Prefiled testimony
Witness: Eric Virkler, Justin Daigle and Sean Riel
Files2
Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
PDF · 129 KB · 1 pageText searchable
Download Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdfRead the text of Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdf
PDF · 158 KB · 33 pagesText searchable
Download ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdfRead the text of ICC - Earthlight Pre-Filed Testimony - Virkler Daigle Riel - FINAL.pdf
Page 4 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. Have you previously testified in any formal hearings before regulatory bodies? 2 A. I have not. 3 Q. Mr. Daigle, please state your full name and business address. 4 A. My name is Justin Daigle. My business address is 128 West Road, Ellington, CT 06029. 5 Q. By whom are you employed and in what position? 6 A. I am employed by Earthlight Technologies as Director of Commercial Construction, a 7 position I have held since 2020. I have been with Earthlight for almost 14 years and have 8 extensive experience in the electrical construction and renewable energy industries dating 9 as far back as 2002. I am a licensed Master Electrician in Connecticut, hold a 10 Massachusetts Journeyman Electrician license, and have been a North American Board of 11 Certified Energy Practitioners-certified Photovoltaic Installation Professional since 2014. 12 13 In my current role as Director of Commercial Construction, I oversee the engineering, 14 preconstruction, procurement, and construction activities associated with Earthlight's 15 commercial solar photovoltaic (PV) and battery energy storage projects. I am responsible 16 for coordinating projects from design development through installation, commissioning, 17 utility interconnection, and final authorization to operate. My primary duties and 18 responsibilities include: commercial construction management, engineering and technical 19 oversight, utility interconnection management, electrical code compliance, field 20 construction coordination, regulatory and policy advocacy. Page 2Page 5 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. Please describe your educational background and employment experience. 2 A. My background is as follows: 3 Education & Training 4 5 6 7 8 9 1995–1999: Technical Trade School – Electrical Studies 2001–2005: Four-Year Electrical Apprenticeship Program Continuing Education: Approximately 30 hours every three years to maintain professional electrical licenses OSHA: 10-Hour Construction Safety Training Professional Licenses & Certifications 10 11 12 13 2005: Connecticut E2 Journeyman Electrician 2008: Connecticut E1 Master Electrician 2012: Massachusetts Journeyman Electrician 2014: NABCEP Photovoltaic Installation Professional (PVIP) 14 Q. Have you previously testified in any formal hearings before regulatory bodies? 15 A. No. 16 Q. Mr. Riel, please state your full name and business address. 17 A. My name is Sean Riel. My business address is 128 West Road, Ellington, CT 06029. 18 Q. By whom are you employed and in what position? 19 A. I have been employed by Earthlight since 2017. In my current role as Director of 20 Residential Sales Operations, I evaluate solar and storage technologies in combination 21 with financial products for use in Earthlight's residential division, and I work with 22 stakeholders across other organizations to develop policies that will encourage growth in 23 solar and storage deployment. I have participated in multiple Public Utilities Regulatory 24 Authority (“PURA” or the “Authority”) dockets this year through participation in written 25 filings and technical meetings, most recently in Dockets 26-06-04, 26-08-02, and 26 26-08-05. Page 3Page 6 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. What is the purpose of your joint testimony in this proceeding? 2 A. The purpose of our testimony is to provide the Authority with Earthlight’s perspective on 3 interconnection practices of The Connecticut Light and Power Company d/b/a 4 Eversource Energy (“Eversource” or the “Company”). These practices directly relate to 5 the review of Eversource rates and charges in this proceeding. Our testimony will: 6 • Describe Earthlight and its Connecticut presence, contractors, and workforce; 7 • Explain the jurisdictional boundary between Eversource’s authority and Authority 8 Having Jurisdiction (“AHJ”) authority over customer-owned, National Electric 9 Code (“NEC”)-compliant equipment, including line-side taps (also known as 10 supply side connections); 11 • 12 Describe several Earthlight projects and Eversource’s coordination and review failures; 13 • 14 Explain why these practices create Eversource, ratepayer, and rate-case problems; and 15 • 16 Recommend changes concerning dispute resolution, engineering review, standard details, jurisdictional boundaries, and NEC-compliant line-side taps. 17 II. Earthlight Overview 18 Q. Please describe Earthlight. 19 A. Earthlight is a Connecticut company that develops, builds, and operates renewable energy 20 projects. Earthlight has developed, designed and built more than 6,400 solar projects, 21 consisting of 6,160 residential solar projects and 270 commercial solar projects. 4,555 of 22 these projects have been constructed in Connecticut, representing approximately 74 MW 23 of capacity, ranging from smaller residential projects to commercial projects up to 1.5 Page 4Page 7 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 MW. Earthlight works on both behind-the-meter and front-of-the-meter solar projects, in 2 both residential and commercial sectors. The majority of Earthlight Connecticut projects, 3 whether they are interconnected behind or in front of the meter, are roof-mounted solar 4 projects in Eversource service territory, meaning that our customers for these projects are 5 also Eversource ratepayers. 6 Q. Does Earthlight use Connecticut contractors? 7 A. Yes. Earthlight is a Connecticut company that employs Connecticut-based staff and 8 installation professionals and while Earthlight relies on Connecticut contractors for 9 engineering, surveying and site work, approximately 95% of the installation is performed 10 by Earthlight employees. 