    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 STATE OF CONNECTICUT PUBLIC UTILITIES REGULATORY AUTHORITY Docket No. 26-05-10 APPLICATION OF THE CONNECTICUT LIGHT AND POWER COMPANY D/B/A EVERSOURCE ENERGY TO AMEND ITS RATE SCHEDULES DIRECT TESTIMONY OF JEAN-PAUL LA MARCHE On Behalf of The Interconnection Customer Coalition October 21, 2026
  2. Page 2 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Table of Contents I. Introduction II. Greenskies Overview III. Eversource Interconnection Issues IV. Why This Is a Rate Case Customer Service Issue V. Why This Is an Eversource Ratepayer Problem VI. Necessary Changes VII. Conclusion Docket No. 26-05-10
  3. Page 3 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 I. Introduction 2 Q. Please state your full name and business address. 3 A. My name is Jean-Paul La Marche. My business address is 127 Washington Avenue, West 4 Building, Lower Level, North Haven, CT 06473. 5 Q. By whom are you employed and in what position? 6 A. I am employed by Greenskies Clean Energy (“Greenskies” or “GCE”) as Vice President 7 of Development, a position I have held since October 2022. In this capacity, I manage 8 the team responsible for developing ground-mounted solar projects from land origination 9 through construction readiness. My team prepares the designs needed for interconnection 10 applications, manages the application and study process, secures executed 11 interconnection agreements, and coordinates with the utility from IA execution through 12 readiness for energization. I have been employed by Greenskies since January 2017. 13 Q. Please describe your educational background and employment experience. 14 A. I hold a B.S. in Mechanical Engineering from the University of California, San Diego. I 15 have worked in the solar photovoltaic industry since 2009 as an engineer and developer 16 and have managed teams since 2014. Before joining Greenskies and Clean Focus, I 17 worked at two startup solar companies designing and developing solar projects and 18 managing their interconnection. 19 Q. Have you previously testified in any formal hearings before regulatory bodies? 20 A. Yes. I have previously testified in support of multiple GCE projects before the 21 Connecticut Siting Council. Page 1
  4. Page 4 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. What is the purpose of your testimony in this proceeding? 2 A. The purpose of my testimony is to provide the Public Utilities Regulatory Authority 3 (“PURA” or the “Authority”) with the perspective of a Connecticut-based solar developer 4 regarding the interconnection customer service practices of The Connecticut Light and 5 Power Company d/b/a Eversource Energy (“Eversource” or the “Company”). These 6 practices directly relate to the review of Eversource’s staffing, rates, and charges in this 7 proceeding. Specifically, my testimony will: 8 • Describe Greenskies and its presence and workforce in Connecticut; 9 • Identify Eversource’s lack of transparency and communication regarding 10 construction timelines for Greenskies projects with interconnection agreements in 11 place, and recurring delays in study reports; 12 • 13 Explain the federal Investment Tax Credit (“ITC”) deadlines that make timeline certainty essential; 14 • 15 Explain why these failures reflect a customer service and staffing issue properly considered in this rate case, and how they harm Eversource ratepayers; and 16 • 17 Recommend rapid, binding dispute resolution rules, with incentives and penalties, so that interconnection customers can rely on Eversource’s timelines. 18 II. Greenskies Overview 19 Q. Please describe Greenskies. 20 A. Greenskies is a Connecticut company that develops, builds, and operates solar and energy 21 storage projects. GCE has developed 743 projects nationwide, 204 of which are located 22 in Connecticut, representing approximately 112.68 MW of capacity. In Connecticut, 23 Greenskies develops rooftop, carport, and ground-mounted commercial solar projects, Page 2
  5. Page 5 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 generally ranging from 250 kWac to 5 MWac, with some larger grid-connected ground- 2 mounted projects. Greenskies is active in the Non Residential Renewable Energy 3 Solutions (“NRES”) and Shared Clean Energy Facilities (“SCEF”) programs. Through 4 spring 2026, Greenskies received 15 SCEF awards representing more than 60 MWac and 5 78 NRES awards representing more than 95 MWac. Most NRES projects use the Buy-All 6 configuration, with a significant number using the Netting configuration. 7 Q. Does Greenskies use Connecticut contractors? 