Response to Motion No. 040
Response type: Supplemental Filing
Filed by Allco Renewable Energy Limited1 file
Part of docket 26-05-10Files1
Allco_Second_Supplement_Motion40_EL26-5_Filings_26-05-10 tm.pdf
PDF · 13 MB · 212 pagesText searchable
Download Allco_Second_Supplement_Motion40_EL26-5_Filings_26-05-10 tm.pdfRead the text of Allco_Second_Supplement_Motion40_EL26-5_Filings_26-05-10 tm.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 44 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 electricity service to commercial and industrial customers. BPERC is the Complainant and seeks relief from allocation of phantom load by Eversource/NSTAR to BPERC through bills rendered by ISO-NE. B. ISO-NE ISO-NE is an independent system operator functioning as the reliability coordinator, market operator, transmission operator, balancing authority operator and planning authority for the six New England states. ISO-NE’s refusal to correct invoices that misallocated phantom load to BPERC gives rise to this Complaint. ISO-NE is a respondent in this proceeding. C. Eversource Energy Eversource is a public utility company that transmits and delivers electricity, natural gas, and water to customers in Connecticut, Massachusetts, and New Hampshire. On information and belief, Eversource is the parent corporation of NSTAR and owns or controls the Omni system which has wholly, or in part, caused the phantom load allocations that are the subject of this Complaint. Eversource is a respondent in this proceeding. D. NSTAR NSTAR Electric Company is a legacy utility that merged into the Eversource corporate structure in 2015. While it now operates under the Eversource brand, NSTAR remains a distinct legal entity and continues to serve as the Assigned Meter Reader and Host Participant for certain load zones in Massachusetts, including the NEMA and SEMA zones. This legal distinction is material because many or all of the erroneous load assignments and billing discrepancies affecting BPERC stem from NSTAR’s role in implementing and reporting data through Eversource’s 4Page 45 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 systems, particularly following the rollout of the Omni billing system in mid-2024. NSTAR is a respondent in this proceeding. III. FACTS 1. On information and belief, in mid-2024, Eversource and NSTAR implemented a new IT software system known as “Omni” to be used for billing purposes. 2. Historically, prior to 2024, meter errors on the ISO-NE system were relatively few in number. From 2019 to 2022, meter data errors ranged from four per year to 15 per year. See Exhibit 29, at 1. 8 3. In 2024, meter data errors and related RBAs increased to 117 per year. Eversource and NSTAR alone accounted for 92 out of 117 errors. See Exhibit 29, at 2. 4. The errors associated with the implementation of Omni by Eversource/NSTAR related at least in part to misallocations of load to retail suppliers. The existence of the errors was sufficiently widely known that the Massachusetts Department of Energy Resources (“DOER”) modified its guidance to retail suppliers filing 2024 RPS/APS/CPS/CES compliance forms to take the anticipated corrections by Eversource into account in completing their compliance forms. See Exhibit 28, at 1. 5. As discussed more fully in the Affidavit of Darlene Fernandez on behalf of BPERC (attached hereto as Exhibit No. 1), BPERC timely filed objections each month to phantom load allocations by Eversource/NSTAR. Specifically, BPERC timely filed disputes to the inaccurate load allocations for August 2024 (35,000 MWh)(filed January 14, 2025); September 2024 (24,000 MWh)(filed February 17, 2025); October 2024 (20,000 MWh)(filed March 14, 2025); November 2024 (20,000 Mwh)(filed April 13, 2025); and December 2024 (11,000 MWh)(filed May 13, 8 The 2023 total number was 33, as Exhibit 29, at 1 shows. 5Page 46 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 2025). See Exhibit 1, at ¶¶ 8-13. Throughout this time frame, BPERC attempted to discuss this issue with Eversource/NSTAR. See Exhibit No. 9. Throughout January, February and March 2025, BPERC requested access to additional backup data from Eversource/NSTAR. Id. These requests appear to have been unmet. Id. 6. In May, June, July and August of 2025, as Ms. Fernandez explains, BPERC continued to request additional explanation from Eversource/NSTAR without receiving definitive answers. Exhibit No. 1 at ¶¶ 14-17. 