Response to Motion No. 040

Response type: Supplemental Filing

Files1

Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Words on different pages
  1. Page 9 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 suppliers.7 Notably, BPERC’s Complaint states that it “would not object to a market-wide remedy consistent with the ISO-NE tariff and FERC policy.”8 NSTAR is eager to resolve concerns about the ISO-NE issued invoices for July, August, and September 2024. However, without the Commission’s intervention, ISO-NE is precluded from resettling the invoices for those months because the time has passed for the Meter Data Error RBA. Accordingly, NSTAR supports BPERC’s request in the Complaint for a waiver to the extent it requests Commission relief from the time limitations in Market Rule 1. To implement this waiver, NSTAR requests that the Commission direct ISO-NE to complete RBAs for July, August, and September 2024 based on updated data to be provided by NSTAR and in accordance with the procedures otherwise set forth in Market Rule 1, and direct that all affected Market Participants be bound to such a resettlement. In the alternative, NSTAR requests that the Commission appoint a settlement judge pursuant to Rule 603,9 and direct ISO-NE, NSTAR, and all affected Market Participants to manually correct the July, August, and September 2024 invoices based on updated data. The requested relief will not only address BPERC’s specific concerns regarding its ISO-NE invoices raised in the Complaint but ensure that all affected suppliers receive 7 NSTAR has notified Massachusetts retail suppliers that NSTAR’s transition to a new billing system and calculations of revised loads submitted to ISO-NE for some suppliers led to load being reported in excess of their actual load, while load for other suppliers was understated. NSTAR has also notified the Massachusetts Department of Public Utilities of these concerns. 8 Complaint at 5, n.8. 9 18 C.F.R. § 385.603. 3
  2. Page 10 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 invoices that are accurate and consistent with the filed rate. As noted above, BPERC does “not object to a market-wide remedy consistent with the ISO-NE tariff and FERC policy.”10 While the time limits in Market Rule 1 provide certainty and finality to the rates charged under the ISO-NE Tariff, the Commission nonetheless has discretion, within the bounds of the filed rate doctrine, to adjust for invoices deviating from the filed rate when, as here, the Meter Data Errors are discovered after the applicable adjustment deadlines. As further discussed in Section III below, if the Commission nonetheless determines that such market-wide relief is barred by the filed rate doctrine, the Commission should dismiss the Complaint in its entirety because any other relief requested by BPERC in the Complaint would thus likewise be barred. I. BACKGROUND A. Eversource Energy and NSTAR Electric Company Eversource is a public utility holding company under the Public Utility Holding Company Act of 200511 that owns and operates over 4,000 miles of transmission facilities in Connecticut, Massachusetts, and New Hampshire, has electric distribution facilities and water delivery systems in each of those states, and serves approximately 4.4 million electric, natural gas, and water customers in New England. NSTAR is a public utility that is a wholly owned subsidiary of Eversource. NSTAR owns and operates Eversource’s transmission and distribution facilities in Massachusetts. NSTAR’s transmission facilities 10 Complaint at 8, n.9. 11 Energy Policy Act of 2005, Pub. L. No. 109-58, § 1262, 119 Stat. 594, 972-73 (2005). 4
  3. Page 11 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 are subject to the operational control of ISO-NE, and transmission services are provided under Section II of the ISO-NE Tariff. NSTAR serves as the Assigned Meter Reader and Host Participant for certain metering domains in Massachusetts. As the Assigned Meter Reader and Host Participant, NSTAR reconciles loads within its metering domains and then reports to ISO-NE the energy quantities associated with each load asset. ISO-NE uses that data for settlement and, ultimately, to invoice and collect payment from Market Participants. NSTAR does not collect or distribute any payments made by Market Participants. B. Load Settlement Process Under Market Rule 1 Following the close of each operating month, ISO‑NE engages in a data reconciliation process during which Market Participants, Assigned Meter Readers, and Host Participants may submit corrected meter data or