Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Files1

Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Words on different pages
  1. Page 18 of 42

    James R. Dauphinais Page 16 1 approved for UI, subject to the same type of hurdle rate analysis and discount cap 2 PURA approved for UI. 3 Q 4 5 SHOULD AN EDR PARTICIPANT HAVE AN OPPORTUNITY TO EXTEND ITS DISCOUNT BEYOND FIVE YEARS? A Yes. CL&P’s proposed EDR tariff provides that “[n]o discounts under this Rider shall 6 continue for more than five years at any service location.”37 I recommend that a 7 participating customer have one opportunity to extend its discount for an additional 8 five-year term, provided that an updated hurdle rate analysis shows that the revenue 9 from the incremental load at the discounted rate will continue to exceed the incremental 10 cost to serve that load. The capital investments associated with industrial expansions 11 typically have service lives well beyond five years. Where the discounted revenue 12 continues to exceed the incremental cost to serve, an extension continues to provide a 13 contribution to CL&P’s fixed costs that benefits CL&P’s other customers. 14 I recognize that PURA declined to extend the term of the UI EDR from five to 15 seven years, finding the necessity of that increase was not clear based on the record 16 in that proceeding.38 The extension I recommend differs from that proposal because it 17 would not be automatic. It would only be available upon a showing that the extension 18 continues to benefit CL&P’s other customers. In addition, the phrase “at any service 19 location” should be clarified so that it does not prevent a separate, later expansion at 20 the same service location from qualifying for its own EDR discount. 37 38 Exhibit CLP-RATES-3 at 439. Docket No. 22-08-08, August 25, 2023 Decision at 251. BRUBAKER & ASSOCIATES, INC.
  2. Page 19 of 42

    James R. Dauphinais Page 17 1 G. Load Retention 2 Q CL&P’S PROPOSED EDR WOULD NOT BE AVAILABLE FOR LOAD RETENTION. 3 4 DO YOU TAKE ISSUE WITH THAT? A Not within the EDR itself, provided CL&P also has a separate load retention special 5 contract policy. In Docket No. 22-08-08, PURA limited the UI EDR to incremental load, 6 finding “that it is more appropriate to utilize the special contracting process” for load 7 retention purposes.39 PURA also directed UI to file its special contracting policy in its 8 next rate case.40 Because CL&P’s proposed EDR is similarly limited to incremental 9 load, it would provide no benefit to an existing customer whose load is at risk of being 10 reduced or relocated outside of CL&P’s service territory. As I discuss in Section III of 11 my testimony, CL&P should be required to adopt a load retention special contract policy 12 similar to UI’s so that it has an appropriate tool to address such situations. 13 H. EDR Recommendations 14 Q PLEASE SUMMARIZE YOUR RECOMMENDATIONS WITH RESPECT TO CL&P’S 15 16 PROPOSED EDR. A I recommend that PURA approve an EDR for CL&P with the following modifications: 17 18 Make the EDR available to the incremental load of existing Rate 39 customers on the same terms as Rate 57 and Rate 58 customers; 19 20 Specify in the EDR tariff a single minimum incremental load threshold applicable to all participants; 21 22 23 24 Replace the discretionary provisions of Qualification 1(C), Qualification 3 and Conditions 2, 3 and 4 with the clear, objective criteria described in Section II.C of my testimony, including an objective hurdle rate analysis with a methodology described in a compliance filing; 39 40 Docket No. 22-08-08, August 25, 2023 Decision at 251. Id. at 254. BRUBAKER & ASSOCIATES, INC.
  3. Page 20 of 42

