    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 7 of 27 incremental capital additions between rate cases, the pressing need for incremental revenue support was mitigated. Without the ability to capture that sales growth, and combined with the absence of an ongoing revenue support mechanism such as an F Factor taking effect on Month 1 of Rate Year 1, the Company would not be in a position to commit to a stay-out of any duration. This is because the Company would never be in a position to cover its cost of service (inclusive of its authorized cost of capital) because its rates would be set on a historical level of plant additions, despite the fact that its capital expenditures are higher than historical levels of depreciation, and because revenue decoupling ensures that even if load growth exists (and even if such load growth is enabled by the Company’s increased level of capital expenditures) the Company is unable to retain additional revenues contributed by new customers, or new load. 4) Positive #4: CT-Bar was designed to align capital revenue support with the DSP. Ignoring its deficiencies, the CT-Bar’s connection to the Distribution System Plan (“DSP”) constituted an essential link between ongoing system investments necessary to meet the objectives of the DSP with the revenues necessary to support those investments. Throughout Docket No. 21-05-15RE01, the Company advocated strongly for clearly defined linkages across all three tracks (RE01, RE02 and RE03), including proposing what would be the final technical session touching upon revenue requirements, in which those linkages were discussed. The Company’s F-Factor is similarly aligned with the capital investment forecast provided in this proceeding for the DSP. The Company’s capital investment forecast serves as the basis for a cap on the level of investment for the F-Factor. Unworkable Features of PURA’s RE01-PFD: 1) Negative #1: No recovery of cost of capital in the revenue requirement for capital investment between rate cases. The single-most problematic feature of the CT-Bar was its intentional exclusion of the cost of capital associated with completing capital plant additions to the benefit of customers. Costs of capital are real costs of providing electric distribution service to customers in the State of Connecticut (or anywhere) and are recognized in statute. Although the cost of capital may be a more challenging cost to conceptualize, it is nonetheless as real as vegetation management, insurance, customer service, or any other cost of service. Cash is not free, a fact arising from its scarcity. Fundamentally, capital markets are where people, banks, corporations and other institutions provide their surplus of cash -- which is limited, to those entities that have cash needs -- which are generally unlimited. Consequently, and unsurprisingly, those entities providing the cash for some period of time expect to be compensated for providing it, thus establishing real cost to acquire capital. The Company, operating in the capital-intensive industry of regulated utilities, is one of those entities that needs to acquire cash to operate its business. As annual capital investments regularly exceed its net cash from operations (i.e. cash from customers), the Company must look to other sources to fund those investments. Those sources are the debt and equity investors supplying the cash to capital markets. This means the Company must compete with ALL other entities participating in those markets. It is simply not possible for the Company to go to those markets and demand cash for free (or for below-market rates, relative to market expectations of risk and reward) when other entities participating in those capital markets offer adequate compensation for the use of funds over time. Therefore, there is a real and tangible cost to acquiring that capital. Please refer to the Company’s pre-filed cost of capital testimony for in-depth discussion of the cost of capital. Allco Exhibit CL-1 — Page 8 of 29
  2. Page 24 of 78Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 8 of 27 The Company provided extensive analysis and discussion on the cost of capital throughout Docket No. 21-05-15RE01, including specifically as it relates to CT-Bar. PURA’s treatment with respect to goingin revenue requirements as well as any ongoing capital revenue support mechanism, such as CT-Bar, is paramount to whether the Company, with effective management and sound decision-making, has the opportunity, but not a guarantee, to cover its cost of service to customers, and to earn its allowed return. The absence of the cost of capital from the CT-Bar, particularly in the present environment where significant increases in the level of necessary system investments are expected, prevents the Company from having any practical opportunity to commit