Prefiled testimony
Witness: Eric Virkler, Justin Daigle and Sean Riel
Files2
Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
PDF · 129 KB · 1 pageText searchable
Download Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdfRead the text of Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdf
PDF · 158 KB · 33 pagesText searchable
Download ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdfRead the text of ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdf
Page 22 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 2 Q. How does Eversource’s permission to operate (PTO) process differ for residential projects from commercial projects? 3 A. Once a residential project receives approval from the local AHJ, an Eversource employee 4 typically visits the site, installs the meter and issues PTO. While scheduling delays may 5 occur, Earthlight's experience is that Eversource does not use the residential PTO process 6 as an opportunity to re-review the interconnection designs or impose new engineering 7 requirements. Once the AHJ has approved that the installation meets the engineered 8 construction drawings, the PTO is generally always issued. 9 10 The residential process stands in contrast to the commercial process where Eversource 11 personnel uses the PTO step in the process as an opportunity to re-review the 12 interconnection method that has already been approved. In our experience, this 13 duplicative review happens on almost every NRES project and brings great uncertainty 14 into the process that never once occurred during all the years of the ZREC program when 15 PTO was a formality as the AHJ has already reviewed and approved the project. 16 Earthlight never knows if its projects will actually get energized or be required to alter 17 what was already installed. 18 19 Q. Does Eversource typically require site visits to determine acceptable residential interconnection designs? 20 A. No. Earthlight's experience is that residential interconnections are generally reviewed 21 using application materials and engineered drawings against the provided standard details 22 without requiring utility site visits to determine how the project should be interconnected. 23 Q. How do unexpected residential meter relocations affect your projects? 24 A. The most significant concern Earthlight has observed in the residential program is 25 Eversource's requirement that existing interior meters be relocated to the exterior of a Page 20Page 23 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 building. When this requirement is imposed on a residential solar project, the added cost 2 almost always makes the project financially infeasible. In Earthlight's experience, nearly 3 all residential customers presented with mandatory meter relocation costs elected not to 4 proceed with solar installation. Historically, approximately 98% of such projects died, 5 and 100% of these projects died in the past year. 6 7 Q. How often did meter relocation costs cause projects to die during the predecessor residential program? 8 A. None. Meter relocation was never required prior to the RRES program. 9 10 Q. Has Earthlight observed circumstances where meter relocation requirements appear inconsistent? 11 A. Yes. Earthlight has encountered situations involving relatively new residential buildings 12 where Eversource previously installed and approved interior meter locations but later 13 required those same meters to be relocated outside when solar generation was later 14 proposed. For example, Earthlight recently evaluated a residence constructed in 2025 15 where at that time Eversource had installed a new 400-amp service with the meter located 16 inside the building. When Earthlight later proposed a solar installation at the same 17 property, Eversource required that the meter be relocated to the exterior to comply with 18 current standards, even though these same standards existed when Eversource installed 19 that very meter less than a year prior. 20 21 Earthlight has observed similar circumstances on new commercial properties, including 22 the example discussed earlier in this testimony. The commercial meter relocation 23 example previously mentioned involved a newly constructed building. These costly 24 meter relocations appear to be the result of at best inconsistent or at worst anticompetitive 25 standards that Eversource is applying to solar projects. Page 21Page 24 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 IV. Why This Is an Eversource Problem 2 3 Q. Surely Eversource must have some role in reviewing Earthlight projects, even if they are not the AHJ? 4 A. Earthlight does not dispute Eversource’s authority over utility-owned equipment, revenue 5 metering, transformer capacity, utility isolation, distribution-system impacts, or 6 legitimate safety tied to utility personnel or facilities. However, when Eversource’s 7 review expands into customer-owned equipment configurations and NEC-compliant 8 interconnection methods, interconnection customers like Earthlight have little recourse to 9 challenge these determinations. 