  1. Page 17 of 43

    that the project was authorized consistent with the relevant PAF and Delegation of Authority. The Second Supplemental Additions are included in the plant additions forecast shown in Schedule B2.1 and B-2.2 of the SFRs, submitted as part of the Rate Application on July 14, 2026. The Third Supplemental Additions present the final project documentation for known and measurable costs incurred by the Company in September 2026, for projects placed in service prior to September 1, 2026, plus 20 projects placed in service through September 30, 2026. The documentation submitted includes the project cover sheet, the project closing report showing a table of the actual charges booked to the job, the PAF and Supplemental Authorization Form, as applicable to the project, along with a copy of the approval screen showing that the project was authorized consistent with the relevant PAF and Delegation of Authority. The Third Supplemental Additions are included in the plant additions forecast shown in Schedule B-2.1 and B-2.2 of the SFRs, submitted as part of the Rate Application on July 14, 2026. 3. The documentary evidence is necessary for the showing of prudence and excluding this documentation improperly cuts off the Company’s right to propose pro forma adjustments specifically recognized by Connecticut case law. PURA should admit the First, Second and Third Supplemental Additions because these documents are directly relevant to the Company’s Rate Application and are critically necessary to the Company in meeting its burden of proof on specific elements of its Rate Application, as well as to ensure that the evidentiary record is complete and consistent with the sworn testimony of the Companies’ witnesses provided on July 14, 2026. The documentation presented in the First, Second and Third Supplemental Additions substantiates the costs incurred for in-service plant additions included in the Company’s Rate Application on a forecasted basis. Under PURA precedent, as affirmed by the Connecticut Supreme Court, the Company cannot prove the prudence of these post-test year capital additions for recovery in this rate case without this documentation. Aquarion Water Company of Connecticut v. Public Utilities -17-
  2. Page 18 of 43

    Regulatory Authority, 352 Conn. 381 (2025) (“Aquarion Water Co.”). The Court’s decision in Aquarion Water Co. is thoroughly on point here. This decision arose from PURA’s final decision in Docket No. 22-07-01, Application of the Aquarion Water Company of Connecticut for an Amendment of Its Rate Schedules, March 15, 2023 (“Aquarion Rate Decision”), wherein PURA stated the following regarding post-test year capital additions: In recognition of these continued investments, the Authority permits utilities to make pro forma adjustments to the test year plant-in-service for a reasonable period of time for “definite, ascertainable expenses maturing or certain to materialize.” The Authority applies the same standard of review to pro forma plant adjustments as it does for test year plant in-service. In other words, the Company must demonstrate that: (1) the plant is in service; and (2) the costs were prudently incurred. The pro forma adjustments must also be “known and measurable” and supported by substantial evidence, with the burden resting on the utility to make such a showing. Aquarion Rate Decision at 16-17. In that case, the Company submitted detailed information on its post-test year capital additions within its SFRs; with discussion of the Company’s decision-making process for capital additions proceeding included in written testimony (of Mr. Lawrence), coupled with detailed spreadsheet listings of projects produced through discovery for post-test year projects placed in service. However, PURA rejected all of this documentation, finding this information to be “deficient,” on the basis that the evidence allegedly did not “explain[s] why the expenditures were made, which options were considered, how the costs were managed, or any of the other factors that would allow the Authority to assess the ‘good faith and reasonableness’ of the management decisions related to the expenditures.” Aquarion Rate Decision at 18-19 (emphasis added). Specifically, PURA disallowed recovery of over $60 million of “used and useful” capital investment, stating that: By failing to submit material evidence as to the prudency of capital additions occurring between September 1, 2022, and December 15, 2022, the Company has failed to meet its burden demonstrating that these capital costs satisfy the standard for a pro forma adjustment to rate base. -18-
  3. Page 19 of 43

