment 122.pdf

Extracted from the file · 29 pages · 4,370 characters

Text of RSR-032 Attachment 121.pdf

Extracted from the file · 50 pages · 7,541 characters

Text of RSR-032 Attachment 120.PDF

Extracted from the file · 2 pages · 3,192 characters

Text of RSR-032 Attachment 119_Part3.pdf

Extracted from the file · 105 pages · 238,387 characters

Text of RSR-032 Attachment 119_Part2.pdf

Extracted from the file · 169 pages · 372,755 characters

Text of RSR-032 Attachment 119_Part1.pdf

Extracted from the file · 51 pages · 61,331 characters

Text of RSR-032 Attachment 118_Part6.pdf

Extracted from the file · 54 pages · 47,246 characters

Text of RSR-032 Attachment 118_Part5.pdf

Extracted from the file · 254 pages · 39,246 characters

Text of RSR-032 Attachment 118_Part4.pdf

Extracted from the file · 378 pages · 97,273 characters

Text of RSR-032 Attachment 118_Part3.pdf

Extracted from the file · 218 pages · 519,182 characters

Text of RSR-032 Attachment 118_Part2.pdf

Extracted from the file · 334 pages · 879,939 characters

Text of RSR-032 Attachment 118_Part1.pdf

Extracted from the file · 164 pages · 353,286 characters

Text of RSR-032 Attachment 117.pdf

Extracted from the file · 55 pages · 49,861 characters

Text of RSR-032 Attachment 116.pdf

Extracted from the file · 2 pages · 5,651 characters

Text of RSR-032 Attachment 115.pdf

Extracted from the file · 135 pages · 191,165 characters

Text of RSR-032 Attachment 114.pdf

Extracted from the file · 123 pages · 185,862 characters

Text of RSR-032 Attachment 113.pdf

Extracted from the file · 4 pages · 596 characters

Text of RSR-032 Attachment 112.pdf

Extracted from the file · 2 pages · 298 characters

Text of RSR-032 Attachment 111.pdf

Extracted from the file · 42 pages · 123,247 characters

Text of RSR-032 Attachment 110.pdf

Extracted from the file · 38 pages · 8,159 characters

Text of RSR-032 Attachment 109.pdf

Extracted from the file · 1 page · 149 characters

Text of RSR-032 Attachment 108.pdf

Extracted from the file · 23 pages · 27,882 characters

Text of RSR-032 Attachment 107.pdf

Extracted from the file · 1 page · 243 characters

Text of RSR-032 Attachment 106.pdf

Extracted from the file · 1 page · 321 characters

Text of RSR-032 Attachment 105.pdf

Extracted from the file · 493 pages · 1,262,208 characters

Text of RSR-032 Attachment 104.pdf

Extracted from the file · 628 pages · 1,570,354 characters

Text of RSR-032 Attachment 103.pdf

Extracted from the file · 40 pages · 129,345 characters

Text of RSR-032 Attachment 102.pdf

Extracted from the file · 2 pages · 298 characters

Text of RSR-032 Attachment 101.pdf

Extracted from the file · 186 pages · 437,630 characters

Text of RSR-032 Attachment 100.pdf

Extracted from the file · 244 pages · 509,938 characters

Text of RSR-032 Attachment 99.pdf

Extracted from the file · 193 pages · 412,257 characters

Text of RSR-032 Attachment 98.pdf

Extracted from the file · 2,201 pages · 3,529,384 characters

Text of RSR-032 Attachment 97.pdf

Extracted from the file · 2 pages · 2,870 characters

Text of RSR-032 Attachment 96.pdf

Extracted from the file · 2 pages · 296 characters

Text of RSR-032 Attachment 95.pdf

Extracted from the file · 27 pages · 8,963 characters

Text of RSR-032 Attachment 94.pdf

Extracted from the file · 3 pages · 5,367 characters

Text of RSR-032 Attachment 93.pdf

Extracted from the file · 3 pages · 5,315 characters

Text of RSR-032 Attachment 92.pdf

Extracted from the file · 3 pages · 5,225 characters

Text of RSR-032 Attachment 91.pdf

Extracted from the file · 2 pages · 2,709 characters

Text of RSR-032 Attachment 90.pdf

Extracted from the file · 2 pages · 2,630 characters

Text of RSR-032 Attachment 89.pdf

Extracted from the file · 2 pages · 2,615 characters

Text of RSR-032 Attachment 88.pdf

Extracted from the file · 2 pages · 2,771 characters

Text of RSR-032 Attachment 87.pdf

Extracted from the file · 2 pages · 2,948 characters

Text of RSR-032 Attachment 86.pdf

Extracted from the file · 2 pages · 2,772 characters

Text of RSR-032 Attachment 85.pdf

Extracted from the file · 2 pages · 2,764 characters

Text of RSR-032 Attachment 84.pdf

Extracted from the file · 2 pages · 2,999 characters

Text of RSR-032 Attachment 83.pdf

Extracted from the file · 2 pages · 2,995 characters

Text of RSR-032 Attachment 82.pdf

Extracted from the file · 2 pages · 2,968 characters

Text of RSR-032 Attachment 81.pdf

Extracted from the file · 2 pages · 2,973 characters

Text of RSR-032 Attachment 80.pdf

Extracted from the file · 2 pages · 296 characters

Text of RSR-032 Attachment 79.pdf

Extracted from the file · 2 pages · 2,694 characters

Text of RSR-032 Attachment 78.pdf

Extracted from the file · 3 pages · 3,876 characters

Text of RSR-032 Attachment 77.pdf

Extracted from the file · 3 pages · 3,646 characters

Text of RSR-032 Attachment 76.pdf

Extracted from the file · 3 pages · 3,805 characters

Text of RSR-032 Attachment 75.pdf

Extracted from the file · 9 pages · 13,840 characters

Text of RSR-032 Attachment 74.pdf

Extracted from the file · 3 pages · 3,990 characters

Text of RSR-032 Attachment 73.pdf

Extracted from the file · 3 pages · 4,170 characters

Text of RSR-032 Attachment 72.pdf

Extracted from the file · 3 pages · 3,957 characters

Text of RSR-032 Attachment 71.pdf

Extracted from the file · 3 pages · 3,642 characters

Text of RSR-032 Attachment 70.pdf

Extracted from the file · 2 pages · 2,078 characters

Text of RSR-032 Attachment 69.pdf

Extracted from the file · 3 pages · 4,357 characters

Text of RSR-032 Attachment 68.pdf

Extracted from the file · 3 pages · 3,165 characters

Text of RSR-032 Attachment 67.pdf

Extracted from the file · 4 pages · 3,715 characters