10 11 Q. In Earthlight’s experience, does Eversource apply lessons from one project to the next? 12 A. No. Eversource requires expectations and requirements to be reset from project to project. 13 Although Eversource sometimes provides a case-by-case exception process, requests are 14 often denied without a clear written technical basis, leaving common NEC-recognized, 15 AHJ-reviewed methods treated as unavailable rather than standardized options. 16 Eversource’s governing documents repeatedly call for case-by-case review.5 Consistent 17 standards enforced through a meaningful dispute resolution process could avoid those 18 reviews on most, if not all, fast-track projects reviewed by the AHJ. 19 20 Q. What does Earthlight's residential experience demonstrate regarding Eversource's ability to improve administration of interconnections on commercial projects? 21 A. Earthlight's generally more positive residential experience demonstrates that Eversource 22 is capable of administering an interconnection process that is predictable, standardized 5 See, e.g., Response to ICC-1, Attachment 4, Eversource Technical Interconnection and Interoperability Requirements for Distributed Energy Resources (DERs), Section 3.4 (“As a part of the Impact Study process, projects will be reviewed on a case-by-case basis to determine if additional relays or other protection devices will be required. Any required protection devices will be included in system modifications required to interconnect the DER facility”). Page 22Page 25 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 and not subject to repeated site reviews or uncertain outcomes. Allowing a supply side 2 connection on commercial projects will remove uncertainty, time, and costs as the NEC 3 already provides standard details for the engineers to follow and for the AHJ to review 4 against. Removing Eversource from the review process of customer owned equipment 5 will save Eversource time, speed up the review process, keep costs from rising, and bring 6 predictability to the entire process. Eversource personnel being instructed to simply 7 install the meter and issue PTO will further remove uncertainty, speed up the process, and 8 keep costs from rising. Earthlight believes many of the same principles applied in the 9 residential program could be applied to commercial projects while preserving system 10 reliability and personnel safety. 11 12 Q. How does Earthlight’s Connecticut Eversource experience compare with other utilities? 13 A. Based on Earthlight’s interconnection experience with National Grid and Eversource East 14 (Massachusetts) projects, the commercial example projects above would have been 15 approved as NEC code-compliant interconnections reviewed by the local building official 16 acting as AHJ. In Massachusetts, the utility generally appropriately focuses on its 17 standards for metering, access, locking and sealing, isolation, and utility-owned 18 equipment. In those territories, the utility does not appear to claim exclusive control over 19 the entire customer service arrangement merely because the interconnection is ahead of 20 the customer’s main service disconnect. That contrast supports Earthlight’s concern that 21 Eversource Connecticut is expanding its review beyond utility-owned equipment into 22 AHJ-reviewed customer equipment and code-compliant design methods. Also, utilities 23 outside of Eversource only require us to meet them on site in very rare circumstances. Page 23Page 26 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Typically, projects are reviewed and approved without Earthlight ever meeting with 2 utility personnel on site. 3 Q. Can you provide an example? 4 A. Earthlight has encountered similar interconnection questions on several projects in 5 Eversource Eastern Massachusetts and National Grid territories over the past year. For 6 example, on two projects in those territories, Earthlight designed supply-side connections 7 by intercepting the existing customer-owned service lateral ahead of the building’s main 8 service disconnect (i.e., a line side tap). During discussions, utility representatives 9 recognized that these conductors and equipment were customer-owned and subject to 10 inspection by the AHJ. The utilities had no concerns with this solution, provided that 11 Earthlight met the applicable utility metering specifications and clearance requirements, 12 as the utilities did not require a direct connection at the transformer service point. 13 14 On another Eversource Eastern Massachusetts project, similar to the Naugatuck project 15 discussed above, the existing customer service equipment had unused provisions that 16 allowed a connection ahead of the customer’s main service disconnect (another line side 17 tap). Eversource East did not require additional review of that connection method, 18 recognizing it as a matter within the AHJ’s jurisdiction. The AHJ approved the 19 interconnection method, and the project was placed into operation relatively quickly. 