    James R. Dauphinais Page 1 STATE OF CONNECTICUT PUBLIC UTILITIES REGULATORY AUTHORITY Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules ) ) ) ) ) ) Docket No. 26-05-10 Direct Testimony of James R. Dauphinais I. INTRODUCTION AND SUMMARY 1 2 Q PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. 3 A James R. Dauphinais. My business address is 16690 Swingley Ridge Road, Suite 140, 4 Chesterfield, MO 63017. 5 Q WHAT IS YOUR OCCUPATION? 6 A I am a consultant in the field of public utility regulation and a Managing Principal with 7 the firm of Brubaker & Associates, Inc. (“BAI”), energy, economic and regulatory 8 consultants. 9 Q PLEASE DESCRIBE YOUR EDUCATIONAL BACKGROUND AND EXPERIENCE. 10 A This information is included in Appendix A to my testimony. 11 Q ON WHOSE BEHALF ARE YOU APPEARING IN THIS PROCEEDING? 12 A I am appearing on behalf of the Connecticut Industrial Energy Consumers (“CIEC”). 13 CIEC’s members are commercial and industrial organizations, including but not limited BRUBAKER & ASSOCIATES, INC.
  2. Page 4 of 42

    James R. Dauphinais Page 2 1 to traditional manufacturers, that purchase a substantial amount of electric delivery 2 service from The Connecticut Light and Power Company d/b/a Eversource 3 Energy (“CL&P,” “Eversource,” or “Company”) principally under CL&P Rate 39 (Large 4 Interruptible Service) and CL&P Rate 57 (Large Time-of-Day Electric Service 5 Manufacturers). 6 Q WHAT IS THE PURPOSE OF YOUR DIRECT TESTIMONY IN THIS CASE? 7 A The purpose of my direct testimony is to address the following issues: (i) CL&P’s 8 proposed Economic Development Rider (“EDR”), (ii) the need for a special contract 9 load retention policy for CL&P similar to the one that has been put in place by The 10 United Illuminating Company (“UI”) with the approval of the Public Utilities Regulatory 11 Authority (“PURA”), and (iii) CL&P’s proposed allocation to customer classes of its 12 Advanced Metering Infrastructure (“AMI”) costs. 13 My silence in my testimony herein with regard to any issue should not be 14 15 construed as an endorsement of the CL&P’s position on that issue. Q 16 17 18 19 20 21 22 23 24 25 26 27 28 PLEASE BRIEFLY SUMMARIZE YOUR CONCLUSIONS AND RECOMMENDATIONS IN THIS PROCEEDING. A My conclusions and recommendations are as follows: 1. CL&P’s proposal to offer an EDR is reasonable in concept, but the EDR should be modified so that eligible customers can determine in advance whether they qualify and what discount they will receive. PURA should: (i) make the EDR available to the incremental load of existing Rate 39 customers; (ii) replace the provisions that leave eligibility to CL&P’s discretion with clear, objective criteria, including an objective hurdle rate analysis; (iii) remove the partial requirements refund provision and the 10% removal provision, or modify them as I describe; (iv) establish in this proceeding a discount that is fixed over the five-year term at levels no lower than the 15% and 20% discounts PURA approved for The United Illuminating Company; and (v) provide participants one opportunity to extend the discount for an additional five-year term, subject to an updated hurdle rate analysis. BRUBAKER & ASSOCIATES, INC.
  3. Page 5 of 42

    James R. Dauphinais Page 3 1 2 3 4 5 6 7 8 9 2. CL&P has no load retention tariff or policy, and its proposed EDR would not be available for load retention purposes. Since CL&P’s last rate case, the combined number of Rate 39 and Rate 57 customers has declined from 119 to 75 and the combined annual sales to Rate 39 and Rate 57 customers has declined by approximately 18%. PURA should direct CL&P to adopt a load retention special contract policy substantially similar to the policy PURA approved for UI in Docket No. 24-10-04, and to file that policy for approval within 90 days of PURA’s final decision in this proceeding after discussing it with the Connecticut Department of Economic and Community Development (“DECD”). 10 11 12 13 14 15 16 17 18 3. CL&P’s proposal to allocate AMI capital costs to customer classes on the basis of class distribution revenue is not cost-based and would allocate Rate 57 and Rate 39 approximately 4.2 and 6.3 times, respectively, the share of those costs they would be allocated using the weighted meter cost allocator in CL&P’s own allocated cost of service study. To the extent PURA allows CL&P to recover AMI costs, AMI meter investments should be allocated using that weighted meter cost allocator, and the same cost-based approach should apply to deferred AMI-related Operations & Maintenance (“O&M”) expense and stranded automated meter reading meter costs. II. CL&P’S PROPOSED ECONOMIC DEVELOPMENT RIDER 19 20 A. Overview of CL&P’s Proposal 21 Q PLEASE SUMMARIZE CL&P’S PROPOSED EDR. 22 A CL&P proposes a new EDR that would provide a discount on the distribution demand 23 and energy charges applicable to the incremental load of qualifying new and existing 24 large commercial and industrial (“C&I”) customers. The discounted rates would be 25 established on a customer-specific basis through a Service Agreement entered into 26 under the EDR.1 The EDR would only be available to incremental load that would 27 normally be served under Rate 57 (manufacturing customers) or Rate 58 28 (non-manufacturing customers).2 The discount would decline over a five-year term and 29 would be subject to a marginal cost floor and an overall cap tied to the incremental 30 distribution revenues associated with the incremental load.3 1 CL&P Witnesses Davis and Parsons Direct (Exhibit CLP-RATES-1) at 23-24 and 28. Exhibit CLP-RATES-3 at 436 and Davis and Parsons Direct at 24-25. 3 Davis and Parsons Direct at 28-29. 2 BRUBAKER & ASSOCIATES, INC.
  4. Page 6 of 42

