Prefiled testimony
Witness: Lindsay J. Griffin
Files1
Direct Testimony of Lindsay J. Griffin - Docket No. 26-05-10 with App. A, B. C.pdf
PDF · 979 KB · 121 pagesText searchable
Download Direct Testimony of Lindsay J. Griffin - Docket No. 26-05-10 with App. A, B. C.pdfRead the text of Direct Testimony of Lindsay J. Griffin - Docket No. 26-05-10 with App. A, B. C.pdf
Search terms highlighted
Eversource rate increase is on 7 pages of the text below, highlighted. Go to the first matchClear highlighting
Page 111 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 6 of 16 9. A DER Services Reported Metric that tracks enrolled assets, total megawatts (MW) enrolled, and MW of peak-demand reduction across four DER programs: Energy Storage Systems, Smart Thermostats, Commercial & Industrial Demand Response, and EV Managed Charging. 19 10. An Energy Storage Performance Metric that tracks whether the EDCs’ energy storage system (ESS) dispatch events actually align with real ISO-New England system peaks, plus MW of peak demand avoided and associated dollar savings from peak shaving. 20 11. A downside-only System Reliability PIM measuring blue-sky (non-major-storm) System Average Interruption Duration Index (SAIDI) and System Average Interruption Frequency Index (SAIFI), excluding CAIDI to reduce redundant reporting. This PIM should be benchmarked to a fixed 5-year historical average, with penalties triggered once performance exceeds 1 standard deviation from that average. Penalty amounts should be set no lower than the maximum SAIDI and SAIFI penalties the Company proposed in Exhibit CLP-ELP-3 (see Direct Testimony, Section VI). 21 12. A Customer Reliability Scorecard that tracks the four sub-metrics proposed in RE02 PFD No. 2 (CEMI-5, percent of repeat CEMI-5 customers, CELID-6, and percent of repeat CELID-6 customers), averaged into a composite score and compared to the fixed 2020– 2024 historical average, with no financial reward and with the option to elevate it to a downside-only PIM once sufficient data are available. This is a change from the upsideonly potential PIM recommendation in RE02 PFD No. 2 (see Direct Testimony, Section 19 20 21 RE02 PFD No. 2 at 35 (2026). RE02 PFD No. 2 at 36 (2026). RE02 PFD No. 2 at 38-42 (2026).Page 112 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 7 of 16 IX). If the Authority nonetheless attaches a reward, the reward threshold should be the historical average minus one standard deviation, so that the Company is rewarded only for improvement beyond normal year-to-year variation. 22 13. An All-in SAIDI Scorecard that tracks total SAIDI including major storms, benchmarked against both a 10-year and a 5-year historical rolling average, with room for an explanatory narrative on storm severity/tree-trimming conditions. 23 14. A Major Storm Reported Metric that requires post-storm restoration data broken out by zip code and customer class, purely for backward-looking transparency. 24 15. Five-Year Outage History, Circuit-Level Performance, Voltage Irregularities, and Power Quality Reported Metric that include outage history by cause over 5 years; circuit-level reliability performance; voltage irregularities/power surges affecting 10+ customers; and general power-quality data. 25 16. An Equitable AMI Scorecard that tracks how Advanced Metering Infrastructure (AMI) is deployed and used among financial-hardship customers, including the percentage of hardship customers with AMI who are disconnected for non-payment (benchmarked against hardship customers without AMI) and enrollment in AMI-dependent offerings like time-of-use rates. 26 22 23 24 25 26 RE02 PFD No. 2 at 42-46 (2026). RE02 PFD No. 2 at 48 (2026). RE02 PFD No. 2 at 49 (2026). RE02 PFD No. 2 at 50 (2026). RE02 PFD No. 2 at 53 (2026).Page 113 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 8 of 16 17. A Power Restoration After Major Storms Reported Metric that tracks restoration speed after major storms in distressed municipalities (using the state Dept. of Economic and Community Development’s list, rather than census-block data), for transparency only. 27 18. An Underserved Communities Inclusion Reported Metric that tracks participation of distressed municipalities, low-income customers, and underserved communities in the RRES, NRES, SCEF, and ESS programs. 