7. On September 3, 2025, Ms. Fernandez reports that she again reached out to Eversource/NSTAR, this time to request an explanation. Id. at ¶ 18. While the corrections to the phantom load allocations BPERC had protested for months in the NEMA zone had started to be made, new phantom load allocations had appeared for the first time in the SEMA zone. Id. 8. Eversource/NSTAR promised to look into the issue on September 9, 2025. Id. at ¶ 9. BPERC submitted an RBA to ISO-NE on September 12, 2025 seeking relief from 20. the following inaccurate load allocations: • • • July 2024 overstatement of approximately 45,000 MWh – Case # 00106594 August 2024 overstatement of approximately 49,000 MWh – Case # 00106595 September 2024 overstatement of approximately 47,000 MWh – Case # 00106596 Id. at ¶ 21. 10. On September 15, 2025, ISO-NE denied the disputes on the 11-month resettlement volumes. The ISO’s transmittals stated that the “ISO Billing Policy does not allow reconciliation due to metering changes after the final settlement. If there are discrepancies after the final settlement, the meter readers and asset owners must resolve them outside of the ISO settlement”. Id. at ¶ 23. See Exhibit Nos. 25, 26, and 27. 6Page 47 of 212
Document Accession #: 20251014-5331 11. Filed Date: 10/14/2025 Under the terms of the ISO-NE tariff, a Host Participant or Host Utility is defined as “a Market Participant or Governance Participant transmission or distribution provider that reconciles the loads within the metering domain with OP-18 compliant metering.” ISO-NE Transmission, Markets and Services Tariff, General Terms and Conditions, Section 1 (Definitions). 12. Under the terms of the ISO-NE tariff, an Assigned Meter Reader “reports to the ISO the hourly and monthly MWh associated with the Asset. These MWh are used for Settlement. The Assigned Meter Reader may designate an agent to help fulfill its Assigned Meter Reader responsibilities; however, the Assigned Meter Reader remains functionally responsible to the ISO.” ISO-NE Transmission, Markets and Services Tariff, General Terms and Conditions, Section 1 (Definitions). 13. Market Rule 1 Accounting Manual M-28, Section 5.2 imposes on the Assigned Meter Reader and Host Participant the duty to engage in “prompt reporting of any discovered metering, calculating, or reporting errors with respect to an asset to the ISO and the Market Participant(s) owning or having rights to the asset.” 14. Eversource and NSTAR functioned at all times relevant to this Complaint as either the Assigned Meter Reader or the Host Participant or both. 15. As an Assigned Meter Reader and/or a Host Participant, Eversource and NSTAR were subject to the requirements of Market Rule 1 Accounting Manual M-28, Section 5.2, as noted above. 16. BPERC alleges, in light of the facts summarized in paragraphs 1-10 above, and as is discussed in detail in Exhibit No. 1, the Affidavit of Ms. Fernandez, that the actions of 7Page 48 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 Eversource/NSTAR described in this Complaint did not meet the requirements of Section 5.2 of Market Rule 1 Accounting Manual M-28. IV. REQUESTED RELIEF First and foremost, BPERC seeks nullification of ISO-NE invoices that assign to it payment obligations associated with 45,000 MWh of phantom load in July 2024, 49,000 MWh of phantom load in August 2024, and 47,000 MWh of phantom load in September 2024. For its part, BPERC seeks relief from charges that are unjust, unreasonable, unduly discriminatory and factually unsupported. BPERC does not request a market-wide remedy or contend that one is necessary to address the problems raised in this Complaint. 9 V. THE ISO-NE TARIFF SHOULD NOT BAR THE RELIEF REQUESTED OR LIMIT THE COMMISSION’S CONSIDERATION OF THIS CASE. This is not a typical “meter data error.” The ISO-NE tariff defines a “meter data error” as “an error in meter data on an invoice issued by ISO-NE after the completion of the Data Reconciliation Process as described in the ISO New England Manuals and section III.3.8 of Market Rule 1”. ISO-NE Tariff Section I.2.2 (Definitions). The EDI data upon which ISO-NE bills its customers is not at issue in this matter. The issue is not that the meters are broken or dysfunctional or poorly calibrated. The cause is not the meter itself but the Eversource/NSTAR system that tracks and reports load responsibilities and the BPERC at the same time would not object to a market-wide remedy consistent with the ISO-NE tariff and FERC policy. 