20 21 Earthlight’s experience in these Massachusetts territories has been that Earthlight has not 22 been required to relocate existing interior customer meters outside solely because a 23 distributed generation system was being added, in contrast to Eversource Connecticut. Page 24Page 27 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 These experiences underscore that Eversource Connecticut finds ways to frustrate the 2 interconnection process and extend its review into inappropriate forums, including 3 customer-owned equipment and interconnection methods that other utilities have 4 accepted subject to AHJ review and compliance with applicable utility requirements. 5 Q. Is there a utility that PURA should look to as an example in this space? 6 A. Yes. Ameren Illinois provides examples in its published interconnection requirements. In 7 Section 1400 of its Electric Service Manual, Ameren expressly recognizes supply-side 8 connections on the line side of the customer’s main service disconnect as an accepted 9 form of interconnection and specifies the required disconnect, overcurrent protection, and 10 utility access provisions.6 Ameren’s Electric Service Manual and DER Bulletin 2023-1 11 also identifies NEC Sections in article 230 as the basis for allowing these types of 12 connections.7 13 14 These documents demonstrate that a utility can establish specific safety and operating 15 requirements while allowing supply-side interconnections rather than requiring every 16 project to connect directly at the transformer. The documents also show that every single 17 project does not have to involve site visits between utility and contractor and be viewed 18 as a unique case, because Ameren’s standards are detailed and complete to the point 19 where they negate the need to meet with the utility on site. A front of meter solar project 20 with a line side tap which we had designed in accordance with their guidelines was 6 https://www.ameren.com/-/media/files/resources-and-support/construction/service-manual/ameren-electricservice-manual.ashx 7 https://www.ameren.com/-/media/illinois-site/files/electricchoice/bulletin-2023.ashx Page 25Page 28 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 project was approved by Ameren without ever requiring a site visit or the meter 2 relocation or existing equipment upgrades. Permission to operate also went flawlessly. 3 4 Q. Why don’t you sit down with Eversource personnel and walk through your issues with their I&R Guidelines? 5 A. We attempted to do that in late 2023 and early 2024. Each area that we raised on was 6 unilaterally rejected due to ambiguous and unsupported safety and general preference 7 concerns. Walking through individual areas of concern in great detail, including 8 discussion of the NEC, resulted in zero improvements. 9 10 Q. Has Eversource ever incorporated other utility standards or stakeholder feedback to improve their guidelines? 11 A. We explained to Eversource that other utilities allow line side taps and showed them that 12 they were NEC compliant. We specifically shared Ameren’s Electric Service Manual as 13 an example of well thought out utility guidelines that eliminate ambiguity and provide 14 NEC-compliant, safe solar interconnection options. We were told that they would 15 collaborate with us and that they would share their draft I&R Guidelines prior to 16 publishing for our feedback. We were told multiple times that they would provide us 17 with their draft, but in the end they never provided it. When new I&R Guidelines were 18 issued, Eversource held a webinar to explain the updates and answer questions. We were 19 told that they sent out an email notification to any electrician in the state that they felt 20 would benefit from understanding the new rules. Not a single electrician at Earthlight 21 was invited to the webinar. We found out about it after it had occurred. Page 26Page 29 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 V. Why This Is a Ratepayer Problem 2 Q. Why are these issues a ratepayer problem? 3 A. Eversource’s inability to provide standard approvals and clear interconnection 4 requirements causes each project to be treated as unique. The result is inconsistent 5 direction, unnecessary site visits, redesign, resubmissions, and delays instead of 6 predictable expectations like those used by other utilities. Our customers are also 7 Eversource ratepayers, and their direct costs increase when Eversource requires 8 unpredictable upgrades for their project. Moreover, their indirect costs also increase, 9 because Eversource team members spend time on site visits, design review and contractor 10 coordination that standard details or adhering to their own jurisdiction would eliminate. 11 Q. How would improving the interconnection process benefit ratepayers? 