Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Files1

Search terms highlighted
Eversource rate increase is on 7 pages of the text below, highlighted. Go to the first matchClear highlighting
7 pages match
  1. Page 43 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 40 of 90 1 adopt it. 76 Neither example supports collecting a return on forecast capital before 2 prudence is established. 3 Q. TOGETHER? 4 5 HOW ARE THE IDSP AND THE CT-BAR INTENDED TO WORK A. The IDSP and the CT-Bar were designed as two halves of one process. The IDSP 6 requires the utility to identify what the grid needs and why. For example, where 7 capacity is constrained, where reliability needs attention, and where hosting 8 capacity must grow to accommodate distributed energy resources. Through the 9 Joint Working Group, public engagement, and the IDSP review docket, the 10 Authority and stakeholders would test and agree on those needs before the rate 11 case. 77 The IDSP establishes that a grid need exists. It does not approve the cost of 12 any particular way of meeting that need. The quantitative review, determining 13 whether the Company’s actual spending was prudent, comes later, in the rate case. 14 As the Authority explained, the IDSP “can provide the basis for evaluating the 15 prudence of grid investments under either a traditional rate filing or a proposed 16 MRP under a PBR framework”. 78 The CT-Bar completes that design by 17 withholding any return on new capital until that prudence finding is made. 79 18 For example, an IDSP ruling might confirm that additional hosting capacity is 19 needed in a particular area and that investment should be made there. That finding 76 77 78 79 RE01 PFD, at pages 31 n. 30, 35 n. 32. RE03 PFD No. 2, at pages 17-24, 69-75. Id., at pages 8-9. RE01 PFD, at pages 31-41. 40
  2. Page 44 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 41 of 90 1 does not settle whether the business decisions the Company makes to deliver that 2 capacity are reasonable: its choice between a traditional wires upgrade and a non- 3 wires alternative, its procurement, its project design, or its cost management. Those 4 business decisions are what a prudence review scrutinizes. The question in the rate 5 case is not whether an investment needed to be made, which the IDSP would have 6 already answered, but whether the Company made it wisely. 7 Q. HOW DOES THE ALLOCATION OF RISK UNDER THE COMPANY’S 8 FORECAST-AND-RECONCILE MECHANISM COMPARE TO THE CT- 9 BAR PROPOSED IN RE01? 10 A. Under the CT-Bar, the utility recovers depreciation, property tax, and gross 11 earnings tax on new capital during the plan term, but it earns no return on that 12 capital, and accrues no carrying charges, until the Authority finds the investment 13 prudent and used and useful in the next rate case. 80 The Authority designed it that 14 way deliberately. The CT-Bar “is not intended to serve as an exception to the well- 15 established principle that utilities may only earn a return on prudently invested 16 capital”. 81 Under traditional cost-of-service regulation, absent a capital tracker, a 17 utility that places new plant in service between rate cases recovers nothing on that 18 investment, neither a return nor depreciation or taxes, until the Authority reviews 19 its prudence in the next rate case and adds it to rate base. The CT-Bar is more 20 generous than that. It lets the utility recover depreciation and taxes on new capital 80 81 Id., at pages 36-39. Id., at page 33. 41
  3. Page 45 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 42 of 90 1 during the plan term, which it “would not ordinarily be permitted to obtain under 2 typical ratemaking principles”. 82 What the CT-Bar withholds until prudence is 3 shown is the return, the part of the revenue requirement that rewards capital 4 spending. 5 The Company’s F-Factor allocates risk differently. Each year, customers would pay 6 the full revenue requirement on the Company’s new capital, including a return, 7 beginning with an allowance based on the Company’s forecast. The Authority 8 would review whether those investments were prudent only in the following year’s 9 reconciliation, after customers had already paid. 83 For example, if the Company 10 places a new substation project in service in 2027, customers would begin paying 11 depreciation, taxes, and a return on it through the F-Factor that year. Prudency 12 would be determined in the 2028 reconciliation. Under the CT-Bar, customers 13 would pay only depreciation and taxes on that project during the plan term, and the 14 Company would earn no return on it until the Authority found it prudent in the next 15 rate case. 16 Ms. Frayer points out that the Company bears the risk of spending above the 17 approved forecast. 84 The converse is also true: up to the forecast, the Company 18 bears little risk at all. Customers would begin paying the full revenue requirement 19 on new plant, including a return, as soon as it enters service. The risk that any of 82 83 84 Id. Exhibit CLP-PBR-1, at pages 68, 71; OCC-423, at pages 10-11. Exhibit CLP-PBR-1, at pages 70-71. 42