11 Q. How many Connecticut employees does Earthlight have? 12 A. Earthlight currently employs 136 people in Connecticut, in positions including, but not 13 limited to engineers, project managers, construction managers, administrative support 14 staff, electricians, installers, human resources, accounting, sales, and service technicians. 15 III. Eversource Interconnection Issues 16 17 A. Eversource Internal Policies Create Significant Cost Overruns and Demonstrate Imprudent Inefficiencies 18 19 Q. Please describe how Earthlight works with Eversource to bring a project to commercial operation. 20 A. Generally, Earthlight is first approached by a residential or commercial customer seeking 21 to add solar and/or storage at their property. After consulting the Eversource Hosting 22 Capacity Map and verifying the indicated availability of capacity to add a distributed 23 generation resource, Earthlight performs a preliminary feasibility analysis of the Page 5Page 8 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 customer’s property to: define the proposed project, determine its feasibility, align it with 2 the customer’s goals, and establish realistic expectations. 3 4 Once Earthlight and the customer agree on a project timeline and cost, Earthlight designs 5 the interconnection to meet applicable codes and standards, including the National 6 Electrical Code (“NEC”), equipment listing and manufacturer requirements, 7 Occupational Safety and Health Administration (“OSHA”) safety requirements, and 8 Eversource’s Information and Requirements (“I&R”) Guidelines. In this preliminary 9 phase, Earthlight also attempts to satisfy all known Eversource requirements, including 10 those communicated outside the published guidelines. 11 12 Earthlight then submits a formal Interconnection Application, and Eversource reviews the 13 project to determine whether additional distribution network upgrades are required. 14 During the application process and through biweekly calls with Eversource, Earthlight 15 provides photographs, drawings, and specific questions to resolve design issues and 16 minimize unnecessary site visits. For complex projects that become stalled in technical 17 desktop review, Earthlight seeks an onsite meeting with Eversource prior to Contingent 18 Approval to discuss the existing conditions and available interconnection options. Where 19 the design depends on conditions inside utility-owned equipment, such as available 20 transformer termination space, Earthlight relies on Eversource to provide corresponding 21 information and photographs. Because most of Earthlight’s projects are smaller 22 commercial and industrial installations, they typically qualify for the fast-track 23 interconnection process. Upon completing its review, Eversource issues Contingent Page 6Page 9 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Approval to interconnect the project. These projects typically do not require distribution, 2 transmission, or substation upgrades, and the approval confirms whether such upgrades 3 are necessary. 4 Q. What does Contingent Approval mean? 5 A. Contingent Approval is a document that Eversource provides to the interconnection 6 applicant stating that Eversource has completed its application review and the project can 7 proceed toward installation and interconnection, while also providing the scope of the 8 necessary utility upgrades. Under Eversource's Guidelines for Generator Interconnection, 9 Section 5.4, Contingent Approval is issued once all EDC application review elements 10 have been satisfied. This allows Earthlight to proceed with construction, subject to the 11 remaining interconnection requirements. 12 13 However, despite receiving Contingent Approval, Eversource field representatives 14 subsequently require design or equipment changes, including after installation is 15 complete, before Permission to Operate ("PTO") is issued. As a result, designs that have 16 already undergone Eversource's application review remain subject to further 17 interpretation of the I&R Guidelines by individual field representatives, creating 18 uncertainty and potential additional costs or delays. 19 20 Importantly, Contingent Approval also does not provide Earthlight with a clear 21 understanding of the costs associated with Eversource's remaining work to complete the 22 physical interconnection. Page 7Page 10 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. What happens after Contingent Approval? 2 A. Once Contingent Approval is received, Earthlight coordinates with Eversource to arrange 3 any necessary site visits, confirm the utility’s scope, obtain cost letters, and schedule 4 required outage and interconnection work. Following sign-off from the AHJ, Earthlight 5 provides the required closeout documentation and follows up with Eversource to move 6 the project through meter installation and PTO. Eversource schedules its meter 7 technicians, but Earthlight typically has no visibility into that schedule, limiting our 8 ability to coordinate site attendance and resolve questions during the visit. Meter 9 technicians sometimes raise additional concerns when they arrive, including concerns 10 that require further discussion to determine whether corrective work is necessary. When 11 the meter is not installed pending resolution, the project can be delayed by several days or 12 even weeks, even though construction and the AHJ inspection are complete. 13 Q. What happens if a project requires unanticipated upgrades or equipment costs? 