other eligible settlement inputs. Market Rule 1 provides that “[t]he Correction Limit for meter data and for [ISO-NE] errors in the processing of meter and other Market Participant data is 101 days from the last Operating Day of the month to which the data applied.”12 After the Correction Limit expires, settlement recalculations are generally prohibited unless the error qualifies as a Meter Data Error eligible for an RBA under Section III.3.7(f) and Section III.3.8 of Market Rule 1. Under Section III.3.8, a Market Participant must submit notification of a Meter Data Error no later than the Meter Data Error RBA Submission Limit, i.e., “the date thirty 30 12 Market Rule 1, Section III.3.6.1. 5
  4. Page 12 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 calendar days after the issuance of the Invoice containing the results of the Data Reconciliation Process as described in the ISO New England Manuals and in Section III.3.6 of Market Rule 1.”13 Eligibility for an RBA due to a Meter Data Error also requires: (1) identification and communication of the error to the appropriate party in advance of the Correction Limit where resolution before the deadline was not possible; (2) an error magnitude of at least 1,000 MWh per asset over a calendar month; or (3) for Coincident Peak Contribution values, an average daily error of at least 5 MW for the month.14 If a Meter Data Error qualifies for correction, the Host Participant Assigned Meter Reader submits corrected meter data to ISO-NE within specific deadlines set forth in Section III.3.8(d). After ISO-NE receives corrected meter data in compliance with these provisions, it administers the final settlement based on that data. ISO-NE uses the revised data to recalculate all charges and credits and includes the final settlement in the next invoice. C. Load Settlement Errors In early June 2024, NSTAR implemented a new customer retail billing platform, known as Omni, for its Eastern Massachusetts customers. In the summer of 2024, system and conversion-related defects led to inaccuracies in the load settlement data sent to ISONE. By mid-October 2024, NSTAR addressed those initially-identified defects and sent revised load settlement data to ISO‑NE and Market Participants. In November 2024, 13 ISO-NE Tariff, Section I.2.2 (defining “Meter Data Error RBA Submission Limit”) & Market Rule 1, Section III.3.8(a). 14 Id. Section III.3.8(c). 6
  5. Page 13 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 however, NSTAR identified further defects affecting load reporting for June and July 2024, prompting renewed corrective efforts. NSTAR completed those efforts in March and April 2025, prior to the deadlines for Meter Data Error RBAs for June and July 2024. At issue in this proceeding are two additional later-identified system defects affecting the invoices resulting from the July, August, and September 2024 RBAs. One issue caused customer load to be assigned to the same accounts multiple times. The other issue similarly caused a doubling of customer loads for certain commercial, industrial, and residential customers. The corrections for both issues did not occur until after submittal of the July, August, and September 2024 RBAs. D. BPERC’s Section 206 Complaint On October 14, 2025, BPERC filed the Complaint with the Commission under FPA Section 206 against ISO-NE, Eversource, and NSTAR. In the Complaint, BPERC seeks relief from the invoices issued by ISO-NE based on load allocated to BPERC by NSTAR for July, August, and September 2024. The Complaint alleges that BPERC was “improperly tagged [] with a total of 144,000 MWh of new load, resulting in additional direct costs to BPERC of about $5,935,6723 for the period July-September 2024.”15 BPERC also alleges that, if the Renewable Portfolio Standard (“RPS”)16 obligations related to BPERC’s load are not corrected, it could increase BPERC’s financial impact “by an 15 Complaint at 2 (citation omitted). 16 The Massachusetts RPS requires retail electricity suppliers to provide a minimum percentage of their retail load from renewable energy sources or meet their obligations by purchasing renewable energy certificates or paying an alternative compliance payment. 7