  4. Page 46 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 43 of 90 1 that spending is imprudent would rest with customers until a later reconciliation. 85 2 But that protection is only as good as the forecast. If the Company prepared its 3 forecast without the guardrails baked into the IDSP process, the Authority would 4 not have an independently reviewed plan against which to test it (see Section V). 5 Under the F-Factor, customers would pay a return on new plant as soon as it enters 6 service, and any finding that a choice was imprudent would come after that return 7 had been collected. The Company states that it does not view the F-Factor as 8 providing a return before prudence review, because amounts collected on 9 investment later found imprudent would be returned to customers through its 10 downward-only reconciliation. But it confirms that the F-Factor allowance “does 11 include the cost of capital, including return on equity investment,” on capital 12 additions the Authority has not yet reviewed, and that its proposal is “intentionally 13 inconsistent” with the CT-Bar on this point. 86 Customers would pay that return first, 14 and would be refunded only if the Authority later finds the investment imprudent. 15 By the Company’s own estimate, the cost of capital alone would add $124.1 million 16 over the plan term relative to the CT-Bar. 87 The objective of a PBR capital funding 17 mechanism is to protect customers from imprudent spending and to reward the 18 utility only when it spends prudently, not to shift substantial risk from utility 19 shareholders onto ratepayers by paying a return before prudence is shown. 85 86 87 OCC-423, at pages 10-11. CLF-AC-004, at pages 1-2. OCC-423, at page 7. 43
  5. Page 47 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 44 of 90 1 Q. APPROACHES? 2 3 CAN YOU ILLUSTRATE THE DIFFERENCES BETWEEN THESE TWO A. Yes. Consider a household deciding whether to replace a car. One spouse proposes 4 using the family’s savings to buy a new car, and the other agrees that a new car is 5 needed. That agreement is the equivalent of the IDSP: it establishes the need, not 6 the price. The first spouse then goes out and buys a large luxury SUV. When the 7 couple later sits down to reconcile their spending, they realize that a reliable, fuel- 8 efficient sedan would have met the family’s needs at far lower cost. By then the 9 savings are spent, the SUV lost a large share of its value the moment it left the lot, 10 and the household is worse off than if the less expensive option had been purchased. 11 Under PURA’s proposed IDSP and the CT-Bar, the household agrees that a new 12 car is needed, but the purchase is reviewed before the household pays for it in full. 13 If the review shows the luxury SUV was the wrong choice, the extra cost of that 14 decision falls on the spouse who made it, not on the family’s savings. Under the 15 Company’s forecast-and-reconcile proposal, the spouse making the purchase 16 proposes the budget, the household agrees in advance to cover whatever is spent up 17 to that budget, and payments begin as soon as the car is chosen. The only automatic 18 check is whether the spouse spent more than the budget they wrote, and not whether 19 the purchase itself was a sensible one. Whether an SUV was the right choice is 20 examined only after the household has already begun paying for it. 44
  6. Page 48 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 45 of 90 1 Q. CT-BAR? 2 3 HOW HAS THE COMPANY EXPLAINED ITS DEPARTURE FROM THE A. The Company’s explanation only reflects its own financial interests. It calls the CT- 4 Bar’s exclusion of the cost of capital “a non-starter from a policy perspective” and 5 states that, without that return, it could not commit to a stay-out. 88 Asked how its 6 approach would produce customer savings or improve affordability compared with 7 including capital in the RE01 revenue cap, the Company offered only general 8 statements about the benefits of planned, systematic investment, which it 9 acknowledged are “difficult to define in terms of the overall cost trends”. 89 The 10 Company has not shown that the proposed F-Factor would produce lower rates, 11 better performance, or any other benefit to customers, compared with the CT-Bar. 12 Its principal argument is that the CT-Bar “did not reflect the economic reality that 13 financing costs are incurred when investments are made and placed in service”. 90 14 That is equally true under traditional cost-of-service regulation, where new plant 15 earns no return until the next rate case, and it does not explain how customers would 16 be better off under the F-Factor. An explanation of why a mechanism is better for 17 the utility’s shareholders does not carry the Company’s burden of showing that the 18 resulting rates are just and reasonable. Under the Company’s plan, those rates 19 would be set by formula for four years. OM&A revenues would escalate each year 20 under its I-X formula, and capital revenues would rise with the F-Factor up to the 88 89 90 OCC-423, at pages 3, 7-8. Id, at pages 12-13. CLF-AC-004, at page 2. 45
  7. Page 49 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 46 of 90 1 Company’s own forecast. The Company has not shown that either formula 2 produces rates that are just and reasonable in any year of the plan, let alone all four. 3 Q. WOULD WITHOLDING THE RETURN ON NEW CAPITAL UNTIL 4 PRUDENCE IS ESTABLISHED DENY THE COMPANY A REASONABLE 5 RETURN? 6 A. No. The Company is entitled to an opportunity to earn a reasonable return on capital 7 that is prudently invested, and the CT-Bar would preserve that opportunity. A utility 8 that invests prudently earns its full return once the investment is reviewed and 9 placed in the rate base. The CT-Bar would affect the timing of that return, not 10 whether the Company would earn it. The deferral would carry a time-value cost for 11 the Company, but that is the same regulatory lag utilities experience under 12 traditional cost-of-service regulation, where a new plant earns no return until 13 prudence is reviewed in a rate case. The CT-Bar is more generous than traditional 14 cost-of-service regulation, because it lets the Company recover depreciation and 15 taxes on new plant during the plan term, before any prudence review. Withholding 16 the return until prudence is established is the trade the Authority designed into the 17 CT-Bar in exchange for that earlier recovery. The Company’s own history shows 18 that it can operate under this kind of regulatory lag. Its last base rate case was 19 decided in April 2018, and the rate plan from that case expired in 2021. 91 Since 20 then, the Company has added roughly $3.3 billion in net utility plant without 91 Application, at page 4 & n. 4; see Docket No. 17-10-46, April 18, 2018 Decision. 46
