  1. Page 16 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 involving an outage during normal working hours had required payment to Eversource. 2 Approximately six additional weeks elapsed before Eversource finally provided the cost 3 letter and the outage was scheduled two weeks thereafter. Even though the outage was 4 requested the beginning of June, the delays caused it to not take place until the middle of 5 August. 6 7 In Earthlight’s view, relocating existing owner or tenant meters should not be a condition 8 of interconnecting a front-of-the-meter project through a new, separate service or through 9 a supply-side connection to existing customer service equipment. Where the existing 10 Eversource metering arrangement is already approved and the proposed interconnection 11 does not affect its safety or operation, requiring relocation imposes additional costs and 12 disruption without a demonstrated need related to the solar interconnection. 13 14 B. Eversource Requirements Frequently Exceed and/or Conflict with the National Electric Code 15 16 Q. Does Earthlight have any recourse when Eversource requires additional equipment or site upgrades? 17 A. No. An example of this is a recent battery storage project. Eversource recently started 18 requiring Real-Time Automation Controller (“RTAC”) equipment on any project 500kW 19 and larger. It is our understanding that this device is traditionally required on much 20 larger projects, and other utilities have established a higher threshold for requiring this 21 equipment, including 1 MW in California1 and 1 MW in New Jersey.2 In addition, 1 See, e.g., California PUC General Order 167, available at https://docs.cpuc.ca.gov/PUBLISHED/GENERAL_Order/108114.htm (Section 3.2 - Small Facilities: “Generating Assets smaller than one megawatt are currently exempt from enforcement of the Standards pursuant to this General Order”). 2 See, e.g., Jersey Central Power & Light Company, Level 2 Interconnection Agreement, Page 3, available at https://www.firstenergycorp.com/content/dam/feconnect/files/retail/nj/NJ-Level-23-Interconnection-ApplicationPage 14
  2. Page 17 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Arizona regulators now generally allow projects up to 2 MW to proceed under Fast Track 2 review without requiring the RTAC equipment.3 3 4 We do not have any recourse, no way to present our case that this equipment should not 5 be required. The only option available to Earthlight and our customers is to downsize the 6 project to avoid this rule but then the project does not meet the customer’s needs. Small 7 C & I projects just over that 500kW threshold have to bear the burden of this extremely 8 costly Eversource owned device, which in Earthlight’s experience ranges in cost between 9 $75,000 and $90,000, and requires additional customer-owned equipment alongside the 10 RTAC which costs an additional $27,500. Moreover, Eversource usually requires 11 additional studies that can add $22,500 or more. These costs can ruin the economics of a 12 project this size and prevent them from being built. 13 14 Q. In Earthlight’s experience, does Eversource strictly apply principles of cost causation when determining site upgrades are needed? 15 A. No. In fact, Eversource frequently requires replacement of existing equipment, such as 16 customer meters and transformers that are wholly unrelated to the installation of solar or 17 energy storage on the site. On one particular project, Eversource issued an 18 Interconnection Agreement and Contingent Approval for the subject Buy-All project that 19 did not identify additional project costs based on the proposed interconnection to the 20 existing on-site transformer. The customer obtained financing based on that approval. Agreement.pdf (“Breaker Trip Control: Generators 2 MW and greater will require remote generator trip/isolation control by JCP&L’s system operations control center via a local SCADA unit or similar device”). 3 See, e.g., Tucson Electric Power, Interconnection Manual for Distributed Generation Projects, available at https://docs.tep.com/wp-content/uploads/TEP-Interconnection-Manual-for-Distributed-Generation.pdf (Section 8.6 “A Customer requesting to interconnect a Generating Facility of Maximum Capacity 21kW to 2000kW, complying with all applicable standards listed in Section 5 along with Screens A through J in Section 8.3, qualifies for the Level 2 Fast Track application process” and Section 10.5 “All costs to implement remote metering for Generating Facilities qualifying for review under Level 2 Fast Track will be borne by TEP”). Page 15
