  1. Page 51 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 48 of 90 1 imprudence. 95 The F-Factor does not meet the first condition: its cap is the 2 Company’s own forecast, which has not been reviewed through an IDSP. On the 3 second, the Company states that amounts collected on investment later found 4 imprudent would be returned to customers through its downward-only 5 reconciliation, but it identifies carrying charges only for investment the Company 6 does not place in service, not for investment found imprudent. 96 If the Authority 7 allows a return during the plan term, it should require that any refund for imprudent 8 investment include carrying costs. 9 Q. FORECAST CAPITAL SPENDING TRAJECTORY? 10 11 WHAT DOES THE RECORD SHOW ABOUT THE COMPANY’S A. The Company forecasts a sustained increase in capital spending well above its 12 historical levels. Its total capital expenditures are forecasted to grow from $551.0 13 million in 2025 (actual) to $884.0 million in 2031 (planned), an increase of 14 approximately 60% (OCC‑424, Attachment 1). 97 The forecast rises in every year, 15 reaching $690.0 million in 2027 and $884.0 million in 2031. By comparison, the 16 Company’s actual capital expenditures averaged approximately $575 million per 17 year from 2021 through 2025. Its highest year in that period was $684.5 million in 18 2023. 98 Every forecast year from 2027 through 2031 exceeds the Company’s 19 highest actual year in the most recent five-year period. The largest driver in this 95 96 97 98 See Docket Nos. 21-05-15RE01 and 21-05-15RE02, Written Exceptions of the Advocates on Proposed Final Decisions (Aug. 15, 2025), at page 2. CLF-AC-004, at pages 1, 3. OCC-424, Attachment 1. Id. 48
  2. Page 52 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 49 of 90 1 cost increase is reliability spending, which is forecasted to more than double, from 2 $164.3 million in 2025 to $377.7 million in 2031. 99 3 Reliability investment may be needed, but it cannot be assumed. The question is 4 whether the Company has provided sufficient justification for its forecasted level 5 of investment. It has not. The Company has not reconciled its forecast against its 6 own past spending or explained why these needs could not be met at historical 7 levels. 8 Ms. Frayer testifies that a formula grounded in historical trends may not produce 9 an adequate revenue trajectory when a utility “is expected to undertake capital 10 investments at a pace significantly greater than historical levels”. 100 Under the 11 Company’s proposed capital funding mechanism, this forecast becomes the cap 12 on capital recovery for the plan term. 101 The Authority, if it adopts Eversource’s 13 capital funding mechanism proposal, would therefore be authorizing capital 14 recovery up to a level roughly 40 percent above the Company’s 2021–2025 15 average spending. 102 99 100 101 102 Id. Exhibit CLP-PBR-1, at pages 23–24. Id, at page 68. The Company’s forecast capital expenditures for 2027–2031 average $797 million per year ($3.985 billion ÷ 5). Actual capital spending for 2021–2025 averaged $574.6 million per year. The difference, $222.4 million, is about 39 percent of the historical average. These figures are in nominal dollars. Adjusting for inflation would reduce the percentage difference but would not eliminate it. 49
  3. Page 53 of 121Match

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 50 of 90 1 Q. HAS THE COMPANY DEMONSTRATED THAT FUNDING CAPITAL 2 AT ITS OWN FORECAST WILL PRODUCE JUST AND REASONABLE 3 RATES? 4 A. No. Under the Company’s proposal, its capital forecast becomes the cap on 5 capital recovery for the plan term, so the reasonableness of that forecast is central 6 to whether the resulting rates are just and reasonable. The Company has not made 7 that showing. Funding capital from a multi-year forecast is reasonable only when 8 that forecast has been vetted. The IDSP process was designed to provide this. It 9 tests grid needs, forecasting assumptions, and alternatives with stakeholders and 10 the Authority before a rate case. 103 The Company’s forecast has not been subject 11 to anything approaching such rigorous review. It is the Company’s own projection 12 of what it intends to spend, and it cannot justify locking in four years of capital 13 recovery (see Section V). 