  1. Page 5 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 13I Cancels M.D.P.U. No. 13H Page 2 of 4 EASTERN MASSACHUSETTS GREATER BOSTON SERVICE AREA LARGE GENERAL SERVICE RATE G-3 RATE ADJUSTMENTS The charges for delivery service shall be subject to the following provisions: Revenue Decoupling Adjustment Mechanism Residential Assistance Adjustment Clause Attorney General Consultant Expense Storm Reserve Adjustment Mechanism Basic Service Cost Adjustment Transmission Service Cost Adjustment Renewable Energy Charge Performance Based Revenue Adjustment Vegetation Management Solar Massachusetts Renewable Target Grid Modernization Factor Provisional System Planning Factor Pension Adjustment Mechanism Net Metering Recovery Surcharge Long Term Renewable Contract Adjustment Storm Cost Recovery Adjustment Solar Program Cost Adjustment Transition Cost Adjustment Energy Efficiency Charge Solar Expansion Cost Recovery Mechanism Miscellaneous Charges 2017 Tax Act Credit Advanced Metering Infrastructure Electric Vehicle Program Factor TRANSMISSION BILLING ADJUSTMENT Customers taking service under this schedule may elect to be billed on the customer’s demand at the time of the ISO New England regional network monthly transmission system peak (the Coincident Peak Demand) for the legacy NSTAR Electric system. Customers must remain on the elected option for a minimum of 12 consecutive months. ADJUSTMENT FOR SERVICE AT TRANSMISSION VOLTAGE If a Customer is provided service at 69 kV or higher, and furnishes, owns and maintains all service transformers and associated equipment except metering, which shall measure transmission voltage, the Customer will not be billed the distribution demand and energy charge effective under this tariff. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  2. Page 6 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 13I Cancels M.D.P.U. No. 13H Page 3 of 4 EASTERN MASSACHUSETTS GREATER BOSTON SERVICE AREA LARGE GENERAL SERVICE RATE G-3 DETERMINATION OF BILLING DEMAND The billing demand will be the maximum fifteen-minute demand (either kilowatts or 90 percent of the kilovolt-amperes) as determined by meter during the monthly billing period, except any demand recorded during off-peak hours will be reduced by 70 percent. Demands established prior to the application of this rate shall be considered as having been established under this rate. The Coincident Peak Demand shall be determined by meter, each calendar month and shall be the customer’s coincident 60-minute kilowatt demand. BILLING In determining if a demand charge reduction is applicable, the following defines the peak and off-peak periods: (1) During the months of June through September, the peak period shall be the hours between 9 A.M. and 6 P.M. weekdays. During the months of October through May, the peak period shall be the hours between 8 A.M. and 9 P.M. weekdays. (2) All other hours shall be off-peak including twelve Massachusetts holidays as follows: New Year's Day Martin L. King Day President's Day Patriot's Day Memorial Day Independence Day Labor Day Columbus Day Veteran's Day Thanksgiving Day Day after Thanksgiving Christmas Day FARM DISCOUNT RIDER A Customer taking service under this rate may be eligible for the Company’s Farm Discount Rider, as in effect from time to time. TERMS OF PAYMENT Charges are net and are payable upon presentation of the Company's bill. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  3. Page 7 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 13I Cancels M.D.P.U. No. 13H Page 4 of 4 EASTERN MASSACHUSETTS GREATER BOSTON SERVICE AREA LARGE GENERAL SERVICE RATE G-3 TERM Service under this rate shall be for a minimum term of 12 consecutive months and shall continue thereafter until terminated on six months’ written notice by the Customer. Except for Customers engaging in net metering, Customers served under this rate must provide the Company with six months’ prior written notice before installing or allowing to be installed for its use a non-emergency generator with a nameplate capacity greater than that in place on the Customer’s location as of October 1, 1993. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  4. Page 8 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 21I Cancels M.D.P.U. No. 21H Page 1 of 4 EASTERN MASSACHUSETTS CAMBRIDGE SERVICE AREA LARGE GENERAL SERVICE RATE G-3 AVAILABILITY This rate is available for all uses of electricity to Customers in the Cambridge service area whose metered load exceeds or is estimated to exceed an average of 100 kilowatts for 12 consecutive billing months and the service voltage is 13,800 volts or higher. Service under this rate is subject to both the Company's printed requirements and the Company's Terms and Conditions - Distribution Service, each as in effect from time to time. CHARACTER OF SERVICE The Company delivers 60 hertz, three-phase, alternating current service at primary voltage under this rate schedule. As available and at the Company's option, such service shall be supplied at approximately 13,800 volts. RATE PER MONTH Delivery Services: Customer Charge: Distribution: Transition: Transmission: As per M.D.P.U. No. 1 as in effect from time to time. As per M.D.P.U. No. 1 as in effect from time to time. As per M.D.P.U. No. 1 as in effect from time to time. As per M.D.P.U. No. 1 as in effect from time to time. Supplier Services: (Optional) Basic Service: As in effect per Tariff Minimum Charge: The minimum charge per month shall be the Customer Charge. