    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 16 of 90 1 capital funding mechanism, a PIMs portfolio, and a five-year “Targeted System 2 Performance Plan”. 23 Eversource states that its proposal “is generally consistent 3 with the framework discussed in Docket No. 21-05-15RE01,” while 4 acknowledging in the same testimony that the Authority had not yet issued a final 5 decision in that docket as of the filing date. 24 Eversource further states that it 6 “started with the ratemaking framework under discussion in PURA’s PBR docket 7 (Docket No. 21-05-15RE01), while also introducing certain new elements to 8 remediate the flaws that would ultimately hinder PURA’s (draft) PBR model from 9 supporting the necessary stay-out terms”. 25 10 Q. MECHANISMS INTO ITS FILING? 11 12 DID EVERSOURCE ADEQUATELY INCORPORATE PBR-RELATED A. No. Eversource’s proposal borrows the structure of the framework developed in 13 RE01, RE02, and RE03, including a four-year term, an upside-only earnings 14 sharing mechanism, a Z-Factor, and reliability PIMs. But it removes or weakens 15 the following cost containment features included in the framework: the CT-Bar’s 16 exclusion of a return on new capital until prudence is established, a revenue cap 17 that applies to total costs, an inflation index and productivity study consistent with 18 the RE01 PFD, and an Authority-reviewed and approved IDSP as the planning 23 24 25 Application, at pages 2, 5-6; Docket No. 26-05-10, July 14, 2026 Exhibit CLP-PBR-1 (Exhibit CLP-PBR-1), at pages 59-60, 66-69. Exhibit CLP-PBR-1, at page 60. Docket No. 26-05-10, Eversource Response to Interrogatory OCC-423 (OCC-423), at page 2. 16
  2. Page 20 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 17 of 90 1 basis for capital spending. 26 Those features were designed to work together to 2 effectively contain costs. Without them, the proposal does not advance the 3 priority outcomes the Authority adopted in its Phase I Decision, and the Company 4 has not shown that the resulting rates would be just and reasonable. 5 Q. IS THE COMPANY’S PROPOSAL “GENERALLY CONSISTENT WITH 6 THE FRAMEWORK DISCUSSED IN DOCKET NO. 21-05-15RE01” AND 7 ITS REOPENERS? 27 8 A. No. As I explain further below, the Company’s proposed PBMRP, PIMs 9 portfolio, and Targeted System Performance Plan are inconsistent with the 10 framework the Authority and stakeholders developed through Docket No. 21-05- 11 15 and its RE01, RE02, and RE03 reopeners. Eversource was an active 12 participant throughout Docket No. 21-05-15 and its reopeners and had every 13 opportunity to shape the framework. In RE01 it argued that the CT-Bar was 14 “unworkable” because it excluded the costs of capital; the Authority considered 15 that argument and proposed to adopt the CT-bar without it. 28 However, the 16 Company now raises the same objection here, asking the Authority to adopt in 17 this rate case the same design it did not secure in the reopeners. 29 26 27 28 29 The CT-Bar is a capital funding mechanism proposed in the July 14, 2025 RE01 Proposed Final Decision, building on the RE01 Revised Straw Proposal. It would fund capital additions in the utility’s Capital Plan, including IDSP-supported investments, by recovering only depreciation, property tax, and gross earnings tax expense, with no return until the investment is found prudent in the next rate case, subject to a downward-only reconciliation. (RE01 PFD, at pages 31–40). The Company describes its proposal as “generally consistent with the framework discussed in Docket No. 21-05-15RE01” (Exhibit CLP-PBR-1), at page 60, lines 1-5). RE01 PFD, at pages 32, 35. OCC-423, at page 3. 17
  3. Page 21 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 18 of 90 1 These differences matter because each departure removes a protection for 2 customers. Three examples illustrate the point: 3 (1) On the revenue adjustment mechanism, Eversource adopted the “I-X” formula 4 concept from RE01 but applied it to OM&A costs only, leaving capital outside 5 any formula. It also departed from the specific inputs the RE01 PFD proposes. 6 The RE01 PFD would base the I-Factor on Gross Domestic Product – Price 7 Index (“GDPPI”) and would require the total factor productivity (“TFP”) study 8 underlying the X-Factor to use at least three outputs: customer count, delivered 9 energy, and peak demand. 