Text of RSR-032 Attachment 66.pdf

Extracted from the file · 3 pages · 3,168 characters

Text of RSR-032 Attachment 65.pdf

Extracted from the file · 3 pages · 444 characters

Text of RSR-032 Attachment 64.pdf

Extracted from the file · 2 pages · 2,099 characters

Text of RSR-032 Attachment 63.pdf

Extracted from the file · 2 pages · 2,062 characters

Text of RSR-032 Attachment 62.pdf

Extracted from the file · 7 pages · 5,200 characters

Text of RSR-032 Attachment 61.pdf

Extracted from the file · 5 pages · 10,643 characters

Text of RSR-032 Attachment 60.pdf

Extracted from the file · 2 pages · 296 characters

Text of RSR-032 Attachment 59.pdf

Extracted from the file · 2 pages · 4,147 characters

Text of RSR-032 Attachment 58.pdf

Extracted from the file · 1 page · 2,448 characters

Text of RSR-032 Attachment 57.pdf

Extracted from the file · 2 pages · 296 characters

Text of RSR-032 Attachment 56.pdf

Extracted from the file · 10 pages · 1,491 characters

Text of RSR-032 Attachment 55_Part10.pdf

Extracted from the file · 286 pages · 344,076 characters

Text of RSR-032 Attachment 55_Part9.pdf

Extracted from the file · 500 pages · 957,292 characters

Text of RSR-032 Attachment 55_Part8.pdf

Extracted from the file · 500 pages · 874,750 characters

Text of RSR-032 Attachment 55_Part7.pdf

Extracted from the file · 500 pages · 470,022 characters

Text of RSR-032 Attachment 55_Part6.pdf

Extracted from the file · 500 pages · 494,317 characters

Text of RSR-032 Attachment 55_Part5.pdf

Extracted from the file · 500 pages · 461,760 characters

Text of RSR-032 Attachment 55_Part4.pdf

Extracted from the file · 500 pages · 492,694 characters

Text of RSR-032 Attachment 55_Part3.pdf

Extracted from the file · 500 pages · 580,603 characters

Text of RSR-032 Attachment 55_Part2.pdf

Extracted from the file · 500 pages · 483,371 characters

Text of RSR-032 Attachment 55_Part1.pdf

Extracted from the file · 500 pages · 881,595 characters

Text of RSR-032 Attachment 54.pdf

Extracted from the file · 121 pages · 447,477 characters

Text of RSR-032 Attachment 53.pdf

Extracted from the file · 204 pages · 625,248 characters

Text of RSR-032 Attachment 52.pdf

Extracted from the file · 130 pages · 298,641 characters

Text of RSR-032 Attachment 51.pdf

Extracted from the file · 57 pages · 123,610 characters

Text of RSR-032 Attachment 50.pdf

Extracted from the file · 6 pages · 8,050 characters

Text of RSR-032 Attachment 49.pdf

Extracted from the file · 83 pages · 194,182 characters

Text of RSR-032 Attachment 48.pdf

Extracted from the file · 3 pages · 8,556 characters

Text of RSR-032 Attachment 47.pdf

Extracted from the file · 10 pages · 14,266 characters

Text of RSR-032 Attachment 46.pdf

Extracted from the file · 7 pages · 10,783 characters

Text of RSR-032 Attachment 45.pdf

Extracted from the file · 373 pages · 490,688 characters

Text of RSR-032 Attachment 44.pdf

Extracted from the file · 38 pages · 6,799 characters

Text of RSR-032 Attachment 43.pdf

Extracted from the file · 49 pages · 83,514 characters

Text of RSR-032 Attachment 42.pdf

Extracted from the file · 25 pages, 14 without text · 13,836 characters

Text of RSR-032 Attachment 41.pdf

Extracted from the file · 3 pages · 5,506 characters

Text of RSR-032 Attachment 40.pdf

Extracted from the file · 1 page · 1,448 characters

Text of RSR-032 Attachment 39.pdf

Extracted from the file · 14 pages · 17,145 characters

Text of RSR-032 Attachment 38.pdf

Extracted from the file · 12 pages · 14,555 characters

Text of RSR-032 Attachment 37.pdf

Extracted from the file · 12 pages · 14,398 characters

Text of RSR-032 Attachment 36.pdf

Extracted from the file · 12 pages · 15,426 characters

Text of RSR-032 Attachment 35.pdf

Extracted from the file · 38 pages · 61,388 characters

Text of RSR-032 Attachment 34.pdf

Extracted from the file · 13 pages · 12,161 characters

Text of RSR-032 Attachment 33.pdf

Extracted from the file · 11 pages · 7,928 characters

Text of RSR-032 Attachment 32.pdf

Extracted from the file · 3 pages · 444 characters

Text of RSR-032 Attachment 31.pdf

Extracted from the file · 26 pages · 3,891 characters

Text of RSR-032 Attachment 30.pdf

Extracted from the file · 18 pages · 2,691 characters

Text of RSR-032 Attachment 29.pdf

Extracted from the file · 9 pages · 10,238 characters

Text of RSR-032 Attachment 28.pdf

Extracted from the file · 127 pages · 218,825 characters

Text of RSR-032 Attachment 27.pdf

Extracted from the file · 12 pages · 12,858 characters

Text of RSR-032 Attachment 26.pdf

Extracted from the file · 12 pages · 14,742 characters

Text of RSR-032 Attachment 25.pdf

Extracted from the file · 14 pages · 16,968 characters

Text of RSR-032 Attachment 24.pdf

Extracted from the file · 13 pages · 16,061 characters

Text of RSR-032 Attachment 23.pdf

Extracted from the file · 19 pages · 8,357 characters

Text of RSR-032 Attachment 22.pdf

Extracted from the file · 1,282 pages · 3,304,505 characters

Words on different pages
