Prefiled testimony
Witness: Eric Virkler, Justin Daigle and Sean Riel
Files2
Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
PDF · 129 KB · 1 pageText searchable
Download Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdfRead the text of Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdf
PDF · 158 KB · 33 pagesText searchable
Download ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdfRead the text of ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdf
Page 12 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 otherwise not retained, requiring additional site verification in June 2026. During the 2 second site review, all but one of the six proposed interconnection methods were 3 eventually approved after months of unnecessary delay. 4 5 For the remaining installation, Eversource identified an existing grading issue and 6 transformer pad concerns, which had been discussed during the initial site visit. At that 7 time, a repair to the affected area was determined as an acceptable path forward. 8 However, after the additional June meeting, Eversource required an additional upgrade to 9 install a new transformer pad and re-grade the transformer site. This added approximately 10 $18,000 in additional Eversource scope and approximately $30,000 overall including 11 related customer costs. This represents an increase in the project cost of 4% for the 12 project connected to this point of interconnection. Based on this new requirement, 13 contingent approval was finally issued in September 2026. 14 Q. Can you provide another example? 15 A. Yes. Eversource’s updated guidelines require projects to connect directly to the service 16 point at the building’s transformer, effectively creating a separate service to the building. 17 This requirement restricts the available interconnection options otherwise permitted by 18 the NEC, as adopted under the Connecticut State Building Code. The NEC provides 19 alternative methods for safely interconnecting distributed generation systems on the 20 supply side of the customer’s service equipment. 21 22 This gap between Eversource and NEC requirements was encountered at another recent 23 project in Naugatuck CT, which involved adding a new NRES system to a service that 24 already had an existing ZREC project onsite. On April 28, 2025, Earthlight proposed a Page 10Page 13 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 supply-side (line-side) interconnection and provided detailed information demonstrating 2 that the new connection was fully compliant with the NEC, would not affect the existing 3 project, and would be the most cost-effective option for the customer. During the site 4 review, Earthlight identified unused supply-side equipment that could accommodate the 5 new distributed generation interconnection, reviewed the proposed installation with 6 Eversource field personnel, and provided photographs showing how the work could be 7 completed safely, more cost-effectively, and in compliance with applicable NEC 8 requirements. At the conclusion of that site review, Earthlight understood that the 9 proposed approach was likely acceptable. 10 11 Eversource subsequently reversed course and advised that supply-side connections were 12 no longer permitted except in limited circumstances, requiring Earthlight to challenge 13 that position, escalate the issue internally, and spend months defending the proposed 14 code-compliant approach. After multiple site visits, extensive correspondence, and 15 repeated reviews, Eversource issued a Contingent Approval on July 16, 2025, approving 16 the exact supply-side connection that had been proposed from the outset. 17 Q. Are these examples isolated incidents? 18 A. Unfortunately, no. Another recent front of meter project, located in Bristol, illustrates 19 Earthlight’s concerns about unexpected costs and pricing transparency. In that case, 20 Earthlight requested a Saturday outage for Eversource to disconnect power to an 21 underground transformer and relocate an interior meter outside. Comparable off-shift 22 Eversource work has historically cost Earthlight approximately $3,500 to $8,500. Page 11Page 14 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Following a late-May site visit, Earthlight requested a cost letter on August 19. After 2 multiple follow-ups, Eversource issued a $12,600 estimate on September 16. 3 4 When Earthlight requested a breakdown to explain the charges to the customer, 5 Eversource refused and offered no process for challenging the estimate, leaving 6 Earthlight and the customer facing a substantially higher charge without sufficient 7 supporting detail. Both Earthlight and the customer are left without recourse, without 8 any opportunity to argue our case, and yet another Eversource unanticipated new 9 precedent. This pattern creates even more uncertainty as it prevents Earthlight from 10 being able to accurately portray a project’s true cost to future customers trying to decide 11 whether or not to install solar or storage. 