28 19. An Environmental Justice Reliability Reported Metric that tracks reliability performance (e.g., outage frequency/duration) specifically within designated Environmental Justice communities. 29 20. A GHG Emissions Scorecard that tracks the EDC’s Scope 1, 2, and 3 greenhouse gas emissions and emissions intensity, benchmarked against a 2019 reference year. 30 21. A Clean Energy Program Attrition Reported Metric that tracks withdrawals/attrition from the Non-Residential Renewable Energy Solutions (NRES) and Shared Clean Energy Facility (SCEF) programs. 31 22. A SF₆ Reported Metric that tracks sulfur hexafluoride leaks, aligned with the EDCs’ existing EPA filings rather than a new separate reporting format. 32 23. A Beneficial Electrification Reported Metric that tracks trends in electrification of previously fossil-fuel-powered end uses (e.g., heating, transportation). 33 27 28 29 30 31 32 33 RE02 PFD No. 2 at 55 (2026). RE02 PFD No. 2 at 57 (2026). RE02 PFD No. 2 at 59 (2026). RE02 PFD No. 2 at 62 (2026). RE02 PFD No. 2 at 65 (2026). RE02 PFD No. 2 at 67 (2026). RE02 PFD No. 2 at 68 (2026).Page 114 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 9 of 16 24. A Time-Varying Rate Scorecard that tracks, by customer class, the number and percentage of customers participating in time-varying rates and the load reduced or shifted because of TVR adoption, with enrollment targets as AMI deployment is completed and participation reported separately for LMI and non-LMI customers, or at a minimum a Reported Metric that converts to a Scorecard. This is a change from the Reported Metric proposed in RE02 PFD No. 2 (see Direct Testimony, Section IX). 34 25. A Customer Data Engagement Reported Metric that tracks how many customers actively access/engage with their AMI usage data (e.g., through online portals), and enable data sharing with third parties. 35 26. A Community Engagement Scorecard built on the three consolidated sub-metrics in RE02 PFD No. 2 (number of activities, public participation, and actionable outcomes), with targets for outreach activity and an equity sub-metric for Environmental Justice community representation on advisory boards, or at a minimum a Reported Metric with a stated path to a Scorecard. This is a change from the Reported Metric in RE02 PFD No. 2 (see Direct Testimony, Section IX). 36 27. A symmetrical Level 1 DER Interconnection PIM measuring the combined pre- and postconstruction timeline for small (Level 1) DER interconnection applications, using a 4step calculation and a 3-year historical average as the benchmark; excluding non-working days and periods when applications sit with the developer. 37 34 35 36 37 RE02 PFD No. 2 at 70-71 (2026). RE02 PFD No. 2 at 73 (2026). RE02 PFD No. 2 at 74-76 (2026). RE02 PFD No. 2 at 79 (2026).Page 115 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 10 of 16 28. A Level 2 DER Interconnection Scorecard that tracks the average number of business days in EDC-controlled processing steps for fast-track Level 2 DER interconnection projects, using the four-step calculation in RE02 PFD No. 2, benchmarked against the EDC interconnection guidelines and a five-year historical average. As a change from RE02 PFD No. 2, the Authority should consider elevating the Scorecard to a PIM if Level 2 processing times lengthen while Level 1 times improve (see Direct Testimony, Section IX). 38 29. A Customer Satisfaction Scorecard that tracks satisfaction via Likert-scale survey ratings across three touchpoints: call-center support, the interconnection process, and service interruptions, segmented by customer class and (for the interruptions category) using IEEE-defined Major Event Days to avoid skewing from minor storms. 39 30. An Existing Customer Service Metric that tracks nine call-center sub-metrics, including average speed of answer, average handle time, abandoned calls and abandoned call rate, first call resolution rate, and quality assurance score, reported annually using existing EDC data. 40 31. A Customer Inquiries Scorecard that tracks the volume/type of customer complaints (categorized by subject, e.g., pricing or interconnection speed, rather than by “preventable” vs. “justified”), contextualized against average customer bill amounts. 