Witness: James R. Dauphinais
Files1
CLP 26-05-10 Direct Testimony and Exhibits of James R. Dauphinais.pdf
PDF · 1.1 MB · 42 pagesText searchable
Download CLP 26-05-10 Direct Testimony and Exhibits of James R. Dauphinais.pdfRead the text of CLP 26-05-10 Direct Testimony and Exhibits of James R. Dauphinais.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 27 of 42
James R. Dauphinais Page 25 1 Q 2 3 IS THE CONCEPT OF A LOAD RETENTION SPECIAL CONTRACT FAMILIAR TO EVERSOURCE? A Yes. Eversource’s New Hampshire electric utility affiliate, Public Service Company of 4 New Hampshire d/b/a Eversource Energy, is subject to a New Hampshire statute that 5 expressly provides for special contracts designed to retain load. Specifically, that 6 statute states: 7 8 9 10 11 12 II. After June 3, 1996 [the effective date of the statute], new special contracts designed to retain load shall be available to an electric utility customer only if the utility represents that the load would otherwise have left the utility, the contract is approved pursuant to RSA 378:18, and the commission determines that no tariffed rate is sufficient to retain the load.60 13 Like the UI policy approved by PURA, the New Hampshire statute makes load 14 retention special contracts available subject to a showing that the load is at risk and 15 approval by the state regulatory commission. 16 E. Load Retention Special Contract Policy Recommendations 17 Q WHAT DO YOU RECOMMEND WITH RESPECT TO A LOAD RETENTION POLICY 18 19 FOR CL&P? A I recommend that PURA direct CL&P to adopt a load retention special contract policy 20 substantially similar to the UI policy approved by PURA in Docket No. 24-10-04. 21 Specifically, CL&P’s policy should: 22 23 24 25 Be available to existing non-residential customers not engaged in local commerce whose sales would otherwise be lost due to the curtailment of all or a material portion of their electricity consumption, using the eligibility language PURA approved for UI; 26 27 Provide for a discount on the distribution component of the customer’s bill, negotiated on a case-by-case basis, with a price floor based on long-run marginal 60 N.H. Rev. Stat. Ann. § 378:18-a, II, https://gc.nh.gov/rsa/html/XXXIV/378/378-18-a.htm. A copy of this statute is provided as Exhibit JRD-3. BRUBAKER & ASSOCIATES, INC.Page 28 of 42
James R. Dauphinais Page 26 1 2 distribution cost and the ability for CL&P to propose larger discounts for PURA’s consideration where the price floor is insufficient to retain the at-risk load; 3 4 5 Identify the information an applicant must provide to support its application, with a facility profit and loss statement required only on a case-by-case basis, consistent with PURA’s determination for UI; 6 7 Require PURA review and approval of each special contract entered into under the policy; and 8 9 10 Be referenced in CL&P’s EDR marketing materials and on CL&P’s website, consistent with PURA’s directive to UI that its special contracting process be noted wherever its EDR is marketed.61 11 Because PURA has already reviewed and approved a load retention policy for 12 UI, there is no need to wait until CL&P’s next rate case to put a similar policy in place 13 for CL&P. I recommend that PURA direct CL&P to discuss its proposed policy with 14 DECD and file the policy for approval in a compliance filing within 90 days of PURA’s 15 final decision in this proceeding, with an opportunity for parties to comment. I also 16 recommend that CL&P report annually to PURA the number of load retention inquiries, 17 applications and approved special contracts. Finally, I note that the UI EDR and special 18 contract policy are not included in its tariff or attached to it as a rider. UI only has an 19 EDR webpage with an online application.62 This omission reduces transparency and is 20 problematic insofar as the EDR is a tariff-based rate discount. PURA can avoid a 21 similar issue here by directing CL&P to include the approved EDR and special contract 22 policy in its tariff. 61 62 Docket No. 22-08-08, August 25, 2023 Decision at 254. See https://www.uinet.com/edr. BRUBAKER & ASSOCIATES, INC.Page 29 of 42
