Prefiled testimony
Witness: Lindsay J. Griffin
Files1
Direct Testimony of Lindsay J. Griffin - Docket No. 26-05-10 with App. A, B. C.pdf
PDF · 979 KB · 121 pagesText searchable
Download Direct Testimony of Lindsay J. Griffin - Docket No. 26-05-10 with App. A, B. C.pdfRead the text of Direct Testimony of Lindsay J. Griffin - Docket No. 26-05-10 with App. A, B. C.pdf
Search terms highlighted
Eversource rate increase is on 7 pages of the text below, highlighted. Go to the first matchClear highlighting
Page 101 of 121
Docket No. 26-05-10 Appendix B October 21, 2026 Page 4 of 7 No. Date Event Docket(s) 57 04/25/2024 5th Set of Interrogatories Issued RE01 58 05/14/2024 Technical Meeting No. 7 RE03 59 05/15/2024 5th Set of Interrogatory Responses Due RE01 60 05/15/2024 Written Comments #4 Due RE01 61 06/07/2024 Technical Meeting #8 - In person RE01 62 06/10/2024 Technical Meeting #5-in Person RE02 63 06/11/2024 Technical Meeting No. 8 RE03 64 07/09/2024 2nd Set of Interrogatories Issued RE03 65 07/18/2024 6th Set of Interrogatories Issued RE01 66 07/30/2024 2nd Set of Interrogatory Responses Due RE03 67 08/01/2024 6th Set of Interrogatory Responses Due RE01 68 08/05/2024 2nd Set of Interrogatories Issued RE02 69 08/12/2024 Technical Meeting #9- In person RE01 70 08/16/2024 7th Set of Interrogatories Issued RE01 71 08/19/2024 2nd Set of Interrogatory Responses Due RE02 72 08/26/2024 Technical Meeting #6- In person RE02 73 08/30/2024 7th Set of Interrogatory Responses Due RE01 74 09/04/2024 3rd Set of Interrogatories Issued RE02 75 09/13/2024 Technical Meeting #10- In person RE01 76 09/18/2024 3rd Set of Interrogatory Responses Due RE02 77 09/26/2024 Technical Meeting #7-In Person RE02 78 10/01/2024 8th Set of Interrogatories Issued RE01 79 10/15/2024 8th Set of Interrogatory Responses Due RE01 80 10/17/2024 Issue Concept Paper RE03 81 10/24/2024 4th Set of Interrogatories Issued RE02 82 10/24/2024 Technical Meeting #11- In person RE01 83 10/28/2024 9th Set of Interrogatories Issued RE01 84 10/31/2024 Technical Meeting #8-In Person RE02Page 102 of 121
Docket No. 26-05-10 Appendix B October 21, 2026 Page 5 of 7 No. Date Event Docket(s) 85 11/06/2024 Written Comments Due RE01 86 11/07/2024 4th Set of Interrogatory Responses Due RE02 87 11/12/2024 9th Set of Interrogatory Responses Due RE01 88 11/18/2024 5th Set of Interrogatories Issued RE02 89 11/18/2024 Technical Meeting #12- In person RE01 90 11/19/2024 Technical Meeting No. 9 (cancelled) RE03 91 11/19/2024 Written Comments Due RE03 92 11/25/2024 10th Set of Interrogatories Issued RE01 93 11/25/2024 Technical Meeting #9-In Person RE02 94 12/02/2024 5th Set of Interrogatory Responses Due RE02 95 12/09/2024 10th Set of Interrogatory Responses Due RE01 96 12/09/2024 Technical Meeting #13 - In Person RE01 97 12/16/2024 6th Set of Interrogatories Issued RE02 98 12/16/2024 Technical Meeting #10-In Person (cancelled) RE02 99 12/17/2024 Technical Meeting No. 10 RE03 100 12/23/2024 11th Set Interrogatories Issued RE01 101 01/08/2025 6th Set of Interrogatory Responses Due RE02 102 01/10/2025 3rd Set of Interrogatories Issued RE03 103 01/13/2025 11th Set of Interrogatory Responses Due RE01 104 01/24/2025 3rd Set of Interrogatory Responses Due RE03 105 01/30/2025 Technical Meeting No. 11 RE03 106 02/27/2025 Issue Revised Straw Proposal & Request for Written RE02 107 02/27/2025 Rev. Straw Proposal & Request for Written Comments RE01 108 03/04/2025 12th Set Interrogatories Issued RE01 109 03/18/2025 12th Set Interrogatories Due RE01 110 03/26/2025 Written Comments Due RE01 111 03/27/2025 Written Comments Due RE02Page 103 of 121
Docket No. 26-05-10 Appendix B October 21, 2026 Page 6 of 7 No. Date Event Docket(s) 112 03/31/2025 Technical Meeting #14 - In Person RE01 113 04/02/2025 Technical Meeting #11- In Person RE02 114 04/04/2025 Issue Straw Proposal RE03 115 04/07/2025 Technical Meeting #15 - In Person RE01 116 04/08/2025 Technical Meeting #12- In Person (cancelled) RE02 117 04/10/2025 13th Set Interrogatories Issued RE01 118 04/21/2025 7th Set of Interrogatories Issued RE02 119 04/24/2025 13th Set Interrogatories Due RE01 120 04/28/2025 14th Set Interrogatories Issued RE01 121 05/01/2025 8th Set of Interrogatories Issued RE02 122 05/05/2025 7th Set Interrogatories Due RE02 123 05/08/2025 Written Comments Due - Straw Proposal RE03 124 05/12/2025 14th Set Interrogatories Due RE01 125 05/13/2025 Technical Meeting No. 12 RE03 126 05/15/2025 8th Set of Interrogatory Responses Due RE02 127 05/19/2025 Revised Notice of Technical Meeting RE01, RE02, RE03 128 05/21/2025 End of Discovery RE01, RE02 129 05/21/2025 Technical Meeting RE01, RE02 130 05/21/2025 Technical Meeting No. 13 RE03 131 05/27/2025 Briefs Due RE01, RE02 132 06/23/2025 Briefs Due RE03 133 07/14/2025 Distribution of Proposed Final Decision RE01, RE02 134 08/08/2025 Distribution of Proposed Final Decision RE03 135 08/15/2025 Written Exceptions Due RE01, RE02 136 08/28/2025 Written Exceptions Due RE03 137 09/03/2025 Oral Arguments, if requested RE01, RE02, RE03 138 10/15/2025 Regular Meeting/Final Decision (cancelled) RE02, RE03Page 104 of 121