104 While the Company’s forecast can be scrutinized in 14 this rate case, that does not substitute for the review process contemplated in the 15 IDSP Proposed Final Decision. For example, information obtained through 16 discovery can test the Company’s cost estimates, but a contested rate case is not 17 designed to test grid needs, forecasting assumptions, and non-wires alternatives 103 104 RE03 PFD No. 2, at pages 8-9, 17-24, 69-75. In RE01, Eversource also requested a “G-Factor” to increase revenues automatically for load and customer growth. The Authority declined this request in its Proposed Final Decision, with a proposed finding that going-in rates, the I-Factor, and the IDSP-linked CT-Bar already account for growth, and that a G-Factor “would undermine the priority outcomes of Business Operations and Investment Efficiency and Affordability by including additional automatic revenue requirement increases.” (RE01 PFD, at pages 27-28). The Company does not re-propose a G-Factor here, but because it proposes neither the CT-Bar nor an IDSP, the growth assumptions in its capital forecast would be funded without the planning review the Authority relied on in rejecting one. 50
  4. Page 54 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 51 of 90 1 with stakeholders over a ten-year planning horizon, as the IDSP was designed to 2 do. 105 Ms. Frayer recognizes that it is “common to hear” that forecast-based 3 approaches present “informational asymmetry between the regulator and the 4 regulated firm,” and that approving utility forecasts “is nonetheless information 5 intensive, and may become complex and contentious”. 106 The Authority has 6 explained that the utility’s statutory burden of proving that its proposed rates are 7 just and reasonable exists to address that kind of information imbalance, by 8 requiring the utility to present sufficient evidence to support its proposal. 107 By 9 the Company’s own estimate, including the cost of capital in the F-Factor would 10 add $124.1 million over the plan term compared with the CT-Bar. 108 A 11 mechanism that would authorize capital recovery up to roughly 40 percent above 12 the Company’s recent historical average and pay a return on that capital before 13 prudence is established, is simply not just and reasonable based on this record. 105 106 107 108 In a contested rate case, meaningful participation generally requires legal counsel, expert witnesses, and the capacity to conduct discovery on a compressed litigation schedule. Many stakeholders with an interest in distribution planning cannot support that commitment. The IDSP process proposed in RE03 PFD No. 2 is designed for broader engagement. It would require the Company to convene at least four Joint Working Group sessions before each IDSP filing, with agendas and background materials circulated in advance. It would also establish a data-sharing protocol so stakeholders can review planning data, and add a public engagement phase for municipal officials, environmental justice communities, and customers. (RE03 PFD No. 2, at pages 18-21). Exhibit CLP-PBR-1, at pages 13-14. RE01 PFD, at pages 44 n.36. OCC-423, at page 7. 51
  5. Page 55 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 52 of 90 C. Plan Term, Stay-Out Provisions, and Going-In Rate Mechanics 1 2 Q. HOW DOES EVERSOURCE’S PROPOSAL ON PLAN TERM, 3 EARNINGS SHARING, AND THE Z-FACTOR COMPARE TO THE RE01 4 2025 PROPOSED FINAL DECISION? 5 A. Eversource’s filing shares some similarities with RE01 in these areas, alongside 6 notable differences: (1) both propose a four-year plan term; (2) both include an 7 Earnings Sharing Mechanism generally along the lines of RE01’s asymmetrical, 8 upside-only 50/50 sharing structure, although Eversource’s version changes how 9 the customer share of overearnings is applied; and (3) both propose a Z-Factor, 10 but at a materially different threshold with 0.5% of distribution revenue in 11 Eversource’s proposal, compared to 0.75% of annual revenue requirement in the 12 RE01 2025 PFD. Eversource advocated a 0.5 percent threshold in RE01; the 13 Authority considered that proposal and proposed 0.75 percent. 109 The Company 14 notes that the other jurisdictions the RE01 PFD cites use thresholds between 0.2 15 and 0.5 percent. 110 109 110 RE01 PFD, at pages 24-26. CLF-AC-001, at pages 12-13. 52