  3. Page 18 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Following on-site meetings, Eversource then determined that the existing transformer 2 would need to be upgraded and relocated before the project could proceed even though it 3 was adequately sized to serve the power from the solar generation. 4 5 Eversource cited concerns that the existing transformer was difficult to access and did not 6 meet current I&R standards because it was located on a slab rather than a vault. 7 Earthlight understood those concerns to relate to existing utility infrastructure and not to 8 any new condition created by the proposed solar project. Eversource has provided no 9 other option, ultimately requiring the customer to pay for additional upgrades to its 10 existing Eversource equipment, which materially changes the project scope and cost and 11 prevents the project from moving forward under the customer’s already-obtained 12 financing. 13 14 Furthermore, Eversource refuses to consider an acceptable alternative line-side tap 15 interconnection method that would result in bypassing direct connection to the existing 16 transformer and would eliminate the costs associated with upgrading the transformer. In 17 several discussions with Eversource, as outlined below, Eversource will not allow this 18 type of interconnection even though it is listed as an acceptable method in the Eversource 19 Connecticut Non-Residential Renewable Energy Solutions Netting & Buy-All Program 20 Guidelines. 21 Q. Isn’t Eversource required to comply with the National Electric Code? 22 A. Yes. The 2024 Eversource I&R Book states: “With respect to Customer’s wiring and 23 electrical installations, no requirement, interpretation, or standard specified in this Page 16
  4. Page 19 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 booklet is intended to supersede or conflict with the standards and regulations of the 2 National Electrical Code, or with any state or municipal law, rule, or ordinance now in 3 force or hereafter enacted or promulgated.”4 4 Q. How does Eversource refuse to accept otherwise NEC-compliant engineering? 5 A. Line-side taps are an NEC-approved interconnection method allowed by other states and 6 utilities under the AHJ review. A line-side tap, also called a supply-side connection, is a 7 method of connecting a parallel power source, such as solar or a battery energy storage 8 system, to the customer’s service conductors or equipment between the utility service 9 point and the building’s main circuit breaker or service disconnect. In simple terms, a 10 line side tap is a connection made after the transformer and before the main breaker 11 rather than through a breaker in the building’s electrical panel or directly into the 12 transformer. The connected system has its own disconnect and overcurrent protection. 13 The NEC expressly provides requirements for safely designing and installing these 14 connections, subject to review and approval by the AHJ. 15 16 The service point is defined as the point at which equipment owner and responsibilities 17 switch from the utility to the building owner. Since the service point is located within the 18 utility transformer, all equipment between the transformer and the building are the 19 customer’s responsibility, to be installed per the NEC, with final design to be reviewed 20 and approved by the local AHJ. 4 See Response to ICC-1, Attachment 5, Section 1, Section 103. Page 17
  5. Page 20 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 In our experience, Eversource universally rejects line-side taps from even being 2 considered as an option in all but the rarest cases, which effectively means that the only 3 permitted point of interconnection will be at a customer’s utility transformer. Under the 4 National Electric Safety Code – different from the NEC – the utility has authority to 5 review and reject the design when the point of interconnection is at the transformer. The 6 NESC covers the utility side up to the service point (typically the utility transformer 7 secondary on an underground service or an overhead service drop installed by Eversource 8 to a customer owned building attachment), and the NEC takes over from the service point 9 inward. Eversource uses these two sets of standard as an opportunity to assert 10 jurisdiction to review these projects and require the customer to pay to upgrade the 11 transformer to its latest standards. If Eversource didn’t actively prevent line-side taps, as 12 permitted under the NEC, the local municipality building official would be the AHJ 13 reviewing that interconnection and additional transformer upgrades would not even be 14 discussed. 15 Q. How does Eversource act as the AHJ? 16 A. Requiring interconnections to be made into the transformer effectively makes Eversource 17 an unchallengeable decisionmaker and allows them to require upgrades to transformers 18 that are currently capable of handling the power from the solar project. 19 20 In our experience, Eversource not only refuses otherwise NEC-compliant design options, 21 and rejects customer-owned, code-compliant methods simply as a matter of utility 22 preference. This leads to unnecessary additional engineering and equipment that is not 23 required under the NEC. This single issue causes most of the delays, project cost Page 18