    Id. at 19 (emphasis added). In its decision in Aquarion Water Co., the Court reviewed PURA’s decision on the project documentation in detail, first acknowledging that “ratemaking is a prospective endeavor, in which PURA makes reasoned estimates about future events to establish a rate that ‘reflects a prospective anticipation of what rate will be necessary adequately to compensate’ the utility. 352 Conn. 381, at 390-391, citing, Office of Consumer Counsel v. Dept. of Public Utility Control, 246 Conn. 18, 23–24 (1998). The Court further acknowledged that “the test year may be adjusted ‘forward for a reasonable period of time’ to permit the utility to recover ‘definite, ascertainable expenses maturing or certain to materialize during that period of time.’” Id. at 391, citing, Connecticut Natural Gas Corp. v. Public Utilities Commission, 29 Conn. Supp. 379, 390–91 (1971). In summarizing the reasoning for PURA’s decision to disallow the post-test year plant additions, the Court expressly referred to PURA’s finding that “[n]one of the evidence explains why the expenditures were made, which options were considered, how the costs were managed, or any of the other factors that would allow [PURA] to assess the good faith and reasonableness of the management decisions related to the expenditures.” Id. at 396 (emphasis added). Ultimately, the Court hinged its conclusion affirming PURA’s decision on that exact statement from PURA’s decision, holding that “Lawrence's narrative testimony constitutes a discernible, articulable difference in the kind and quality of evidence submitted in support of the test year and preapplication pro forma plant additions…,” whereas, “the data provided with respect to the post-application pro forma plant additions can reasonably be seen as lacking the particularity and detail necessary to ascertain exactly why the costs were prudently incurred” Id. at 401-402 (emphasis added). In footnote 15 of its decision, the Court expanded on that finding stating that: -19-
  4. Page 20 of 43

    Aquarion contends that there is no principled, coherent distinction between the evidence submitted in support of the different categories of plant additions because Lawrence's prefiled testimony described Aquarion's four stage process for planning, designing, and delivering infrastructure projects, and addressed future plant additions beyond August 31, 2022. We reject this claim as grounds for reversal because Lawrence's general descriptions of Aquarion's four stage process for water infrastructure projects and five year capital investment plan are untethered to the facts and lack the particularity and detail that accompanied the narrative description of the major test year and preapplication pro forma plant additions. 352 Conn. 381, 402, fn.15 (emphasis added). Thus, the Court’s decision essentially locks in the need for the Company (or any company filing a rate case) to submit all of the project documentation submitted in the First, Second and Third Supplemental Additions to provide the facts with “particularity and detail” that only the project-specific Project Authorization Forms and associated documentation can provide. It is not possible for the Company to provide this detail in testimony for hundreds of projects over a multiyear period. In testimony, the Company cannot explain the details of every one of hundreds of projects, providing the reasons “why” the project was undertaken and/or alternatives considered. Only the project documentation can convey that level of detail, making the project documentation necessary for a showing of prudence in relation to a Rate Application that includes proposed posttest year adjustments. Moreover, the Court has found that PURA is within its discretion to find that – without that level of detail and documentation – PURA can flat-out disallow those project costs for a failure of documentation. Conversely, under applicable case law for discovery, a party is required to produce discovery documents if they are “material and necessary to [an] action.” Dotson v. Hartford Roman Catholic Diocesan Corp., No. CV106012742S, 2011 WL 1021745, (Conn. Super. Ct. Feb. 17, 2011) (citing Berger v. Cuomo, 230 Conn. 1, 7 (1994)). At this point in the proceeding, there would be no bar on a party requesting these documents for production to the record and, in fact, the parties (including PURA) are making requests that involve the production of substantial -20-
  5. Page 21 of 43

    amounts of documentation, which the Company is responding to with all due diligence. The only difference with respect to the First, Second and Third Supplemental Additions is that the Company is submitting documentary evidence, on its own accord, consistent with its burden under Conn. Gen. Stat. § 16-22, rather than being asked to produce the documents. However, the documentation remains necessary and appropriate for entry to the record at this point of the proceeding to inform the resolution of issues presented to PURA in the Company’s Rate Application. Absent these documents in the record, the Company’s due process rights will be impaired and its fundamental right to a fair proceeding will be affected. Consequently, well-established ratemaking procedures allow the Company to include pro forma adjustments to the test year in its Rate Application, including “known and measurable” costs incurred “forward for a reasonable period of time,” where those costs are “definite, ascertainable expenses maturing or certain to materialize during that period of time.” Aquarion Water Co., 352 Conn. 381, at 390-91. In this case, the Company’s capital costs incurred between January 1, 2026 and December 31, 2026, for projects placed in service prior to December 31, 2025, or during calendar year 2026, meet this definition. Because these costs are incurred after the end of the test year in relation to projects placed in service during the test year, or projects that are placed in service during the rate proceeding and presented in the Rate Amendment on a forecasted basis, the project documentation is not fully available at the time of the initial rate application, or even within 30 days of the rate application. Based on PURA’s findings in the Aquarion Rate Decision, and the Connecticut Supreme Court’s validation of those findings, the Company cannot prove the prudence of those post-test year adjustments – nor that the post-test year costs are “known and measurable” -- without the detailed project documentation, including PAFs, that describe why projects were undertaken, what alternatives were reviewed, what the benefits of the projects may be, and how much cost was actually incurred. -21-
  6. Page 22 of 43