  1. Page 13 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 13 of 1005 Phase III ESA analytical samples were collected into laboratory provided and preserved sample containers, chilled on ice and maintained under chain-of-custody prior to delivery to the analytical testing laboratory, Phoenix Environmental Laboratories, Inc. (Phoenix) in Manchester, CT. Phoenix is a Connecticut Department of Health (CTDPH)-approved commercial environmental laboratory (PH-0618). Analytical samples were analyzed by reasonable confidence protocol (RCP) analytical methods. Samples were analyzed for site constituent of concern (COCs) by the following methods: volatile organic compounds (VOCs) via EPA Method 8260, SVOCs via EPA Method 8270, total CTDEEP RSR metals, leachable CTDEEP RSR metals and cyanide via synthetic precipitation leaching procedure (SPLP), extractable total petroleum hydrocarbons (ETPH) via CTDEEP ETPH Method and total cyanide via EPA 9012. Select soil samples were analyzed for leachable VOCs, ETPH and polycyclic aromatic hydrocarbons (PAHs) via EPA Method 1312. Surficial soil samples were also analyzed for polychlorinated biphenyls (PCBs) by EPA Method 8082 within and adjacent to Inner Substation. In addition, sediment samples were analyzed for total organic carbon. A sediment grain size sample was collected to assess grain size distribution at a representative sample location. A summary of detected analytical results are provided by media, soils, groundwater, sediment and surface water on Table 2 through Table 5 in Appendix B. Analytical laboratory data reports are provided in Appendix D. A summary of Phase III ESA work completed on-site at 13 Maple Street and at off-site areas of investigation are discussed below. 2.2 On-Site Investigations and Findings On-site investigations were completed between mid-August and November 2017. Phase III ESA investigation included: • Advancement of 26 soil borings o o o Thirteen soil borings (SB-01 through SB-13) Six soil borings for monitoring well installations (MW-2BR, MW-7D, MW8SR, MW-16S, MW-17S and MW-18D) Seven shallow soil borings (SB-20 through SB-24 and SB-26 and SB-27) • Excavation of seven test pits: TP-01 through TP-07 • Installation of ten monitoring wells • o Five water table monitoring wells (including three replacement wells designated “R”): MW-16S, MW-17S, MW-2SR, MW-8SR, and MW-10SR o Two deep overburden wells: MW-7D and MW-18D o Three bedrock wells (MW-2BR, MW-3BR, and MW-10BR) Excavation of seven test pits (TP-01 through TP-07) Phase III ESA analytical samples collected on-site included: • Thirty-six soil samples, including two blind duplicate samples • Eleven surficial soil samples (SS-100 through SS-108 and SB-25), including one blind duplicate within the top six inches of soil
  2. Page 14 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 14 of 1005 • Eight groundwater samples were collected from newly installed monitoring wells. Groundwater samples were not collected from MW-2SR and MW-10SR because coal tar blebs, staining and/or sheens were observed during the development of the wells. • Seven sediment samples (SED-01 through SED-06) including one blind duplicate sample within the Hockanum River • Five surface water samples (SW-1 through SW-4) including one blind duplicate from the Hockanum River A summary of On-site Phase III ESA findings are provided below. A preliminary site conceptual model table is provided as Table 6. 2.2.1 Subsurface Soils • Test pit excavations (TP-01 through TP-07) encountered the foundations of the former MGP. The foundations for the former Generator House (AOC-1), former Purifier House (AOC-2]), former Gas Holders #1, #2, and #3 (AOC-3, AOC-4 and AOC-5). Fill materials (bricks, roof tiles) were observed within soils within the former Purifier House foundation. Concentrations of ETPH and PAHs exceeded the Res DEC and/or the GB PMC. Tar-impacted soils were encountered within the bottom of the Gas Holder #1 and Gas Holder #2 foundations from approximately 5.75 to 15 feet below grade. Drill refusal occurred at 15 feet and brick was recovered in the tip which suggests the bottom of the holder foundation is present. Concentrations of ETPH, VOCs, and PAHs exceeded the Res DEC and/or GB PMC. Visually clean fill was encountered at TP-07 within Gas Holder #3. The concrete foundation was encountered at approximately 8 feet below grade. Based upon shallow subgrade holder foundation, it is likely that Gas Holder #3 was a distribution holder. ETPH and VOCs were not detected. PAHs, cyanide and metals were detected below RSR criteria. • Surface soil samples (SS-100 through SS-106) and soil borings encountered shallow fill, including coal, ash, slag, brick, and/or glass, near the southeast corner of the Inner Substation (AOC-9) and the outer substation (AOC 12) and on the overgrown portion of the site to the south of the Hockanum River (AOC-13). Concentrations of ETPH and PAHs in the shallow fill exceeded the Res DEC and GB PMC. • Surface soils within the Inner Substation at the former Coal House (AOC-6), former Transformer House (AOC-7) and Current Substation (AOC-8). Fill material (large pieces of coal) were observed in surficial soil SS-102 within the footprint of the former Coal Shed. Fill materials were observed within the top 5 feet of the ground surface in soil borings SB-10, SB-11 and MW-2BR (soil boring) on the southern portion of the Inner Substation near the existing brick 26-inch sanitary sewer line. Concentrations of ETPH, PAHs, metals (arsenic and lead) exceeded the Res DEC and/ or the GB PMC. • Shallow subsurface soils within SB-21 within the northern portion of the site (AOC-9) contained detections of PAHs that exceeded the Res DEC and/or GB PMC. SPLP PAH analysis did not detect PAHs which indicates that PAHs are not leachable.