  6. Page 21 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 increases, increased Earthlight engineering manhours and frustration in working with 2 Eversource and affects approximately 90% of Earthlight’s front-of-the-meter projects. 3 4 Q. In Earthlight’s experience, do these problems affect both commercial and residential projects equally? 5 A. No. Earthlight's residential division regularly interconnects residential distributed 6 generation systems in Eversource territory, and our experience has generally been that the 7 residential interconnection process is more predictable and more standardized than 8 Earthlight’s experiences on commercial projects. Residential projects do face the same 9 meter relocation requirements, though, which are generally more problematic for RRES 10 projects than NRES projects. Earthlight performs line side tap interconnections for most 11 of our residential netting projects. Eversource does not allow line side taps for residential 12 buy-all projects. Eversource's even administration of residential interconnections 13 demonstrates that a more streamlined and predictable process is achievable. 14 15 Q. Does Eversource also require transformer upgrades or utility pole upgrades for residential projects? 16 A. No. In Earthlight's experience, residential projects under 25 kW are not required to 17 upgrade transformers to satisfy Eversource's latest construction standards because the 18 interconnection point is not within the transformer itself. This contrasts with commercial 19 projects where Earthlight frequently encounters requirements to upgrade transformers 20 that are otherwise capable of supporting the proposed solar generation. From Earthlight's 21 perspective, mandating commercial interconnections be made at the transformer opens 22 the door to Eversource being able to force the customer to pay to for unnecessary 23 upgrades. Page 19
  7. Page 22 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 2 Q. How does Eversource’s permission to operate (PTO) process differ for residential projects from commercial projects? 3 A. Once a residential project receives approval from the local AHJ, an Eversource employee 4 typically visits the site, installs the meter and issues PTO. While scheduling delays may 5 occur, Earthlight's experience is that Eversource does not use the residential PTO process 6 as an opportunity to re-review the interconnection designs or impose new engineering 7 requirements. Once the AHJ has approved that the installation meets the engineered 8 construction drawings, the PTO is generally always issued. 9 10 The residential process stands in contrast to the commercial process where Eversource 11 personnel uses the PTO step in the process as an opportunity to re-review the 12 interconnection method that has already been approved. In our experience, this 13 duplicative review happens on almost every NRES project and brings great uncertainty 14 into the process that never once occurred during all the years of the ZREC program when 15 PTO was a formality as the AHJ has already reviewed and approved the project. 16 Earthlight never knows if its projects will actually get energized or be required to alter 17 what was already installed. 18 19 Q. Does Eversource typically require site visits to determine acceptable residential interconnection designs? 20 A. No. Earthlight's experience is that residential interconnections are generally reviewed 21 using application materials and engineered drawings against the provided standard details 22 without requiring utility site visits to determine how the project should be interconnected. 23 Q. How do unexpected residential meter relocations affect your projects? 24 A. The most significant concern Earthlight has observed in the residential program is 25 Eversource's requirement that existing interior meters be relocated to the exterior of a Page 20
  8. Page 23 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 building. When this requirement is imposed on a residential solar project, the added cost 2 almost always makes the project financially infeasible. In Earthlight's experience, nearly 3 all residential customers presented with mandatory meter relocation costs elected not to 4 proceed with solar installation. Historically, approximately 98% of such projects died, 5 and 100% of these projects died in the past year. 6 7 Q. How often did meter relocation costs cause projects to die during the predecessor residential program? 8 A. None. Meter relocation was never required prior to the RRES program. 9 10 Q. Has Earthlight observed circumstances where meter relocation requirements appear inconsistent? 