    As a result, preventing the submission of this evidentiary documentation effectively terminates the Company’s right to propose proper, close-in-time, post-test year adjustments, although these adjustments are necessary to incorporate used and useful, prudently incurred capital additions in rates, causing a tangible loss of value to the Company that cannot ever be restored due to the fact that in-service capital projects will continue to depreciate until such time that the costs are incorporated into base rates in a future rate proceeding. Accordingly, there is good cause for PURA to admit the project documentation supporting its forecasted post-test year adjustment. 4. PURA has previously found that the admission of evidence can properly occur during the discovery period. With respect to the timing of the submission of evidentiary exhibits within the context of a rate proceeding, PURA has previously held that: 11 [R]equests to submit substantial new evidence during or just before hearings disrupts the administrative process and may prejudice the rights of parties and intervenors…. Moving forward and for purposes of administrative efficiency and fairness, parties and intervenors should submit evidence during the discovery period to permit sufficient time for review by other parties and intervenors. Absent good cause, the Authority may deny untimely requests to submit evidence into the record. Id. at 2 (emphasis added). With respect to timing and volume, the October 23rd Correspondence from PURA asserts that, in this case, “the scale of the underlying application” and “the magnitude of the Company’s proposed amendments,” require PURA to reconsider its past practices and implement a more orderly process to ensure fundamental fairness for all parties and intervenors, asserting that the “15,000 pages” of supplemental project documentation is in addition to “300,000 pages” already submitted by the Company as part of its Rate Application, implying an undue burden to PURA 11 In its Ruling on Motion No. 61, PURA noted that it was allowing the proffered exhibits because parties and intervenors waived objection to the exhibits “during the February 17, 2023 hearing,” which was the first evidentiary hearing day in Docket No. 22-08-08. -22-
  7. Page 23 of 43

    and other parties to the proceeding. October 23rd Correspondence at 4. However, a critical point here is that PURA has been conducting prudence reviews for the Electric System Infrastructure (“ESI”) factor on an annual basis. This has had a profound effect of limiting the project documentation that is necessary for the parties to review in this proceeding. Specifically, Exhibit CLP-Exhibit-4 lists 1,671 unique projects, placed in service through December 31, 2025, of which approximately 83% of the projects, or 1,390 projects were already subject to a prudence review and included in rate base in the annual contested ESI proceedings. This means that the bulk of the “300,000 pages” referenced by PURA have already been submitted to PURA in past proceedings in relation to capital projects already deemed prudent. In fact, only 281 projects placed in service prior to December 31, 2025, with project costs incurred prior to that date, require original review in this docket. In addition, the documentation submitted as part of the First, Second and Third Supplemental Additions encompasses only 120 projects included in the forecast of plant additions and placed in service in the period January 1, 2026, through September 30, 2026. The remainder of the project documentation pertains to projects placed in service prior to the end of the test year, December 31, 2025, in circumstances where the Company has incurred “carryover costs” during calendar year 2026, which means that PURA is already contemplating the prudence review on these projects as part of the test year. Although there is no question that resources will need to be applied to the review of this documentation on a limited time frame by PURA, OCC and potentially other participants in the docket, the Company stands ready to do whatever it can to facilitate that review. Moreover, determining the prudence of capital projects is the central proposition for a distribution rate proceeding, particularly where PURA has made a determination that prudence cannot be proven unless the applicant provides project documentation with sufficient “particularity and detail” regarding the specifics of each individual project undertaken by the -23-
  8. Page 24 of 43

    Company each year. 12 Accordingly, a practice of using motion filings to submit supplemental evidence that all parties can comment on, is warranted and appropriate. ⇒ Direct Pre-Filed Testimony of OCC With respect to other parties, it is important to note that, on October 21, 2026, OCC submitted direct pre-filed testimony providing recommendations on the Company’s proposal in its Rate Application to recover “Planned Plant Additions in 2026 and 2027” (Direct Testimony of Nikhil Balakumar, at pages 90-92). There, among other reasonable critiques, OCC’s witness testifies that: PURA should therefore include in rate base only plant completed, in service and documented through the Company’s final supplemental filing before the record closes, and exclude all forecasted additions. My recommendations on plant will be finalized based on that filing. (page 92, emphasis added). The Company appreciates OCC’s accurate acknowledgement of the Company’s proposals associated with its Rate Application and the Company assumes that OCC and its witness are relying on PURA practice and precedent in all recent rate cases to accept supplementary documentation during the discovery phase of the docket. This leads to two important points. First, the Company’s filings on September 15, 2026 and October 19, 2026, did allow OCC to obtain a portion of the project documentation prior to its filing of direct testimony, which the Company hopes assisted in the preparation of OCC’s direct testimony. Second, the Company has the opportunity to file rebuttal testimony on November 18, 2026, and it is squarely within the 12 352 Conn. 381, 402, fn.15. The Company does not challenge the necessity of this review. The production of project documentation is also a rigid requirement in Massachusetts and disallowances have occurred for a failure to produce the necessary documentation. However, it does mean that PURA’s rate-case processes have to be structured to provide for this review, while preserving the rights of all parties, including PURA and the Company. A Motion to Admit Evidence is the proper method for balancing these interests. -24-
  9. Page 25 of 43