  3. Page 15 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 15 of 1005 • Subsurface soil impacts (sheens with petroleum and/or coal tar-like odor) were observed in soils borings (MW-2BR, SB-10, and SB-11) and previous site investigation TB-33 [AOC-11] from approximately 5 feet to 21 feet below grade on the southern portion of the Inner Substation near the sewer main. Concentrations of ETPH, PAHs and/or metals (arsenic and lead) exceeded the Res DEC and/or GB PMC in SB-11 and MW-2BR. • Deep subsurface Phase III ESA and previous site investigation soil borings encountered coal tar/creosote-related impacts below 17 feet below grade outside Gas Holders (AOC-3 and AOC-4). The heaviest coal tar impacted soils were observed in soil borings SB-04 and SB-05 next to Gas Holders #1 and Gas Holder #2 (AOC-3 and AOC-4) where impacts were observed from approximately 19.5 to 39 feet below grade. Isolated deeper intervals of coal tar-impacted soil were encountered from approximately 44.5 feet to 50 feet below grade in SB-04 and at 71 to 74 feet below grade at SB-05. Coal tar-impacted soils were primarily observed in soils located near or below the apparent water table. Concentrations of ETPH, VOCs and PAHs were detected at concentrations exceeding the GB PMC in a sample collected from 20 to 21 feet below grade in SB-05. Coal tar impacts extended from the former Gas Holders #1 and #2 (AOC-3 and AOC-4) to the northwest corner of the site (AOC-14). Coal tar impacts were observed in soils located approximately 25 feet to 39 feet below grade SB-12 and SB-13 at depths below the apparent water table. 2.2.2 Bedrock Bedrock, Portland Arkose, was encountered during the drilling soil boring (SB-09A, MW07D, MW-02BR, MW-03BR, MW-10BR) during the Phase III ESA and in MW-6D, MW11D, and MW-12D during previous site investigations. Bedrock was encountered at 34 feet below grade in MW-2BR within the Inner Substation adjacent to the Hockanum River to 87.5 feet below grade in MW-3BR at the northwest corner of the site. The bedrock surface is sloped to the north as shown in Figure 5. No evidence of visual impacts, elevated PID readings or apparent odors were observed in cored bedrock. 2.2.3 Groundwater On-site groundwater impacts were assessed under AOC-15. A summary of RSR exceedances in groundwater are summarized by shallow (water table) and deep monitoring wells that are screened within the overburden aquifer and bedrock wells for the Phase III ESA sampling completed during 2017. Figures 6, 7, and 8 provide a groundwater contour maps and inferred flow direction for the shallow (water table), deep overburden aquifer and bedrock aquifer beneath the site based upon 2017 gauging data. Groundwater flow is northward in the shallow (water table) and deep overburden aquifer. Groundwater flow in the bedrock aquifer is to the north/northeast. Shallow (Water table) Monitoring Wells ETPH and total cyanide were not detected in MW-8SR, MW-16S and MW-17S within and adjacent to the Inner Substation at the western site boundary. VOCs were not detected in groundwater at MW-8SR and MW-16S. Tetrachloroethene, a chlorinated VOC, was detected in MW-17S at a concentration below RSR criteria.
  4. Page 16 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 16 of 1005 PAHs were not detected in MW-16S and MW-17S at the western site boundary and Inner Substation area. PAHs were detected in MW-8SR at concentrations above the SWPC adjacent to the sewer line within the Inner Substation area. Concentrations of metals were detected in each of the water table monitoring wells with the highest concentrations detected within MW-8SR. It is likely that the elevated detections of PAHs and metals in MW-8SR are attributable to high turbidity measured during the collection of the groundwater sample at MW-8SR. Deep Monitoring Wells VOCs were detected at levels below the SWPC. Concentrations of PAHs were detected in MW-7D and MW-18D. Acenaphthylene was detected above the SWPC in MW-18D at the northwest corner of the site. Concentrations of phenanthrene in MW-7D and MW-18D were detected below the SWPC criteria of 14 microgram/ Liter (ug/L). ETPH was detected in MW-18D above the SWPC at the northwest corner of the site. Metals were detected at concentrations below the SWPC in MW-7D and MW-14D. Bedrock Monitoring Wells VOCs were either not detected or were detected at levels below the SWPC. Concentrations of PAHs were detected in each bedrock monitoring well. Acenaphthylene was detected at 1.6 ug/L in MW-3BR which exceeded the SWPC. Concentrations of phenanthrene in MW-3BR and MW-10BR were detected below the SWPC criteria of 14 ug/L. ETPH was not detected in MW-2BR and was detected below SWPC in MW-3BR and MW-10BR. Metals were detected at concentrations below the SWPC. Hockanum River Sediments VOCs, cyanide, and PCBs were not detected in Hockanum River sediment samples. PAHs were detected in each sediment sample. The highest PAH concentrations were detected in SED-01 located at the upstream site boundary and directly below the West Main Street Bridge, which suggests an upstream source or impacts from roadway run-off. ETPH concentrations ranged from non-detected to 1,100 milligram/Kilogram (mg/kg) at the SED-06 location. Metals were detected in each sediment sample with the highest concentrations were detected at SED-06. Total organic ranged from 5,100 mg/Kg to 24,000 mg/Kg. SED-06 is located adjacent to a former cast iron pipe but is also downstream from the two outfalls beneath the Maple Street that discharge to a tributary to the Hockanum River. A plastic outfall pipe conveys drainage from upgradient properties; the extent of which is unknown. The second is a square stone and masonry outfall from the former Hockanum Mill that reportedly discharged to the Hockanum River during the operation of the mill. Hockanum River Surface Water VOCs, SVOCs, ETPH, and total cyanide were not detected in the Hockanum River surface waters. Dissolved metals (barium, chromium and zinc) were detected. Concentrations of these compounds were detected upstream at the site boundary which suggests concentrations of these compounds are present as part of natural stream water conditions or are attributable to upstream sources. 2.3 Off-Site Investigation and Findings Off-site Phase III ESA investigations were completed within the Maple Street ROW and three privately-owned properties to the north/northwest of the site. Eversource conducted outreach with off-site private property owners to secure access during the 2nd
