Response to Motion No. 040

Response type: Supplemental Filing

Files1

Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Words on different pages
  1. Page 201 of 212

    Document Accession #: 20251014-5331 Filed Date: 10/14/2025 B. Documents that contain CEII must include a top center header on each page of the document with the following text: CUI//CEII. Any corresponding electronic files must also include this text in the file name. C. Documents that contain both Privileged Material and CEII must include a top center header on each page of the document with the following text: CUI//CEII/PRIV. Any corresponding electronic files must also include this text in the file name. D. The specific content on each page of the document that constitutes Privileged Material and/or CEII must also be clearly identified. For example, lines or individual words or numbers that include both Privileged Material and CEII shall be prefaced and end with “BEGIN CUI//CEII/PRIV” and “END CUI//CEII/PRIV”. 15. Nothing in this Protective Agreement shall be construed as precluding any Participant from objecting to the production or use of Privileged Material and/or CEII on any appropriate ground. 16. Nothing in this Protective Agreement shall preclude any Participant from requesting the Commission, or any other body having appropriate authority, to find this Protective Agreement should not apply to all or any materials previously designated Privileged Material pursuant to this Protective Agreement. The Commission, or any other body having appropriate authority may alter or amend this Protective Agreement as circumstances warrant at any time during the course of this proceeding. 17. Each Participant governed by this Protective Agreement has the right to seek changes in it as appropriate from the Commission, or any other body having appropriate authority. 18. Subject to Paragraph 17, the Commission shall resolve any disputes arising under this Protective Agreement pertaining to Privileged Material according to the following procedures. Prior to presenting any such dispute to the Commission, the Participants to the dispute shall employ good faith best efforts to resolve it. A. Any Participant that contests the designation of material as Privileged Material shall notify the Participant that provided the Privileged Material by specifying in writing the material for which the designation is contested. B. In any challenge to the designation of material as Privileged Material, the burden of proof shall be on the Participant seeking protection. If the Commission finds that the material at issue is not entitled to the designation, the procedures of Paragraph 18 shall apply. C. The procedures described above shall not apply to material designated by a Participant as CEII. Material so designated shall remain subject to the provisions of this Protective Agreement, unless a Participant requests and obtains a determination from the Commission’s CEII Coordinator that such material need not retain that designation.
  2. Page 202 of 212

    Document Accession #: 20251014-5331 Filed Date: 10/14/2025 19. The designator will have five (5) days in which to respond to any pleading requesting disclosure of Privileged Material. Should the Commission determine that the information should be made public, the Commission will provide notice to the designator no less than five (5) days prior to the date on which the material will become public. This Protective Agreement shall automatically cease to apply to such material on the sixth (6th) calendar day after the notification is made unless the designator files a motion with the Commission, as appropriate, with supporting affidavits, demonstrating why the material should continue to be privileged. Should such a motion be filed, the material will remain confidential until such time as the issue has been addressed by the Commission, as provided in the Commission’s regulations. No Participant waives its rights to seek additional administrative or judicial remedies after a decision regarding Privileged Material or the Commission’s denial of any appeal thereof or determination in response to any certified question. The provisions of 18 C.F.R. §§ 388.112 and 388.113 shall apply to any requests under the Freedom of Information Act (5 U.S.C. § 552) for Privileged Material and/or CEII in the files of the Commission. 20. Privileged Material and/or CEII shall remain available to Participants until the later of 1) the date an order terminating this proceeding no longer is subject to judicial review, or 2) the date any other Commission proceeding relating to the Privileged Material and/or CEII is concluded and no longer subject to judicial review. After this time, the Participant that produced the Privileged Material and/or CEII may request (in writing) that all other Participants return or destroy the Privileged Material and/or CEII. This request must be satisfied with within fifteen (15) days of the date the request is made. However, copies of filings, official transcripts and exhibits in this proceeding containing Privileged Material, or Notes of Privileged Material, may be retained if they are maintained in accordance with Paragraph 5 of this Protective Agreement. If requested, each Participant also must submit to the Participant making the request an affidavit stating that to the best of its knowledge it has satisfied the request to return or destroy the Privileged Material and/or CEII. To the extent Privileged Material and/or CEII are not returned or destroyed, they shall remain subject to this Protective Agreement. 21. Regardless of any order terminating this proceeding, this Protective Agreement shall remain in effect until specifically modified or terminated by the Commission. All CEII designations shall be subject to the “[d]uration of the CEII designation” provisions of 18 C.F.R. § 388.113(e). 22. Any violation of this Protective Agreement and of any Non-Disclosure Certificate executed hereunder shall constitute a breach of this Agreement. Mark R. Haskell Counsel for BP Energy Retail Company LLC Date: October 14, 2025
  3. Page 203 of 212

    Document Accession #: 20251014-5331 Filed Date: 10/14/2025 Agreed to and Accepted by: Name: Title: Party or Participant Represented: Date:
  4. Page 204 of 212

    Document Accession #: 20251014-5331 Filed Date: 10/14/2025 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION BP Energy Retail Company LLC Complainant, v. ISO New England Inc., Eversource Energy, and NSTAR Electric Company Respondents. ) ) ) ) ) ) ) ) ) ) Docket No. EL26-__-000 NON-DISCLOSURE CERTIFICATE I hereby certify my understanding that access to Privileged Material and/or Critical Energy/Electric Infrastructure Information (CEII) is provided to me pursuant to the terms and restrictions of the Protective Agreement in this proceeding, that I have been given a copy of and have read the Protective Agreement, and that I agree to be bound by it. I understand that the contents of Privileged Material and/or CEII, any notes or other memoranda, or any other form of information that copies or discloses such materials, shall not be disclosed to anyone other than in accordance with the Protective Agreement. I acknowledge that a violation of this certificate constitutes a violation of the Protective Agreement. By: ______________________________________ Printed Name: _____________________________ Title: ____________________________________ Representing: _____________________________ Date: ____________________________________
  5. Page 205 of 212