9 8Page 49 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 impact of that system on the ISO-NE invoicing process. The specific error at issue in this case creates a discrepancy between the EDI data used for customer billing purposes and the ISO-NE invoices. This discrepancy creates the potential that the data errors at issue may create winners and losers. This issue should be addressed under the procedures of the ISO-NE Billing Policy as opposed to Market Rule 1, given the unique facts of this case. Treating this issue as if it were a one-off meter misalignment results in substantial injustice. It is flatly inequitable to assign millions of dollars to a retail market participant simply because the incumbent utility has adopted a software system that is not functioning properly, leading to incorrectly assigned load obligations or The requirements of the ISO-NE billing policy have been met. The RBA has been presented to ISO-NE as required, and has been denied. This complaint has been filed within the required 20 business days. The dispute resolution provisions of Section 1.6 of the Markets and Services Tariff should not delay or prevent the filing of this Complaint. While that provision generally requires a sixtyday period of good faith negotiations, that provision does not apply to cases in which “a party identifies exigent circumstances reasonably requiring expedited resolution of the dispute by the Commission or a court or agency with jurisdiction over the dispute.” Exigent circumstances exist here because under the terms of Section 6.3.6 of ISO-NE’s billing policy, ISO-NE’s denial of the 9Page 50 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 RBA will be final unless challenged by, inter alia, a complaint filed with the Commission within 20 business days. 10 VI. THE COMMISSION’S DECISION IN LIBERTY POWER IS INAPPLICABLE TO THIS CASE. In Liberty Power Holdings, LLC v. Eversource Energy Co., 172 FERC ¶ 61,031 (2020), the Commission denied a complaint in which a market participant challenged a past-period load allocation to it by Eversource. Liberty argued that it had no opportunity to correct an erroneous load allocation and no notice of that error. The Commission found that the specific dispute then at issue which involved the date on which Liberty became responsible for the load at issue was deemed to be a Meter Data Error subject to the dispute resolution procedures of Market Rule 1 and Manual M-28 and not Section 6.3.6 of the ISO-NE Billing Policy in part because Liberty in fact had multiple opportunities to detect and correct the alleged error during the allowed time period. Again, the issue was when Liberty’s load allocation took effect, . This case presents different facts in virtually every respect. In Liberty, Eversource was able to show that it had in fact provided Liberty with timely notice of the error at issue. Here, although Eversource/NSTAR was subject to the duty to notify both ISO-NE and BPERC of the errors at issue promptly under the ISO-NE Market Rules, Eversource/NSTAR did not do so or were not able to do so because of issues with the Omni system. BPERC had no actual notice of the last-minute shift of phantom load from NEMA to SEMA until RBA Resettlement volumes The relevant procedure provides a potential alternate path for an appeal through a AAA approved arbitration proceeding; however, BPERC seeks alternative relief in the form of a waiver of the ISO-NE tariff provisions, which would fall well outside the jurisdiction of the AAA arbitration. As a result, the only practical forum in which BPERC can pursue its issue is the Commission. 10 10Page 51 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 were received. BPERC attempted without success for months to seek an explanation from Eversource/NSTAR for the repeated errors in load allocation it faced. None was provided on a timely basis. To this day, Eversource/NSTAR have still not provided a detailed explanation. This dispute is the result of a known significant systems failure. Leaving that failure uncorrected and unexplained is unwarranted. BPERC still does not know how many times during July to September 2024 the load may have been inflated. Further, as BPERC alleges, Eversource/NSTAR failed to comply with the requirements of Section 5.2 of Manual M-28 by not providing prompt notice to BPERC of the disputes at issue. The strict timelines in Manual M-28 assume that the market participants are adhering to those responsibilities. If they are not or if they cannot comply with the requirements due to systems issues, and if the disputes do not involve meter calibration or accuracy (as here) the general billing dispute resolution policies should apply. The Liberty decision is inapplicable here. 11Page 52 of 212