  5. Page 17 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 17 of 1005 through 3rd quarter 2017. Once access was secured, each location was marked out for public utilities by CBYD prior to commencing drilling activities. Off-site Phase III ESA activities included the advancement of ten soil borings and four monitoring wells to assess off-site impacts to the north and east of the site. A summary of off-site investigations is provided on the table below. Location St. Joseph’s Church [Parking Lot] 17 Maple Street [Residence] Maple Street ROW USPS Access Road Soil Borings SB-14, SB-15, SB-16 Monitoring Wells MW-19S, MW-20S and MW-23S (soil borings) SB-17 MW-19S, MW-20S and MW-21S SB-18 and SB-19 MW-23 (soil boring) Monitoring Well Not Installed MW-23 Monitoring Well Not Installed Phase III ESA analytical samples collected off-site included eleven soil samples and six groundwater samples from newly installed monitoring wells and existing monitoring wells (MW-14S, MW-14D). MW-21S was not sampled due to the presence of coal tar blebs and staining during development. Off-site soil impacts to the north of the site beneath the St. Joseph School parking lot were addressed under AOC-16 and impacts within the Maple Avenue ROW are addressed under AOC-17. Off-site groundwater impacts for St. Joseph Church and Maple Street ROW are addressed under AOC-23. 2.3.1 Subsurface Soils St. Joseph Church Parking lot Soils with visual coal tar impacts were observed in SB-14 from 20.5 to 23 feet below grade, in SB-15 from 31.5 to 34 feet below grade and 35 to 38 feet below grade within the St. Joseph Church Parking lot. The vertical and horizontal extent of impacts are generally consistent with the previous site investigations completed by Northeast Utilities Service Co. Visual evidence of coal tar impacts were not observed in the soil borings for MW-19S and MW-21S, and SB-16 which define the extent of impacts within the St. Joseph Church Parking Lot. VOCs, ETPH, PAHs, and total cyanide were not detected in soils above the water table in samples collected within the St. Joseph Church parking lot. Metals were detected in each soil sample. Concentrations of metals were detected below the applicable RSR criteria. Two soil samples collected from SB-14 and MW-20S below the apparent water table and within coal tar-impacted zones contained concentrations of VOCs, PAHs, and EPTH; however, because of the deep nature of the impacts below the water table the RSR criteria does not apply. Concentrations at SB-14 were at lower levels than soils at similar depths completed in on-site borings. 17 Maple Street No evidence of coal tar impacts was observed in SB-17 completed in the backyard of 17 Maple Street. VOCs, PAHs, ETPH and cyanide were not detected. Concentrations of
  6. Page 18 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 18 of 1005 metals were detected but at similar concentrations as other off-site soil samples indicating that concentrations are likely attributable to natural concentrations in soils. Maple Street ROW Area Two soil borings (SB-17 and SB-18) were completed in the Maple Street ROW and one soil boring for MW-23S that was completed in the USPS Access Road (AOC-17). A combination of apparent petroleum and coal tar impacts were noted within SB-18 and SB-19 within the Maple Street ROW. Staining with strong petroleum odors were in SB-19 from 11 to 19 feet and within SB-18 from 19 to 23 feet below grade. Fuel oil impacts were previously encountered from 15 to 27 feet below grade on 8 Maple and 12 Maple Street properties during a previous site investigation by Northeast Utilities Service Co. During the Phase I ESA, a 1,000-gallon leaking underground storage tank (LUST) used for heating oil storage at the former 8 Maple Street Residence was identified in CTDEEP Spill report (Case No. 2003-06991) during the Phase I ESA. A fuel distribution company, Gottier Fuel is located upgradient of the site at 221 West Main Street. Staining with coal tar odors were observed in SB-18 from 21 to 23 feet and 26.5 to 29 feet below grade and in SB-19 from 19 to 26.5 feet below grade. No visual impacts were observed below 29 feet to the termination of the soil borings. The coal tar impacts appear to below the apparent water table based upon visual observations during drilling. No observation of visual impacts, odors or elevated PID readings were observed in the soil boring for MW-23S within the USPS ROW to the east of Maple Street. Samples collected within petroleum-impacted soils contained concentrations of VOCs, PAHs, and ETPH exceeded applicable RSR criteria. Metals were detected below RSR criteria. 2.3.2 Off-site Groundwater Impacts Off-site groundwater impacts (AOC-23) are summarized below by St. Joseph Church property and the USPS Access Road. St. Joseph Church Property VOCs, PAHs, ETPH and cyanide were not detected in shallow water table monitoring wells (MW-14S, 19S, MW-21S) downgradient of the site. Metal concentrations were detected but at concentrations below the SWPC. Elevated metal concentrations were detected in MW-14S are likely attributable to slightly elevated turbidity in the sample. MW-20S within the driveway to the church parking lot was not sampled because coal tar staining and sheens were encounter during the development of the well. MW-13S was dry at the time of sampling during the Phase III ESA. In the deep overburden monitoring well (MW-14D), concentrations of VOCs, were detected below the SWPC. Methyl-tert-butyl-ether (VOC), a historic gasoline additive, was detected in MW-14D which suggests impacts could be partially attributable to a release of petroleum near the well. PAHs were also detected in MW-14D at concentrations below the SWPC criteria. Metals were detected in MW-14D at concentrations below RSR criteria. MW-13D was unable to be located within the church parking lot and was likely paved over.