    James R. Dauphinais Page 4 1 Q IS THE EDR TARIFF PROPOSED BY CL&P IN FINAL FORM? 2 A No. CL&P describes its proposed EDR as “preliminary and subject to further 3 amendment as the specific functional aspects of the rider are developed 4 (e.g., qualification or form and applicability of pricing discounts).”4 Each page of the 5 proposed EDR tariff is marked “[PRELIMINARY – SUBJECT TO CHANGE]” and the 6 discount percentages for years one through five are shown only as “X.”5 CL&P has 7 also asked PURA to “help facilitat[e] further development of qualifying criteria for its 8 proposed EDR.”6 My recommendations below are intended to assist PURA in that 9 effort. 10 Q 11 12 HAS PURA APPROVED AN EDR FOR ANOTHER CONNECTICUT ELECTRIC DISTRIBUTION COMPANY? A Yes. In Docket No. 22-08-08, PURA approved an EDR for UI.7 The key terms of the 13 UI EDR approved by PURA include: 14 15 16 A fixed discount of 15% on UI’s base distribution rate over a five-year term, increased to 20% for incremental load located in Distressed Municipalities and Environmental Justice Communities; 17 18 19 20 A cap on the discount equal to 50% of the difference between the standard rate revenues over the term from the incremental load and the incremental cost to serve that load, enforced through a simple hurdle rate analysis performed by UI for each application; 21 22 Availability to all C&I customers, without any cap on participation, other than certain C&I customers directly participating in local commerce; and 23 24 A requirement that participating customers participate in at least one clean energy, grid modernization or energy efficiency program.8 4 Davis and Parsons Direct at 24. Exhibit CLP-RATES-3 at 436-439. 6 Davis and Parsons Direct at 26. 7 Docket No. 22-08-08, August 25, 2023 Decision at 249-255. 8 Id. at 249-252 and 255. 5 BRUBAKER & ASSOCIATES, INC.
  5. Page 7 of 42

    James R. Dauphinais Page 5 1 Q WHAT WAS PURA’S PRIMARY OBJECTIVE IN APPROVING THE UI EDR? 2 A PURA explained its primary objective as follows: 3 4 5 6 7 … the primary reason the Authority is approving an EDR is to attract incremental (i.e., new or expanded) load, while still receiving revenues from Subscribers in excess of the incremental cost to serve, which will drive down rates for all other customers, including existing commercial and industrial customers.9 8 CL&P describes the objective of its proposed EDR similarly, stating that its EDR 9 “is intended first and foremost to benefit ratepayers through improved system 10 economics and affordability, while also supporting broader economic development 11 objectives.”10 12 Q DO YOU SUPPORT CL&P OFFERING AN EDR? 13 A Yes. As PURA has recognized, commercial and industrial electric rates in Connecticut 14 are high relative to the national average,11 and that fact remains true today. 15 well-designed EDR can help attract new and expanded load to CL&P’s service territory 16 and, to the extent the revenue from that load exceeds the incremental cost to serve it, 17 place downward pressure on the rates of CL&P’s other customers. However, an EDR 18 can only influence a customer’s siting or expansion decision if the customer can 19 determine, at the time it is making that decision, whether it will qualify and what discount 20 it will receive. 21 certainty, and several others differ from the EDR PURA approved for UI without CL&P 22 explaining why the difference is warranted. I address these provisions below. A Several provisions of CL&P’s proposed EDR do not provide that 9 Docket No. 22-08-08, August 25, 2023 Decision at 250. Davis and Parsons Direct at 31. 11 Docket No. 22-08-08, August 25, 2023 Decision at 250. 10 BRUBAKER & ASSOCIATES, INC.
  6. Page 8 of 42

