Prefiled testimony
Witness: Jean-Paul La Marche
Files2
Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
PDF · 129 KB · 1 pageText searchable
Download Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdfRead the text of Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
ICC - Greenskies Pre-Filed Testimony - La Marche - FINAL.pdf
PDF · 88 KB · 17 pagesText searchable
Download ICC - Greenskies Pre-Filed Testimony - La Marche - FINAL.pdfRead the text of ICC - Greenskies Pre-Filed Testimony - La Marche - FINAL.pdf
Page 4 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. What is the purpose of your testimony in this proceeding? 2 A. The purpose of my testimony is to provide the Public Utilities Regulatory Authority 3 (“PURA” or the “Authority”) with the perspective of a Connecticut-based solar developer 4 regarding the interconnection customer service practices of The Connecticut Light and 5 Power Company d/b/a Eversource Energy (“Eversource” or the “Company”). These 6 practices directly relate to the review of Eversource’s staffing, rates, and charges in this 7 proceeding. Specifically, my testimony will: 8 • Describe Greenskies and its presence and workforce in Connecticut; 9 • Identify Eversource’s lack of transparency and communication regarding 10 construction timelines for Greenskies projects with interconnection agreements in 11 place, and recurring delays in study reports; 12 • 13 Explain the federal Investment Tax Credit (“ITC”) deadlines that make timeline certainty essential; 14 • 15 Explain why these failures reflect a customer service and staffing issue properly considered in this rate case, and how they harm Eversource ratepayers; and 16 • 17 Recommend rapid, binding dispute resolution rules, with incentives and penalties, so that interconnection customers can rely on Eversource’s timelines. 18 II. Greenskies Overview 19 Q. Please describe Greenskies. 20 A. Greenskies is a Connecticut company that develops, builds, and operates solar and energy 21 storage projects. GCE has developed 743 projects nationwide, 204 of which are located 22 in Connecticut, representing approximately 112.68 MW of capacity. In Connecticut, 23 Greenskies develops rooftop, carport, and ground-mounted commercial solar projects, Page 2Page 5 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 generally ranging from 250 kWac to 5 MWac, with some larger grid-connected ground- 2 mounted projects. Greenskies is active in the Non Residential Renewable Energy 3 Solutions (“NRES”) and Shared Clean Energy Facilities (“SCEF”) programs. Through 4 spring 2026, Greenskies received 15 SCEF awards representing more than 60 MWac and 5 78 NRES awards representing more than 95 MWac. Most NRES projects use the Buy-All 6 configuration, with a significant number using the Netting configuration. 7 Q. Does Greenskies use Connecticut contractors? 8 A. Yes. Greenskies is a Connecticut company that employes Connecticut staff and relies on 9 Connecticut contractors for civil engineering and construction work. GCE engages four 10 civil engineering firms with Connecticut offices—SLR, VHB, Langan, and Verdantas— 11 and approximately eight to ten civil contractors, including Earth Dynamics, Avery 12 Construction, Standard Builders, and Supreme Industries. These contractors also use 13 Connecticut subcontractors for work such as landscaping and fencing. Greenskies has 14 spent more than $10 million using these Connecticut businesses to support its projects. 15 Q. How many Connecticut employees does Greenskies have? 16 A. Greenskies currently employs more than 50 people in Connecticut, in positions including 17 executive leadership, asset management, construction project management, design and 18 estimating, procurement, financial planning and analysis, business development, legal, 19 operations and maintenance, and project delivery. Page 3Page 6 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 III. Eversource Interconnection Issues 2 A. Eversource Does Not Provide Construction Timeline Certainty 3 Q. What deadlines control the Connecticut Interconnection process? 