  7. Page 19 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 19 of 1005 USPS VOCs, PAHs, ETPH and cyanide were not detected in MW-23S located in the USPS Access Road. Metals were detected at levels below the SWPC.
  8. Page 20 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 20 of 1005 Section 3 Quality Assurance/ Quality Control Quality assurance/quality control measures were implemented as part of the Phase III ESA including the collection of field QA/QC samples and laboratory sample analysis via RCP analytical methods. A summary of the Phase III ESA QA/QC measures are provided below. A full data quality assessment/ data usability evaluation will be completed as part of the Final Phase III ESA report. Field QA/QC samples included the collection of blind duplicate samples for each sample media (soil, groundwater, sediment and surface water) and the collection/submittal of blank samples (equipment blank and trip blank samples. Duplicate sample results are provided next to the primary sample on Table 2 through Table 5, respectively. The equipment blank sample did not contain site-related COCs. Methylene chloride, a common laboratory cleaning solvent, was detected in the equipment blank but not the corresponding groundwater samples or sediment samples. The methylene chloride detections are flagged as possible laboratory contamination. VOCs were not detected in trip blanks. Phase III ESA samples were analyzed by Phoenix in accordance with CTDEEP’s RCPs. Each laboratory analytical data package contains a Laboratory Analysis Quality Assurance/ Quality Control Certification Form which indicates that laboratory followed the specified QA/QC performance criteria. Phase III ESA analytical samples were submitted within laboratory-provided and preserved sample jars and were analyzed within analytical method within holding times. The RCP analytical data packages provide a summary of QA/QC non-conformances are in Laboratory Analysis Quality Assurance/ Quality Control Certification Form and also are described in the QA/QC information within the back of each data analytical data package. Several non-conformances were identified for non-target compounds that are not COCs at the site. In instances where non-conformances were identified for siterelated COCs (i.e., metals and SVOCs), slight variability and biases were identified. During our review, one instance of an elevated sample temperature of 6.2° C with cooling initiated for a sample delivery of four samples to the laboratory which is just above the required 6.0° C temperature. It is possible for a low bias for VOCs in one soil sample [SB-05 (20-21)]. This sample contained VOC detections well above the GB PMC, as such is not adversely impacted. Based on the review of the non-conformances and the laboratory certification documentation, each lab report meets CTDEEP RCP. The non-conformances identified do not adversely affect the usability of the laboratory data. In those areas where COCs were involved, the data quality is only slightly affected by these non-conformances and is sufficient to satisfy the data quality objectives (DQOs) for the project.
  9. Page 21 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 21 of 1005 Section 4 Conceptual Site Model A CSM is a representation of an environmental system at a site that is used as a tool to identify releases, migration pathways, potential receptors, and ultimately risk. The CSM is used to develop work plans and provide a framework to address issues that arise during the investigation of a site. The CSM is refined throughout the site characterization process as new data are acquired. The final CSM will fully define the environmental system at the site and validate the hypotheses regarding the environmental fate of released contaminants. A final, validated CSM includes the following components: • Description of the site and environmental setting • Identification of AOCs and associated COCs • Potential release mechanisms for COCs at each AOC • Evaluation of migration pathways and locations at which environmental media are most likely to have been impacted by a release • Identification of AOCs at which releases have occurred as well as AOCs at which no releases have occurred • Evaluation of the nature and three-dimensional extent of contaminants • Data and rationale to support conclusion Table 6 provides a preliminary CSM summary that was developed for the Rockville MGP site and has been updated based upon the findings of the 2017 Phase III ESA activities. A full CSM will be provided as part of the Phase III ESA Report. Based upon the CSM, additional investigations are needed to assess the nature and extent of impacts at the site and off-site AOCs as discussed below in Phase III ESA data gaps. The following off-site AOCs related to surface soil impacts were not assessed during the Phase III ESA: AOC-19 Suspected Fill #12 and #14 Maple Street, AOC-21 Off-site Surface Soils Maple Street School and AOC-22 Off-site Surface Soils 175 Union Street. Historic PAH impacts in surface soils were determined to attributable to off-site source (airborne deposition) based upon information encountered during the preparation of the Phase I ESA for the site. Off-site Petroleum Impacts #8 and #12 Maple Street (AOC-18) was not assessed during the Phase III ESA because a record of LUST record for a 1,000-gallon heating oil UST at #8 Maple Property was encountered during the Phase I ESA
  10. Page 22 of 1,005