to a stay-out to avoid the next rate case. As discussed in the Company’s response to OCC-435, based on the Company’s current assessment of system investment needs in the near future, the revenue requirement associated exclusively with the cost of capital pertaining to future capital additions (excluding GET and Uncollectible) would amount to an incremental $15.6 million for Rate Year 1; an incremental $32.8 million for Rate Year 2; an incremental $36.4 million for Rate Year 3; and an incremental $39.5 million for Rate Year 4, or $124.1 million in total. This means that -- even if 100% of those future plant additions were only partially supported with CTBar revenues (i.e. revenue covering depreciation expense and property taxes only); and even if the Company’s future cost of service otherwise was 100% supported with rates; and even with perfect operational decision making -- the Company would still need to find $124.1 million of annual savings by Rate Year 4 in order to offset the loss of revenue associated with carrying costs on incremental investment over the term of the PBMRP, which would be necessary to commit to a stay-out term. For perspective, the total O&M expense included in the Company’s cost of service filed in this proceeding is $547.5 million. Thus, to earn its authorized ROE, all else equal, the Company would have to generate cost savings amounting to $124.1 million, or nearly 23%, of its Rate Year O&M level by Year 4, to offset the impact of the accumulating carrying costs on the incremental capital additions completed on the system after base rates are set in this case. This is nearly 34% of operating expense, excluding vegetation management and storm restoration costs, which is a very substantial proportion of the cost of service. For example, the amount of $124M is nearly two-thirds of the Company’s labor and labor-related operating expense, or 60% more than the entire vegetation management program. It simply is not possible for the Company to cut this level of O&M expense without grossly debilitating the Company’s ability to provide service to customers. In fact, it is not plausible to expect that the Company could generate even 10% in annual incremental O&M savings in the face of 2-3% annual inflation and, as a result, the Company could not agree to a stay out under circumstances where there is no recovery of the cost of capital on incremental investment over the PBMRP term. Moreover, even if the Company were somehow able to find such remarkable cost savings, the going-in revenue requirement of the subsequent multi-year rate plan would capture those cost savings. Assuming continuation of the same PBR framework and required system investment, the Company would again be in the position of having to find an additional 34% of O&M savings (i.e. more than 60% cumulatively from Rate Year 1) in order to sustain itself over the next PBR term. Clearly, a framework that does not provide revenue supporting the full cost of incremental investment over a four-year period, as well as the next four-year period, is not a plausible or lasting framework. Thus, exclusion of the cost of capital from a capital support mechanism in an environment in which significant increases in capital investments are expected all but ensures the Company has no realistic opportunity to survive the PBR term without a critical need for a rate case to realign costs and rates. Consequently, the overall framework as outlined in the REO1-PFD had no practical chance of sustaining the Company financially for the four-year term, Allco Exhibit CL-1 — Page 9 of 29
  3. Page 25 of 78

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 9 of 27 nor would the Company have been able to even agree to a stay-out. To address this indelible flaw, the Company’s proposed PBMRP in this docket is designed to produce the revenue necessary to support ongoing system investment through the F-Factor, which calculates a revenue requirement inclusive of the costs of capital unlike the CT-Bar, while preserving the customer benefits and inherent incentives of a PBR plan. 2) Negative #2: Exclusion of cost of removal from the revenue requirement on capital investment between rate cases. CT-Bar excluded the cost of removal, which is a real cost for all utilities. As a simple example, to install a new utility pole where there is an existing one that needs replacement, the Company must first remove the existing utility pole. That cost is separate and distinct from the cost of the utility pole itself; yet, similarly recovered (as an estimate) over the life a utility pole. The Company’s capital investment forecast in the present docket includes approximately $136 million of cost of removal for January 1, 2026 through June 30, 2028, and approximately $60-70 million per year thereafter. A total of $60-70 million in annual investment equates to pre-tax cost of capital of $6-7 million annual incremental revenue requirement (e.g. $6 million year 1, $12 million year 2, $18 million year 3, etc.). The CT-Bar revenue requirement intentionally excluded this component of the capital investment revenue requirement. The Company’s proposed F-Factor calculation properly restores this component to the rate base computation. 