4 A. Connecticut interconnection is generally administered under guidelines that at one time 5 were formally reviewed and approved by PURA or its predecessor the DPUC. 6 Eversource cites to a variety of dockets in its response to ICC-2 where it says the 7 Interconnection Guidelines were filed, but it is unclear to us whether PURA has fully 8 reviewed and approved the Guidelines since 2003. Moreover, it is further unclear 9 whether PURA ever stepped in to review and approve Eversource’s Standard Fast Track 10 and Study Process Generator Interconnection Agreement (“Standard IA”). Other states 11 use tariffs1 or form interconnection agreements that impose automatic penalties for utility 12 timeline misses.2 13 14 Q. How is Eversource required to support an interconnection customer’s construction timelines under the Standard IA? 15 A. The Standard IA lays out a series of milestones that bind both the interconnection 16 customer and Eversource. In order to meet the project’s in-service date (“ISD”), all 17 stated milestones must be completed at least 3 weeks prior, including all easement 18 requirements for the project. Under Appendix F, Attachment 1, Eversource is supposed 19 to have a construction kick off meeting 15 business days after the interconnection 20 customer makes 100% payment. 1 See California PUC, Electric Rule 21: Generating Facility Interconnections, available at https://www.cpuc.cA.gov/rule21/. 2 See, e.g., Maine PUC, Docket No,. 2013-00531, Order Adopting Standard Form Interconnection Agreement, available at https://www.maine.gov/mpuc/sites/maine.gov.mpuc/files/inline-files/2013-531-ODR-5-28-14.pdf; see also FERC Explainer on the Interconnection Final Rule - Improvements to Generator Interconnection Procedures and Agreements, Docket No. RM22-14-000, Order No. 2023, available at https://www.ferc.gov/explainerinterconnection-final-rule. Page 4Page 7 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 2 Q. In GCE’s experience, do these milestones allow for sufficient transparency and predictability into project construction? 3 A. No. Greenskies has four Eversource projects with executed interconnection agreements 4 (“IAs”) that are targeted for in-service in 2026 or early 2027. Eversource itself has 5 identified the in-service dates (“ISDs”) reflected in those IAs as follows: Eversource Project Location ISD per IA INT-94763 Morris December 31, 2026 INT-60376 Woodbury March 2027 INT-81326 Scotland Q1 2027 INT-82635 Stonington December 31, 2026 6 7 Despite repeated requests, and involving outside counsel, Greenskies has been unable to 8 achieve construction timeline certainty for any of these projects. 9 10 Q. What efforts has Greenskies made to obtain construction schedules from Eversource? 11 A. On July 16, 2026, Greenskies’ Interconnection Specialist Engineer first requested 12 meetings with Eversource to align on the construction schedule and critical milestones for 13 these 2026 and 2027 projects, confirm developer and utility responsibilities, identify 14 outstanding engineering and construction items, track the path to energization, and 15 establish communication protocols. Greenskies also asked Eversource to include the 16 appropriate Engineering, Easements, Construction, Protection and Control, Metering, and 17 Outage Coordination personnel so as to facilitate a productive meeting. Since that time, 18 despite repeated follow up inquiries from multiple Greenskies personnel, Eversource’s 19 project manager has refused to participate in any such meeting and has yet to provide 20 estimated construction timelines or construction team contact information for projects 21 that are targeted to be in service by the end of the year. Page 5Page 8 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 B. Eversource Study Reports Are Consistently Late 2 Q. Has Greenskies experienced delays earlier in the process at the study stage? 3 A. Yes. GCE has experienced repeated delays in receiving study reports and study 4 agreements. Over a dozen pending projects have delayed study reports, as follows: 5 • INT-115515: impact study report, due September 8, 2026, delayed; 6 • INT-100786: distribution impact study report delayed; the draft report omitted the 7 estimated cost required by the study agreement; and issuance of the facility study 8 agreement was delayed; 9 • INT-113967/113964: study report, due September 17, 2026, delayed; 10 • INT-98869: study report and facility study agreement delayed, with drastic 11 changes in the estimated interconnection cost; 12 • INT-117135: impact study report, due at the end of August 2026, delayed; and 13 • INT-121014, 121016, 121017, 121018, 121361, 121691, and 121692: delays in 14 issuing study agreements. 