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 29, 2026 RSR-032 Attachment 21 Page 22 of 1005 Section 5 Well Receptor Survey Tighe & Bond completed a Water Supply Well Receptor Survey during November 2017 in general accordance with CTDEEP’s Water Supply Well Receptor Survey Guidance Document dated September 2009 (revised January 2015). For this report, a receptor is defined as a residential or commercial potable well that is in use. The receptor survey is intended to determine the extent of public water service at a minimum of within 500-feet of the site and identify those properties where potable groundwater supply wells may still be in-use. The site is located within a mixed residential and commercial area of Rockville. Residential properties are located to the east, west and north of the site. Commercial (liquor store and office), vacant (former machine shop), and high-voltage power line ROW are located to the south. A commercial heating oil company (Gottier Fuel Company) is located to the southeast across West Main Street and the Saxony Mill Park is located to the southwest across West Street. As indicated above, the site is located within a GB groundwater classification area. The area to the west of West Street is classified as GA which indicates that it is area of existing private water supply wells or an area with the potential to provide water to public or private water supply wells and is at a minimum, suitable for drinking or other domestic uses without treatment. 5.1 Water Supply Well Survey Methods The following methods were used by Tighe & Bond to assess the presence of water supply wells in the vicinity of the site. Tighe & Bond initially used a 500-foot search radius to assess the presence for the use of private wells. However, based upon the Phase III ESA Conceptual Site Model and CTDEEP input the radius was increased to a more conservative 1,000-foot radius. A geographic information system (GIS) was created to establish a 500-foot and 1,000foot buffer zones surrounding the site (Figure 9). Sixty-two (62) properties were identified within a 500-foot radius of the site and two hundred and two (202) properties were identified within a 1,000-foot radius search area. The street address and parcel ID information for the parcels within the radius search area were obtained from the Town of Vernon and Town of Ellington tax assessor information. The list of properties was submitted to the Connecticut Water Company on November 2, 2017 to request information regarding water service connection information. In addition, a visual “windshield survey” was conducted by Tighe & Bond from the sidewalks within the public street ROWs on November 13 and 21, 2017 within the 1,000-foot buffer area to identify potential residential well-heads, if present, and public water source indicators, e.g. water lines, and fire hydrants. We reviewed the following information sources to assess for potential water supply wells in the vicinity of the site: • • Water Quality Classification Maps of Connecticut provided on CT ECO website. Public Water Supply Map published by the Connecticut Department of Health (http://www.ct.gov/dph/cwp/view.asp?a=3139&q=513480)