    Company’s procedural rights to submit the First, Second and Third Supplemental Additions as part of its Rebuttal testimony in response to OCC, which it is planning to do. Specifically, in response to OCC’s testimony, the Company is planning to exercise its existing procedural due process and statutory right to submit rebuttal testimony addressing OCC’s recommendation that “only plant completed, in service and documented” through this proceeding be included in base rates, which the Company plans to limit in rebuttal testimony to plant additions through December 31, 2026, rather than further on through the proceeding. The Company has decided that it will not file any further supplemental additions after January 15, 2027 (for project documentation through December 31, 2026), in order to make sure all documentation is on the record prior to the start of evidentiary hearings. 13 This schedule will assure that there is time for cross-examination of the Company’s project documentation at some point during the evidentiary hearing phase. Lastly, PURA’s October 23rd Correspondence states that it is necessary for the Company to file a motion demonstrating good cause for the admission of the supplemental exhibits because “parties and intervenors may have reasonable concerns with preparing their case-in-chief and how these supplements may impact their review of the Company’s Application in relation to the docket schedule.” October 23rd Correspondence at 5. However, no party or intervenor other than OCC has raised any issue with the Company’s capital additions in their “case-in-chief.” Of course, all parties and intervenors, as well as PURA, have the right to cross-examine the Company on any and all of these materials, even if not referenced in testimony comprising their “case-in-chief.” If PURA does not adopt the PBMRP in the final result, or does not otherwise provide for recovery of capital additions after January 1, 2027, the Company’s expectation is that it will need to file a sequential rate case to incorporate those plant additions for 2027 into rates. Either way, the Company recognizes that the administrative efficiency of this proceeding necessitates a cut-off of December 31, 2026 for production of evidence supporting the post-test year adjustments listed in the Rate Application. 13 -25-
  10. Page 26 of 43Match

    B. Barring the Entry of the Supplemental Documentation Contravenes the Company’s Due Process Rights for Several Reasons. In its October 23rd Correspondence, PURA acknowledges that the Company has submitted the documentary evidence to the record as part of the Company’s efforts to meet its burden under Conn. Gen. Stat. § 16-22 “by providing sufficient documentation to support its proposed Application.” October 23rd Correspondence at 5. However, PURA characterizes that effort as the Company “choos[ing] to increase the scope of evidence after the initial filing date” and that the parties and intervenors “must increase their scope of review without a corresponding increase in the amount of time afforded to do so.” Id. The Company understands and acknowledges this concern, although the actual scope of the review associated with the Company’s documentation is not as broad as might be imagined given the impact of the ESI prudence reviews (discussed below). As noted above, the supplemental filings add only 120 projects to the 281 projects commenced and completed prior to December 31, 2025, for review in this proceeding, totaling 401 capital projects (netting out the projects already subject to a prudence review through the ESI mechanism). As noted above, the total number of projects placed in service prior to December 31, 2025, was approximately 1,671 projects -- resulting in circumstances where only approximately 25% of this amount is within the scope of this proceeding. In addition, PURA acknowledges that it “has admitted supplemental evidence offered by the applicant through the close of the evidentiary record, without requiring or ruling on motions,” in previous cases, which it not only has done for Eversource, but also has done in all of Avangrid’s recent rate cases – as it should. Id. at 4. In addition to the Yankee Rate Decision, PURA has consistently allowed documentation of capital projects completed between the test year and evidentiary hearings in all its recent rate decisions. This practice enables utilities to provide necessary support for pro forma adjustments to Test Year plant-in-service, provided the additions are used and useful and the costs prudently incurred. These dockets include Docket No. 24-10-26-

As listed on the current system

Motion No. 117 11/13/2026 (CL&P dba Eversource Energy) - Motion to Admit Evidence [26-05-10]

This filing on the current system (opens in a new tab)