3) Negative #3: Depreciation expense is used as a reduction to plant additions rather than to total rate base, consistent with fundamental ratemaking principles. CT-Bar’s calculation treats depreciation expense as a net against plant additions. Although the Company appreciated that PURA found it important to capture ongoing depreciation expense in the annual revenue requirement calculations, the overall execution of the computation was not correct. The Company’s FFactor corrects for this methodological error. Please refer to the example below outlining the mathematical problem: ($ Millions) 1 Correct treatment of depreciation's accumulation in rate base 2 Rate Base RevReq 3 Year 1 Year 2 Year 1 Year 2 4 Plant Additions $1,000 $1,000 5 Cumulative Gross Plant $1,000 $2,000 x 3.6% Depreciation $36.0 $72.0 6 Accumulated Depreciation -$300 -$600 7 Cumulative Rate Base $700 $1,400 x 9.8% Cost of Capital $68.6 $137.2 8 Total Revenue Requirement $104.6 $209.2 9 10 CT Bar 11 12 13 Plant Additions 14 Depreciation Expense 15 Net Plant Additions Rate Base Year 1 Year 2 $1,000 $1,000 -$300 -$300 $700 $700 RevReq Year 1 Year 2 Allco Exhibit CL-1 — Page 10 of 29
  4. Page 26 of 78

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 10 of 27 16 Cumulative Depreciable Base$700 17 Cumulative Rate Base $700 18 18 $1,400 $1,400 x 3.6% Depreciation x 9.8% Cost of Capital Total Revenue Requirement Error $25.2 $50.4 $68.6 $137.2 $93.8 $187.6 -$10.8 -$21.6 The table above is a simplified example of CT-Bar’s improper incorporation of ongoing depreciation in a revenue-requirement calculation. Effectively, the CT-Bar reduces plant additions by depreciation expense, which improperly reduces the total amount of plant to be depreciated, thereby reducing the incremental depreciation expense to be supported by the rate mechanism. The correct approach is to handle the plant additions separately from accumulated depreciation (see lines 4 and 6 in the table above). Note that both methods result in the same return on rate base, demonstrating that both calculations reflect the reduction to return on rate base resulting from ongoing/accumulating depreciation. The error is limited to the resulting new depreciation expense reflected in the revenue requirement, which is understated in the above example by $10.8 million in Year 1 and $21.6 million in Year 2 under the CT-Bar as compared to the Company’s proposal in this proceeding, which mirrors in concept to how the Company records depreciation expense on gross plant additions (not on net plant additions, as in the CTBar). Characteristics of the Company’s Proposed F-Factor (same as CT-Bar, except for three features). The Company is proposing a capital support mechanism (the “F” factor in the formula) that tracks as close as possible to PURA’s CT-Bar, except that it addresses the three major impairments described above, which would prevent the Company from being able to agree to a stay-out. These three items are the exclusion of the cost of capital in the revenue-requirement computation for incremental plant additions, the cost of removal and the mechanical deduction of depreciation expense from plant additions instead of rate base. In the Company’s FFactor, these first two items are included in the formula and the third mechanical process is addressed. Beyond that, the F Factor would operate from a fixed annual capital investment level for each year of the PBMRP, with reconciliation through PURA’s annual RAM proceedings. The fixed annual investment level would be set at the Company’s capital forecast, as approved in this proceeding. As described previously, the Company has presented different investment trajectories in the Company’s 5-Year TSP and is proposing to establish the capital support mechanism of the PBR adjustment consistent with the annual capital funding requirements presented in Figure 7 of Exhibit CLP-ELP-1. Consistent with the structure of the CT-Bar in the RE01-PFD, the F-Factor would commence on July 1, 2027, coincident with new base rates, collecting an allowance developed from the Company’s capital forecast presented in Exhibit CLP-TSP-3. In this proceeding, the Company has proposed base rates that include capital additions through the Rate Year. This means that the F-Factor implemented on July 1, 2027 (commensurate with new rates in this proceeding) would be set to zero at that time, since base rates would be set to collect the revenue requirement on