41 32. An Affordability & Disconnection Minimization Scorecard that tracks the annual percentage change in non-payment-related service terminations for non-hardship 38 39 40 41 RE02 PFD No. 2 at 79-81(2026). RE02 PFD No. 2 at 83 (2026). RE02 PFD No. 2 at 89 (2026). RE02 PFD No. 2 at 87 (2026).Page 116 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 11 of 16 residential customers, reflecting increased participation in programs like the Low-Income Discount Rate (LIDR) and the Matching Payment Program (MPP). 42 33. An Affordability & Electricity Burden Scorecard that measures the share of household income spent on electricity specifically (as opposed to total energy burden), using Dept. of Social Services data (average household size of 1.8, rounded to 2) and DSS incomeeligibility-tier midpoints to estimate income. 43 34. An Accounts Receivable and Uncollectibles Scorecard with five sub-metrics (average residential monthly arrears, residential accounts receivable, actual residential write-offs, the allowed uncollectible rate, and accounts receivable over 60 days as a percentage of revenue over a rolling 12-month period), benchmarked to 2023 and reported in quarterly segments. 44 35. LIDR Implementation Reported Metrics on enrollment, usage patterns, energy burden, and customer movement between tiers within the state’s Low Income Discount Rate program, aligned with the recent LIDR Modification Decision. 45 42 43 44 45 RE02 PFD No. 2 at 90-95 (2026). RE02 PFD No. 2 at 97 (2026). RE02 PFD No. 2 at 100. RE02 PFD No. 2 at 101 (2026).Page 117 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 12 of 16 Integrated Distribution System Planning Elements Recommendations The following recommendations reflect the IDSP requirements as proposed in RE03 PFD No. 2 (July 17, 2026), except where an item is identified as a change discussed in my direct testimony. 1. A planning document built around the following six steps of integrated planning, such as to: (a) assess system needs, (b) identify and evaluate solutions (wires and non-wires), (c) select solutions, (d) develop capital and long-term investment plans, (e) engage stakeholders throughout, and (f) file the plan for Authority review and approval. 46 2. A ten-section document structure covering: an executive summary; planning policy; current state of the system; IDSP methodology; stakeholder engagement and social equity; load forecasting; grid needs assessment; solution selection process; a capital investment plan covering a ten-year planning horizon; and a long-term strategic plan covering the period beyond ten years, together with a consolidated checklist of every content requirement. 47 3. A single "Joint Working Group" made up of the utility, PURA staff, the Office of Consumer Counsel, and interested stakeholders, serving as the central forum for engagement on the IDSP throughout its development, rather than separate ad hoc stakeholder processes for each section. 48 PURA Investigation into the Establishment of Integrated Distribution System Planning within a Performance-Based Regulation Framework, Docket No. 21-05-15RE03, Proposed Final Decision at 11 (Connecticut Public Utilities Regulatory Authority Aug. 8, 2025); PURA Investigation into the Establishment of Integrated Distribution System Planning within a Performance-Based Regulation Framework, Docket No. 21-05-15RE03, Proposed Final Decision No. 2 at 11 (Connecticut Public Utilities Regulatory Authority July 17, 2026). 47 RE03 PFD No. 2 at 11-14, Appendix A. 48 RE03 PFD No. 2 at 18, 22. 46Page 118 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 13 of 16 4. An EDC-developed data-sharing protocol, subject to Authority review and approval and modeled on the NWS Process non-disclosure agreements, for sharing planning data (load, hosting-capacity, and system data) with Joint Working Group members, so that stakeholders without utility-level access can meaningfully participate without exposing commercially sensitive or security-sensitive information. 49 5. A two-phase engagement approach: first, substantive stakeholder input into planning decisions, and second, broader public education and outreach about the plan and its impacts. 