  1. Page 10 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. What happens after Contingent Approval? 2 A. Once Contingent Approval is received, Earthlight coordinates with Eversource to arrange 3 any necessary site visits, confirm the utility’s scope, obtain cost letters, and schedule 4 required outage and interconnection work. Following sign-off from the AHJ, Earthlight 5 provides the required closeout documentation and follows up with Eversource to move 6 the project through meter installation and PTO. Eversource schedules its meter 7 technicians, but Earthlight typically has no visibility into that schedule, limiting our 8 ability to coordinate site attendance and resolve questions during the visit. Meter 9 technicians sometimes raise additional concerns when they arrive, including concerns 10 that require further discussion to determine whether corrective work is necessary. When 11 the meter is not installed pending resolution, the project can be delayed by several days or 12 even weeks, even though construction and the AHJ inspection are complete. 13 Q. What happens if a project requires unanticipated upgrades or equipment costs? 14 A. In that event, Earthlight first seeks an explanation in order to describe the changes to its 15 end-user customer and requests an itemized cost. Eversource typically rejects any 16 request to itemize or provide additional granularity on its costs, so there is only a lump 17 sum cost that we can share with the customer. There are four potential outcomes when 18 unanticipated costs are added to a project: 19 20 21 22 23 24 1) The customer agrees to pay the cost, degrading the economics of the project, and proceeds with the approved plan; 2) The customer and Earthlight share in the costs, hurting the economics for both parties, and proceeds with the approved plan; 3) The costs are too great, the project is no longer financially viable for either the customer or Earthlight, and the project does not get built; or Page 8
  2. Page 11 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 4) Earthlight finds an approved way to alter the project, often reducing its size, and 2 eliminating or greatly reducing the cost increase. The new project gets reviewed 3 and approved by Eversource and the customer. The end project usually does not 4 meet the customer’s needs. 5 6 Q. Can you provide an example of unanticipated Eversource requirements that either increased costs or reduced the project size? 7 A. Earthlight developed a group of front-of-the-meter affordable multifamily rooftop 8 interconnections. In December 2025, the hosting capacity map showed approximately 5 9 MW of available capacity at that location, which was sufficient capacity to develop this 10 group of projects. Shortly after the projects were designed and submitted in February 11 2026, Earthlight was made aware that available capacity had been reduced to 12 approximately 200 kW with no explanation, forcing at least two of the group projects to 13 be reduced from approximately 300 kW AC to 200 kW AC. This unexplained change 14 created redesign effort, customer/program uncertainty, and a material change to project 15 economics after significant development work had already occurred. 16 17 Eversource also required a multi-department site review in March 2026, including Field 18 Engineering, line/underground, metering, and Distributed Generation personnel. That 19 review focused on transformer locations, metering arrangements, existing service 20 conditions, and acceptable interconnection configurations, which had already been 21 verbally reviewed and generally accepted, with minor accommodations needed to resolve 22 potential issues. Earthlight was not permitted to view or photograph the transformer 23 during this site visit. Following up on this site visit, Eversource later advised that the 24 Field Engineering notes and photos from the March site visit were either unavailable or Page 9
  3. Page 12 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 otherwise not retained, requiring additional site verification in June 2026. During the 2 second site review, all but one of the six proposed interconnection methods were 3 eventually approved after months of unnecessary delay. 4 5 For the remaining installation, Eversource identified an existing grading issue and 6 transformer pad concerns, which had been discussed during the initial site visit. At that 7 time, a repair to the affected area was determined as an acceptable path forward. 8 However, after the additional June meeting, Eversource required an additional upgrade to 9 install a new transformer pad and re-grade the transformer site. This added approximately 10 $18,000 in additional Eversource scope and approximately $30,000 overall including 11 related customer costs. This represents an increase in the project cost of 4% for the 12 project connected to this point of interconnection. Based on this new requirement, 13 contingent approval was finally issued in September 2026. 