Document Accession #: 20251014-5331 VII. Filed Date: 10/14/2025 IF THIS CASE IS SUBJECT TO THE PROCEDURES IN MARKET RULE 1 AND MANUAL M-28, THE 101-DAY LIMIT ON MAKING CORRECTIONS SHOULD BE WAIVED AS NECESSARY TO ADDRESS AND CORRECT A KNOWN SYSTEMS ERROR. If, notwithstanding the foregoing, the Commission determines that this dispute is presumptively subject to the dispute resolution procedures applicable to Meter Data Errors under Market Rule 1 and Manual M-28, BPERC requests that the Commission waive the 101-day limit on making corrections to permit correction of a known external systems error (specifically the assignment of phantom load by Eversource/NSTAR). Good cause exists to grant this request. The Commission has granted waiver of tariff provisions where: (1) the applicant acted in good faith; (2) the waiver is of limited scope; (3) the waiver addresses a concrete problem; and (4) the waiver does not have undesirable consequences, such as harming third parties. 11 BPERC has acted in good faith. In the process of integrating new information management systems, transitional issues can occur, warranting equitable adjustment by the Commission.12 Further, BPERC has exercised appropriate due diligence. BPERC timely objected to each instance of phantom load and sought explanations and related data on an ongoing basis. BPERC thought it had secured a correction of its issues; however, at the last minute, a new and unexplained issue arose in a different zone, saddling BPERC with millions of dollars in costs for services it did not take. The waiver at issue is of limited scope; it seeks only to fix a known and measurable error associated with a specific cause. The waiver also addresses a concrete defined problem: removing See, e.g., Citizens Sunrise Transmission, LLC, 171 FERC ¶ 61,106 at P 10 (2020). The Commission has, for example, previously waived penalties under the CAISO tariff caused in part by issues associated with changes to utility information management systems. See, e.g., Direct Energy Business Marketing LLC v. CAISO, 186 FERC ¶ 61,228 at PP 13-15 (2024). 11 12 12Page 53 of 212
Document Accession #: 20251014-5331 Filed Date: 10/14/2025 phantom load and ensuring that correct bills are rendered reflecting the services parties actually receive and provide. The waiver also does not cause undue harm to third parties. Ignoring a dispute of this type would undermine the equitable jurisdiction of the Commission. For example, if a small C&I customer in ISO-NE received the power bill of a data center two counties away on the 101st day of the ISO-NE challenge period, would ISO-NE’s interest in finality outweigh the interests of the C&I customer who mistakenly was billed for service it never took? BPERC seeks only relief from charges it should not have borne in the first place for services it did not and could not offer. BPERC requests no market-wide remedy. If any other party should contend that others should bear those charges in some amount, BPERC submits that the prospect of doing so would not constitute “harm” for purposes of assessing the waiver request. The Commission has, for example, permitted via waiver NYISO to correct past period errors in its computation of the ACA charge to increase the cost allocation to some participants and decrease it to others to correct a clear error. 13 No party should have a legitimate vested reliance interest in having another pay its bills. That said, If this route is taken, and if the waiver is granted, BPERC requests that the Commission direct ISO-NE to nullify the specified phantom load allocation to BPERC directly or, in the alternative, to remand to ISO-NE to reopen the record to fix the proper billed amount to BPERC for the months of July, August and September 2024 for the SEMA load charges still at issue and 13 New York Independent System Op., 192 FERC ¶ 61,045 at P 19 (2025). 13