50 6. A requirement that Eversource document any relevant social equity metrics and considerations factored into planning and solution selection, and include in the IDSP’s Stakeholder Engagement and Social Equity chapter a Social Equity Strategy subsection that identifies the equity metrics it uses and explains how they influence planning and investment decisions. 51 7. A requirement that EDCs convene a “Forecast Working Group” as a sub-group of the JWG to develop the load forecast underlying the plan, including hourly (8,760-hour) load forecasts and appropriate data protections for customer-level information used in the forecast. Furthermore, there should be a requirement for at least three scenarios (low/middle/high), each developed at the system, planning region, substation, and feeder levels, with the middle scenario designated as the baseline for planning purposes. 52 49 50 51 52 RE03 PFD No. 2 at 20. RE03 PFD No. 2 at 18. RE03 PFD No. 2 at 22, 24, 51. RE03 PFD No. 2 at 30, 32.Page 119 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 14 of 16 8. A section identifying where and why the grid needs investment, presented in a tabular format organized by region/circuit rather than as a narrative, so that needs can be compared consistently across the service territory. 53 9. A Grid Needs Assessment that is built from several required sub-analyses: a steady-state (loading/thermal) analysis, an N-1 contingency analysis (system performance with one element out of service), a reliability analysis, and a resiliency analysis. 54 10. A Hosting Capacity sub-analysis showing how much additional distributed energy resource (DER) capacity the grid can accommodate, and a DER Interconnection Queue / Interconnection Plan sub-analysis addressing the backlog and cost-allocation treatment of pending interconnection requests. 55 11. A requirement that EDCs evaluate both wires (traditional) and non-wires solutions (NWS) to identified grid needs using the existing NWS Process and its benefit-cost analysis (BCA) methodology as the common evaluation framework, rather than a separate bespoke IDSP evaluation method. 56 12. A tiered cost-effectiveness screen for solutions, combining cost thresholds carried over from the NWS Process with an evaluation approach where smaller, lower-cost projects get a lighter-touch review while larger investments get fuller BCA scrutiny. 57 13. A formally defined set of “least-regrets planning principles” favoring solutions that perform reasonably well across a range of future scenarios (load growth, DER adoption, 53 54 55 56 57 RE03 PFD No. 2 at 40. RE03 PFD No. 2 at 40-42. RE03 PFD No. 2 at 40-42. RE03 PFD No. 2 at 52. RE03 PFD No. 2 at 52.Page 120 of 121
Docket No. 26-05-10 Appendix C October 21, 2026 Page 15 of 16 policy change) rather than being optimized for a single forecast that Eversource must apply as a qualitative review factor when selecting among solution options. 58 14. A required standard format for documenting the solutions-identification, evaluation, and selection process within the IDSP, so that reviewers can trace how each grid need was matched to a solution and why. 59 15. A section that categorizes investments by grid-need type and presents them via a Summary Table, Explanatory Narrative, and Individual Project Listing Table Appendix. 60 16. An explorative planning approach for the 10+ year horizon, require a Long-Term Plan Working Group with a narrative demand assessment, data exchange, and scenarios spanning both meeting and missing decarbonization targets. The working group should convene at least twice in the 12 months before each IDSP filing, with the membership specified in RE03 PFD No. 2. The long-term plan should be illustrative rather than binding and include a Strategic Planning narrative, with integrated gas-electric planning addressed in a separate proceeding. 61 17. A requirement that the full IDSP is refiled every 4 years (aligned with the Multi-year Rate Plan duration proposed herein), submitted 3-6 months ahead of the corresponding rate case (or within 18 months of the final RE03 decision, whichever is earlier) so its investment conclusions can feed into rate-case planning. 62 58 59 60 61 62 RE03 PFD No. 2 at 54-55. RE03 PFD No. 2 at 51. RE03 PFD No. 2 at 60. RE03 PFD No. 2 at 65-67. RE03 PFD No. 2 at 72-75, 78.
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Lindsay J. Griffin [26-05-10]