    James R. Dauphinais Page 18 1 2 3 Require CL&P to provide a written explanation for any denial of an EDR application and to report annually to PURA the number of EDR inquiries, applications, approvals and denials; 4 5 Remove Condition 1 or, at a minimum, clarify that a customer’s choice of energy supplier does not affect its eligibility for the EDR or trigger any refund of discounts; 6 7 8 9 Remove Condition 7 or, if a performance requirement is retained, measure it against the incremental load in the customer’s Service Agreement over a period of no less than a year, excluding documented maintenance outages and other temporary reductions; 10 11 Establish in this proceeding a discount that is fixed over the five-year term at levels no lower than the 15% and 20% discounts PURA approved for UI; and 12 13 14 15 Provide participants one opportunity to extend the discount for an additional five-year term, subject to an updated hurdle rate analysis, and clarify that a separate, later expansion at the same service location may qualify for its own discount. 16 In addition, as I discuss in Section III of my testimony, CL&P should be required 17 to adopt a load retention special contract policy similar to UI’s. III. NEED FOR A LOAD RETENTION SPECIAL CONTRACT POLICY 18 19 A. Absence of a CL&P Load Retention Policy 20 Q DOES CL&P HAVE A TARIFF OR POLICY THAT ADDRESSES THE RETENTION 21 22 OF EXISTING LOAD THAT IS AT RISK OF BEING LOST? A No. As I discussed in Section II of my testimony, CL&P’s proposed EDR would not be 23 available “for load retention purposes.”41 CL&P’s Rates Panel direct testimony does 24 not propose any other rate, rider or policy to address the retention of existing load. The 25 only provision of CL&P’s tariff that addresses special contracts is Section 5F of its 26 Terms and Conditions for Delivery Service, which states: 27 28 29 30 In the event that the service desired by a customer is not available under any standard rate of the Company, such service (including auxiliary or parallel operation service, service for abnormally large or fluctuating loads, and other types of service under unusual circumstances) may be 41 Davis and Parsons Direct at 25. BRUBAKER & ASSOCIATES, INC.
  4. Page 21 of 42

    James R. Dauphinais Page 19 1 2 3 4 5 obtained, in the sole discretion of the Company, through special contract with the Company to the extent permitted under applicable Terms and Conditions and provided that no discrimination against other customers would result thereby. All such special contracts are subject to review and approval of PURA.42 6 Q IS SECTION 5F A LOAD RETENTION POLICY? 7 A No. Section 5F is a general provision for service that is not available under a standard 8 rate, such as service for abnormally large or fluctuating loads. It does not mention load 9 retention, establishes no eligibility criteria, identifies no information a customer would 10 need to provide, and provides no guidance on the form or level of any discount. 11 Whether to offer a special contract is left to CL&P’s sole discretion. As a result, an 12 existing customer that is considering curtailing or relocating its operations has no way 13 to know whether CL&P would consider a retention rate, or on what terms. 14 Q 15 16 DOES CL&P RECOGNIZE THE IMPORTANCE OF RETAINING EXISTING BUSINESSES IN CONNECTICUT? A Yes. CL&P’s Leadership Panel states that CL&P is proposing economic development 17 rates to stimulate “economic growth by attracting and retaining businesses in 18 Connecticut,” and describes CL&P’s proposed Economic Development Rate as 19 “designed to attract and retain new electric load that businesses might otherwise locate 20 outside Connecticut.”43 However, as I noted above, the EDR actually proposed by 21 CL&P would not be available “for load retention purposes,”44 and CL&P has not 22 proposed any other mechanism to retain existing load that is at risk of being lost due 23 to a competitive alternative or financial circumstances. A load retention special contract 42 Exhibit CLP-RATES-3 at 210-211. CL&P Witnesses Scacco, Chatterjee and Horton Direct (Exhibit CLP-ELP-1) at 10 and 119. 44 Davis and Parsons Direct at 25. 43 BRUBAKER & ASSOCIATES, INC.
  5. Page 22 of 42

    James R. Dauphinais Page 20 1 policy would provide CL&P with the tool needed to address the retention objective its 2 own Leadership Panel identifies. 3 B. UI’s Load Retention Special Contract Policy 4 Q HOW HAS PURA ADDRESSED LOAD RETENTION FOR UI? 5 A In Docket No. 22-08-08, CIEC proposed that UI’s EDR include a load retention 6 provision.45 PURA declined to include load retention in the EDR, but recognized that: 7 8 9 10 11 12 While retaining load that asserts an intention to leave UI’s territory may be economically equivalent to attracting new or expanded load within the territory, it is significantly more difficult to assess whether and how an EDR Rider retained load in Connecticut than it is to assess whether it attracted a new business or load growth by existing Connecticut businesses.46 13 PURA concluded that “it is more appropriate to utilize the special contracting 14 process” for load retention.47 However, PURA also found that UI’s special contracting 15 process was, “at a minimum, not accessible enough to Connecticut businesses or 16 appropriately well known by those business or relevant government agencies, through 17 no fault of their own.”48 PURA therefore directed UI to file its special contracting policy 18 as part of its next rate case application, after discussing the policy with the Connecticut 19 Department of Economic and Community Development (“DECD”).49 20 Q DID UI FILE SUCH A POLICY? 21 A Yes. In Docket No. 24-10-04, UI filed a special contract policy for load retention 22 purposes, which PURA approved with modifications in its October 28, 2025 Decision.50 45 Docket No. 22-08-08, August 25, 2023 Decision at 247. Id. at 251. 47 Id. 48 Id. at 251-252. 49 Id. at 254. 50 Docket No. 24-10-04, October 28, 2025 Decision at 229-231. 46 BRUBAKER & ASSOCIATES, INC.
  6. Page 23 of 42