Docket No. 26-05-10 Appendix B October 21, 2026 Page 7 of 7 No. Date Event 139 07/07/2026 Updated time schedule for remaining events (no proposed final decision issued) 07/14/2026 CL&P rate case application filed Docket(s) RE01 26-05-10 140 07/17/2026 Proposed Final Decision Issued RE03 141 07/27/2026 Proposed Final Decision Issued RE02 142 08/06/2026 Remaining decision events removed from schedule; RE01, RE02, RE03 dates to be announced Phase I events from Docket No. 21-05-15, April 26, 2023 Decision (Phase 1 Decision), at pages 5–8; Reopener events from PURA time schedules for Docket Nos. 21-05-15RE01, 21-05-15RE02, and 21-05-15RE03 (last revised 8/12/2026), including schedule comments dated 7/7/2026, 7/17/2026, 7/27/2026, and 8/6/2026; Docket No. 26-05-10 time schedule (last revised 9/22/2026). Events scheduled on the same date with the same title in more than one docket are listed once. Cancelled events are shown in italics.Page 105 of 121
Appendix C: RecommendationsPage 106 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 1 of 16 Revenue Adjustment Mechanism Recommendations The following recommendations reflect the revenue adjustment mechanisms as proposed in the RE01 Proposed Final Decision (July 14, 2025), except where an item is identified as a change discussed in my direct testimony. 1. Adopt a Revenue Cap Formula (rather than a cost-forecast approach) applied to the total revenue requirement (capital and OM&A costs), excluding items funded separately such as the CT-Bar, capital trackers, and PIMs. 1 2. Set a 4-year MYRP, with the next rate case filed in Rate Year 4. 2 3. Adopt the CT-Bar with its 6-step calculation methodology, distinguishing Capital Plan from non-Capital Plan additions, subject to downward-only reconciliation and no return on investment until the next rate case's prudency review, with revenue collected for investment later found imprudent returned to customers with carrying charges. As a change from the RE01 PFD (see Direct Testimony, Section IX), the CT-Bar should not fund any capital additions, including the Rate Year 1 CT-Bar additions the RE01 PFD proposed would include in going-in rates, until Eversource has refiled its Targeted System Performance Plan in a form that conforms to the IDSP proposed requirements in RE03 PFD No. 2 and the Authority has reviewed it; the reviewed plan should then provide the Capital Plan input for the remaining rate years. 3 PURA Investigation into Revenue Adjustment Mechanisms for a Performance-Based Regulation Framework, Docket No. 21-05-15RE01, Proposed Final Decision, at page 8 (Connecticut Public Utilities Regulatory Authority July 14, 2025); Id at 20-21 & n.19. 2 Id at 9. 3 Id at 31-40. 1Page 107 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 2 of 16 4. Require Eversource to accept the stay-out commitment in writing within 10 days of the decision of the MYRP mechanisms; if it does not, default Eversource to a 1-year rate plan that excludes the Revenue Cap Formula and CT-Bar. 4 5. Design a Revenue Cap Formula (a) that bases the I-Factor on GDPPI, reset annually using the most recent 4 quarters; (b) that bases the X-Factor on a TFP study using at least three outputs (customer count, delivered energy, and peak demand), with the data and models made available to parties; and that does not permit a negative X-Factor unless supported by a study that meets these requirements (a change from the RE01 PFD; see Direct Testimony, Section IX); (c) that sets any S-Factor in this proceeding based on a benchmarking study, using a simple tiered approach under which a utility shown to be less efficient than its peers receives a larger S-Factor; (d) that follows the Hawaii-PUCstyle Z-Factor eligibility criteria with a materiality threshold of 0.75% of the annual revenue requirement, and disallows carrying charges until after the prudency review; and (e) that excludes a G-Factor. 5 6. Permit capital cost trackers only for discrete, extraordinary cost recovery, each governed by the decision that establishes it. 6 7. Omit an Efficiency Carryover Mechanism, consistent with the RE01 Proposed Final Decision. 