    James R. Dauphinais Page 6 1 B. Eligibility 2 Q WHICH CUSTOMERS WOULD BE ELIGIBLE FOR CL&P’S PROPOSED EDR? 3 A Eligibility would be limited to incremental load that would normally be served under 4 Rate 57 or Rate 58. CL&P states that the EDR “is not available to any other service 5 class or for load retention purposes.”12 As a result, incremental load served under 6 Rate 39 (Large Interruptible Service) would not be eligible for the EDR. 7 Q 8 9 HAS CL&P EXPLAINED WHY RATE 39 LOAD SHOULD BE EXCLUDED FROM THE EDR? A No. CL&P’s direct testimony does not provide a reason for the exclusion. Rate 39 is 10 available to primary voltage customers that, by contract, agree to interrupt at least 11 2,000 kW of load above their Firm Contract Demand when requested by CL&P, and 12 has been closed to new applications since February 5, 1999.13 Rate 39 customers are 13 therefore existing large industrial customers. An expansion of load by a Rate 39 14 customer would provide the same type of incremental distribution revenue, and the 15 same potential benefit to CL&P’s other customers, as an expansion by a Rate 57 or 16 Rate 58 customer. I also note that PURA made the UI EDR available to all C&I 17 customers other than certain customers directly participating in local commerce.14 18 Q 19 20 21 DO RATE 39 CUSTOMERS ALREADY RECEIVE A DISTRIBUTION SERVICE DISCOUNT? A No. Rate 39 customers are subject to a lower Production/Transmission Demand Charge consistent with the lower capacity cost to serve them. They do not receive a 12 Davis and Parsons Direct at 25. Exhibit CLP-RATES-3 at 286. 14 Docket No. 22-08-08, August 25, 2023 Decision at 252. 13 BRUBAKER & ASSOCIATES, INC.
  7. Page 9 of 42

    James R. Dauphinais Page 7 1 discount on their distribution service charges. Specifically, Rate 39 customers pay an 2 undiscounted distribution demand charge that is actually higher than the distribution 3 demand charge for Rate 57 customers.15 4 Q 5 6 IS THE MINIMUM AMOUNT OF INCREMENTAL LOAD NEEDED TO QUALIFY FOR THE EDR CLEAR? A No. CL&P’s testimony describes eligibility as limited to Rate 57 and Rate 58 customers 7 “with demand generally exceeding one megawatt” and states that a minimum 8 incremental load threshold would be “established in the contract.”16 The proposed EDR 9 tariff, on the other hand, specifies a minimum Incremental Load of 500 kW only for 10 non-tax-exempt facilities, and does not specify any minimum for tax-exempt 11 manufacturing plants or customers located in an Enterprise Zone.17 12 leaving determination of the minimum incremental load subject to the Company’s 13 discretion on a case-by-case basis, a customer should be able to determine from the 14 tariff whether its project is large enough to qualify. Rather than 15 Q WHAT DO YOU RECOMMEND WITH RESPECT TO ELIGIBILITY? 16 A I recommend that PURA require CL&P to: (i) make the EDR available to the incremental 17 load of existing Rate 39 customers on the same terms as Rate 57 and Rate 58 18 customers, whether that load is billed under Rate 39 or under an otherwise applicable 19 firm service rate; and (ii) specify in the EDR tariff a single minimum incremental load 20 threshold applicable to all participants rather than establishing that threshold on a 21 contract-by-contract basis. 15 Exhibit CLP-RATES-3 at 87 and 109. Davis and Parsons Direct at 24-25 and 27. 17 Exhibit CLP-RATES-3 at 436. 16 BRUBAKER & ASSOCIATES, INC.
  8. Page 10 of 42

    James R. Dauphinais Page 8 1 C. Discretionary Qualification Criteria and Conditions 2 Q PLEASE DESCRIBE THE QUALIFICATION REQUIREMENTS OF CL&P’S 3 4 PROPOSED EDR. A Under Qualification 1, a customer must be: (A) an existing or proposed new tax-exempt 5 manufacturing plant; (B) an existing or proposed new customer located in an Enterprise 6 Zone; or (C) a non-tax-exempt facility that has an Incremental Load of 500 kW or more 7 and “provides added value to the Company’s service territory, as determined by the 8 Company.” In addition, the customer must either: (2) obtain economic development 9 funds or loan guarantees from specified state agencies; or (3) “[d]emonstrate to the 10 satisfaction of the Company that concessions provided by this Rider, either alone or in 11 conjunction with concessions from others provide a significant incentive to cause the 12 Customer to add the Incremental Load in the Company’s service area.”18 13 Q WHAT ARE YOUR CONCERNS WITH THESE REQUIREMENTS? 14 A Qualification 1(C) and Qualification 3 leave a customer’s eligibility to CL&P’s discretion 15 without any stated criteria. The proposed tariff does not define “added value” or explain 16 how CL&P will determine whether a project provides it. 17 information a customer would need to provide to demonstrate a “significant incentive” 18 to CL&P’s satisfaction. A customer evaluating whether to expand or locate in CL&P’s 19 service territory would therefore have no reasonable way to know in advance whether 20 it would qualify for the EDR. This uncertainty undermines the ability of the EDR to 21 influence siting and expansion decisions. It also creates the potential for similarly 22 situated customers to be treated differently. 18 Exhibit CLP-RATES-3 at 436. BRUBAKER & ASSOCIATES, INC. Nor does it identify the
  9. Page 11 of 42