15 C. ITC Timeline Implications 16 Q. Why does timeline certainty matter so much right now? 17 A. Because of the federal Investment Tax Credit (“ITC”) changes, the key hard deadline for 18 project completion is December 31, 2029 for certain Greenskies projects relying on a 19 module safe harbor. Simply put, if a project is unable to achieve commercial operation 20 by this date, it will be totally uneconomic and will be terminated in advance of incurring 21 more costs. This is in essence a portfolio risk management strategy. Page 6Page 9 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Because of this brightline date – which the industry has referred to as a cliff – if a project 2 is significantly delayed or it becomes otherwise uncertain that it will achieve operations 3 by a certain date, the interconnection customer may be incentivized to terminate it much 4 earlier and redeploy its safe-harbored equipment to projects with more certain timelines. 5 Q. How does project timeline uncertainty affect Greenskies’ Connecticut portfolio? 6 A. Many of these projects are already permitted and are awaiting next steps from Eversource 7 to begin construction. These are shovel-ready projects that can contribute to 8 Connecticut’s zero carbon power supply as soon as December of this year. Importantly, 9 every solar and storage project lost in this way contributes to Connecticut missing its 10 renewable energy goals. 11 IV. Why This Is a Rate Case Customer Service Issue 12 Q. Why are these interconnection issues relevant to this rate case? 13 A. Eversource’s staffing directly affects the speed at which these projects can be deployed. 14 The pattern described above (no kickoff, no construction schedule, no status updates, and 15 late study reports) reflects a lack of appropriate Company resources dedicated to 16 interconnection customer service. 17 Q. Does Eversource’s use of vendors affect customer service? 18 A. Yes. Greenskies’ primary Eversource point of contact for these projects is a contractor 19 from Burns & McDonnell serving as Eversource’s Distributed Resources Project 20 Manager. Reliance on such vendors incentivizes poor customer service, because contract 21 personnel have little incentive to respond or collaborate with interconnection customers, 22 and Eversource bears no consequence when their contractors do not respond. Page 7Page 10 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. Can interconnection customers simply take their business elsewhere? 2 A. No. Interconnection customers are captive. A project located in Connecticut Eversource’s 3 service territory can only interconnect with Eversource, and there is no meaningful 4 recourse for addressing utility delays. Standard IAs impose no penalty, and Eversource 5 suffer no consequences for failure to meet their own deadlines. As a result, 6 interconnection disputes increasingly take up valuable Authority time and resources in 7 dispute resolution. More frequently, however, without rapid, binding dispute resolution, 8 interconnection customers are choosing to terminate projects instead. 9 Q. Are these issues common across utilities? 10 A. No. In our experience, these issues arise primarily in Eversource’s Connecticut service 11 territory. Two Greenskies projects located in United Illuminating (“UI”) service territory 12 with requested 2026 ISDs are both on track. By contrast, of the four Eversource projects 13 for which Greenskies requested 2026 ISDs, Eversource has provided no hard dates, no 14 updates, and thus GCE no confidence that the in-service goals will be reached. 15 16 The following chart compares Greenskies’ Soundview project in UI territory with its 17 Lantern Hill and Morris projects in Eversource territory: Page 8Page 11 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 Milestone Soundview (UI) Lantern Hill (Eversource) Morris (Eversource) Application submitted June 17, 2024 June 27, 2023 May 23, 2024 IA fully executed March 16, 2026 April 9, 2026 May 7, 2026 Days from application to IA 637 1,017 714 Easement documents submitted February 2, 2026 February 5, 2026 March 10, 2026 Utility easement approval June 1, 2026 TBD (pending Eversource) TBD (pending Eversource) Construction begins October 1, 2026 (confirmed) TBD TBD Utility construction complete October 28, 2026 (confirmed) TBD TBD Initial energization November 9, 2026 (confirmed) TBD TBD PTO granted November 20, 2026 (confirmed) TBD TBD 1 2 Notably, Eversource completed the system impact studies for both projects in fewer 3 elapsed days than UI. Greenskies does not claim that every Eversource milestone is 4 slower to achieve. But UI has demonstrably reached IA execution faster end-to-end, 5 approved easements within four months, and has consistently provided Greenskies with a 6 reliable forward schedule through PTO. Eversource has not approved easements 7 submitted in February and March 2026 as of the date of this filing and has not confirmed 8 any construction, energization, or PTO date for either 2026 project. 