  8. Page 50 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 47 of 90 1 earning a return on that plant through base rates until this rate case. 92 The 2 Company’s witness has acknowledged that rates based on historical plant additions 3 gave the utilities “an opportunity, if they could manage their costs under those 4 revenues, to earn their authorized return.” 93 The Company argues that, without a 5 return on new capital, it would have to cut O&M expense by roughly 23 percent by 6 Rate Year 4 to earn its authorized return, and that it would instead file rate cases as 7 often as every 18 months. 94 But it has not reconciled that position with its own 8 experience of adding $3.3 billion in plant since 2021 without a capital tracker, or 9 explained why the CT-Bar, which would provide more interim revenue than the 10 Company has received since 2021, would leave it worse off. 11 Q. IF THE AUTHORITY DECIDES TO ALLOW A RETURN ON NEW 12 CAPITAL DURING THE PLAN TERM, WHAT CONDITIONS SHOULD 13 APPLY? 14 A. If the Authority decides to allow a return on new capital during the plan term, that 15 approach could be reasonable from a policy perspective only if two conditions keep 16 the risk of imprudent spending on the Company first. 17 First, recovery should be capped at a capital plan reviewed through the IDSP 18 process rather than at the Company’s own forecast. Second, any return collected 19 should be subject to refund to customers, with carrying costs, upon a finding of 92 93 94 Application, at page 3. Docket Nos. 21-05-15RE01, 21-05-15RE02, and 21-05-15RE03, Technical Meeting Transcript (May 21, 2025), at pages 103-104 (D. Horton). CLF-AC-001, at pages 9-10. 47
  9. Page 51 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 48 of 90 1 imprudence. 95 The F-Factor does not meet the first condition: its cap is the 2 Company’s own forecast, which has not been reviewed through an IDSP. On the 3 second, the Company states that amounts collected on investment later found 4 imprudent would be returned to customers through its downward-only 5 reconciliation, but it identifies carrying charges only for investment the Company 6 does not place in service, not for investment found imprudent. 96 If the Authority 7 allows a return during the plan term, it should require that any refund for imprudent 8 investment include carrying costs. 9 Q. FORECAST CAPITAL SPENDING TRAJECTORY? 10 11 WHAT DOES THE RECORD SHOW ABOUT THE COMPANY’S A. The Company forecasts a sustained increase in capital spending well above its 12 historical levels. Its total capital expenditures are forecasted to grow from $551.0 13 million in 2025 (actual) to $884.0 million in 2031 (planned), an increase of 14 approximately 60% (OCC‑424, Attachment 1). 97 The forecast rises in every year, 15 reaching $690.0 million in 2027 and $884.0 million in 2031. By comparison, the 16 Company’s actual capital expenditures averaged approximately $575 million per 17 year from 2021 through 2025. Its highest year in that period was $684.5 million in 18 2023. 98 Every forecast year from 2027 through 2031 exceeds the Company’s 19 highest actual year in the most recent five-year period. The largest driver in this 95 96 97 98 See Docket Nos. 21-05-15RE01 and 21-05-15RE02, Written Exceptions of the Advocates on Proposed Final Decisions (Aug. 15, 2025), at page 2. CLF-AC-004, at pages 1, 3. OCC-424, Attachment 1. Id. 48
  10. Page 52 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 49 of 90 1 cost increase is reliability spending, which is forecasted to more than double, from 2 $164.3 million in 2025 to $377.7 million in 2031. 99 3 Reliability investment may be needed, but it cannot be assumed. The question is 4 whether the Company has provided sufficient justification for its forecasted level 5 of investment. It has not. The Company has not reconciled its forecast against its 6 own past spending or explained why these needs could not be met at historical 7 levels. 8 Ms. Frayer testifies that a formula grounded in historical trends may not produce 9 an adequate revenue trajectory when a utility “is expected to undertake capital 10 investments at a pace significantly greater than historical levels”. 100 Under the 11 Company’s proposed capital funding mechanism, this forecast becomes the cap 12 on capital recovery for the plan term. 101 The Authority, if it adopts Eversource’s 13 capital funding mechanism proposal, would therefore be authorizing capital 14 recovery up to a level roughly 40 percent above the Company’s 2021–2025 15 average spending. 102 99 100 101 102 Id. Exhibit CLP-PBR-1, at pages 23–24. Id, at page 68. The Company’s forecast capital expenditures for 2027–2031 average $797 million per year ($3.985 billion ÷ 5). Actual capital spending for 2021–2025 averaged $574.6 million per year. The difference, $222.4 million, is about 39 percent of the historical average. These figures are in nominal dollars. Adjusting for inflation would reduce the percentage difference but would not eliminate it. 49

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Lindsay J. Griffin [26-05-10]

This filing on the current system (opens in a new tab)