30 Eversource instead proposes a composite index of 10 utility labor costs and Gross Domestic Product – Implicit Price Deflator for 11 Final Sales to Domestic Purchasers (“GDP-FSDP”), and its consultant’s 12 productivity study uses the number of customers as its only output. 31 A study 13 with customers as its only output does not account for growth in energy 14 delivered or peak demand, so it cannot show whether the resulting X-Factor 15 reflects the productivity gains customers should expect. The Company 16 confirmed that its X-Factor applies only to OM&A costs, while capital revenue 17 is adjusted separately based on capital placed in service. 32 The Company also 18 describes its I-Factor as based on GDPPI and an Employment Cost Index, which 30 31 32 RE01 PFD, at page 25. Exhibit CLP-PBR-1, at pages 34-35, 38, 63. Docket No. 26-05-10, Eversource Response to Interrogatory CLF-AC-005 (CLF-AC-005), at page 2 (quoting CLF-AC-002(b)). 18
  4. Page 22 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 19 of 90 1 differs from Ms. Frayer’s description of a composite of a utility labor cost index 2 and GDP-FSDP. 33 The Company should clarify which index it is proposing. 3 (2) On capital funding, Eversource replaced the proposed CT-Bar with its own 4 “F-Factor.” The Company describes the F-Factor as tracking the CT-Bar “as 5 close as possible” except in three respects, the most significant of which is 6 that the F-Factor would collect a return on new capital during the plan term, 7 before the Authority has found that capital prudent. 34 The CT-Bar, as 8 developed and proposed through the RE01 reopener proceedings, deliberately 9 withholds that return until prudence is established in the next rate case. 35 By 10 the Company’s own estimate, that difference is worth $15.6 million in Rate 11 Year 1, rising to $39.5 million in Rate Year 4, or $124.1 million in total. 36 The 12 Company estimated the pretax return on incremental rate base included in the 13 F-Factor at $31 million to $36 million per year, or about $133 million over the 14 four rate years, calculated at its currently authorized 9.25 percent return on 15 equity rather than the 10.25 percent it requests in this case. 37 On either 16 estimate, F-Factor would allow the Company to collect a return on up to $120 17 million over the plan term, before the Authority conducts a prudence review. 18 (3) On performance mechanisms, Eversource proposed reliability PIMs that 19 follow the general structure of the RE02 designs, but changed their baselines 33 34 35 36 37 CLF-AC-001, at page 11. OCC-423, at pages 4, 10. RE01 PFD, at pages 33, 36–39. OCC-423, at page 7. CLF-AC-004, at page 2 & Att. 1. 19
  5. Page 23 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 20 of 90 1 and payout structure, folded the Level 1 DER Interconnection PIM into a 2 composite “Customer Suite” with a Company-selected target, omitted the 3 NWS Shared Savings Mechanism, and offers all of its PIMs as contingent on 4 approval of its multi-year plan. 38 The RE01 Proposed Final Decision makes 5 performance mechanisms applicable whether or not a utility accepts a multi- 6 year rate plan. 39 As I explain in Section VI, each of these changes weakens the 7 Company’s accountability for performance. 8 The RE01/RE02/RE03 Proposed Final Decisions represent the Authority’s 9 considered judgment, reached after years of stakeholder engagement about how a 10 PBR framework for Connecticut should be designed. The three dockets are at 11 different procedural stages: the Authority issued second Proposed Final Decisions 12 in RE03 and RE02 in July 2026, while the most recent draft decision in RE01 is 13 the Proposed Final Decision issued in July 2025. Although the RE01 Proposed 14 Final Decision has not been updated, it remains the Authority’s most recent 15 guidance on revenue adjustment mechanisms. As the applicant, Eversource bears 16 the burden of demonstrating that its proposed rates and ratemaking mechanisms 17 are just and reasonable. 40 Departing from the Authority’s proposed design is not 18 itself a flaw. But where the Company proposes mechanisms that do depart from 19 that design, the Company should be expected, at a minimum, to identify each 38 39 40 Docket No. 26-05-10, July 14, 2026 Exhibit CLP-ELP-3 (Exhibit CLP-ELP-3), at pages 1-2; Docket No. 26-05-10, July 14, 2026 Exhibit CLP-ELP-1 (Exhibit CLP-ELP-1), at pages 50, 103117. RE01 PFD, at page 10. Conn. Gen. Stat. § 16-22; also see Section III, infra. 20