  6. Page 14 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 estimated additional $3,566,372 for a total impact of $9,502,044.”17 BPERC seeks a remedy for itself, but “would not object to a market-wide remedy consistent with the ISONE tariff and FERC policy.”18 II. REQUEST FOR REMEDIAL RELIEF AND ANSWER A. The Commission Should Direct ISO-NE to Correct the Load Settlement Errors. Since discovering the load settlement errors described above, NSTAR has worked with its vendors and IT department to correct the system defects and has implemented enhanced monitoring, validation, and review procedures for load settlement data. NSTAR also has attempted to resolve the load settlement errors.19 However, under Market Rule 1, even verifiable and undisputed Meter Data Errors cannot be corrected if they fall outside the narrowly prescribed conditions and timelines in Section III.3.8, leaving market invoices to reflect inaccurate settlement quantities and charges that differ from the filed rate. Accordingly, NSTAR supports BPERC’s request in the Complaint for a waiver to the extent it requests Commission relief from the time limitations in Market Rule 1. To implement this waiver, NSTAR requests that the Commission direct ISO-NE to complete RBAs for July, August, and September 2024 based on updated data to be provided by NSTAR and in accordance with the procedures otherwise set forth in Market Rule 1, and 17 Complaint at 2. 18 Id. at 8 n.9. 19 In the Complaint, BPERC recognizes that “it has worked with Eversource/NSTAR to attempt to resolve this situation,” “BPERC will continue to do so,” and NSTAR “ha[s] expressed willingness to resolve the load errors that are the subject of this Complaint and ha[s] agreed on the volumes of over-inflated load allocations.” BPERC also noted that it only filed the Complaint “to preclude any claim of waiver of any of its rights.” Id. at 3. 8
  7. Page 15 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 that all affected Market Participants be bound to such a resettlement. In the alternative, NSTAR requests that the Commission appoint a settlement judge pursuant to Rule 603,20 and direct ISO-NE, NSTAR, and all affected Market Participants to manually correct the July, August, and September 2024 invoices based on updated data. B. The Commission Has Authority Under FPA Section 309 to Grant Relief from the Time Limits in Market Rule 1. Eversource and NSTAR recognize that the time limits in Market Rule 1 are part of the filed tariff and are important to provide certainty and finality to the rates charged under the ISO-NE Tariff.21 But the Commission nonetheless has discretion, within the bounds of the filed rate doctrine, to adjust for invoices deviating from the filed rate when, as here, the Meter Data Errors are discovered after the applicable adjustment deadlines. Such correction is essential to ensuring a just and reasonable result and does not contravene any term of the FPA. Indeed, granting the relief sought here would conform to Congress’ articulated purposes and policies; the D.C. Circuit has emphasized, “the primary aim [of the FPA] is the protection of consumers from excessive rates and charges.”22 FPA Section 309 vests in the Commission authority to “perform any and all acts, and to prescribe, issue, make, amend, and rescind such orders, rules, and regulations as it 20 18 C.F.R. § 385.603. 21 The Commission recently re-affirmed the waiver process. Waiver of Tariff Requirements, 193 FERC ¶ 61,135 (2025). As further discussed below, if the Commission finds that the relief requested herein is foreclosed by the filed rate doctrine, it also would preclude the relief sought by BPERC in the Complaint, and any similar relief sought by other Market Participants. 22 Xcel Energy Servs., Inc. v. FERC, 815 F.3d 947, 952 (D.C. Cir. 2016) (“Xcel”) (citations omitted). 9
  8. Page 16 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 may find necessary or appropriate to carry out the provisions of this chapter.”23 Courts have upheld the Commission’s use of this authority in myriad circumstances.24 For example, in a case concerning the discretion to order refunds and impose retroactive surcharges as a remedy to an unjust and unreasonable cost allocation, the Commission found that “under the factual circumstances” present, the equitable considerations warranted refunds to customers allocated excessive costs under the previous cost allocation methodology, even though those refunds would be implemented through surcharges to customers that paid too little.25 The Commission also has allowed the New York Independent System Operator (“NYISO”) to revise prior invoices to correct errors that were the result of NYISO failing to compute compensation in accordance with the filed rate schedule’s rates, terms, and conditions because of software implementation errors.26 The Commission held that “rates are not being changed retroactively, nor is NYISO making refunds. To the contrary, NYISO is attempting to ensure that final bills, as far as possible, conform to its filed rate schedules.”27 23 16 U.S.C. § 825h. 24 See, e.g., Verso Corp. v. FERC, 898 F.3d 1, 10 (D.C. Cir. 2018), (“Verso Corp.”); TNA Merchant Projects, Inc. v. FERC, 857 F.3d 354, 362 (D.C. Cir. 2017); Towns of Concord v. FERC, 955 F.2d 67, 73 (D.C. Cir. 1992); Xcel, 815 F.3d at 954. 25 Michigan Pub. Serv. Comm’n v. Midcontinent Independent System Operator, Inc., 156 FERC ¶ 61,205, at P 51 (2016); aff’d, Verso Corp., 898 F.3d 1. 26 N.Y. Indep. Sys. Operator, Inc., 115 FERC ¶ 61,026, at P 45 (2006). 27 Id. 10