14 A. In that event, Earthlight first seeks an explanation in order to describe the changes to its 15 end-user customer and requests an itemized cost. Eversource typically rejects any 16 request to itemize or provide additional granularity on its costs, so there is only a lump 17 sum cost that we can share with the customer. There are four potential outcomes when 18 unanticipated costs are added to a project: 19 20 21 22 23 24 1) The customer agrees to pay the cost, degrading the economics of the project, and proceeds with the approved plan; 2) The customer and Earthlight share in the costs, hurting the economics for both parties, and proceeds with the approved plan; 3) The costs are too great, the project is no longer financially viable for either the customer or Earthlight, and the project does not get built; or Page 8Page 11 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 4) Earthlight finds an approved way to alter the project, often reducing its size, and 2 eliminating or greatly reducing the cost increase. The new project gets reviewed 3 and approved by Eversource and the customer. The end project usually does not 4 meet the customer’s needs. 5 6 Q. Can you provide an example of unanticipated Eversource requirements that either increased costs or reduced the project size? 7 A. Earthlight developed a group of front-of-the-meter affordable multifamily rooftop 8 interconnections. In December 2025, the hosting capacity map showed approximately 5 9 MW of available capacity at that location, which was sufficient capacity to develop this 10 group of projects. Shortly after the projects were designed and submitted in February 11 2026, Earthlight was made aware that available capacity had been reduced to 12 approximately 200 kW with no explanation, forcing at least two of the group projects to 13 be reduced from approximately 300 kW AC to 200 kW AC. This unexplained change 14 created redesign effort, customer/program uncertainty, and a material change to project 15 economics after significant development work had already occurred. 16 17 Eversource also required a multi-department site review in March 2026, including Field 18 Engineering, line/underground, metering, and Distributed Generation personnel. That 19 review focused on transformer locations, metering arrangements, existing service 20 conditions, and acceptable interconnection configurations, which had already been 21 verbally reviewed and generally accepted, with minor accommodations needed to resolve 22 potential issues. Earthlight was not permitted to view or photograph the transformer 23 during this site visit. Following up on this site visit, Eversource later advised that the 24 Field Engineering notes and photos from the March site visit were either unavailable or Page 9Page 12 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 otherwise not retained, requiring additional site verification in June 2026. During the 2 second site review, all but one of the six proposed interconnection methods were 3 eventually approved after months of unnecessary delay. 4 5 For the remaining installation, Eversource identified an existing grading issue and 6 transformer pad concerns, which had been discussed during the initial site visit. At that 7 time, a repair to the affected area was determined as an acceptable path forward. 8 However, after the additional June meeting, Eversource required an additional upgrade to 9 install a new transformer pad and re-grade the transformer site. This added approximately 10 $18,000 in additional Eversource scope and approximately $30,000 overall including 11 related customer costs. This represents an increase in the project cost of 4% for the 12 project connected to this point of interconnection. Based on this new requirement, 13 contingent approval was finally issued in September 2026. 14 Q. Can you provide another example? 15 A. Yes. Eversource’s updated guidelines require projects to connect directly to the service 16 point at the building’s transformer, effectively creating a separate service to the building. 17 This requirement restricts the available interconnection options otherwise permitted by 18 the NEC, as adopted under the Connecticut State Building Code. The NEC provides 19 alternative methods for safely interconnecting distributed generation systems on the 20 supply side of the customer’s service equipment. 21 22 This gap between Eversource and NEC requirements was encountered at another recent 23 project in Naugatuck CT, which involved adding a new NRES system to a service that 24 already had an existing ZREC project onsite. On April 28, 2025, Earthlight proposed a Page 10Page 13 of 33
Earthlight Technologies Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 supply-side (line-side) interconnection and provided detailed information demonstrating 2 that the new connection was fully compliant with the NEC, would not affect the existing 3 project, and would be the most cost-effective option for the customer. During the site 4 review, Earthlight identified unused supply-side equipment that could accommodate the 5 new distributed generation interconnection, reviewed the proposed installation with 6 Eversource field personnel, and provided photographs showing how the work could be 7 completed safely, more cost-effectively, and in compliance with applicable NEC 8 requirements. At the conclusion of that site review, Earthlight understood that the 9 proposed approach was likely acceptable. 10 11 Eversource subsequently reversed course and advised that supply-side connections were 12 no longer permitted except in limited circumstances, requiring Earthlight to challenge 13 that position, escalate the issue internally, and spend months defending the proposed 14 code-compliant approach. After multiple site visits, extensive correspondence, and 15 repeated reviews, Eversource issued a Contingent Approval on July 16, 2025, approving 16 the exact supply-side connection that had been proposed from the outset. 17 Q. Are these examples isolated incidents? 18 A. Unfortunately, no. Another recent front of meter project, located in Bristol, illustrates 19 Earthlight’s concerns about unexpected costs and pricing transparency. In that case, 20 Earthlight requested a Saturday outage for Eversource to disconnect power to an 21 underground transformer and relocate an interior meter outside. Comparable off-shift 22 Eversource work has historically cost Earthlight approximately $3,500 to $8,500. Page 11
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Eric Virkler, Justin Daigle and Sean Riel [26-05-10]