14 Q. Can you provide another example? 15 A. Yes. Eversource’s updated guidelines require projects to connect directly to the service 16 point at the building’s transformer, effectively creating a separate service to the building. 17 This requirement restricts the available interconnection options otherwise permitted by 18 the NEC, as adopted under the Connecticut State Building Code. The NEC provides 19 alternative methods for safely interconnecting distributed generation systems on the 20 supply side of the customer’s service equipment. 21 22 This gap between Eversource and NEC requirements was encountered at another recent 23 project in Naugatuck CT, which involved adding a new NRES system to a service that 24 already had an existing ZREC project onsite. On April 28, 2025, Earthlight proposed a Page 10
  4. Page 13 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 supply-side (line-side) interconnection and provided detailed information demonstrating 2 that the new connection was fully compliant with the NEC, would not affect the existing 3 project, and would be the most cost-effective option for the customer. During the site 4 review, Earthlight identified unused supply-side equipment that could accommodate the 5 new distributed generation interconnection, reviewed the proposed installation with 6 Eversource field personnel, and provided photographs showing how the work could be 7 completed safely, more cost-effectively, and in compliance with applicable NEC 8 requirements. At the conclusion of that site review, Earthlight understood that the 9 proposed approach was likely acceptable. 10 11 Eversource subsequently reversed course and advised that supply-side connections were 12 no longer permitted except in limited circumstances, requiring Earthlight to challenge 13 that position, escalate the issue internally, and spend months defending the proposed 14 code-compliant approach. After multiple site visits, extensive correspondence, and 15 repeated reviews, Eversource issued a Contingent Approval on July 16, 2025, approving 16 the exact supply-side connection that had been proposed from the outset. 17 Q. Are these examples isolated incidents? 18 A. Unfortunately, no. Another recent front of meter project, located in Bristol, illustrates 19 Earthlight’s concerns about unexpected costs and pricing transparency. In that case, 20 Earthlight requested a Saturday outage for Eversource to disconnect power to an 21 underground transformer and relocate an interior meter outside. Comparable off-shift 22 Eversource work has historically cost Earthlight approximately $3,500 to $8,500. Page 11
  5. Page 14 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Following a late-May site visit, Earthlight requested a cost letter on August 19. After 2 multiple follow-ups, Eversource issued a $12,600 estimate on September 16. 3 4 When Earthlight requested a breakdown to explain the charges to the customer, 5 Eversource refused and offered no process for challenging the estimate, leaving 6 Earthlight and the customer facing a substantially higher charge without sufficient 7 supporting detail. Both Earthlight and the customer are left without recourse, without 8 any opportunity to argue our case, and yet another Eversource unanticipated new 9 precedent. This pattern creates even more uncertainty as it prevents Earthlight from 10 being able to accurately portray a project’s true cost to future customers trying to decide 11 whether or not to install solar or storage. 12 13 Q. Does Earthlight have any ability to question or challenge the multiple site visit requirements? 14 A. No. Regrettably, this seems to be a new trend, because site visits were not required under 15 the LREC/ZREC Program. Any time Eversource requests a site visit, we have to attend. 16 Eversource dictates all terms of the site visit, never offering any scheduling flexibility for 17 the customer or for Earthlight. If we request a different date, Eversource refuses to 18 respond to that email. 19 20 Earthlight recently completed a project where the existing Eversource building/customer 21 service equipment and meters were located within an exterior-accessible electrical room 22 and had already been approved as part of the building’s service configuration a few years 23 prior during a major remodel. The electrical room contained multiple tenant meters and a 24 single owner’s meter. Because the solar system was interconnecting ahead of the Page 12