7 8. Design Earnings Sharing Mechanisms (a) as asymmetrical (upside-only sharing), (b) that excludes dead bands, (c) that excludes tiers, (d) that calculate earnings using the lesser of 4 5 6 7 Id at 10-11. Id at 22-28. Id at 40. Id at 43.Page 108 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 3 of 16 the authorized or actual carried common equity position, based on average rate base/capitalization ratio, with calendar-year reporting retained, and (e) that exclude PIM rewards/penalties, and exclude disallowed or omitted OM&A costs, from the ROE calculation used for the ESM (excluding depreciation, property tax, GET, and post-testyear debt cost from that exclusion). 8 9. Continue the revenue decoupling mechanism, with annual reconciliation, and determine in the rate case whether to exclude from reconciliation and sales forecasts any revenues associated with power not restored after an extended service outage. 9 10. Consider Totex Ratemaking following the finalization of the instant rate case and PBR proceeding. 10 8 9 10 Id at 47-53. Id at 55; id. at App. A, pp. xii–xiii. Id at 57.Page 109 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 4 of 16 Performance Mechanism Recommendations The following recommendations reflect the performance mechanisms as proposed in RE02 PFD No. 2 (July 27, 2026), effective whether or not a multi-year rate plan is approved, except where an item is identified as a change discussed in my direct testimony. 1. A Cost Efficiency Scorecard that pairs a “Total Cost” metric (overall EDC financial performance) as the primary measure with six sub-metrics (operating expenditures, controllable Opex, authorized controllable Opex, capital expenditures, capital cost, and total cost), all normalized per customer/line-mile and benchmarked against a 10-year historical average for context. 11 2. An Inspection & Maintenance System Reported Metric that requires the EDC to publish data from its routine grid inspection and maintenance programs, to increase transparency around infrastructure upkeep. 12 3. Reliability Cost Metrics carried over from the Authority’s 2022 Reliability and Resilience Decision (Docket 17-12-03RE08), organized by reliability program and showing performance, program cost, performance-to-cost ratios, and rate impact, to give context for the Cost Efficiency Scorecard. Cite to “Table 19” template from the Reliability and Resilience Decision. 13 PURA Investigation into Performance Mechanisms for a Performance-Based Regulation Framework, Docket No. 21-05-15RE02, Proposed Final Decision at 13, (Connecticut Public Utilities Regualtory Authority July 14, 2025); PURA Investigation into Performance Mechanisms for a Performance-Based Regulation Framework, Docket No. 21-05-15RE02, Proposed Final Decision No. 2 at 16 (Connecticut Public Utilities Regualtory Authority July 27, 2026). 12 RE02 PFD No. 2 at 18 (2026). 13 RE02 PFD No. 2 at 22 (2026). 11Page 110 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 5 of 16 4. The existing NWS Shared Savings Mechanism, under which EDCs and ratepayers split savings achieved when non-wires solutions are chosen over traditional infrastructure, into the PIMs portfolio without introducing any new penalties or incentives beyond what the mechanism already provides. 14 5. A Distribution System Losses Reported Metric that quantifies electricity lost in distribution, split into technical losses (physical/engineering) and non-technical losses (e.g., theft, metering error), calculated via an energy-balance method. 15 6. A DER and NWS Avoided Cost Metric that tracks the system costs avoided or deferred by operational DERs (500 kW and larger) and non-wires solutions (NWS), including avoided energy use and non-energy benefits from those DERs, with avoided costs calculated net of incremental interconnection costs and NWS-related costs valued using the present worth method. 16 7. A Peak Demand Scorecard, using a three-year (rather than five-year) historical moving average as the benchmark to better reflect recent trends, that tracks four sub-metrics against that benchmark: annual peak demand, monthly peak demand, estimated DER contributions to peak demand, and system load factor. 17 8. An EV Managed Charging Scorecard that tracks enrollment and performance in the EDCs’ EV managed-charging programs, using the two-tier program structure from the annual EV Charging Program dockets (No. XX-08-06). 18 14 15 16 17 18 RE02 PFD No. 2 at 25 (2026). RE02 PFD No. 2 at 33 (2026). RE02 PFD No. 2 at 19 (2026). RE02 PFD No. 2 at 28 (2026). RE02 PFD No. 2 at 30 (2026).
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Lindsay J. Griffin [26-05-10]