capital placed into service in the Rate Year. However, if PURA declines to incorporate rate-year capital additions into base rates in this proceeding, the F-Factor taking effect on July 1, 2027, would reflect the revenue requirement for the period July 1, 2027 through June 30, 2028 on capital additions placed in service (or estimated to be placed in service) from the point in time where PURA cuts off capital for inclusion in base rates and through June 30, 2028.1 In the next year, as part of the Company’s annual RAM compliance filing, actual plant additions placed in service during the applicable plan year would be reconciled against the F-Factor allowance put into rates on July 1, 2027. In that reconciliation, the Company would present its project document for a prudence review and, based on PURA’s findings in that prudence review, the cost of actual plant additions for calendar year 2027, less whatever PURA has already included in rates for capital Allco Exhibit CL-1 — Page 11 of 29
  5. Page 27 of 78Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 11 of 27 additions in 2027, would be actually incorporated into rate base at that point. Following PURA’s determination that the Company’s actual plant additions are prudent, used and useful, the Company’s rate base would be adjusted and associated revenue requirement allowed for recovery that would be limited to the lesser of: 1. The total revenue requirement for the forecasted capital approved in this proceeding for the first implementation of the F Factor; or 2. The total revenue requirement for the actual plant in service. If the cost of the Company’s actual capital additions were to exceed the forecasted amount approved in this proceeding, the Company would not be permitted to obtain recovery of the incremental investment during the initial four-year PBMRP Term. Instead, any such investment would remain subject to review and consideration in a subsequent base rate proceeding or successor PBMRP Term. This Company’s proposed capital funding mechanism sets a defined cap on capital recovery during the plan term, providing customers with greater rate certainty and placing the risk of excess capital spending requirements on the Company. The annual reconciliation further protects customers by blocking recovery of investments that are delayed, deferred, canceled, or not placed in service, since those costs would not be reflected in the F factor, which is based on plant in service. For these reasons, the proposal aligns cost recovery with prudent investment, promotes accurate capital forecasting, and incentivizes efficient execution of the capital program, all while preventing customer over-collection. III. Specific Responses to Parts (a), (b) and (c), above. (a) Why are O&M expenses appropriately subject to an externally indexed revenue cap, while capital expenditures require separate recovery through an F-Factor based on a fixed annual capital investment forecast? The capital investments the Company must make to provide electric service to customers in the State of Connecticut is a “local” concept. Those investments are driven by the circumstances and objectives of the State of Connecticut and the history and current status of the distribution grid in Connecticut. Those circumstances and objectives, which require long-term system planning and appropriate capital resources, are not encapsulated by a single index. O&M, though it is similarly influenced by local circumstances, does not change at the same rate as capital investment. For example, the Company’s annual capital investment is expected to increase nearly 40% from $549 million in 2025 to $758 million by 2028, or more than 11% annually, on average. In contrast, over the same timeframe O&M (excluding storm funding and vegetation management) is projected to increase approximately 3-4% annually. The Company’s proposed PBMRP aligns revenues with drivers of cost while maintaining the incentive to control costs. In addition, under PBR theory, where capital inputs are contemplated in the indexed formula, then the X factor is negative, implying that the annual adjustment is inflation plus an additional factor. The testimony of London Economics in Exhibit CLP-PBR-1 reviews the results of their total factor productivity study producing this result. In this case, the Company elected to adhere as closely as possible to PURA’s (draft) CT-Bar in order to remain synched with PURA’s policy direction. (b) How will the Company's proposed treatment of capital expenditures be expected to produce customer cost savings or otherwise improve customer affordability relative to including capital expenditures within a revenue cap formula. Allco Exhibit CL-1 — Page 12 of 29
  6. Page 28 of 78