  6. Page 15 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 customer meters and directly at the transformer, the location of the existing customer 2 meters had no material electrical impact on the distributed generation interconnection or 3 production metering arrangement. 4 5 Because the updated guidelines required meters to be relocated outside, Earthlight 6 requested a variance during the interconnection application process to allow the existing 7 Eversource meters to remain inside. Had Eversource denied the variance, relocating all 8 of the meters would have imposed substantial costs on the customer and caused extended 9 disruption to residents. Earthlight estimated that relocating the owner’s meter alone 10 would cost between $8,000 and $10,000, excluding any Eversource charges for meter 11 work. Relocating the tenant meters would have added further costs and disruption. After 12 Earthlight provided photographs and revised design drawings, Eversource approved the 13 variance approximately three months after the initial application was submitted. 14 15 However, following approval, Earthlight constructed the project and engaged Eversource 16 to perform the necessary outage required to complete the interconnection. What should 17 have been a simple process required multiple additional Eversource site visits. During 18 the first visit, Eversource representatives again stated that the existing meters needed to 19 be relocated outside. Earthlight provided the representatives with the previously issued 20 variance approval, and additional discussions followed. 21 22 This was the first time Earthlight had received a cost letter requiring payment for 23 interconnection outage work performed during normal working hours. No prior project Page 13
  7. Page 16 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 involving an outage during normal working hours had required payment to Eversource. 2 Approximately six additional weeks elapsed before Eversource finally provided the cost 3 letter and the outage was scheduled two weeks thereafter. Even though the outage was 4 requested the beginning of June, the delays caused it to not take place until the middle of 5 August. 6 7 In Earthlight’s view, relocating existing owner or tenant meters should not be a condition 8 of interconnecting a front-of-the-meter project through a new, separate service or through 9 a supply-side connection to existing customer service equipment. Where the existing 10 Eversource metering arrangement is already approved and the proposed interconnection 11 does not affect its safety or operation, requiring relocation imposes additional costs and 12 disruption without a demonstrated need related to the solar interconnection. 13 14 B. Eversource Requirements Frequently Exceed and/or Conflict with the National Electric Code 15 16 Q. Does Earthlight have any recourse when Eversource requires additional equipment or site upgrades? 17 A. No. An example of this is a recent battery storage project. Eversource recently started 18 requiring Real-Time Automation Controller (“RTAC”) equipment on any project 500kW 19 and larger. It is our understanding that this device is traditionally required on much 20 larger projects, and other utilities have established a higher threshold for requiring this 21 equipment, including 1 MW in California1 and 1 MW in New Jersey.2 In addition, 1 See, e.g., California PUC General Order 167, available at https://docs.cpuc.ca.gov/PUBLISHED/GENERAL_Order/108114.htm (Section 3.2 - Small Facilities: “Generating Assets smaller than one megawatt are currently exempt from enforcement of the Standards pursuant to this General Order”). 2 See, e.g., Jersey Central Power & Light Company, Level 2 Interconnection Agreement, Page 3, available at https://www.firstenergycorp.com/content/dam/feconnect/files/retail/nj/NJ-Level-23-Interconnection-ApplicationPage 14
  8. Page 17 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Arizona regulators now generally allow projects up to 2 MW to proceed under Fast Track 2 review without requiring the RTAC equipment.3 3 4 We do not have any recourse, no way to present our case that this equipment should not 5 be required. The only option available to Earthlight and our customers is to downsize the 6 project to avoid this rule but then the project does not meet the customer’s needs. Small 7 C & I projects just over that 500kW threshold have to bear the burden of this extremely 8 costly Eversource owned device, which in Earthlight’s experience ranges in cost between 9 $75,000 and $90,000, and requires additional customer-owned equipment alongside the 10 RTAC which costs an additional $27,500. Moreover, Eversource usually requires 11 additional studies that can add $22,500 or more. These costs can ruin the economics of a 12 project this size and prevent them from being built. 13 14 Q. In Earthlight’s experience, does Eversource strictly apply principles of cost causation when determining site upgrades are needed? 