  6. Page 24 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 21 of 90 1 departure, explain the reasons for it, compare the outcomes customers could 2 expect under each design, address the risks its alternative shifts to customers, and 3 explain why its alternative design both (1) better serves the priority outcomes 4 adopted in the Phase 1 Decision and (2) produces just and reasonable rates. The 5 Company has not done so. Without that explanation, the Authority has no basis 6 for giving the Company’s design more weight than the framework developed on 7 the reopener record. 8 The Company stated that it “did not perform additional analysis,” and it produced 9 no analysis comparing customer outcomes under its design with those under the 10 Proposed Final Decisions. 41 Its explanations concern its own ability to commit to 11 a stay-out, not any benefits to customers. A well-designed performance-based 12 framework shifts risk to the utility for underperformance and rewards it only for 13 demonstrated results, using mechanisms that are interdependent by design: the 14 capital-funding tool, the productivity-based revenue cap, and the incentive 15 mechanisms all lean on one another to produce an optimal risk allocation. 16 Eversource’s proposal removes the return-exclusion feature from capital recovery, 17 removes the total-cost discipline from the revenue cap, and offers its PIMs only if 18 the Authority approves its proposed PBMRP. 42 Each departure moves the 19 recovery mechanism closer to a conventional rate-base, rate-of-return recovery 20 where costs are ordinarily recovered once and not reconciled downward, and 41 42 CLF-AC-001, at page 13; CLF-AC-003, at page 2; CLF-AC-005, at pages 1-2. Exhibit CLP-ELP-1, at pages 50, 115. 21
  7. Page 25 of 121Match

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 22 of 90 1 incentive payments are structured as generalized compliance metrics rather than 2 as sharply targeted rewards for outperformance. Layered together, Eversource’s 3 PBMRP proposal functions less like a performance-based rate plan and more like 4 a traditional cost-of-service filing cloaked in the guise of PBR. The Company 5 itself describes both its PBMRP and a cycle of traditional rate cases as “designed 6 to roughly track with the cost of service.” 43 7 Q. CAPITAL BIAS IN TRADITIONAL COST-OF-SERVICE REGULATION? 8 9 DOES PERFORMANCE-BASED REGULATION HELP ADDRESS THE A. Yes, when it is designed properly. Under traditional cost-of-service regulation, a 10 utility earns a return on the capital it adds to the rate base but earns no return on 11 its operating expenses. That gives the utility a financial reason to favor capital- 12 intensive solutions over lower-cost operational or non-wires alternatives, and to 13 spend on infrastructure rather than become more efficient. At the same time, cost- 14 of-service regulation provides only a limited incentive to control operating costs: 15 prudently incurred O&M expenses are recovered dollar-for-dollar in rates, 16 without a return, so while the utility has no reason to increase them, it also has 17 little reason to reduce them beyond the savings it can retain between rate cases, 18 which are reset to actual costs at the next rate case. 19 A well-designed PBR framework blunts this bias by placing capital and operating 20 costs under the same productivity discipline and by tying earnings to performance 43 CLF-AC-001, at page 30 (EOE-156). 22