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 12 of 27 There are three main opportunities for customer benefit in the PBR framework, which are: (1) the opportunity to leverage the stay-out term to drive operational efficiency and cost savings; (2) the opportunity to spread rate changes out over time to smooth impacts for customers and employ the concept of gradualism rather than promoting the cost and inefficiency of a traditional rate-case cycle; and (2) the opportunity to develop a systematic investment plan that promotes operational efficiency and cost-saving procurement strategies, while taking advantage of the smoothing impacts of the PBR framework to mitigate cost impacts. The Company has submitted substantial testimony and documentation in this proceeding to provide insight into the level of capital investment that is needed on the system to provide adequate service to customers and to support the economic vitality of the State of Connecticut. Customers benefit directly when investment can be undertaken on a planned, systematic and consistent basis over time because (1) it is consistently more expensive to complete infrastructure projects tomorrow rather than today due to price inflation and other factors; and (2) the Company’s process inputs (i.e., primarily labor and materials) cost less when procured on a planned and systematic basis rather than on an emergent basis. Although difficult to define in terms of the overall cost trends, there are significant benefits for customers in an operating approach that is consistent, systematic, planned and carefully managed, which is an outcome that the Company is hoping to promote with its proposals in this proceeding. Bottomline – the Company is looking to establish a ratemaking framework that will promote efficiency of operations for the benefit of customers and the F-Factor is the optimal mechanism for that purpose. Assuming that OCC’s referenced alternative for a capital-cost mechanism “within a revenue cap formula,” means that the PBMRP would rely exclusively on an “I-X” revenue cap formula, with or without X defined with a negative factor, the Company’s experience is that it is not adequate to support necessary capital investment, while raising issues for stakeholders. With the negative X factor, there is no direct link between the actual cost of capital plant additions and the revenue collection through customer rates, leaving it to be insufficient to support necessary capital investments and unsatisfactory for stakeholders that want transparency between the costs collected in rates and the rates that customers pay. As a result, achieving the efficiency needed to support a cost-effective capital plan is illusory in this model. (c) How does the proposed F-Factor mitigate or avoid any incentive to favor capital expenditures over O&M solutions, including in circumstances where either a capital or O&M solution could be used to address the same system need? In the Company’s experience, implementation of the X factor mechanism (with a negative X factor) to cover capital investment was thought to be a mechanism that would promote efficient solutions between capital and O&M because the revenue allowance was not predicated on actual plant additions; rather, was simply formulaic. In 2017, the Massachusetts Department of Public Utilities (“MDPU”) approved a negative X factor within a revenue cap for NSTAR Electric Company d/b/a Eversource Energy – and it remained operative for the five-year term of the plan. However, the fact is that – during an extended stay-out period, there is no incentive to incur any greater level of expense than is absolutely necessary to run the business. Therefore, there is no greater impetus than would exist in any event to make the optimal choice between expense and capitalization, where such a choice exists. And again, with the negative X factor, the MDPU felt it had no line of sight as to whether funds allowed to NSTAR Electric through the annual PBR allowance were, indeed, being leveraged for system investment. Therefore, in 2022, the MDPU instituted the K-Bar providing an allowance for system infrastructure Allco Exhibit CL-1 — Page 13 of 29
  7. Page 29 of 78

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 13 of 27 projects, coupled with reporting requirements on investment levels. The MDPU maintained the I-X formula to cover the O&M portion of the approved revenue requirement, which is what the Company is proposing in this case. In reality, there are very few instances when system needs can be easily transitioned between a capitalwork solution or a work solution that can be expense. The prudence review is the primary and most effective tool that regulators possess for evaluating these situations. ii OCC-522 Question: Leadership Panel Exhibit CLP-ELP-1 – Storm Cost Recovery (Carrying charges applied to SCRAF) In its proposal, the Company notes, “should PURA implement the