12 13 Q. Does Earthlight have any ability to question or challenge the multiple site visit requirements? 14 A. No. Regrettably, this seems to be a new trend, because site visits were not required under 15 the LREC/ZREC Program. Any time Eversource requests a site visit, we have to attend. 16 Eversource dictates all terms of the site visit, never offering any scheduling flexibility for 17 the customer or for Earthlight. If we request a different date, Eversource refuses to 18 respond to that email. 19 20 Earthlight recently completed a project where the existing Eversource building/customer 21 service equipment and meters were located within an exterior-accessible electrical room 22 and had already been approved as part of the building’s service configuration a few years 23 prior during a major remodel. The electrical room contained multiple tenant meters and a 24 single owner’s meter. Because the solar system was interconnecting ahead of the Page 12Page 15 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 customer meters and directly at the transformer, the location of the existing customer 2 meters had no material electrical impact on the distributed generation interconnection or 3 production metering arrangement. 4 5 Because the updated guidelines required meters to be relocated outside, Earthlight 6 requested a variance during the interconnection application process to allow the existing 7 Eversource meters to remain inside. Had Eversource denied the variance, relocating all 8 of the meters would have imposed substantial costs on the customer and caused extended 9 disruption to residents. Earthlight estimated that relocating the owner’s meter alone 10 would cost between $8,000 and $10,000, excluding any Eversource charges for meter 11 work. Relocating the tenant meters would have added further costs and disruption. After 12 Earthlight provided photographs and revised design drawings, Eversource approved the 13 variance approximately three months after the initial application was submitted. 14 15 However, following approval, Earthlight constructed the project and engaged Eversource 16 to perform the necessary outage required to complete the interconnection. What should 17 have been a simple process required multiple additional Eversource site visits. During 18 the first visit, Eversource representatives again stated that the existing meters needed to 19 be relocated outside. Earthlight provided the representatives with the previously issued 20 variance approval, and additional discussions followed. 21 22 This was the first time Earthlight had received a cost letter requiring payment for 23 interconnection outage work performed during normal working hours. No prior project Page 13Page 16 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 involving an outage during normal working hours had required payment to Eversource. 2 Approximately six additional weeks elapsed before Eversource finally provided the cost 3 letter and the outage was scheduled two weeks thereafter. Even though the outage was 4 requested the beginning of June, the delays caused it to not take place until the middle of 5 August. 6 7 In Earthlight’s view, relocating existing owner or tenant meters should not be a condition 8 of interconnecting a front-of-the-meter project through a new, separate service or through 9 a supply-side connection to existing customer service equipment. Where the existing 10 Eversource metering arrangement is already approved and the proposed interconnection 11 does not affect its safety or operation, requiring relocation imposes additional costs and 12 disruption without a demonstrated need related to the solar interconnection. 13 14 B. Eversource Requirements Frequently Exceed and/or Conflict with the National Electric Code 15 16 Q. Does Earthlight have any recourse when Eversource requires additional equipment or site upgrades? 17 A. No. An example of this is a recent battery storage project. Eversource recently started 18 requiring Real-Time Automation Controller (“RTAC”) equipment on any project 500kW 19 and larger. It is our understanding that this device is traditionally required on much 20 larger projects, and other utilities have established a higher threshold for requiring this 21 equipment, including 1 MW in California1 and 1 MW in New Jersey.2 In addition, 1 See, e.g., California PUC General Order 167, available at https://docs.cpuc.ca.gov/PUBLISHED/GENERAL_Order/108114.htm (Section 3.2 - Small Facilities: “Generating Assets smaller than one megawatt are currently exempt from enforcement of the Standards pursuant to this General Order”). 