8 A. Yes. Greenskies is a Connecticut company that employes Connecticut staff and relies on 9 Connecticut contractors for civil engineering and construction work. GCE engages four 10 civil engineering firms with Connecticut offices—SLR, VHB, Langan, and Verdantas— 11 and approximately eight to ten civil contractors, including Earth Dynamics, Avery 12 Construction, Standard Builders, and Supreme Industries. These contractors also use 13 Connecticut subcontractors for work such as landscaping and fencing. Greenskies has 14 spent more than $10 million using these Connecticut businesses to support its projects. 15 Q. How many Connecticut employees does Greenskies have? 16 A. Greenskies currently employs more than 50 people in Connecticut, in positions including 17 executive leadership, asset management, construction project management, design and 18 estimating, procurement, financial planning and analysis, business development, legal, 19 operations and maintenance, and project delivery. Page 3
  6. Page 6 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 III. Eversource Interconnection Issues 2 A. Eversource Does Not Provide Construction Timeline Certainty 3 Q. What deadlines control the Connecticut Interconnection process? 4 A. Connecticut interconnection is generally administered under guidelines that at one time 5 were formally reviewed and approved by PURA or its predecessor the DPUC. 6 Eversource cites to a variety of dockets in its response to ICC-2 where it says the 7 Interconnection Guidelines were filed, but it is unclear to us whether PURA has fully 8 reviewed and approved the Guidelines since 2003. Moreover, it is further unclear 9 whether PURA ever stepped in to review and approve Eversource’s Standard Fast Track 10 and Study Process Generator Interconnection Agreement (“Standard IA”). Other states 11 use tariffs1 or form interconnection agreements that impose automatic penalties for utility 12 timeline misses.2 13 14 Q. How is Eversource required to support an interconnection customer’s construction timelines under the Standard IA? 15 A. The Standard IA lays out a series of milestones that bind both the interconnection 16 customer and Eversource. In order to meet the project’s in-service date (“ISD”), all 17 stated milestones must be completed at least 3 weeks prior, including all easement 18 requirements for the project. Under Appendix F, Attachment 1, Eversource is supposed 19 to have a construction kick off meeting 15 business days after the interconnection 20 customer makes 100% payment. 1 See California PUC, Electric Rule 21: Generating Facility Interconnections, available at https://www.cpuc.cA.gov/rule21/. 2 See, e.g., Maine PUC, Docket No,. 2013-00531, Order Adopting Standard Form Interconnection Agreement, available at https://www.maine.gov/mpuc/sites/maine.gov.mpuc/files/inline-files/2013-531-ODR-5-28-14.pdf; see also FERC Explainer on the Interconnection Final Rule - Improvements to Generator Interconnection Procedures and Agreements, Docket No. RM22-14-000, Order No. 2023, available at https://www.ferc.gov/explainerinterconnection-final-rule. Page 4
  7. Page 7 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 2 Q. In GCE’s experience, do these milestones allow for sufficient transparency and predictability into project construction? 3 A. No. Greenskies has four Eversource projects with executed interconnection agreements 4 (“IAs”) that are targeted for in-service in 2026 or early 2027. Eversource itself has 5 identified the in-service dates (“ISDs”) reflected in those IAs as follows: Eversource Project Location ISD per IA INT-94763 Morris December 31, 2026 INT-60376 Woodbury March 2027 INT-81326 Scotland Q1 2027 INT-82635 Stonington December 31, 2026 6 7 Despite repeated requests, and involving outside counsel, Greenskies has been unable to 8 achieve construction timeline certainty for any of these projects. 9 10 Q. What efforts has Greenskies made to obtain construction schedules from Eversource? 11 A. On July 16, 2026, Greenskies’ Interconnection Specialist Engineer first requested 12 meetings with Eversource to align on the construction schedule and critical milestones for 13 these 2026 and 2027 projects, confirm developer and utility responsibilities, identify 14 outstanding engineering and construction items, track the path to energization, and 15 establish communication protocols. Greenskies also asked Eversource to include the 16 appropriate Engineering, Easements, Construction, Protection and Control, Metering, and 17 Outage Coordination personnel so as to facilitate a productive meeting. Since that time, 18 despite repeated follow up inquiries from multiple Greenskies personnel, Eversource’s 19 project manager has refused to participate in any such meeting and has yet to provide 20 estimated construction timelines or construction team contact information for projects 21 that are targeted to be in service by the end of the year. Page 5