SCRAF, which provides for more timely review and recovery of storm and pre-staging costs, the Company accepts the Prime rate from the date of cost incurrence, applied to the net balance of the storm fund and pre-staging reserve fund 6 for storms occurring after March, 2025.” (p.143) Did the company consider or analyze setting carrying charges on costs recovered through SCRAF to be equal to the commercial paper index or the utility's actual cost of short-term debt, rather than the prime rate? a. If yes, provide the analysis conducted and the rationale for proposing the use of the Prime rate instead. b. If not, explain why the Company did not consider proposing that the carrying charges on SCRAF recovery to be set at either the commercial paper index or actual cost of short-term debt. OCC-522 Response: a. and b. Carrying costs are the mechanism by which the Company recovers its cost of money. Thus, carrying costs must be tied to the actual cost that the Company is incurring to carry the storm deferral. When the storm deferral is relatively larger and carried for a relatively extended time period, then the Company’s weighted average cost of capital (“WACC”) is its actual carrying cost. If PURA establishes a ratemaking mechanism that provides more systematic reviews and more timely recovery, then the cost of money may be susceptible to approximation with lower cost sources of funds. The relationship between time and quantity and the cost of capital is clearly demonstrated through a utility’s cost of service whereby a utility’s rate base (comprised mainly of the Company’s plant which is paid back by customers over many years) receives a return at the Company’s authorized WACC. Applying the Company’s WACC to long-term assets aligns the carrying charge calculation with the manner in which comparable long-term assets are reflected for ratemaking purposes. Similarly, the WACC is the appropriate rate for calculating carrying charges on long-term funded regulatory assets because it reflects the Company’s actual cost of funding those customer “debts”, including storm restoration costs, over an extended period of time. Financing obligations – certainly obligations of this magnitude – cannot be supported exclusively through debt financing, whether short-term or long-term. Instead, the Company must balance its capital requirements through a reasonable mix of both debt and equity to ensure financial stability and continued access to reasonably priced capital. With respect to the appropriate carrying charge rate to utilize for the Storm Cost Recovery Adjustment Factor (“SCRAF”), the Company provided a thorough response to this question in response to LFE-031, in Docket No. 2512-13. The Company is providing that response as OCC-522, Attachment 1. The analysis shows that: (1) necessary uses of cash routinely exceed available sources of cash, creating a persistent funding gap; (2) commercial paper is a Allco Exhibit CL-1 — Page 14 of 29
  8. Page 30 of 78

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 14 of 27 tool to maintain liquidity, not to finance investments or deferred expenses; and (3) short-term borrowing capacity is limited, and the Company cannot plan to operate at or near its short-term debt capacity without putting its ability to operate the system in severe jeopardy. Given all of the considerations elucidated by Attachment 1, the Company recognizes that the appropriate treatment of carrying charges may vary based on the regulatory framework established within each jurisdiction. Different regulatory constructs reflect differing policy objectives and mechanisms designed to balance the Company’s financing needs with customer impacts. In establishing a going-forward framework for storm cost recovery, the Company agrees that it would be within PURA’s discretion to strike a balance between the Company’s costs of financing storm costs while ensuring that the Company is not ‘profiting’ on a force majeure event like a storm. This is the Company’s experience in Massachusetts, as well, where the MDPU has authorized a carrying charge rate that is different from and generally less than the Company’s WACC, but that still recognizes that the Company is using its longer-term capital resources to finance storm costs (not its shorter term commercial paper source of liquidity). Thus, the Company stated that “should PURA implement the SCRAF, which provides for more timely review and recovery of storm and pre-staging costs, the Company accepts the Prime rate from the date of cost incurrence, applied to the net balance of the storm fund and pre-staging reserve fund for storms occurring after March, 2025.” iii EOE-156 Question: (PBMRP CAPITAL SUPPORT MECHANISM) Refer to Exhibit CLP-ELP-1, pp. 101-103. Provide a working, unlocked Excel spreadsheet that would serve as a representative tool used to