James R. Dauphinais Page 27 IV. CL&P’S PROPOSED ALLOCATION OF AMI COSTS 1 2 A. CL&P’s AMI Proposal and Cost Recovery 3 Q PLEASE BRIEFLY DESCRIBE CL&P’S AMI PROPOSAL. 4 A CL&P proposes to begin deploying AMI in 2027. The deployment would include a new 5 Customer Information System (“CIS”) and Meter Data Management System (“MDMS”), 6 an AMI communications network, and the replacement of approximately 1.35 million 7 meters between 2029 and 2032.63 CL&P estimates the total AMI build-out cost from 8 2027 through 2033 at $1.253 billion, consisting of $970.3 million in capital expenditures 9 and $282.8 million in O&M expense.64 10 Q HOW DOES CL&P PROPOSE TO RECOVER THESE COSTS? 11 A CL&P is not proposing to recover AMI costs in base distribution rates in this proceeding. 12 Instead, it proposes to recover AMI capital costs through the capital funding 13 mechanism (“F Factor”) of its proposed Performance-Based Multi-Year Rate 14 Plan (“PBMRP”), and to defer incremental AMI-related O&M expense and stranded 15 automated meter reading (“AMR”) meter costs for future securitization.65 16 Q 17 18 HOW DOES CL&P PROPOSE TO ALLOCATE AMI CAPITAL COSTS TO CUSTOMER CLASSES? A CL&P proposes to allocate AMI capital costs on the basis of class distribution revenue. 19 CL&P’s AMI Panel testimony does not address the allocation of AMI costs to customer 20 classes. However, in response to discovery, CL&P stated: 63 CL&P Witnesses Lawrence and Horton Direct (Exhibit CLP-AMI-1) at 4-5 and 15. Id. at 19. 65 Lawrence and Horton Direct at 5 and 27-28; and CL&P Response to Data Request OCC-739. A copy of all data request responses cited to in this testimony can be found in Exhibit JRD-1 in alphanumeric order. 64 BRUBAKER & ASSOCIATES, INC.Page 30 of 42
James R. Dauphinais Page 28 1 2 3 Under the Company’s proposed PBMRP tariff, costs would be allocated to rate classes on the basis of class distribution revenue (class allocation factors) described in the tariff.66 4 The proposed PBMRP tariff defines Class Allocation Factors as “proportional 5 shares of Base Revenue Requirement for each Customer Class in the Prior Year,” and 6 provides that the incremental revenue adjustment under the PBMRP “will be allocated 7 among Customer Classes using the Class Allocation Factors.”67 With respect to the 8 deferred O&M expense and stranded AMR meter costs, CL&P states that it intends to 9 submit a proposal on the allocation of those costs at the time it seeks to securitize 10 them.68 11 B. Distribution Revenue Is Not a Cost-Based Allocator for AMI Costs 12 Q IS ALLOCATING AMI COSTS ON THE BASIS OF CLASS DISTRIBUTION 13 14 REVENUE COST-BASED? A No. A class’s share of distribution revenue reflects all of the costs recovered through 15 distribution rates, including the demand-related costs of the poles, conductors, 16 transformers and other facilities that are driven by class peak demands. It bears no 17 particular relationship to the number or type of meters serving the class, or to the cost 18 of the communications network and systems needed to read, communicate with and 19 manage data from those meters. AMI costs are driven by the number and type of 20 meters deployed and the number of customers served, not by a class’s share of 21 distribution revenue. 66 CL&P Response to Data Request OCC-740. Exhibit CLP-RATES-3 at 431 and 433. 68 CL&P Response to Data Request OCC-740. 67 BRUBAKER & ASSOCIATES, INC.Page 31 of 42
James R. Dauphinais Page 29 1 Q 2 3 HOW DOES CL&P’S OWN ALLOCATED COST OF SERVICE STUDY ALLOCATE METER COSTS? A CL&P’s allocated cost of service study (“ACOS”) treats meter costs as 4 customer-related. CL&P Witness Nieto explains that “[c]ustomer-related costs vary 5 with the number and type of customers” and that: 6 7 8 9 Allocation factors for the meter plant were based on the relative ratios of the average installed meter cost within a class; with the relative weight of a residential customer set equal to one, each of the other classes is assigned weighting factors.69 10 CL&P’s ACOS uses this weighted meter cost allocator to allocate the meter 11 plant recorded in Account 370 to customer classes.70 In other words, CL&P’s own cost 12 study recognizes that meter costs are caused by the number and type of meters serving 13 each class. 14 Q 15 16 WHAT IS THE EFFECT OF ALLOCATING AMI COSTS ON THE BASIS OF CLASS DISTRIBUTION REVENUE RATHER THAN ON A COST BASIS? A It shifts AMI costs to classes whose share of distribution revenue is large relative to the 17 number and cost of their meters, which are primarily the larger commercial and 18 industrial classes. Table JRD-2 below compares, for selected rate classes, each 19 class’s share of test year distribution revenue with its share of meter plant under the 20 weighted meter cost allocator used in CL&P’s ACOS.71 69 CL&P Witness Nieto ACOS Direct (Exhibit CLP-ACOS-1) at 6. Exhibit CLP-ACOS-2 at 16-20. 71 Exhibit CLP-ACOS-2 at 16-20 (Account 370 meter plant allocation) and 137-142 (test year class distribution revenue). Test year distribution revenue is used here as a proxy for the class shares of Base Revenue Requirement that would be used under CL&P’s proposed PBMRP tariff. 70 BRUBAKER & ASSOCIATES, INC.Page 32 of 42