9 10 Q. Does Greenskies have any experience with utilities outside of Connecticut on these issues? 11 A. Greenskies has had a more transparent experience with Ameren in Illinois. Ameren’s 12 PowerClerk system includes “chess clock” functionality that automatically identifies the 13 responsible party, tracks the time allowed for the next deliverable, and updates project Page 9Page 12 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 status. This allows developers and utilities to jointly monitor progress and prepare for the 2 next required action. By contrast, Eversource has not implemented comparable 3 functionality in Connecticut, and in our experience its PowerClerk records are often not 4 updated to reflect the project’s current stage or deliverable. Without defined action 5 windows, delays cannot readily be attributed to the responsible party. 6 7 Greenskies has also found the interconnection application and study processes of 8 California utilities San Diego Gas & Electric and Southern California Edison to be well 9 defined: both utilities followed established timelines, communicated effectively, and 10 provided clear expectations that supported informed business decisions. Their detailed 11 hosting-capacity maps also provide feeder-level information that helps developers select 12 sites and more reliably anticipate interconnection feasibility and costs. 13 V. Why This Is an Eversource Ratepayer Problem 14 Q. How do these issues affect Eversource ratepayers? 15 A. Ratepayers are harmed in several ways. First, ratepayers and municipalities are harmed 16 through delays on specific projects. For example, Greenskies developed a project with 17 Eversource on a capped landfill in Portland. The project reached the interconnection- 18 agreement stage in June 2024 and has since awaited an update concerning other work 19 required on the feeder before the solar project can proceed. Those delays have cost the 20 Town of Portland approximately $100,000 in savings to date. The Town has an NRES 21 agreement with Greenskies under which the project would provide lower-cost energy. 22 Absent the interconnection delay, the project would already be operational and producing 23 those savings. Greenskies continues to experience unexplained long-term delays with no Page 10Page 13 of 17
Greenskies Clean Energy, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 concrete next steps from Eversource. If Eversource cannot advance the interconnection 2 shortly, Greenskies may be forced to abandon the project. 3 4 Second, lack of predictable interconnection costs frustrates efficient and timely NRES 5 and SCEF procurements. By way of example, two recent Greenskies projects were 6 awarded contracts through State programs and were ultimately terminated because of 7 high Eversource interconnection costs. The Goshen and Maple Hill projects were 8 proposed for the SCEF Program because the Eversource hosting capacity map at the time 9 showed no interconnection issues, and required upgrades were anticipated to be minimal. 10 Both projects were submitted into the SCEF RFP in 2020 and were awarded in late 11 2020/early 2021. Maple Lane submitted its interconnection application in April 2021, 12 with the requisite study completed in December 2021 resulting in approximately $9 13 million in required interconnection upgrades. Goshen submitted its interconnection 14 application in June 2020, with the study completed in January 2022 that identified 15 interconnection costs of approximately $3 million. An accurate Hosting Capacity Map 16 would have provided lower-cost energy resources and savings to ratepayers. Instead, 17 these projects now represent wasted time by both Greenskies and regulators in 18 Connecticut. The availability of Pre-Application system and response from Eversource 19 could also have informed Greenskies of the potential for high costs prior to dollars spent 20 on development and permitting work. 21 22 Third, high interconnection costs, uncertain timelines, and a history of missed Eversource 23 timelines are all factored into Greenskies’ NRES and SCEF bid prices. These higher bid Page 11
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Jean-Paul La Marche [26-05-10]