11 A. Yes. Earthlight has encountered situations involving relatively new residential buildings 12 where Eversource previously installed and approved interior meter locations but later 13 required those same meters to be relocated outside when solar generation was later 14 proposed. For example, Earthlight recently evaluated a residence constructed in 2025 15 where at that time Eversource had installed a new 400-amp service with the meter located 16 inside the building. When Earthlight later proposed a solar installation at the same 17 property, Eversource required that the meter be relocated to the exterior to comply with 18 current standards, even though these same standards existed when Eversource installed 19 that very meter less than a year prior. 20 21 Earthlight has observed similar circumstances on new commercial properties, including 22 the example discussed earlier in this testimony. The commercial meter relocation 23 example previously mentioned involved a newly constructed building. These costly 24 meter relocations appear to be the result of at best inconsistent or at worst anticompetitive 25 standards that Eversource is applying to solar projects. Page 21
  9. Page 24 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 IV. Why This Is an Eversource Problem 2 3 Q. Surely Eversource must have some role in reviewing Earthlight projects, even if they are not the AHJ? 4 A. Earthlight does not dispute Eversource’s authority over utility-owned equipment, revenue 5 metering, transformer capacity, utility isolation, distribution-system impacts, or 6 legitimate safety tied to utility personnel or facilities. However, when Eversource’s 7 review expands into customer-owned equipment configurations and NEC-compliant 8 interconnection methods, interconnection customers like Earthlight have little recourse to 9 challenge these determinations. 10 11 Q. In Earthlight’s experience, does Eversource apply lessons from one project to the next? 12 A. No. Eversource requires expectations and requirements to be reset from project to project. 13 Although Eversource sometimes provides a case-by-case exception process, requests are 14 often denied without a clear written technical basis, leaving common NEC-recognized, 15 AHJ-reviewed methods treated as unavailable rather than standardized options. 16 Eversource’s governing documents repeatedly call for case-by-case review.5 Consistent 17 standards enforced through a meaningful dispute resolution process could avoid those 18 reviews on most, if not all, fast-track projects reviewed by the AHJ. 19 20 Q. What does Earthlight's residential experience demonstrate regarding Eversource's ability to improve administration of interconnections on commercial projects? 21 A. Earthlight's generally more positive residential experience demonstrates that Eversource 22 is capable of administering an interconnection process that is predictable, standardized 5 See, e.g., Response to ICC-1, Attachment 4, Eversource Technical Interconnection and Interoperability Requirements for Distributed Energy Resources (DERs), Section 3.4 (“As a part of the Impact Study process, projects will be reviewed on a case-by-case basis to determine if additional relays or other protection devices will be required. Any required protection devices will be included in system modifications required to interconnect the DER facility”). Page 22
  10. Page 25 of 33

    Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 and not subject to repeated site reviews or uncertain outcomes. Allowing a supply side 2 connection on commercial projects will remove uncertainty, time, and costs as the NEC 3 already provides standard details for the engineers to follow and for the AHJ to review 4 against. Removing Eversource from the review process of customer owned equipment 5 will save Eversource time, speed up the review process, keep costs from rising, and bring 6 predictability to the entire process. Eversource personnel being instructed to simply 7 install the meter and issue PTO will further remove uncertainty, speed up the process, and 8 keep costs from rising. Earthlight believes many of the same principles applied in the 9 residential program could be applied to commercial projects while preserving system 10 reliability and personnel safety. 11 12 Q. How does Earthlight’s Connecticut Eversource experience compare with other utilities? 13 A. Based on Earthlight’s interconnection experience with National Grid and Eversource East 14 (Massachusetts) projects, the commercial example projects above would have been 15 approved as NEC code-compliant interconnections reviewed by the local building official 16 acting as AHJ. In Massachusetts, the utility generally appropriately focuses on its 17 standards for metering, access, locking and sealing, isolation, and utility-owned 18 equipment. In those territories, the utility does not appear to claim exclusive control over 19 the entire customer service arrangement merely because the interconnection is ahead of 20 the customer’s main service disconnect. That contrast supports Earthlight’s concern that 21 Eversource Connecticut is expanding its review beyond utility-owned equipment into 22 AHJ-reviewed customer equipment and code-compliant design methods. Also, utilities 23 outside of Eversource only require us to meet them on site in very rare circumstances. Page 23