Response to Motion No. 040
Response type: Supplemental Filing
Filed by Allco Renewable Energy Limited1 file
Part of docket 26-05-10Files1
Allco_Second_Supplement_Motion40_EL26-5_Filings_26-05-10 tm.pdf
PDF · 13 MB · 212 pagesText searchable
Download Allco_Second_Supplement_Motion40_EL26-5_Filings_26-05-10 tm.pdfRead the text of Allco_Second_Supplement_Motion40_EL26-5_Filings_26-05-10 tm.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 42 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 to be based solely on an extensive IT systems error across multiple months. BPERC properly challenged these errors as they arose. BPERC believes that Eversource/NSTAR reported the same basic issues to ISO-NE. ISO-NE corrected the overallocation in the Northeast Massachusetts (“NEMA”) zone through the Meter Data Error RBA Resettlements process; however, a second over-allocation arose in the South East Massachusetts (“SEMA”) zone for the first time that improperly tagged BPERC with a total of 144,000 MWh of new load, resulting in additional direct costs to BPERC of about $5,935,672 3 for the period July-September 2024. If the Renewable Portfolio Standard (“RPS”) obligations related to this phantom load are not corrected, that could increase the financial impact by an estimated additional $3,566,372 for a total impact of $9,502,044. 4 BPERC had no actual knowledge of this readjustment. 5 ISO-NE states that the Request for Billing Adjustment (“RBA”) is barred by the 101-day limit on billing adjustments under its Manual M-28 directing BPERC to resolve discrepancies outside of the ISO settlement framework. 6 BPERC had no notice or opportunity to correct this error, and as a result it has been saddled with millions of dollars in costs for load it does not serve, despite the fact that it timely objected to prior phantom load allocations. This is a result that is unjust, unreasonable, and unduly discriminatory, warranting corrective action by the Commission. Accordingly, BPERC respectfully requests that the Commission direct ISO-NE to nullify these phantom load charges, and to grant any and all necessary waivers of the ISO-NE tariff, operating procedures or protocols necessary to implement this result and to direct Eversource/NSTAR to provide to ISO-NE corrected data to fix the actual SEMA load for BPERC The inflated load amounts are 45,000 MWh in July 2024; 49,000 MWh in August 2024; and 47,000 MWh in September 2024. See Exhibit No. 31. 4 See Exhibit No. 31. 5 BPERC also had requested on multiple occasions that Eversource/NSTAR provide access to additional information to support any claimed allocation of load to BPERC; on information and belief, those requests were not met. Representative communications are attached as Exhibit 9. 6 See Exhibit Nos. 25, 26 and 27 and Exhibit No. 1. 3 2Page 43 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 during the time periods at issue and going forward. In the alternative, BPERC requests that the Commission issue an order remanding the case to ISO-NE to reopen the record to fix the proper billed amount to BPERC for the months of July, August and September 2024 for the SEMA load charges still at issue, without regard to the 101-day limit in Market Rule 1 and Manual M-28 and to nullify the phantom load charges for those months. At the outset, BPERC notes that it has worked with Eversource/NSTAR to attempt to resolve this situation. BPERC will continue to do so. Eversource/NSTAR have expressed willingness to resolve the load errors that are the subject of this Complaint and have agreed on the volumes of over-inflated load allocations; however, to date, Eversource/NSTAR have provided neither a process nor a timeline for any such resolution. Given the high cost of these inaccurate load allocations to BPERC—slightly under $10 million—BPERC has filed this Complaint to preclude any claim of waiver of any of its rights. In support hereof, BPERC states as follows: I. COMMUNICATIONS AND CORRESPONDENCE All communications with regard to this filing should be directed to the following persons: 7 Betsy Carr Senior Counsel BP America Inc. 201 Helios Way Houston, TX 77079 Tel.: [phone removed] [email removed] II. Mark R. Haskell Jane Thomas Blank Rome LLP 1825 Eye Street, NW Washington, DC 20006 Tel.: [phone removed] Fax: [phone removed] [email removed] [email removed] THE PARTIES A. BPERC BPERC is a retail energy provider in the state of Massachusetts and provides retail BPERC respectfully requests waiver of Rule 203(b)(3) to the extent necessary to permit designation of more than two persons for service on its behalf in these proceedings. See 18 C.F.R. § 385.203(b)(3). 