  8. Page 26 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 23 of 90 1 rather than the size of rate base. The framework developed throughout the RE01 2 proceeding was built to do exactly that. It includes a Revenue Cap Formula that 3 applies to total costs (i.e., capital and OM&A together) and the CT-Bar withholds 4 any return on new capital until the investment is determined prudent. 44 5 Eversource’s proposed PBMRP does not correct this bias. The Company’s I-X 6 formula applies productivity pressure only to OM&A costs, while capital is 7 recovered through a separate forecast-based mechanism that collects the capital 8 revenue requirement, which ordinarily includes a return on rate base, as plant 9 enters service, up to the Company’s own forecast. 45 In practice, up to the level of 10 its capital forecast, every dollar the Company can shift from an operating solution 11 to a capital solution escapes the productivity factor and moves into a mechanism 12 that earns a return. The Company’s proposal gives it two reasons to spend more. 13 First, any cost it shifts from operations to capital avoids the productivity factor 14 and earns a return. Second, the Company’s proposed productivity factor itself is 15 negative (−0.03 percent), so it applies no productivity pressure of its own. Even 16 combined with the Company’s proposed 0.30 percent Consumer Dividend, the net 17 annual offset to inflation would be only about 0.27 percent. That offset would 18 apply to a cost level the Company’s own consultant found was 11.9 percent above 19 benchmark on average from 2015 through 2024, and 31.5 percent above 20 benchmark in 2024. 46 Like cost-of-service regulation, the proposal rewards 44 45 46 RE01 PFD, at pages 5, 20-21 & n. 19, 31-41. Exhibit CLP-PBR-1, at pages 42, 68. Id., at pages 56, 64. 23
  9. Page 27 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 24 of 90 1 spending over efficiency. The Company offers three responses to this incentive, 2 and none of them remove it. 3 First, its consultant states that, relative to its peers, the Company “has historically 4 relied more heavily on OM&A expenditures than capital-related expenditures.” 5 But the Company’s past spending mix reflects how it behaved under past rules, 6 not how it would respond to this new mechanism that pays a return on capital 7 during the plan term while applying productivity pressure only to OM&A. If 8 anything, a utility that has historically relied on OM&A has more room to shift 9 spending toward capital. Second, the Company states that “there are very few 10 instances when system needs can be easily transitioned between a capital-work 11 solution or a work solution that can be expense.” But the non-wires and DER 12 alternatives that the IDSP and the Authority’s NWS process are designed to 13 evaluate exist precisely because some grid needs can be met with either a capital 14 investment or an operating solution. Third, the Company contends that the 15 prospect of a future prudence review “eliminates any perceived financial benefit 16 for the Company to ‘over invest’ today”. It does not. A prudence review asks 17 only whether the Company’s choice was reasonable when made. If the Company 18 chooses a reasonable capital project when a lower-cost operating or non-wires 19 solution would have met the same need, that project passes review and customers 20 pay for it in full. Under the F-Factor, they would also pay a return on it from the 21 day it enters service, before any review occurs. A prudence review screens out 24
  10. Page 28 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 25 of 90 1 unreasonable spending, not unnecessary spending, so it cannot stop the Company 2 from choosing the more expensive option. C. Timeline of the PBR Proceedings Relative to Eversource’s Rate Case 3 Filing 4 5 Q. PLEASE DESCRIBE THE TIMELINE OF THE RE01, RE02, AND RE03 6 REOPENER PROCEEDINGS RELATIVE TO EVERSOURCE’S RATE 7 CASE FILING. 8 A. A timeline sequencing the events and dates related to the PBR docket and its 9 reopeners, as well as Eversource’s rate case application, is provided as 10 Appendix B. 11 Q. TO THE AUTHORITY’S PBR PROCEEDINGS? 12 13 WHEN DID EVERSOURCE FILE ITS PROPOSED PBMRP RELATIVE A. Eversource filed its rate case proposing a first-generation PBMRP on July 14, 14 2026, including a capital funding mechanism and a PIMs portfolio, before the 15 Authority issued final decisions in RE01, RE02, or RE03. 47 16 The timing of the filing was the Company’s decision. Eversource’s last base 17 distribution rate case was decided more than eight years ago, in April 2018, and 18 the three-year rate plan approved in that case expired on April 30, 2021. 48 The 19 Company has operated under those rates for more than five years since that plan 20 ended. Nothing precluded the Company from proposing a PBR plan before the 47 48 Application, at page 1. Id., at page 4 & n. 4. 25