James R. Dauphinais Page 30 TABLE JRD-2 Class Shares of Distribution Revenue and Meter Plant Share of Distribution Revenue Share of Meter Plant Ratio of Revenue Share to Meter Share Rate 1 (Residential) 54.724% 66.248% 0.8 Rate 5 (Residential Electric Heat) 8.879% 8.849% 1.0 Rate 30 (Small General) 16.970% 18.017% 0.9 Rate 37 (Intermediate Time-of-Day) 4.034% 1.663% 2.4 Rate 39 (Large Interruptible) 0.114% 0.018% 6.3 Rate 56 (Intermediate TOD Non-Manf.) 4.318% 1.005% 4.3 Rate 57 (Large TOD Manufacturers) 1.287% 0.309% 4.2 Rate 58 (Large TOD Non-Manufacturers) 2.692% 0.426% 6.3 Rate Class 1 As shown in Table JRD-2, under CL&P’s proposal, Rate 57 would be allocated 2 about 4.2 times, and Rate 39 about 6.3 times, the share of AMI costs they would be 3 allocated using the weighted meter cost allocator from CL&P’s own ACOS. 4 example, for every $1 million of AMI revenue requirement, Rate 57 would be allocated 5 approximately $12,900 under CL&P’s proposal, compared to approximately $3,100 6 using the weighted meter cost allocator.72 Conversely, the residential Rate 1 class 7 would be allocated a smaller share of AMI costs than its share of meter plant. 72 $12,900 ≈ $12,870 = $1,000,000 x 1.287%; $3,100 ≈ $3,090 = $1,000,000 x 0.309%. BRUBAKER & ASSOCIATES, INC. ForPage 33 of 42
James R. Dauphinais Page 31 1 C. AMI Cost Allocation Recommendations 2 Q WHAT DO YOU RECOMMEND WITH RESPECT TO THE ALLOCATION OF AMI 3 4 COSTS? A I take no position in my testimony on whether PURA should approve CL&P’s AMI 5 deployment or its proposed PBMRP. However, to the extent PURA allows CL&P to 6 recover AMI costs, whether through the PBMRP or another mechanism, I recommend 7 that PURA reject CL&P’s proposal to allocate those costs on the basis of class 8 distribution revenue. Instead, AMI costs should be separately identified and allocated 9 on a cost basis by using the weighted meter cost allocator used in CL&P’s ACOS to 10 allocate Account 370 meter plant. 11 I also recommend that PURA direct CL&P to use the same cost-based 12 allocation for the deferred AMI-related O&M expense and stranded AMR meter costs 13 when it seeks recovery of those costs, unless CL&P demonstrates that a different 14 cost-based method is more appropriate. 15 Q DOES THIS CONCLUDE YOUR DIRECT TESTIMONY? 16 A Yes, it does. BRUBAKER & ASSOCIATES, INC.Page 34 of 42
Appendix A James R. Dauphinais Page 1 Qualifications of James R. Dauphinais 1 2 Q PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. 3 A James R. Dauphinais. My business address is 16690 Swingley Ridge Road, Suite 140, 4 Chesterfield, MO 63017, USA. 5 Q PLEASE STATE YOUR OCCUPATION. 6 A I am a consultant in the field of public utility regulation and a Managing Principal with 7 the firm of Brubaker & Associates, Inc. (“BAI”), energy, economic and regulatory 8 consultants. 9 Q PLEASE SUMMARIZE YOUR EDUCATIONAL BACKGROUND AND EXPERIENCE. 10 A I graduated from Hartford State Technical College in 1983 with an Associate's Degree 11 in Electrical Engineering Technology. Subsequent to graduation, I was employed by 12 the Transmission Planning Department of the Northeast Utilities Service Company73 as 13 an Engineering Technician. 14 While employed as an Engineering Technician, I completed undergraduate 15 studies at the University of Hartford. I graduated in 1990 with a Bachelor's Degree in 16 Electrical Engineering. Subsequent to graduation, I was promoted to the position of 17 Associate Engineer. Between 1993 and 1994, I completed graduate level courses in 18 the study of power system analysis, power system transients and power system 19 protection through the Engineering Outreach Program of the University of Idaho. By 20 1996 I had been promoted to the position of Senior Engineer. 21 In the employment of the Northeast Utilities Service Company, I was 22 responsible for conducting thermal, voltage and stability analyses of the Northeast 73 In 2015, Northeast Utilities changed its name to Eversource Energy. BRUBAKER & ASSOCIATES, INC.Page 35 of 42