2 See, e.g., Jersey Central Power & Light Company, Level 2 Interconnection Agreement, Page 3, available at https://www.firstenergycorp.com/content/dam/feconnect/files/retail/nj/NJ-Level-23-Interconnection-ApplicationPage 14Page 17 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Arizona regulators now generally allow projects up to 2 MW to proceed under Fast Track 2 review without requiring the RTAC equipment.3 3 4 We do not have any recourse, no way to present our case that this equipment should not 5 be required. The only option available to Earthlight and our customers is to downsize the 6 project to avoid this rule but then the project does not meet the customer’s needs. Small 7 C & I projects just over that 500kW threshold have to bear the burden of this extremely 8 costly Eversource owned device, which in Earthlight’s experience ranges in cost between 9 $75,000 and $90,000, and requires additional customer-owned equipment alongside the 10 RTAC which costs an additional $27,500. Moreover, Eversource usually requires 11 additional studies that can add $22,500 or more. These costs can ruin the economics of a 12 project this size and prevent them from being built. 13 14 Q. In Earthlight’s experience, does Eversource strictly apply principles of cost causation when determining site upgrades are needed? 15 A. No. In fact, Eversource frequently requires replacement of existing equipment, such as 16 customer meters and transformers that are wholly unrelated to the installation of solar or 17 energy storage on the site. On one particular project, Eversource issued an 18 Interconnection Agreement and Contingent Approval for the subject Buy-All project that 19 did not identify additional project costs based on the proposed interconnection to the 20 existing on-site transformer. The customer obtained financing based on that approval. Agreement.pdf (“Breaker Trip Control: Generators 2 MW and greater will require remote generator trip/isolation control by JCP&L’s system operations control center via a local SCADA unit or similar device”). 3 See, e.g., Tucson Electric Power, Interconnection Manual for Distributed Generation Projects, available at https://docs.tep.com/wp-content/uploads/TEP-Interconnection-Manual-for-Distributed-Generation.pdf (Section 8.6 “A Customer requesting to interconnect a Generating Facility of Maximum Capacity 21kW to 2000kW, complying with all applicable standards listed in Section 5 along with Screens A through J in Section 8.3, qualifies for the Level 2 Fast Track application process” and Section 10.5 “All costs to implement remote metering for Generating Facilities qualifying for review under Level 2 Fast Track will be borne by TEP”). Page 15Page 18 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Following on-site meetings, Eversource then determined that the existing transformer 2 would need to be upgraded and relocated before the project could proceed even though it 3 was adequately sized to serve the power from the solar generation. 4 5 Eversource cited concerns that the existing transformer was difficult to access and did not 6 meet current I&R standards because it was located on a slab rather than a vault. 7 Earthlight understood those concerns to relate to existing utility infrastructure and not to 8 any new condition created by the proposed solar project. Eversource has provided no 9 other option, ultimately requiring the customer to pay for additional upgrades to its 10 existing Eversource equipment, which materially changes the project scope and cost and 11 prevents the project from moving forward under the customer’s already-obtained 12 financing. 13 14 Furthermore, Eversource refuses to consider an acceptable alternative line-side tap 15 interconnection method that would result in bypassing direct connection to the existing 16 transformer and would eliminate the costs associated with upgrading the transformer. In 17 several discussions with Eversource, as outlined below, Eversource will not allow this 18 type of interconnection even though it is listed as an acceptable method in the Eversource 19 Connecticut Non-Residential Renewable Energy Solutions Netting & Buy-All Program 20 Guidelines. 21 Q. Isn’t Eversource required to comply with the National Electric Code? 22 A. Yes. The 2024 Eversource I&R Book states: “With respect to Customer’s wiring and 23 electrical installations, no requirement, interpretation, or standard specified in this Page 16Page 19 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 booklet is intended to supersede or conflict with the standards and regulations of the 2 National Electrical Code, or with any state or municipal law, rule, or ordinance now in 3 force or hereafter enacted or promulgated.”4 4 Q. How does Eversource refuse to accept otherwise NEC-compliant engineering? 