    Document Accession #: 20251014-5331 Filed Date: 10/14/2025 CERTIFICATE OF SERVICE I hereby certify that I have this day served the foregoing document upon each of the Respondents’ designated contacts for service of process. Dated at New York, NY this 14th day of October, 2025 /s/ Jane Thomas Jane Thomas Blank Rome LLP 1271 Avenue of the Americas New York, NY 10020 Tel: [phone removed] [email removed]
  6. Page 206 of 212

    Document Accession #: 20251014-5331 Filed Date: 10/14/2025 Document Content(s) BPERC Transmittal Letter.pdf..............................................1 Redacted Filing Set.pdf...................................................3
  7. Page 207 of 212

    EXHIBIT D
  8. Page 208 of 212

    UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION BP Energy Retail Company LLC Complainant, ) ) ) ) ) ) ) ) ) ) v. ISO New England Inc., Eversource Energy, and NSTAR Electric Company Respondents. Docket No. EL26-5-000 Motion for Leave to File Supplement and Supplement to Prior Filings of BP Energy Retail Company LLC Pursuant to Rules 212 and 215 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission1 (“Commission”), BP Energy Retail Company LLC (“BPERC”), the Complainant in the above-captioned action, hereby submits this Motion For Leave to File Supplement and Supplement to BPERC’s prior filings in the above-referenced docket.2 I. Motion for Leave to File Good cause exists to grant this request. The request supplements and clarifies the scope of BPERC’s complaint based on newly obtained information. The case has not been set for hearing procedures and granting the request will not result in substantial prejudice or inconvenience. No other supplements or amendments are proposed at this time. 1 18 C.F.R. §§ 385.212 and 385.215 (2025). See Complaint Seeking Relief from Phantom Load Allocations, Docket No. EL26-5-000, Accession Nos. 202510145331 and 20251014-5332 (Oct. 14, 2025) [hereinafter BPERC Complaint]; Motion for Leave to File Limited Supplement and/or Amendment to Complaint and Limited Supplement and/or Amendment to Complaint of BP Energy Retail Company LLC, Docket No. EL26-5-000, Accession No. 20251017-5137 (Oct. 17, 2025); Answer to Eversource Motion to Dismiss and Motion for Leave to Reply and Reply to ISO New England Inc. Answer and Response of BP Energy Retail Company LLC, Docket No. EL26-5-000, Accession No. 20251229-5510 (Dec. 29, 2025) [hereinafter BPERC Answer and Reply]. 2 1
  9. Page 209 of 212

    II. Supplement BPERC supplements its prior filings in this docket with the following update: In its Answer to BPERC’s Complaint filed on December 12, 2025, Eversource advised that “NSTAR is currently working with DOER and plans to update the data that provides the basis for RPS compliance.”3 That process has evidently concluded. On February 11, 2026 and on February 23, 2026, BPERC received communications from the Massachusetts (“MA”) Department of Energy Resources advising that BPERC’s final revised calendar year 2024 load allocation had been redetermined. BPERC understands that the load redetermination for establishing BPERC’s MA renewable portfolio standard (“RPS”) obligation was based on updated data the Department of Energy Resources received from Eversource Energy and NSTAR Electric Company (“Eversource”). BPERC understands based on this communication that there are no further outstanding corrections still pending from Eversource that would alter this redetermined amount. The redetermined load allocation corrects the disputed amount for BPERC’s RPS obligation identified in BPERC’s prior filings in this docket.4 Consequently, BPERC advises that this portion of the dispute has been resolved, reducing the amount at issue from a total of $9.5 million to approximately $6 million. BPERC has been unable to determine whether Eversource intends to similarly adjust BPERC’s load allocation for settlement charges. The approximate $6 million disputed amount under the Commission’s jurisdiction is still the subject of this complaint. Eversource/NSTAR’s recent RPS load allocation correction, for July – September 2024, more than 15 months late and only after multiple billing disputes and a complaint was filed, demonstrates that the requested tariff 3 Request for Remedial Relief, Answer, and Motion to Dismiss of Eversource Energy and NSTAR Electric Company, Docket No. EL26-5-000, Accession No. 20251212-5233 at 13 n. 35 (Dec. 12, 2025). 4 See, e.g., BPERC Complaint at 2, 17; BPERC Answer and Reply at 13. 2
  10. Page 210 of 212

    waiver is supported. Now that Eversource/NSTAR has finally determined BPERC’s accurate load allocation, Eversource/NSTAR must provide that information to ISO-NE, and ISO-NE must be required to sync the correct settlement load allocation to BPERC and refund or credit the previous settlement overcharges of $6 million. The relief sought is limited to a discrete three-month period and a single market participant. The requested correction does not require a market-wide resettlement. BPERC alone has sought relief. Denying relief on these facts would create an outcome that would erode confidence in the fairness and accuracy of settlements in Commission-jurisdictional markets. A system error of this magnitude cannot be dismissed with a shrug and the observation that there just are “winners and losers.” III. Conclusion WHEREFORE, for the foregoing reasons, BPERC respectfully requests that the Commission accept this Motion for Leave to File Supplement and accept this supplement to BPERC’s prior filings. 3

As listed on the current system

Response to Motion No.: 040 - 10/19/2026 (Allco Renewable Energy Limited) - Type Response = Supplemental Filing [26-05-10]