7 3Page 44 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 electricity service to commercial and industrial customers. BPERC is the Complainant and seeks relief from allocation of phantom load by Eversource/NSTAR to BPERC through bills rendered by ISO-NE. B. ISO-NE ISO-NE is an independent system operator functioning as the reliability coordinator, market operator, transmission operator, balancing authority operator and planning authority for the six New England states. ISO-NE’s refusal to correct invoices that misallocated phantom load to BPERC gives rise to this Complaint. ISO-NE is a respondent in this proceeding. C. Eversource Energy Eversource is a public utility company that transmits and delivers electricity, natural gas, and water to customers in Connecticut, Massachusetts, and New Hampshire. On information and belief, Eversource is the parent corporation of NSTAR and owns or controls the Omni system which has wholly, or in part, caused the phantom load allocations that are the subject of this Complaint. Eversource is a respondent in this proceeding. D. NSTAR NSTAR Electric Company is a legacy utility that merged into the Eversource corporate structure in 2015. While it now operates under the Eversource brand, NSTAR remains a distinct legal entity and continues to serve as the Assigned Meter Reader and Host Participant for certain load zones in Massachusetts, including the NEMA and SEMA zones. This legal distinction is material because many or all of the erroneous load assignments and billing discrepancies affecting BPERC stem from NSTAR’s role in implementing and reporting data through Eversource’s 4Page 45 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 systems, particularly following the rollout of the Omni billing system in mid-2024. NSTAR is a respondent in this proceeding. III. FACTS 1. On information and belief, in mid-2024, Eversource and NSTAR implemented a new IT software system known as “Omni” to be used for billing purposes. 2. Historically, prior to 2024, meter errors on the ISO-NE system were relatively few in number. From 2019 to 2022, meter data errors ranged from four per year to 15 per year. See Exhibit 29, at 1. 8 3. In 2024, meter data errors and related RBAs increased to 117 per year. Eversource and NSTAR alone accounted for 92 out of 117 errors. See Exhibit 29, at 2. 4. The errors associated with the implementation of Omni by Eversource/NSTAR related at least in part to misallocations of load to retail suppliers. The existence of the errors was sufficiently widely known that the Massachusetts Department of Energy Resources (“DOER”) modified its guidance to retail suppliers filing 2024 RPS/APS/CPS/CES compliance forms to take the anticipated corrections by Eversource into account in completing their compliance forms. See Exhibit 28, at 1. 5. As discussed more fully in the Affidavit of Darlene Fernandez on behalf of BPERC (attached hereto as Exhibit No. 1), BPERC timely filed objections each month to phantom load allocations by Eversource/NSTAR. Specifically, BPERC timely filed disputes to the inaccurate load allocations for August 2024 (35,000 MWh)(filed January 14, 2025); September 2024 (24,000 MWh)(filed February 17, 2025); October 2024 (20,000 MWh)(filed March 14, 2025); November 2024 (20,000 Mwh)(filed April 13, 2025); and December 2024 (11,000 MWh)(filed May 13, 8 The 2023 total number was 33, as Exhibit 29, at 1 shows. 5Page 46 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 2025). See Exhibit 1, at ¶¶ 8-13. Throughout this time frame, BPERC attempted to discuss this issue with Eversource/NSTAR. See Exhibit No. 9. Throughout January, February and March 2025, BPERC requested access to additional backup data from Eversource/NSTAR. Id. These requests appear to have been unmet. Id. 6. In May, June, July and August of 2025, as Ms. Fernandez explains, BPERC continued to request additional explanation from Eversource/NSTAR without receiving definitive answers. Exhibit No. 1 at ¶¶ 14-17. 