5 A. Line-side taps are an NEC-approved interconnection method allowed by other states and 6 utilities under the AHJ review. A line-side tap, also called a supply-side connection, is a 7 method of connecting a parallel power source, such as solar or a battery energy storage 8 system, to the customer’s service conductors or equipment between the utility service 9 point and the building’s main circuit breaker or service disconnect. In simple terms, a 10 line side tap is a connection made after the transformer and before the main breaker 11 rather than through a breaker in the building’s electrical panel or directly into the 12 transformer. The connected system has its own disconnect and overcurrent protection. 13 The NEC expressly provides requirements for safely designing and installing these 14 connections, subject to review and approval by the AHJ. 15 16 The service point is defined as the point at which equipment owner and responsibilities 17 switch from the utility to the building owner. Since the service point is located within the 18 utility transformer, all equipment between the transformer and the building are the 19 customer’s responsibility, to be installed per the NEC, with final design to be reviewed 20 and approved by the local AHJ. 4 See Response to ICC-1, Attachment 5, Section 1, Section 103. Page 17Page 20 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 In our experience, Eversource universally rejects line-side taps from even being 2 considered as an option in all but the rarest cases, which effectively means that the only 3 permitted point of interconnection will be at a customer’s utility transformer. Under the 4 National Electric Safety Code – different from the NEC – the utility has authority to 5 review and reject the design when the point of interconnection is at the transformer. The 6 NESC covers the utility side up to the service point (typically the utility transformer 7 secondary on an underground service or an overhead service drop installed by Eversource 8 to a customer owned building attachment), and the NEC takes over from the service point 9 inward. Eversource uses these two sets of standard as an opportunity to assert 10 jurisdiction to review these projects and require the customer to pay to upgrade the 11 transformer to its latest standards. If Eversource didn’t actively prevent line-side taps, as 12 permitted under the NEC, the local municipality building official would be the AHJ 13 reviewing that interconnection and additional transformer upgrades would not even be 14 discussed. 15 Q. How does Eversource act as the AHJ? 16 A. Requiring interconnections to be made into the transformer effectively makes Eversource 17 an unchallengeable decisionmaker and allows them to require upgrades to transformers 18 that are currently capable of handling the power from the solar project. 19 20 In our experience, Eversource not only refuses otherwise NEC-compliant design options, 21 and rejects customer-owned, code-compliant methods simply as a matter of utility 22 preference. This leads to unnecessary additional engineering and equipment that is not 23 required under the NEC. This single issue causes most of the delays, project cost Page 18Page 21 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 increases, increased Earthlight engineering manhours and frustration in working with 2 Eversource and affects approximately 90% of Earthlight’s front-of-the-meter projects. 3 4 Q. In Earthlight’s experience, do these problems affect both commercial and residential projects equally? 5 A. No. Earthlight's residential division regularly interconnects residential distributed 6 generation systems in Eversource territory, and our experience has generally been that the 7 residential interconnection process is more predictable and more standardized than 8 Earthlight’s experiences on commercial projects. Residential projects do face the same 9 meter relocation requirements, though, which are generally more problematic for RRES 10 projects than NRES projects. Earthlight performs line side tap interconnections for most 11 of our residential netting projects. Eversource does not allow line side taps for residential 12 buy-all projects. Eversource's even administration of residential interconnections 13 demonstrates that a more streamlined and predictable process is achievable. 14 15 Q. Does Eversource also require transformer upgrades or utility pole upgrades for residential projects? 16 A. No. In Earthlight's experience, residential projects under 25 kW are not required to 17 upgrade transformers to satisfy Eversource's latest construction standards because the 18 interconnection point is not within the transformer itself. This contrasts with commercial 19 projects where Earthlight frequently encounters requirements to upgrade transformers 20 that are otherwise capable of supporting the proposed solar generation. From Earthlight's 21 perspective, mandating commercial interconnections be made at the transformer opens 22 the door to Eversource being able to force the customer to pay to for unnecessary 23 upgrades. Page 19
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Eric Virkler, Justin Daigle and Sean Riel [26-05-10]