    James R. Dauphinais Page 21 1 PURA found that the policy, as modified, “provides sufficient flexibility while limiting the 2 risk of free ridership and meets the just and reasonable standard.”51 3 Q 4 5 PLEASE SUMMARIZE THE KEY ELEMENTS OF UI’S POLICY AS APPROVED BY PURA. A Based on PURA’s Decision in Docket No. 24-10-04, the key elements of UI’s policy 6 include: 7 8 9 10 Eligibility for existing non-residential customers not engaged in local commerce, for the purpose of retaining sales that would otherwise be lost due to customers curtailing all or a material portion of their electricity consumption due to the cost of electric distribution service or the availability of lower cost alternative fuels;52 11 12 A discount negotiated on a case-by-case basis that applies only to the delivery component of the customer’s bill;53 13 14 15 16 A price floor for the discounted distribution rate based on long-run marginal distribution cost, with UI permitted to propose larger discounts for PURA’s consideration in circumstances where the price floor is insufficient to retain at-risk load;54 17 18 19 Submission of a profit and loss statement where required by UI or PURA on a case-by-case basis, as one of the factors used to assess the risk of the customer terminating or reducing its operations in Connecticut;55 and 20 PURA approval of any discount provided under a special contract.56 51 Id. at 231. Id. at 230-231. 53 Id. at 230. 54 Id. 55 Id. at 230-231. Required submission of a profit and loss statement on no more than a case-by-case basis, when required by UI or PURA, is a critical finding by PURA as the risk of loss of a particular large customer load may not be related to profits and losses, but instead related to the availability of competitive alternatives to the customer or other unique circumstances not related to the profits and losses of the customer. As PURA noted in the aforementioned portion of its Docket No. 24-10-04 decision, there is no “one size fits all” approach for special contracts. 56 Id. at 230. 52 BRUBAKER & ASSOCIATES, INC.
  7. Page 24 of 42

    James R. Dauphinais Page 22 1 C. Decline in CL&P’s Large Industrial Load 2 Q HAS THE LOAD OF CL&P’S LARGE INDUSTRIAL RATE CLASSES CHANGED 3 4 SINCE CL&P’S LAST RATE CASE? A Yes, it has declined. Table JRD-1 below compares the number of customers and 5 annual sales of Rate 39 and Rate 57 used in CL&P’s last base rate case, Docket 6 No. 17-10-46, with those used in CL&P’s allocated cost of service study in this 7 proceeding.57 TABLE JRD-1 Rate 39 and Rate 57 Customers and Sales Docket No. 17-10-46 Docket No. 26-05-10 Change Percent Change Customers 7 3 (4) (57.1%) Sales (MWh) 274,029 226,711 (47,318) (17.3%) Rate 39 (Large Int. Service) Rate 57 (Lrg. TOD Elec. Srv. Manf.) Customers 112 72 (40) (35.7%) Sales (MWh) 936,448 762,979 (173,469) (18.5%) Customers 119 75 (44) (37.0%) Sales (MWh) 1,210,477 989,690 (220,787) (18.2%) Rate 39 and Rate 57 Combined 57 Docket No. 17-10-46, Exhibit TRP-17, tab “Pg. 8 – Unit Rates,” a copy of which is provided as Exhibit JRD-2; and Exhibit CLP-ACOS-2 at 133-134. BRUBAKER & ASSOCIATES, INC.
  8. Page 25 of 42