  6. Page 56 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 53 of 90 1 V. FORECAST 2 3 EVERSOURCE HAS NOT ADEQUATELY SUPPORTED ITS CAPITAL Q. WHY DOES THE PLANNING BASIS FOR THE COMPANY’S CAPITAL 4 FORECAST BEAR ON WHETHER THE COMPANY HAS CARRIED ITS 5 BURDEN? 6 A. Because the Company’s capital forecast would set its capital recovery for the entire 7 plan term, the Company must show that its forecast accurately reflects necessary 8 grid investments over this time period. The IDSP is the proposed process the 9 Authority designed to establish that need before a rate case, through a documented 10 grid needs assessment, scenario-based load forecasting, evaluation of non-wires 11 alternatives, and stakeholder review. 111 The Company’s Targeted System 12 Performance Plan, as I explain below, does not provide enough information for a 13 reasonable assessment of those needs on the merits. Without a plan that has been 14 tested in that way, the Company has not substantiated the capital forecast on which 15 its plan depends. For this reason, I recommend in Section IX that the Authority 16 direct Eversource to refile its Targeted System Performance Plan so that it conforms 17 to the IDSP requirements in RE03 PFD No. 2, and that capital funding beyond the 18 first rate year be based on the refiled plan once it has been reviewed. 111 RE03 PFD No. 2, at pages 8-9, 17-24, 30. 53
  7. Page 57 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 54 of 90 1 Q. SUPPORT ITS CAPITAL FORECAST? 2 3 WHAT PLANNING DOCUMENT DID EVERSOURCE FILE TO A. The Company filed a “Five-Year Targeted System Performance Plan” (“TSP”). 112 4 That plan is the Company’s own capital planning document, created without any 5 stakeholder feedback or external evaluation of assumptions, inputs, or modeling 6 during development. 7 Q. FOR ITS CAPITAL FORECAST. 8 9 EXPLAIN WHY THE COMPANY’S TSP IS NOT AN ADEQUATE BASIS A. The Targeted System Performance Plan covers some of the same subject matter as 10 an IDSP, such as an overview of the state of the system and an investment plan. 11 However, it does not follow the structure, process, or planning horizon the 12 Authority has developed throughout the RE03 proceeding. These elements are not 13 superfluous; they are critical to the demonstration that a grid need is real and 14 requires a solution. The Company described its plan as aligning “generally” with 15 the IDSP content “while also reflecting practical differences.” 113 16 If the RE03 PFD No. 2 is finalized, each EDC’s IDSP would have to include, at a 17 minimum, ten defined sections, each with detailed content requirements the PFD 18 specifies. 114 The TSP does not map into that structure. Instead, it is organized by 112 113 114 Docket No. 26-05-10, July 14, 2026 Exhibits CLP-TSP-1 through CLP-TSP-5 OCC-566, at page 2. The ten sections are: (1) Executive Summary; (2) Planning Policy; (3) Current State of the System; (4) IDSP Methodology; (5) Stakeholder Engagement and Social Equity; (6) Load Forecasting; (7) Grid Needs Assessment; (8) Solution Selection Process; (9) Capital Investment Plan, covering a ten-year planning horizon; and (10) Long-Term Strategic Plan, covering the period beyond ten years (RE03 PFD No. 2, at page 9 & App. A). 54
  8. Page 58 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 55 of 90 1 investment category: substations, lines, new customer, asset health, capacity, grid 2 modernization, vegetation management, resiliency, and so on. When asked to 3 identify where the TSP addresses each IDSP section, the Company pointed to 4 scattered pages across several exhibits. 115 For several sections, those references fall 5 well short of what the IDSP would require: 6 • Stakeholder Engagement and Social Equity. An IDSP would have to 7 explain how stakeholders participate in the planning process and how equity 8 considerations are addressed. The Company points to no part of the TSP for 9 this section. It cites two pages of its leadership panel testimony that discuss 10 wholesale supply costs and public benefits charges, not stakeholder 11 participation in grid planning. 12 • Solution Selection Process. An IDSP would have to set out the criteria and 13 methods used to identify, compare, and select both traditional and non-wires 14 solutions. The Company points to three pages of the TSP. 15 • Planning Policy and Long-Term Strategic Plan. An IDSP would have to 16 address the state and local policies that inform grid planning, and separately 17 describe the Company's strategic plans beyond a ten-year horizon. The 18 Company cites the same two pages for both. 19 Notably, the TSP reflects no stakeholder review of any kind. It does not describe 20 any stakeholder process for evaluating load forecasting or long-term planning, or 115 OCC-566, at pages 2-3. 55