  8. Page 8 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 B. Eversource Study Reports Are Consistently Late 2 Q. Has Greenskies experienced delays earlier in the process at the study stage? 3 A. Yes. GCE has experienced repeated delays in receiving study reports and study 4 agreements. Over a dozen pending projects have delayed study reports, as follows: 5 • INT-115515: impact study report, due September 8, 2026, delayed; 6 • INT-100786: distribution impact study report delayed; the draft report omitted the 7 estimated cost required by the study agreement; and issuance of the facility study 8 agreement was delayed; 9 • INT-113967/113964: study report, due September 17, 2026, delayed; 10 • INT-98869: study report and facility study agreement delayed, with drastic 11 changes in the estimated interconnection cost; 12 • INT-117135: impact study report, due at the end of August 2026, delayed; and 13 • INT-121014, 121016, 121017, 121018, 121361, 121691, and 121692: delays in 14 issuing study agreements. 15 C. ITC Timeline Implications 16 Q. Why does timeline certainty matter so much right now? 17 A. Because of the federal Investment Tax Credit (“ITC”) changes, the key hard deadline for 18 project completion is December 31, 2029 for certain Greenskies projects relying on a 19 module safe harbor. Simply put, if a project is unable to achieve commercial operation 20 by this date, it will be totally uneconomic and will be terminated in advance of incurring 21 more costs. This is in essence a portfolio risk management strategy. Page 6
  9. Page 9 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Because of this brightline date – which the industry has referred to as a cliff – if a project 2 is significantly delayed or it becomes otherwise uncertain that it will achieve operations 3 by a certain date, the interconnection customer may be incentivized to terminate it much 4 earlier and redeploy its safe-harbored equipment to projects with more certain timelines. 5 Q. How does project timeline uncertainty affect Greenskies’ Connecticut portfolio? 6 A. Many of these projects are already permitted and are awaiting next steps from Eversource 7 to begin construction. These are shovel-ready projects that can contribute to 8 Connecticut’s zero carbon power supply as soon as December of this year. Importantly, 9 every solar and storage project lost in this way contributes to Connecticut missing its 10 renewable energy goals. 11 IV. Why This Is a Rate Case Customer Service Issue 12 Q. Why are these interconnection issues relevant to this rate case? 13 A. Eversource’s staffing directly affects the speed at which these projects can be deployed. 14 The pattern described above (no kickoff, no construction schedule, no status updates, and 15 late study reports) reflects a lack of appropriate Company resources dedicated to 16 interconnection customer service. 17 Q. Does Eversource’s use of vendors affect customer service? 18 A. Yes. Greenskies’ primary Eversource point of contact for these projects is a contractor 19 from Burns & McDonnell serving as Eversource’s Distributed Resources Project 20 Manager. Reliance on such vendors incentivizes poor customer service, because contract 21 personnel have little incentive to respond or collaborate with interconnection customers, 22 and Eversource bears no consequence when their contractors do not respond. Page 7
  10. Page 10 of 17

    Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. Can interconnection customers simply take their business elsewhere? 2 A. No. Interconnection customers are captive. A project located in Connecticut Eversource’s 3 service territory can only interconnect with Eversource, and there is no meaningful 4 recourse for addressing utility delays. Standard IAs impose no penalty, and Eversource 5 suffer no consequences for failure to meet their own deadlines. As a result, 6 interconnection disputes increasingly take up valuable Authority time and resources in 7 dispute resolution. More frequently, however, without rapid, binding dispute resolution, 8 interconnection customers are choosing to terminate projects instead. 9 Q. Are these issues common across utilities? 10 A. No. In our experience, these issues arise primarily in Eversource’s Connecticut service 11 territory. Two Greenskies projects located in United Illuminating (“UI”) service territory 12 with requested 2026 ISDs are both on track. By contrast, of the four Eversource projects 13 for which Greenskies requested 2026 ISDs, Eversource has provided no hard dates, no 14 updates, and thus GCE no confidence that the in-service goals will be reached. 15 16 The following chart compares Greenskies’ Soundview project in UI territory with its 17 Lantern Hill and Morris projects in Eversource territory: Page 8

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Jean-Paul La Marche [26-05-10]