    James R. Dauphinais Page 23 1 As shown in Table JRD-1, the number of Rate 39 customers declined from 2 seven to three and the number of Rate 57 customers declined from 112 to 72. 3 Combined annual sales to the two classes declined by approximately 221,000 MWh, 4 or about 18%. 5 Q 6 7 WHAT ARE THE IMPLICATIONS OF THESE DECLINES FOR CL&P’S OTHER CUSTOMERS? A Much of the cost of CL&P’s distribution system is fixed and does not decline when a 8 customer’s load is lost. When load leaves CL&P’s system, the contribution that load 9 was making toward those fixed costs must instead be recovered from CL&P’s 10 remaining customers. 11 I am not suggesting that all of the decline shown in Table JRD-1 was caused 12 by the level of CL&P’s distribution rates, or that all of it could have been avoided with a 13 load retention policy. 14 However, the decline shows that the load of CL&P’s largest industrial customers cannot 15 be taken for granted. As PURA has recognized, commercial and industrial electric 16 rates in Connecticut are high relative to the national average.58 Yet CL&P currently has 17 no defined means to respond when an existing customer’s load is at risk due to the 18 availability of a competitive alternative or the cost of electric distribution service. Facility closures and curtailments occur for many reasons. 19 CL&P’s Leadership Panel also acknowledges that the volumetric recovery of 20 public benefits charges drives up electricity costs for commercial and industrial 21 customers, making them “less competitive relative to their peers in other states where 22 similar costs are not levied through electric rates.” 23 consequence for other customers: “By impairing the ability of businesses to increase 58 Docket No. 22-08-08, August 25, 2023 Decision at 250. BRUBAKER & ASSOCIATES, INC. It further recognizes the
  9. Page 26 of 42

    James R. Dauphinais Page 24 1 load and stifling the creation of new commercial customers, more of the cost must be 2 shouldered by residential customers, contributing to affordability concerns for critical 3 energy service in a state with some of the highest electric rates in the country.”59 The 4 same is true when existing commercial and industrial load is lost. 5 D. Benefits of a Load Retention Policy 6 Q HOW WOULD A LOAD RETENTION SPECIAL CONTRACT POLICY BENEFIT 7 8 CL&P’S OTHER CUSTOMERS? A Where a customer’s load is genuinely at risk, a discounted rate that keeps that load on 9 CL&P’s system while still recovering more than the marginal cost of serving it leaves 10 CL&P’s other customers better off than if the load were lost. 11 continues to contribute toward CL&P’s fixed costs, even at a discounted rate, rather 12 than shifting that contribution to other customers. The price floor, case-by-case review 13 and PURA approval required under UI’s policy are intended to provide this protection 14 while limiting the risk of free ridership. 15 Q 16 17 The retained load HOW WOULD A LOAD RETENTION POLICY RELATE TO CL&P’S PROPOSED EDR? A The two would be complementary. The EDR is designed to attract new and expanded 18 load, while a load retention policy addresses existing load that is at risk of being lost 19 due to a competitive alternative or financial circumstances. An EDR alone provides no 20 benefit to an existing customer whose load is at risk but who is not expanding. Adopting 21 both would give CL&P the same two tools that PURA has approved for UI. 59 Scacco, Chatterjee and Horton Direct at 28. BRUBAKER & ASSOCIATES, INC.
  10. Page 27 of 42

    James R. Dauphinais Page 25 1 Q 2 3 IS THE CONCEPT OF A LOAD RETENTION SPECIAL CONTRACT FAMILIAR TO EVERSOURCE? A Yes. Eversource’s New Hampshire electric utility affiliate, Public Service Company of 4 New Hampshire d/b/a Eversource Energy, is subject to a New Hampshire statute that 5 expressly provides for special contracts designed to retain load. Specifically, that 6 statute states: 7 8 9 10 11 12 II. After June 3, 1996 [the effective date of the statute], new special contracts designed to retain load shall be available to an electric utility customer only if the utility represents that the load would otherwise have left the utility, the contract is approved pursuant to RSA 378:18, and the commission determines that no tariffed rate is sufficient to retain the load.60 13 Like the UI policy approved by PURA, the New Hampshire statute makes load 14 retention special contracts available subject to a showing that the load is at risk and 15 approval by the state regulatory commission. 16 E. Load Retention Special Contract Policy Recommendations 17 Q WHAT DO YOU RECOMMEND WITH RESPECT TO A LOAD RETENTION POLICY 18 19 FOR CL&P? A I recommend that PURA direct CL&P to adopt a load retention special contract policy 20 substantially similar to the UI policy approved by PURA in Docket No. 24-10-04. 21 Specifically, CL&P’s policy should: 22 23 24 25 Be available to existing non-residential customers not engaged in local commerce whose sales would otherwise be lost due to the curtailment of all or a material portion of their electricity consumption, using the eligibility language PURA approved for UI; 26 27 Provide for a discount on the distribution component of the customer’s bill, negotiated on a case-by-case basis, with a price floor based on long-run marginal 60 N.H. Rev. Stat. Ann. § 378:18-a, II, https://gc.nh.gov/rsa/html/XXXIV/378/378-18-a.htm. A copy of this statute is provided as Exhibit JRD-3. BRUBAKER & ASSOCIATES, INC.

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: James R. Dauphinais [26-05-10]

This filing on the current system (opens in a new tab)