12 A. Improving interconnection by reducing timelines and upgrade costs while supporting the 13 deployment of distributed energy resources statewide. This, in turn, can accelerate clean 14 energy development and may reduce the grid investments required to accommodate load 15 growth, ultimately benefiting all ratepayers. Providing standard details that align with the 16 NEC instead of viewing every project as unique would reduce the amount of time 17 Eversource personnel spend reviewing (site visits, back and forth communication with 18 the applicant, multiple design revisions) interconnection applications. Providing a clear 19 line of demarcation for jurisdictional review would also reduce the amount of time 20 Eversource personnel spend reviewing as interconnections outside their purview would 21 be reviewed by the AHJ (as is done in other utilities) and that cost not borne by the 22 ratepayers. Fewer Eversource manhours spent and faster approvals of less costly 23 interconnection solutions would be the outcome, which would be win for all parties. Page 27Page 30 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 VI. Why This Is a Rate Case Issue 2 Q. Why is this an issue for this rate case? 3 A. Eversource staffing directly affects the speed at which these projects can be deployed. 4 Eversource staff resources are being directed to review and approve areas already spelled 5 out clearly in the electrical code that should be or already have been reviewed and 6 approved by the AHJ. Those resources should instead be focused on utility-owned 7 equipment, metering, transformer capacity, utility isolation, distribution-system impacts, 8 and safety tied to utility personnel and facilities. Repeated, duplicative and inefficient use 9 of ratepayer-funded employees is the clearest example of imprudence. 10 Q. How do inconsistent reviews affect Eversource’s resources? 11 A. Inconsistent reviews lead to uncertainty by engineers within the solar industry as they do 12 not know with certainty what will be approved on that particular project, the opposite of 13 what is necessary for an efficient design and review process. Eversource’s inconsistent 14 and inefficient review practices, together with a lack of coordination among its 15 departments, lead to unnecessary and duplicative uses of resources. Treating each project 16 as unique, requiring repeated site visits, and revisiting customer-owned equipment issues 17 slows deployment and consumes resources without improving review of the utility- 18 owned facilities within Eversource’s proper scope. 19 VII. Necessary Changes 20 Q. What changes does Earthlight recommend? 21 A. First, the Authority should establish rapid, binding dispute resolution with real 22 engineering support. Interconnection dispute resolution works through PURA’s Office of 23 Education, Outreach and Enforcement (“EOE”), while program dispute resolution works Page 28Page 31 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 through the Connecticut Ombudsperson who is employed by Sustainable Energy 2 Advantage (“SEA”). While these options have at times been successful, EOE and SEA 3 lack both engineering resources to challenge Eversource’s judgment and meaningful tools 4 to incent their compliance. Without having engineering resources to determine the 5 validity of a claim, they are usually left to simply mediate a resolution. Had such a 6 resolution been obtainable, the issue would never have been brought to dispute 7 resolution. Importantly, a Maine ombudsperson fee model could help fund this third- 8 party engineering review.8 Connecticut already requires third-party review in areas 9 including stormwater and construction ecology monitoring.9 10 11 Second, the Authority should standardize interconnection rules, as other states have done, 12 with appropriate oversight and stakeholder input from the beginning. Eversource should 13 be prohibited from reviewing customer-owned electrical equipment as part of this 14 process. Earthlight does not believe that Eversource should be upgrading their own 15 equipment on the backs of customers installing solar. If Eversource transformers are 16 inadequate, or if Eversource wants them to meet their latest standards, they should go 17 through the normal processes and have those costs reimbursed per the usual process. 8 See Maine PUC Docket No. 2024-00218: https://mpuccms.maine.gov/CQM.Public.WebUI/MatterManagement/MatterFilingItem.aspx?FilingSeq=127078&CaseNumber= 2024-00218. 9 See, e.g., DEEP Construction Stormwater General Permit, available at https://portal.ct.gov//media/deep/water_regulating_and_discharges/stormwater/construction/december-2025-reissuance-docs/2026-0101-construction-stormwater-general-permitfinal.pdf?rev=c9f351bc14cb49e1b80eba48b6fed942&hash=7E7D84CB5E9A1E18DA814BBCC703323B (requiring a “Qualified Inspector” to evaluate the effectiveness of erosion and sediment controls, structural controls, stabilization practices, and any other controls implemented to prevent pollution through a regular monitoring process). Page 29
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Eric Virkler, Justin Daigle and Sean Riel [26-05-10]