15 A. No. In fact, Eversource frequently requires replacement of existing equipment, such as 16 customer meters and transformers that are wholly unrelated to the installation of solar or 17 energy storage on the site. On one particular project, Eversource issued an 18 Interconnection Agreement and Contingent Approval for the subject Buy-All project that 19 did not identify additional project costs based on the proposed interconnection to the 20 existing on-site transformer. The customer obtained financing based on that approval. Agreement.pdf (“Breaker Trip Control: Generators 2 MW and greater will require remote generator trip/isolation control by JCP&L’s system operations control center via a local SCADA unit or similar device”). 3 See, e.g., Tucson Electric Power, Interconnection Manual for Distributed Generation Projects, available at https://docs.tep.com/wp-content/uploads/TEP-Interconnection-Manual-for-Distributed-Generation.pdf (Section 8.6 “A Customer requesting to interconnect a Generating Facility of Maximum Capacity 21kW to 2000kW, complying with all applicable standards listed in Section 5 along with Screens A through J in Section 8.3, qualifies for the Level 2 Fast Track application process” and Section 10.5 “All costs to implement remote metering for Generating Facilities qualifying for review under Level 2 Fast Track will be borne by TEP”). Page 15
  9. Page 18 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Following on-site meetings, Eversource then determined that the existing transformer 2 would need to be upgraded and relocated before the project could proceed even though it 3 was adequately sized to serve the power from the solar generation. 4 5 Eversource cited concerns that the existing transformer was difficult to access and did not 6 meet current I&R standards because it was located on a slab rather than a vault. 7 Earthlight understood those concerns to relate to existing utility infrastructure and not to 8 any new condition created by the proposed solar project. Eversource has provided no 9 other option, ultimately requiring the customer to pay for additional upgrades to its 10 existing Eversource equipment, which materially changes the project scope and cost and 11 prevents the project from moving forward under the customer’s already-obtained 12 financing. 13 14 Furthermore, Eversource refuses to consider an acceptable alternative line-side tap 15 interconnection method that would result in bypassing direct connection to the existing 16 transformer and would eliminate the costs associated with upgrading the transformer. In 17 several discussions with Eversource, as outlined below, Eversource will not allow this 18 type of interconnection even though it is listed as an acceptable method in the Eversource 19 Connecticut Non-Residential Renewable Energy Solutions Netting & Buy-All Program 20 Guidelines. 21 Q. Isn’t Eversource required to comply with the National Electric Code? 22 A. Yes. The 2024 Eversource I&R Book states: “With respect to Customer’s wiring and 23 electrical installations, no requirement, interpretation, or standard specified in this Page 16
  10. Page 19 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 booklet is intended to supersede or conflict with the standards and regulations of the 2 National Electrical Code, or with any state or municipal law, rule, or ordinance now in 3 force or hereafter enacted or promulgated.”4 4 Q. How does Eversource refuse to accept otherwise NEC-compliant engineering? 5 A. Line-side taps are an NEC-approved interconnection method allowed by other states and 6 utilities under the AHJ review. A line-side tap, also called a supply-side connection, is a 7 method of connecting a parallel power source, such as solar or a battery energy storage 8 system, to the customer’s service conductors or equipment between the utility service 9 point and the building’s main circuit breaker or service disconnect. In simple terms, a 10 line side tap is a connection made after the transformer and before the main breaker 11 rather than through a breaker in the building’s electrical panel or directly into the 12 transformer. The connected system has its own disconnect and overcurrent protection. 13 The NEC expressly provides requirements for safely designing and installing these 14 connections, subject to review and approval by the AHJ. 15 16 The service point is defined as the point at which equipment owner and responsibilities 17 switch from the utility to the building owner. Since the service point is located within the 18 utility transformer, all equipment between the transformer and the building are the 19 customer’s responsibility, to be installed per the NEC, with final design to be reviewed 20 and approved by the local AHJ. 4 See Response to ICC-1, Attachment 5, Section 1, Section 103. Page 17

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Eric Virkler, Justin Daigle and Sean Riel [26-05-10]