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  5. Page 9 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 21I Cancels M.D.P.U. No. 21H Page 2 of 4 EASTERN MASSACHUSETTS CAMBRIDGE SERVICE AREA LARGE GENERAL SERVICE RATE G-3 RATE ADJUSTMENTS The charges for delivery service shall be subject to the following provisions: Revenue Decoupling Adjustment Mechanism Residential Assistance Adjustment Clause Attorney General Consultant Expense Storm Reserve Adjustment Mechanism Basic Service Cost Adjustment Transmission Service Cost Adjustment Renewable Energy Charge Performance Based Revenue Adjustment Vegetation Management Solar Massachusetts Renewable Target Grid Modernization Factor Provisional System Planning Factor Pension Adjustment Mechanism Net Metering Recovery Surcharge Long Term Renewable Contract Adjustment Storm Cost Recovery Adjustment Solar Program Cost Adjustment Transition Cost Adjustment Energy Efficiency Charge Solar Expansion Cost Recovery Mechanism Miscellaneous Charges 2017 Tax Act Credit Advanced Metering Infrastructure Electric Vehicle Program Factor TRANSMISSION BILLING ADJUSTMENT Customers taking service under this schedule may elect to be billed on the customer’s demand at the time of the ISO New England regional network monthly transmission system peak (the Coincident Peak Demand) for the legacy NSTAR Electric system. Customers must remain on the elected option for a minimum of 12 consecutive months. ADJUSTMENT FOR SERVICE AT TRANSMISSION VOLTAGE If a Customer is provided service at 69 kV or higher, and furnishes, owns and maintains all service transformers and associated equipment except metering, which shall measure transmission voltage, the Customer will not be billed the distribution demand and energy charge effective under this tariff. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  6. Page 10 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 21I Cancels M.D.P.U. No. 21H Page 3 of 4 EASTERN MASSACHUSETTS CAMBRIDGE SERVICE AREA LARGE GENERAL SERVICE RATE G-3 DETERMINATION OF BILLING DEMAND The demand for billing purposes shall be the highest 15-minute demand in kilovolt-amperes established during the Peak Load Period of the billing month as measured on a suitable meter or as determined by any other accepted method, at the option of the Company, but shall not be less than 26% of the maximum 15-minute demand in kilovolt-amperes established during any billing period of the billing month. The Coincident Peak Demand shall be determined by meter, each calendar month and shall be the customer’s coincident 60-minute kilowatt demand. BILLING PERIODS Peak Load Period: During that portion of the year when eastern daylight savings time is in effect, the period beginning at 9:00 a.m. and ending at 6:00 p.m. on all weekdays, Monday through Friday. During that portion of the year when eastern standard time is in effect, the period beginning at 4:00 p.m. and ending at 9:00 p.m. on all weekdays, Monday through Friday. Low Load Period: All hours not included in the Peak Load Period. The Low Load Period shall be further divided into 2 separate time periods as follows: Low Load Period A: All hours not included in the Peak Load Period or Low Load Period B. Low Load Period B: During both eastern daylight savings time and eastern standard time, the period beginning at 10:00 p.m. and ending at 7:00 a.m. on all weekdays, Monday through Friday, and all hours on Saturday and Sunday. FARM DISCOUNT RIDER A Customer taking service under this rate may be eligible for the Company’s Farm Discount Rider, as in effect from time to time. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  7. Page 11 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 21I Cancels M.D.P.U. No. 21H Page 4 of 4 EASTERN MASSACHUSETTS CAMBRIDGE SERVICE AREA LARGE GENERAL SERVICE RATE G-3 TERMS OF PAYMENT Charges are net and are payable upon presentation of the Company's bill. TERM Service under this rate shall be for a minimum term of 12 consecutive months and shall continue thereafter until terminated on six months’ written notice by the Customer. Except for Customers engaging in net metering, Customers served under this rate must provide the Company with six months’ prior written notice before installing or allowing to be installed for its use a non-emergency generator with a nameplate capacity greater than that in place on the Customer’s location as of March 1, 1995. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  8. Page 12 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 31I Cancels M.D.P.U. No. 31H Page 1 of 4 EASTERN MASSACHUSETTS SOUTH SHORE, CAPE COD & MARTHA’s VINEYARD SERVICE AREA LARGE GENERAL SERVICE RATE G-3 AVAILABILITY This rate is available for all uses of electricity to Customers in the South Shore, Cape Cod & Martha’s Vineyard service area who establish demands in excess of an average of 500 kilowatts for 12 consecutive months. Service under this rate is subject to both the Company's printed requirements and the Company's Terms and Conditions - Distribution Service, each as in effect from time to time. CHARACTER OF SERVICE The Company delivers 60 hertz, alternating current service at secondary voltage under this rate schedule. As available and at the Company's option, such service shall be either single-phase at approximately 120/240 or 120/208 volts or 4-wire, three-phase at approximately 120/208 or 277/480 volts. RATE PER MONTH Delivery Services: Customer Charge: Distribution: Transition: Transmission: As per M.D.P.U. No. 1 as in effect from time to time. As per M.D.P.U. No. 1 as in effect from time to time. As per M.D.P.U. No. 1 as in effect from time to time. As per M.D.P.U. No. 1 as in effect from time to time. Supplier Services: (Optional) Basic Service: As in effect per Tariff Minimum Charge: The minimum charge per month shall be the Customer Charge. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  9. Page 13 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 31I Cancels M.D.P.U. No. 31H Page 2 of 4 EASTERN MASSACHUSETTS SOUTH SHORE, CAPE COD & MARTHA’s VINEYARD SERVICE AREA LARGE GENERAL SERVICE RATE G-3 RATE ADJUSTMENTS The charges for delivery service shall be subject to the following provisions: Revenue Decoupling Adjustment Mechanism Residential Assistance Adjustment Clause Attorney General Consultant Expense Storm Reserve Adjustment Mechanism Basic Service Cost Adjustment Transmission Service Cost Adjustment Renewable Energy Charge Performance Based Revenue Adjustment Vegetation Management Solar Massachusetts Renewable Target Grid Modernization Factor Provisional System Planning Factor Pension Adjustment Mechanism Net Metering Recovery Surcharge Long Term Renewable Contract Adjustment Storm Cost Recovery Adjustment Solar Program Cost Adjustment Transition Cost Adjustment Energy Efficiency Charge Solar Expansion Cost Recovery Mechanism Miscellaneous Charges 2017 Tax Act Credit Advanced Metering Infrastructure Electric Vehicle Program Factor PRIMARY METERING CREDIT When the Company meters electricity at primary voltage to a Customer taking primary voltage service, a discount of 2% will apply to the volumetric (per kWh) charges determined under all of the foregoing provisions of this rate schedule. TRANSFORMER OWNERSHIP ALLOWANCE If a Customer furnishes, installs, owns and maintains at his expense all the protective devices, transformers, and other equipment required, as specified by the Company upon request, the electricity so supplied will be metered by the Company at line voltage and the monthly demand charges will be reduced by $1.09 per kilovolt-ampere of demand when the nominal voltage is 13,200 volts or higher. TRANSMISSION BILLING ADJUSTMENT Customers taking service under this schedule may elect to be billed on the customer’s demand at the time of the ISO New England regional network monthly transmission system peak (the Coincident Peak Demand) for the legacy NSTAR Electric system. Customers must remain on the elected option for a minimum of 12 consecutive months. Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
  10. Page 14 of 33

    NSTAR ELECTRIC COMPANY d/b/a EVERSOURCE ENERGY M.D.P.U. No. 31I Cancels M.D.P.U. No. 31H Page 3 of 4 EASTERN MASSACHUSETTS SOUTH SHORE, CAPE COD & MARTHA’s VINEYARD SERVICE AREA LARGE GENERAL SERVICE RATE G-3 ADJUSTMENT FOR SERVICE AT TRANSMISSION VOLTAGE If a Customer is provided service at 69 kV or higher, and furnishes, owns and maintains all service transformers and associated equipment except metering, which shall measure transmission voltage, the Customer will not be billed the distribution demand and energy charge effective under this tariff. DETERMINATION OF BILLING DEMAND The demand for billing purposes shall be the highest 15-minute demand in kilovolt-amperes established during the Peak Load Period of the billing month as measured on a suitable meter or as determined by any other accepted method, at the option of the Company, but shall not be less than 35% of the maximum 15minute demand in kilovolt-amperes established during any billing period of the billing month. The Coincident Peak Demand shall be determined by meter, each calendar month and shall be the customer’s coincident 60-minute kilowatt demand. BILLING PERIODS Peak Load Period: During that portion of the year when eastern daylight savings time is in effect, the period beginning at 9:00 a.m. and ending at 6:00 p.m. on all weekdays, Monday through Friday. During that portion of the year when eastern standard time is in effect, the period beginning at 4:00 p.m. and ending at 9:00 p.m. on all weekdays, Monday through Friday. Low Load Period: All hours not included in the Peak Load Period. The Low Load Period shall be further divided into 2 separate time periods as follows: Low Load Period A: All hours not included in the Peak Load Period or Low Load Period B. Low Load Period B: During both eastern daylight savings time and eastern standard time, the period beginning at 10:00 p.m. and ending at 7:00 a.m. on all weekdays, Monday through Friday, and all hours on Saturday and Issued by: Douglas W. Foley President Filed: Effective: October 31, 2024 January 1, 2025
2 pages match

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Eben Perkins [26-05-10]

This filing on the current system (opens in a new tab)