7. On September 3, 2025, Ms. Fernandez reports that she again reached out to Eversource/NSTAR, this time to request an explanation. Id. at ¶ 18. While the corrections to the phantom load allocations BPERC had protested for months in the NEMA zone had started to be made, new phantom load allocations had appeared for the first time in the SEMA zone. Id. 8. Eversource/NSTAR promised to look into the issue on September 9, 2025. Id. at ¶ 9. BPERC submitted an RBA to ISO-NE on September 12, 2025 seeking relief from 20. the following inaccurate load allocations: • • • July 2024 overstatement of approximately 45,000 MWh – Case # 00106594 August 2024 overstatement of approximately 49,000 MWh – Case # 00106595 September 2024 overstatement of approximately 47,000 MWh – Case # 00106596 Id. at ¶ 21. 10. On September 15, 2025, ISO-NE denied the disputes on the 11-month resettlement volumes. The ISO’s transmittals stated that the “ISO Billing Policy does not allow reconciliation due to metering changes after the final settlement. If there are discrepancies after the final settlement, the meter readers and asset owners must resolve them outside of the ISO settlement”. Id. at ¶ 23. See Exhibit Nos. 25, 26, and 27. 6Page 47 of 212
Document Accession #: 20251014-5331 11. Filed Date: 10/14/2025 Under the terms of the ISO-NE tariff, a Host Participant or Host Utility is defined as “a Market Participant or Governance Participant transmission or distribution provider that reconciles the loads within the metering domain with OP-18 compliant metering.” ISO-NE Transmission, Markets and Services Tariff, General Terms and Conditions, Section 1 (Definitions). 12. Under the terms of the ISO-NE tariff, an Assigned Meter Reader “reports to the ISO the hourly and monthly MWh associated with the Asset. These MWh are used for Settlement. The Assigned Meter Reader may designate an agent to help fulfill its Assigned Meter Reader responsibilities; however, the Assigned Meter Reader remains functionally responsible to the ISO.” ISO-NE Transmission, Markets and Services Tariff, General Terms and Conditions, Section 1 (Definitions). 13. Market Rule 1 Accounting Manual M-28, Section 5.2 imposes on the Assigned Meter Reader and Host Participant the duty to engage in “prompt reporting of any discovered metering, calculating, or reporting errors with respect to an asset to the ISO and the Market Participant(s) owning or having rights to the asset.” 14. Eversource and NSTAR functioned at all times relevant to this Complaint as either the Assigned Meter Reader or the Host Participant or both. 15. As an Assigned Meter Reader and/or a Host Participant, Eversource and NSTAR were subject to the requirements of Market Rule 1 Accounting Manual M-28, Section 5.2, as noted above. 16. BPERC alleges, in light of the facts summarized in paragraphs 1-10 above, and as is discussed in detail in Exhibit No. 1, the Affidavit of Ms. Fernandez, that the actions of 7Page 48 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 Eversource/NSTAR described in this Complaint did not meet the requirements of Section 5.2 of Market Rule 1 Accounting Manual M-28. IV. REQUESTED RELIEF First and foremost, BPERC seeks nullification of ISO-NE invoices that assign to it payment obligations associated with 45,000 MWh of phantom load in July 2024, 49,000 MWh of phantom load in August 2024, and 47,000 MWh of phantom load in September 2024. For its part, BPERC seeks relief from charges that are unjust, unreasonable, unduly discriminatory and factually unsupported. BPERC does not request a market-wide remedy or contend that one is necessary to address the problems raised in this Complaint. 9 V. THE ISO-NE TARIFF SHOULD NOT BAR THE RELIEF REQUESTED OR LIMIT THE COMMISSION’S CONSIDERATION OF THIS CASE. This is not a typical “meter data error.” The ISO-NE tariff defines a “meter data error” as “an error in meter data on an invoice issued by ISO-NE after the completion of the Data Reconciliation Process as described in the ISO New England Manuals and section III.3.8 of Market Rule 1”. ISO-NE Tariff Section I.2.2 (Definitions). The EDI data upon which ISO-NE bills its customers is not at issue in this matter. The issue is not that the meters are broken or dysfunctional or poorly calibrated. The cause is not the meter itself but the Eversource/NSTAR system that tracks and reports load responsibilities and the BPERC at the same time would not object to a market-wide remedy consistent with the ISO-NE tariff and FERC policy. 