  9. Page 59 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 56 of 90 1 any public engagement. Although no stakeholder process was required for the TSP, 2 the absence of one matters. A plan that has not been tested by anyone outside the 3 Company rests entirely on the Company’s own assumptions about load growth, 4 grid needs, and solutions, and those are the assumptions that would set its capital 5 recovery. Other states have recognized this and require stakeholder engagement 6 before a utility files its grid plan. Illinois requires utilities to develop their multi- 7 year integrated grid plans through at least six stakeholder workshops over a 8 minimum of five months, run by an independent facilitator, before filing. 116 Maine 9 requires technical conferences or stakeholder workshops before filing to identify 10 the priorities, assumptions, goals, methods, and tools for the utility’s grid plan. 117 11 The TSP covers five years. 118 The Company already prepares ten-year substation 12 plans under N-1 contingency scenarios 119, so the shorter horizon reflects a choice 13 rather than a limitation. RE03 PFD No. 2 would require a ten-year Capital 14 Investment Plan and a Long-Term Strategic Plan looking 10 to 25 years ahead. 120 15 A longer horizon matters because the equipment the Company installs may remain 16 in service for 40 years or more. A five-year view cannot show whether an 116 117 118 119 120 220 Ill. Comp. Stat. 5/16-105.17(d)(6), (e) (requiring that integrated grid planning “ensure opportunities for robust public participation through open, transparent planning processes,” and establishing a stakeholder workshop process of at least six workshops over a minimum of five months, conducted by an independent facilitator selected by the Illinois Commerce Commission, before the utility files its plan). Me. Rev. Stat. tit. 35-A, § 3147(2) (“The commission shall hold technical conferences or stakeholder workshops before the filing to identify priorities, assumptions, goals, methods and tools that will assist the covered utility in developing a grid plan.”). Exhibit CLP-TSP-1, at page 13; Application, at pages 5-6. RE03 PFD No. 2, at p. 35. Id, at pages 9, 65-66. 56
  10. Page 60 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 57 of 90 1 investment made today will still fit the grid’s needs as load growth, DER adoption, 2 and electrification evolve. It also limits the Authority’s ability to see long-term 3 trends and to consider whether some investments could be deferred or right-sized. 4 RE03 PFD No. 2 also contemplates that a Comprehensive IDSP would be filed and 5 reviewed in its own docket three to six months before a rate case. 121 That separate 6 review would give stakeholders and the Authority time to examine the plan, ask 7 questions through discovery and technical meetings, and comment, and it would 8 give the Company an opportunity to revise the plan before it is used to support a 9 rate request. 122 The TSP was filed as a rate case exhibit, with no prior review. 10 The Company’s load forecasting falls short in several respects. RE03 PFD No. 2 11 directs the EDCs to develop at least three forecasts (low, middle, and high), with 12 the middle forecast serving as the baseline for identifying grid needs; to forecast at 13 the system, planning region, substation, and distribution feeder levels; and to use 14 leading indicators for DER and electrification adoption in the baseline and high 15 scenarios. 123 16 The Company forecasts load only at the substation level, and only for each 17 substation’s annual peak hour. It develops a 24-hour load profile only after that 18 peak-hour forecast identifies a capacity need. 124 That approach limits what the 19 forecast can reveal in three ways. First, it can miss grid needs that occur outside the 121 122 123 124 Id, at pages 73-74. Id., at page 73. RE03 PFD No. 2, at pages 30, 34. OCC-574. 57

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Lindsay J. Griffin [26-05-10]