  9. Page 17 of 212

    Document Accession #: 20251212-5233 Filed Date: 12/12/2025 Similarly, the Commission has allowed the California Independent System Operator (“CAISO”) to make price corrections to prevent harm to market participants overcharged due to a software defect.28 It also has allowed CAISO to correct a billing error that occurred at “the very end of the billing process, causing Shell Energy difficulty in meeting the tariff deadline.”29 The Commission noted that it has granted relief of billing statement tariff provisions because “significant injustice would result absent Commission action.”30 The Commission explicitly recognized that, while “the purpose of dispute deadlines is to promote finality, it is also necessary to balance this goal against the need for invoices to be correct in the first place and completed in accordance with the filed rate.”31 Like in those cases, Commission approval of this request for remedial relief will ensure that all Market Participants affected by the July, August, and September 2024 RBAs, including BPERC, are charged the filed rate. Moreover, the fact that time limits on RBAs in Market Rule 1 are considered part of the filed rate does not mean that granting relief of those limits is beyond the Commission’s authority under FPA Section 309. Doing so does not contravene any part of the FPA and there is nothing that limits the Commission’s ability to exercise its authority under Section 309 to grant the requested relief.32 28 See Cal. Indep. Sys. Operator Corp., 147 FERC ¶ 61,111, at P 14 (2014). 29 Shell Energy North America (US), L.P. v. Cal. Indep. Sys. Operator, 153 FERC ¶ 61,307, at P 31 (2018). 30 Id. (citation omitted). 31 Id. 32 Eversource and NSTAR recognize that the Commission has previously denied requests for remedial relief to correct billing errors, including in Southwest Power Pool, Inc., 181 FERC ¶ 61,138, (2022). However, in that case, the Commission had previously denied a request for waiver of the same one-year billing adjustment limitation tariff provision at issue in the request for 11
  10. Page 18 of 212

    Document Accession #: 20251212-5233 C. Filed Date: 12/12/2025 The Commission Should Grant Relief of the Time Limitations in Market Rule 1 in these Circumstances. The Commission’s four-part analysis for waiver requests under Rule 207 and remedial relief under FPA Section 309 supports the instant request. Notably, the Commission recently granted ISO-NE’s request for a waiver of the ISO-NE Tariff and certain provisions of the ISO-NE Billing Policy to enable ISO-NE to not assess and to return a performance payment charge to a Market Participant.33 The Commission found that the circumstances of ISO-NE’s waiver request satisfied the Commission’s four part test, i.e., “(1) the applicant acted in good faith; (2) the waiver is of limited scope; (3) the waiver addresses a concrete problem; and (4) the waiver does not have undesirable consequences, such as harming third parties.”34 Likewise, the four-part test is met here. First, the system errors were inadvertent and made in good faith. As discussed above, the load settlement errors are the result of inadvertent system and software conversion-related defects that emerged during NSTAR’s transition to Omni. NSTAR has worked diligently with its vendors, its IT team, ISO-NE, and Market Participants to remedy any incorrect charges as permitted by the ISO-NE Tariff. NSTAR has also implemented enhanced monitoring, validation, and review procedures for load settlement data to prevent recurrence of these issues. remedial relief under Section 309, a decision upheld by the D.C. Circuit. See Oklahoma Gas & Electric Co. v. FERC, 11 F.4th 821, 833 (D.C. Cir. 2021). The Commission thus reasonably found that “it is inappropriate to exercise our authority under FPA section 309.” 181 FERC ¶ 61,138 at P 22 (citation omitted). No such prior rulings exist here. 33 ISO New England Inc., 193 FERC ¶ 61,084 (2025). 34 Id. P 16 (citations omitted). 12