Interrogatory responses
Answers to questions 59
Files6
RSR-059_Final.pdf
PDF · 234 KB · 4 pagesText searchable
Download RSR-059_Final.pdfRead the text of RSR-059_Final.pdf
RSR-059 Attachment 1.pdf
PDF · 858 KB · 2 pagesText searchable
Download RSR-059 Attachment 1.pdfRead the text of RSR-059 Attachment 1.pdf
RSR-059 Attachment 2.pdf
PDF · 1.2 MB · 6 pagesText searchable
Download RSR-059 Attachment 2.pdfRead the text of RSR-059 Attachment 2.pdf
RSR-059 Attachment 3.pdf
PDF · 3.5 MB · 19 pagesText searchable
Download RSR-059 Attachment 3.pdfRead the text of RSR-059 Attachment 3.pdf
RSR-059 Attachment 4.pdf
PDF · 74 KB · 1 pageText searchable
Download RSR-059 Attachment 4.pdfRead the text of RSR-059 Attachment 4.pdf
RSR-059 Attachment 4.xlsx
Excel · 23 KBText searchable
Download RSR-059 Attachment 4.xlsxRead the text of RSR-059 Attachment 4.xlsx
Page 1 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 1 of 19 Spring ICC – Carlsbad, CA April 29, 2026 Subcommittee A PROVEN CABLE PERFORMANCE ASSESSMENT AFTER 40 YEARS OF FIELD AGING Paul Brigandi* — Dow Wire & Cable Timothy Person — Dow Wire & Cable Brent Richardson — Richardson Bros. Services Stephen Wolbach — Alabama Power Company Diana Ramirez-Wong — Georgia Tech, NEETRAC *Application Technology Leader, Wire & Cable, Dow Email: [email removed] ®Trademark of The Dow Chemical CompanyPage 2 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 2 of 19 PRESENTATION OVERVIEW ▪ Why 40 Years Matters ▪ Galleria Mall Field Study Overview ▪ Cables & Test Program ▪ 40-Year Electrical & Material Performance ▪ Key Findings & Implications 2Page 3 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 3 of 19 WHY A 40-YEAR FIELD EVALUATION OF MV CABLE SYSTEM? ▪ For decades, ~40 years has been widely considered the expected service life for underground MV cable systems* ▪ Many 1st generation TR-XLPE installations are now at or beyond this design-life projection ▪ Utilities face critical decisions: ➢ When is replacement needed? ➢ Extend service? ➢ Re-rate or re-purpose existing assets? ▪ The Galleria Mall system offers a rare opportunity to assess the current state near the end of expected service life *Thue, W., Burnstein, B.; Electric Power Research Institute (EPRI), Distribution Cable Research Digest 2000, EPRI Publication BR-110693, Palo Alto, CA, USA, 2000. (Available to EPRI members only). 3Page 4 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 4 of 19 WHY THE GALLERIA MALL SYSTEM IS A RARE OPPORTUNITY ➢ One of the earlier TR-XLPE installations on the Alabama Power system ➢ Installed in 1985, now past the historically expected ~40-year service life ➢ Half loops of TR-XLPE and EPR insulated cables with the same voltage class, loading, and environment ➢ Previously evaluated at 17 and 25 years, enabling a true long-term aging trend assessment ▪ Study Scope Field-removed TR-XLPE and EPR cables after ~40 years of continuous service ➢ Identical operating and environmental exposure for both insulation systems ➢ Direct continuity with prior 17- and 25-year evaluations of the same system ➢ ▪ Key Objectives Evaluate 40-year field performance of TR-XLPE and EPR cables ➢ Assess current health condition and continued fitness for service of the 40-year-old cable system ➢ Directly compare TR-XLPE vs. EPR performance after four decades ➢ Benchmark 40-year results against prior 17- and 25-year evaluations ➢ 4Page 5 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 5 of 19 GALLERIA MALL • Constructed 1984–1985; opened 1986 • ~2 million ft² super-regional mall; largest in the Southeast at time of construction • Located ~10 miles south of Birmingham, Alabama (Hoover) • Major commercial facility with an electrical demand of approximately 20 MVA • Supplied by four 200-A underground distribution loops at 34.5 kV https://hooversun.com/news/what-s-next-for-the-riverchase-galleria/ 5Page 6 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 6 of 19 EPR Cable Removed (17 yr; 2001) EPR Cable Removed (25 yr; 2010) Galleria Mall TR-XLPE Cable Removed (40 yr; 2025 TR-XLPE Cable Removed (17yr;2001)Page 7 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 7 of 19 TEAM REMOVES CABLES FROM THE GALLERIA MALL LOOP 7Page 8 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 8 of 19 SIMILAR 35 KV CABLE DESIGNS Cable Component TR-XLPE EPR No. 1/0 Copper Conductor (strand fill*) No. 1/0 Copper Conductor (strand fill*) XLPE Semi-Conductive Conductor Shield EPR Semi-Conductive Conductor Shield 345 mils TR-XLPE Insulation 345 mils EPR Insulation Insulation Shield Strippable XLPE Insulation Shield EPR Semi-Conductive Insulation Shield Concentric Neutral 16 x #14 Copper Concentric Neutral 16 x #14 Copper Concentric Neutral Jacket 80 mils Semi-Conductive PE Jacket 80 mils PE Insulating Jacket Conductor Conductor Shield Insulation *TR-XLPE Cable used a viscous fill material within and over the conductor strands with a semi-con tape layer over the filled conductor. EPR Cable used a soft rubber strand fill material. 8Page 9 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 9 of 19 TEST PROGRAM ▪ TR-XLPE and EPR 35kV cables with 40 years of field service ▪ 300 circuit feet from each cable removed for stress testing was done by NEETRAC an independent 3rd party testing organization ➢ HVTT (Ambient) ➢ Impulse (90 °C) ➢ DF 60Hz versus Temp Performed by NEETRAC ➢ Treeing analysis ➢ VLF tan d ➢ TR additive analysis Performed by Dow ➢ Moisture Analysis 9Page 10 of 19
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 16, 2026 RSR-059 Attachment 3 Page 10 of 19 ST A B L E TR E E RE T A R D A N T AD D IT IV E DIS T R IB U T IO N IN TR-XLPE 3.00 2.50 Intensity 2.00 1.50 1.00 0.50 0.00 0 1000 2000 Cable A Intensity 3000 4000 5000 Distance (micrometer) Cable B Intensity 6000 7000 8000 Cable C Intensity ▪ Normalized absorbance of a peak assigned to the TR additive relative to one assigned to PE ▪ The spectra were collected in 11 evenly spaced steps (about every 800 µm) along each slice from the insulation shield to the conductor shield 10
Text of RSR-059 Attachment 4.pdf
Extracted from the file · 1 page · 426 characters
Text of RSR-059 Attachment 4.xlsx
Sheet names, column headings and text cells; numbers left out
As listed on the current system
Question(s) Answered 59 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 11/06/2026