    James R. Dauphinais Page 9 1 Q 2 3 DO OTHER PROVISIONS OF CL&P’S PROPOSED EDR DEPEND ON CL&P’S DISCRETION? A Yes. Conditions 2, 3 and 4 of the proposed EDR tariff also depend on CL&P’s 4 discretion: 5 6 7 Condition 2 requires the customer to begin and/or continue implementation of cost-effective energy efficiency and load management measures and programs “as determined appropriate by the Company.” 8 9 10 Condition 3 requires the customer to seek participation in available local, state and federal economic development programs “as determined appropriate by the Company.” 11 12 13 14 15 16 Condition 4 provides that, if the customer has not obtained economic development funds or loan guarantees from the specified state agencies, “the Company must be able to demonstrate, to its satisfaction,” that serving the customer’s Incremental Load at the discount will increase the revenue requirements recovered from CL&P’s remaining customers by less than if the Incremental Load were not served by CL&P.19 17 I do not object to requiring EDR participants to invest in energy efficiency or 18 load management, or to encouraging them to seek other economic development 19 assistance. 20 subsidizing the incremental load. My concern is that, as written, neither customers nor 21 PURA can determine what these conditions actually require, and it is unclear what 22 information a customer would need to provide for CL&P to make the Condition 4 23 demonstration to its own satisfaction. I also agree that the discount should not result in other customers 24 Q WHAT DO YOU RECOMMEND WITH RESPECT TO THESE PROVISIONS? 25 A Eligibility for the EDR should be determined by clear, objective criteria stated in the 26 tariff rather than by CL&P’s discretion. Specifically, I recommend that PURA require 27 CL&P to: 19 Exhibit CLP-RATES-3 at 437. BRUBAKER & ASSOCIATES, INC.
  10. Page 12 of 42

    James R. Dauphinais Page 10 1 2 3 4 5 Remove the requirement in Qualification 1(C) that a facility provide “added value to the Company’s service territory, as determined by the Company,” so that any C&I facility meeting the minimum incremental load threshold may qualify, subject to the same exception for customers directly participating in local commerce that PURA approved for UI; 6 7 8 9 10 Replace the “satisfaction of the Company” standard in Qualification 3 with a requirement that the customer provide a narrative description of why its load is increasing or, for a new customer, the role of the EDR in its decision to locate in CL&P’s service territory, similar to the application requirement PURA approved for UI;20 11 12 13 Replace Condition 2 with a requirement that the customer participate in at least one clean energy, grid modernization or energy efficiency program, as PURA required for UI;21 14 15 16 17 18 Remove Condition 3 as a condition of eligibility. CL&P may encourage EDR participants to seek other economic development assistance, but eligibility should not depend on whether the customer seeks such assistance, since some projects may have limited or no access to it. The UI EDR approved by PURA contains no such requirement; 19 20 21 22 23 24 25 26 27 Replace Condition 4 with an objective hurdle rate analysis, applied in the same manner to every application, under which CL&P compares the net present value of the revenue from the incremental load over the term, inclusive of the discount, to the incremental cost to serve that load, similar to the analysis PURA required of UI.22 CL&P should describe the methodology for this analysis in a compliance filing so that customers and PURA understand how it will be performed. This is consistent with CL&P’s own proposal to anchor the discount to a marginal cost floor and cap it based on the incremental distribution revenue from the incremental load;23 and 28 29 30 31 Provide a written explanation to any customer whose EDR application is denied, and report annually to PURA the number of EDR inquiries, applications, approvals and denials, similar to the information PURA required UI to include in its annual EDR report.24 20 Docket No. 22-08-08, August 25, 2023 Decision at 252. Id. 22 Docket No. 22-08-08, August 25, 2023 Decision at 250-251. 23 Davis and Parsons Direct at 28-29. 24 Docket No. 22-08-08, August 25, 2023 Decision at 253. 21 BRUBAKER & ASSOCIATES, INC.