calculate the Company’s incremental revenue requirements resulting from the proposed capital support mechanism (F-Factor) for each year of the MRP. As part of the submission, discuss the calculations and separately identify and explain all critical assumptions, using cited information from the Company’s rate case submission where relevant (e.g., depreciation rate from the Company’s depreciation study). In support of the request, please use the Company’s proposed 5 Year Targeted System Performance (TSP) Plan within the spreadsheet’s initial inputs and apply an initial assumption that the Company incurred actual plant-in-service additions of 5% more than the proposed annual TSP funding. Additionally, please configure the spreadsheet to allow for the weighted average carrying costs (WACC) to be individually adjusted for both ROE and Cost of Debt. EOE-156 Response: The Company appreciates the opportunity to respond to EOE’s thoughtful question regarding the operation of the PBMRP proposed in this proceeding, which the Company views as key to reaching a long-term reliability and resiliency plan for Connecticut, while meeting affordability needs for customers. The Company’s response to this request is organized as follows: A. Overview and Results B. F-Factor Discussion C. Impact of 5% Additional Capital Investment D. Model overview Attachments referenced in this response: EOE-156, Attachment 1, provides the Company’s working model, with projected capital investment as filed in this proceeding. See, e.g., Exhibit CLP-ELP-1, Figure 7. EOE-156, Attachment 2, provides a second model that is identical in every respect to Attachment 1 except that capital investments are 5% greater than the forecast submitted to this proceeding in Exhibit CLP-ELP-1, Figure 7, as stipulated by EOE’s data request. A. Overview and Results Allco Exhibit CL-1 — Page 15 of 29
  9. Page 31 of 78Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 15 of 27 Ultimately, the Company’s goal in this proceeding is to establish a sustainable, cohesive ratemaking framework that supports electric utility service in the State of Connecticut in an affordable manner for customers, over a long term. This is the Company’s goal because the CL&P system needs investment for reliability, resiliency and modernization. For this infrastructure investment to be affordable for customers, a coherent ratemaking plan needs to be instituted that will consider the interests of customers over a longer term than just the next rate case. That framework needs to balance: (1) the reliability and performance requirements of the Company’s customers and the broader State of Connecticut; (2) customer rate stability and affordability; (3) incentives for cost efficiency in utility operations; and (4) implementation of a revenue support mechanism sufficient to cover the cost of delivering these objectives to customers, including the cost of capital. The Company’s PBMRP is designed to address these objectives in a holistic, balanced way. To do this, the Company started with the ratemaking framework under discussion in PURA’s PBR docket (Docket No. 21-05-15RE01), while also introducing certain new elements to remediate the flaws that would ultimately hinder PURA’s (draft) PBR model from supporting the necessary stay out terms. As discussed below, the stay-out term is the critical element of the PBMRP that creates the cost-efficiency incentive inherent in a performance based ratemaking plan. This context is vital to understand both the design and mechanics of the Company’s proposed PBMRP, including both the F-Factor and “I-X” components. To augment understanding of how the plan would work over the stay-out period, the Company has incorporated the projected costs of service set forth in EOE-156, Attachment 1, Worksheet, entitled “COS-1 Total,” which is the Company’s cost of service, as filed. The Company does not intend to imply that these dollar amounts are certain for the future and there will undoubtedly be changes in a litigated result. However, these figures serve as a reasonable basis for presenting this analysis to reflect the Company’s PBMRP proposal. Moreover, assuming that there will be changes to the underlying cost of service that serves as the “going in revenue requirement,” all of the projections made herein become highly optimistic, as discussed below. Increasing capital investment on the Connecticut distribution system is a given for the reasons described in the testimony of the Company’s Leadership Panel and Targeted System Plan (“TSP”) Panel – the Connecticut distribution system needs additional investment to maintain service reliability to customers and even more investment to achieve a level of modernization. The Company will need to make this investment to meet the interests of customers, with or without a multi-year