Appendix A James R. Dauphinais Page 2 1 Utilities' transmission system to support planning and operating decisions. This 2 involved the use of load flow, power system stability and production cost computer 3 simulations. It also involved examination of potential solutions to operational and 4 planning problems including, but not limited to, transmission line solutions and the 5 routes that might be utilized by such transmission line solutions. Among the most 6 notable achievements I had in this area include the solution of a transient stability 7 problem near Millstone Nuclear Power Station, and the solution of a small signal (or 8 dynamic) stability problem near Seabrook Nuclear Power Station. In 1993 I was 9 awarded the Chairman's Award, Northeast Utilities’ highest employee award, for my 10 work involving stability analysis in the vicinity of Millstone Nuclear Power Station. 11 From 1990 to 1996, I represented Northeast Utilities on the New England Power 12 Pool Stability Task Force. I also represented Northeast Utilities on several other 13 technical working groups within the New England Power Pool (“NEPOOL”) and the 14 Northeast Power Coordinating Council (“NPCC”), including the 1992-1996 New York- 15 New England Transmission Working Group, the Southeastern Massachusetts/Rhode 16 Island Transmission Working Group, the NPCC CPSS-2 Working Group on Extreme 17 Disturbances and the NPCC SS-38 Working Group on Interarea Dynamic Analysis. 18 This latter working group also included participation from a number of ECAR, PJM and 19 VACAR utilities. 20 From 1990 to 1995, I also acted as an internal consultant to the 21 Nuclear Electrical Engineering Department of Northeast Utilities. This included 22 interactions with the electrical engineering personnel of the Connecticut Yankee, 23 Millstone and Seabrook nuclear generation stations and inspectors from the Nuclear 24 Regulatory Commission (“NRC”). 25 In addition to my technical responsibilities, from 1995 to 1997, I was also 26 responsible for oversight of the day-to-day administration of Northeast Utilities' Open BRUBAKER & ASSOCIATES, INC.Page 36 of 42
Appendix A James R. Dauphinais Page 3 1 Access Transmission Tariff. This included the creation of Northeast Utilities' pre-FERC 2 Order No. 889 transmission electronic bulletin board and the coordination of Northeast 3 Utilities' transmission tariff filings prior to and after the issuance of Federal Energy 4 Regulatory Commission (“FERC” or “Commission”) FERC Order No. 888. I was also 5 responsible for spearheading the implementation of Northeast Utilities' Open Access 6 Same-Time Information System and Northeast Utilities’ Standard of Conduct under 7 FERC Order No. 889. During this time, I represented Northeast Utilities on the Federal 8 Energy Regulatory Commission's "What" Working Group on Real-Time Information 9 Networks. Later I served as Vice Chairman of the NEPOOL OASIS Working Group 10 and Co-Chair of the Joint Transmission Services Information Network Functional 11 Process Committee. I also served for a brief time on the Electric Power Research 12 Institute facilitated "How" Working Group on OASIS and the North American Electric 13 Reliability Council facilitated Commercial Practices Working Group. 14 In 1997 I joined the firm of Brubaker & Associates, Inc. The firm includes 15 consultants with backgrounds in accounting, engineering, economics, mathematics, 16 computer science and business. Since my employment with the firm, I have filed or 17 presented testimony before the Federal Energy Regulatory Commission in Consumers 18 Energy Company, Docket No. OA96-77-000; Midwest Independent Transmission 19 System Operator, Inc., Docket No. ER98-1438-000; Montana Power Company, Docket 20 No. ER98-2382-000; Inquiry Concerning the Commission’s Policy on Independent 21 System Operators, Docket No. PL98-5-003; SkyGen Energy LLC v. Southern 22 Company Services, Inc., Docket No. EL00-77-000; Alliance Companies, et al., Docket 23 No. EL02-65-000, et al.; Entergy Services, Inc., Docket No. ER01-2201-000; 24 Remedying Undue Discrimination through Open Access Transmission Service, 25 Standard Electricity Market Design, Docket No. RM01-12-000; Midwest Independent 26 Transmission System Operator, Inc., Docket No. ER10-1791-000; NorthWestern BRUBAKER & ASSOCIATES, INC.