9 8Page 49 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 impact of that system on the ISO-NE invoicing process. The specific error at issue in this case creates a discrepancy between the EDI data used for customer billing purposes and the ISO-NE invoices. This discrepancy creates the potential that the data errors at issue may create winners and losers. This issue should be addressed under the procedures of the ISO-NE Billing Policy as opposed to Market Rule 1, given the unique facts of this case. Treating this issue as if it were a one-off meter misalignment results in substantial injustice. It is flatly inequitable to assign millions of dollars to a retail market participant simply because the incumbent utility has adopted a software system that is not functioning properly, leading to incorrectly assigned load obligations or The requirements of the ISO-NE billing policy have been met. The RBA has been presented to ISO-NE as required, and has been denied. This complaint has been filed within the required 20 business days. The dispute resolution provisions of Section 1.6 of the Markets and Services Tariff should not delay or prevent the filing of this Complaint. While that provision generally requires a sixtyday period of good faith negotiations, that provision does not apply to cases in which “a party identifies exigent circumstances reasonably requiring expedited resolution of the dispute by the Commission or a court or agency with jurisdiction over the dispute.” Exigent circumstances exist here because under the terms of Section 6.3.6 of ISO-NE’s billing policy, ISO-NE’s denial of the 9Page 50 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 RBA will be final unless challenged by, inter alia, a complaint filed with the Commission within 20 business days. 10 VI. THE COMMISSION’S DECISION IN LIBERTY POWER IS INAPPLICABLE TO THIS CASE. In Liberty Power Holdings, LLC v. Eversource Energy Co., 172 FERC ¶ 61,031 (2020), the Commission denied a complaint in which a market participant challenged a past-period load allocation to it by Eversource. Liberty argued that it had no opportunity to correct an erroneous load allocation and no notice of that error. The Commission found that the specific dispute then at issue which involved the date on which Liberty became responsible for the load at issue was deemed to be a Meter Data Error subject to the dispute resolution procedures of Market Rule 1 and Manual M-28 and not Section 6.3.6 of the ISO-NE Billing Policy in part because Liberty in fact had multiple opportunities to detect and correct the alleged error during the allowed time period. Again, the issue was when Liberty’s load allocation took effect, . This case presents different facts in virtually every respect. In Liberty, Eversource was able to show that it had in fact provided Liberty with timely notice of the error at issue. Here, although Eversource/NSTAR was subject to the duty to notify both ISO-NE and BPERC of the errors at issue promptly under the ISO-NE Market Rules, Eversource/NSTAR did not do so or were not able to do so because of issues with the Omni system. BPERC had no actual notice of the last-minute shift of phantom load from NEMA to SEMA until RBA Resettlement volumes The relevant procedure provides a potential alternate path for an appeal through a AAA approved arbitration proceeding; however, BPERC seeks alternative relief in the form of a waiver of the ISO-NE tariff provisions, which would fall well outside the jurisdiction of the AAA arbitration. As a result, the only practical forum in which BPERC can pursue its issue is the Commission. 10 10Page 51 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 were received. BPERC attempted without success for months to seek an explanation from Eversource/NSTAR for the repeated errors in load allocation it faced. None was provided on a timely basis. To this day, Eversource/NSTAR have still not provided a detailed explanation. This dispute is the result of a known significant systems failure. Leaving that failure uncorrected and unexplained is unwarranted. BPERC still does not know how many times during July to September 2024 the load may have been inflated. Further, as BPERC alleges, Eversource/NSTAR failed to comply with the requirements of Section 5.2 of Manual M-28 by not providing prompt notice to BPERC of the disputes at issue. The strict timelines in Manual M-28 assume that the market participants are adhering to those responsibilities. If they are not or if they cannot comply with the requirements due to systems issues, and if the disputes do not involve meter calibration or accuracy (as here) the general billing dispute resolution policies should apply. The Liberty decision is inapplicable here. 11
As listed on the current system
Response to Motion No.: 040 - 10/19/2026 (Allco Renewable Energy Limited) - Type Response = Supplemental Filing [26-05-10]