plan. However, without a multi-year rate plan, whether in the form of the Company’s proposed PBMRP or another reasonable model, the Company’s only viable course of action to support this level of needed investment will be to file traditional cost-of-service rate cases, as closely to annually as possible. Effectively, these sequential cases will “roll in” unrecovered capital investment into base rates to maintain a nexus between what the Company needs to invest in the system and what rates are reflecting for recovery of costs. In a world in which system investment needs are relatively flat, economy-wide inflation is modest and predictable at 2% annually, and rates are fully coupled with growing sales revenues (and no revenue decoupling mechanism), it is conceivable that a utility could offset the cost increases it incurs with organic sales growth, as electric utilities could do in past decades. However, that is not the reality of today’s operating environment. The distribution system investment needs are extensive and growing and the financial consequences of these circumstances are factors that need to be considered in determining a reasonable and workable regulatory plan. Establishment of a reasonable multiyear, performance-based ratemaking plan is the mechanism that can support the system needs in a manner that is wholly transparent and stable for customers, allowing for a smoother trajectory of rate changes than would otherwise occur. Results of F-Factor Implementation Assuming Capped Forecast Investment EOE-156, Chart 1, below, provides illustrative rate increases comparing circumstances where the Company is pursuing a traditional rate-case cycle with filings as close to annually as possible under Connecticut law, as compared Allco Exhibit CL-1 — Page 16 of 29
  10. Page 32 of 78Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ALLCO-05 Date Issued September 08, 2026 ALLCO-054 Page 16 of 27 to the proposed PBMRP. These amounts assume the Company’s revenue requirement proposed in this docket is authorized without modification, except that the Company has used its existing weighted average cost of capital to perform the analysis, in order to isolate the functioning of the F-Factor operation - apart from changes in the cost of capital (i.e., the analysis uses a 9.25% return on equity and 47%/53% debt to equity capital structure). As noted above, the cost-of-service projections are shown in EOE-156, Attachment 1, Worksheet “COS-1 Total,” Line 35. In the absence of a multi-year rate plan, the Company anticipates filing rate cases on a rolling basis, with base rate changes effective January 1, 2029, July 1, 2030, and January 1, 2032. Chart 1, below, also spans the time period covering one year beyond the Company’s proposed four-year plan. 2032 is shown for illustrative purposes. EOE-156, Chart 1 Annual Incremental Revenue Increase, $ Millions Note: Chart 1 assumes base-rate amendments effective 1/1/2029, 7/1/2030 and 1/1/2032. In Chart 1, a rolling rate-case cycle is depicted as the orange series, with the Company estimating new rates effective January 1, 2029 (18 months after the present docket concludes), with additional revenues of $129 million; followed by another $183 million rate change effective July 1, 2030, and a further $147 million effective January 1, 2032. These rate adjustments arise primarily as a result of capital investment rather than O&M changes, which means that the associated rate changes are reasonably foreseeable and ultimately predictable. In contrast, the Company’s proposed PBMRP would yield revenue increases of $77.6 million for rates effect July 1, 2028, $81.1 million July 1, 2029, and $83 million July 1, 2030 (EOE-156, Attachment 1, worksheet “PBR-1 Total PBRA”, Line 41). For purposes of discussion, the Company estimates that the subsequent rate case taking effect after the proposed PBMRP would be $119 million in 2031, followed by $89 million in 2032 assuming continuation of the proposed framework. Uncertainty grows as the timeframe of projections extends, as the Company will inevitably experience cost increases in relation to both operating expenses and capital investment, as time passes. Therefore, the later years (particularly 2031 and 2032) should be interpreted as illustrative for purposes of discussing the principles and conceptual impacts of the PBMRP and traditional rate case frameworks. As Chart 1 illustrates, whether through a multi-year rate plan or sequential rate cases, ongoing revenue support is essential to the electric system. Revenue increases for the Company are rate increases for customers, so that a smoother and more predictable customer impact occurs through the Company’s PBMRP, which is the fundamental purpose of Allco Exhibit CL-1 — Page 17 of 29

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Christopher Little [26-05-10]