Text of RSR-032 Attachment 20_Part2.pdf

Extracted from the file · 109 pages · 16,568 characters

Text of RSR-032 Attachment 20_Part1.pdf

Extracted from the file · 150 pages · 190,904 characters

Text of RSR-032 Attachment 19.pdf

Extracted from the file · 23 pages · 39,103 characters

Text of RSR-032 Attachment 18.pdf

Extracted from the file · 8 pages · 12,671 characters

Text of RSR-032 Attachment 17_Part3.pdf

Extracted from the file · 282 pages · 740,441 characters

Text of RSR-032 Attachment 17_Part2.pdf

Extracted from the file · 500 pages · 1,293,274 characters

Text of RSR-032 Attachment 17_Part1.pdf

Extracted from the file · 500 pages · 1,270,790 characters

Text of RSR-032 Attachment 16.pdf

Extracted from the file · 46 pages · 130,280 characters

Text of RSR-032 Attachment 15.pdf

Extracted from the file · 17 pages · 25,967 characters

Text of RSR-032 Attachment 14.pdf

Extracted from the file · 10 pages · 15,944 characters

Text of RSR-032 Attachment 13.pdf

Extracted from the file · 17 pages · 29,849 characters

Text of RSR-032 Attachment 12.pdf

Extracted from the file · 12 pages · 20,731 characters

Text of RSR-032 Attachment 11.pdf

Extracted from the file · 15 pages · 23,899 characters

Text of RSR-032 Attachment 10.pdf

Extracted from the file · 145 pages · 332,684 characters

Text of RSR-032 Attachment 9.pdf

Extracted from the file · 897 pages · 1,943,866 characters

Text of RSR-032 Attachment 8.pdf

Extracted from the file · 203 pages · 512,054 characters

Text of RSR-032 Attachment 7.pdf

Extracted from the file · 12 pages · 13,977 characters

Text of RSR-032 Attachment 6.pdf

Extracted from the file · 335 pages · 685,056 characters

Text of RSR-032 Attachment 5.pdf

Extracted from the file · 65 pages · 194,221 characters

Text of RSR-032 Attachment 4.pdf

Extracted from the file · 570 pages · 1,357,502 characters

Text of RSR-032 Attachment 3.pdf

Extracted from the file · 8 pages · 15,762 characters

Text of RSR-032 Attachment 2.pdf

Extracted from the file · 26 pages · 3,865 characters

Text of RSR-032 Attachment 1.pdf

Extracted from the file · 18 pages · 2,673 characters

As listed on the current system

Question(s) Answered 32 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/30/2026

This filing on the current system (opens in a new tab)