    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 74 of 90 1 state explicitly that its decision does not set precedent for the design of multi-year 2 rate plans for Eversource or any other Connecticut electric distribution company. 3 Q. WHAT ARE THE TIMING CONSEQUENCES OF APPROVING A 4 COMPANY-DESIGNED PBMRP BEFORE THE STATEWIDE 5 FRAMEWORK IS FINAL? 6 A. They are significant. If the Authority approves a PBMRP for Eversource in this 7 docket, the Company’s mechanisms would presumably govern its rates for the full 8 plan term. Incorporating the eventual outcomes of RE01, RE02, and RE03 into that 9 already-approved plan would likely require a multi-year lag and a subsequent 10 proceeding to true it up. 11 Q. WHY SHOULD THE AUTHORITY CONSIDER THE RECORD 12 DEVELOPED IN THE PBR REOPENER DOCKETS WHEN 13 EVALUATING THE COMPANY’S PROPOSAL? 14 A. Many of the organizations that invested years of staff time in Docket No. 21-05-15 15 and the RE01, RE02, and RE03 reopeners are Connecticut-based nonprofits, 16 frontline and consumer advocacy organizations, and other parties with limited 17 resources. Their staff live and work in the communities Eversource serves, the same 18 communities that experience the outages, the bill impacts, and the affordability 19 pressures these dockets ultimately seek to address. Their recommendations in the 20 reopeners were informed by direct, on-the-ground experience with how the 21 Company’s rates and performance affect Connecticut customers. 74
  2. Page 78 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 75 of 90 1 Those organizations were able to participate meaningfully in the reopeners because 2 they were uncontested proceedings designed for multi-stakeholder engagement 3 over an extended timeline, with technical meetings, straw proposals, and repeated 4 opportunities for written comment. A base distribution rate case is different. 5 Meaningful participation in a contested proceeding requires legal representation, 6 expert witnesses, discovery, and a compressed, resource-intensive litigation 7 schedule that many of those same organizations cannot support. 8 If the Authority decides first-generation PBR mechanics in this rate case without 9 reference to the reopener record, its decision would rest on a much narrower set of 10 perspectives. It would also allow a single company’s filing, made before the 11 reopeners are finalized, to supersede years of stakeholder engagement. This 12 outcome would undermine the substantial resources that docket participants 13 invested in the PBR proceedings and discourage participation in the Authority’s 14 future stakeholder processes. 15 IX. IX. RECOMMENDATIONS. C. The Authority should reject Eversource’s Proposed PBMRP 16 17 Q. WHAT IS YOUR PRINCIPAL RECOMMENDATION? 18 A. The Authority should reject the Company’s proposed PBMRP, including its 19 revenue adjustment mechanism, capital funding mechanism, and PIMs portfolio. 20 The Company bears the burden of demonstrating that its proposal will produce just 21 and reasonable rates, serve the public interest, and advance the priority outcomes 22 adopted in the Phase 1 Decision. For the reasons set out in Sections IV through 75
  3. Page 79 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 76 of 90 1 VIII, it has not done so. Because the plan’s flaws are structural, they cannot be 2 cured by adjusting individual parameters. In its place, the Authority should apply 3 the PBR framework developed in Docket No. 21-05-15 and its reopeners, as 4 reflected in the RE01, RE02, and RE03 Proposed Final Decisions, to the extent it 5 adopts PBR mechanisms for Eversource in this proceeding. Under that approach, 6 the Authority should set going-in rates for the first rate year and direct Eversource 7 to refile its Targeted System Performance Plan so that it conforms to the IDSP 8 requirements in RE03 PFD No. 2, with the reviewed plan providing the basis for 9 capital funding in the remaining years. If the Authority declines to do so, it should 10 set the Company's base distribution rates through traditional cost-of-service 11 ratemaking. In either case, it should adopt the RE02 performance mechanisms, with 12 the few modifications I describe below, and require Eversource to file a 13 Comprehensive IDSP in accordance with the final decision in Docket No. 21-05- 14 15RE03. D. Primary Recommendation: Apply the Framework Developed in Docket 15 No. 21-05-15 and Its Reopeners 16 17 Q. OF THE COMPANY’S PROPOSAL? 18 19 WHAT DO YOU RECOMMEND THE AUTHORITY ADOPT IN PLACE A. To the extent the Authority adopts PBR mechanisms for Eversource in this 20 proceeding, I recommend that it adopt the elements described below, which are 21 drawn from the RE01, RE02, and RE03 Proposed Final Decisions. The Authority 22 should also state explicitly that its decision does not set precedent for the design 76
  4. Page 80 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 77 of 90 1 of multi-year rate plans, and that the statewide framework that emerges from the 2 reopeners will govern future plans for Eversource and the other electric 3 distribution company. 4 I recognize that the Company has said it could not commit to a stay-out if the 5 capital funding mechanism excludes the cost of capital, as the CT-Bar does. 166 6 The RE01 Proposed Final Decision anticipates that possibility. If a utility declines 7 the stay-out, the multi-year plan does not take effect, the Revenue Cap Formula 8 and CT-Bar are not available, and rates are set for the first rate year only, while 9 the performance mechanisms and IDSP requirements continue to apply. 167 That 10 outcome would be consistent with the framework and with my alternative 11 recommendation below. 12 Q. WHY SHOULD THE AUTHORITY ADOPT THE PBR ELEMENTS 13 DRAWN FROM THE RE01, RE02, AND RE03 PROPOSED FINAL 14 DECISIONS? 15 A. Because those elements are the product of years of deliberate, collaborative work. 16 The PBR elements in the three reopener proposed final decisions were developed 17 through an open process in which every stakeholder, including Eversource, had 18 repeated opportunities to shape the outcome. The Authority described the RE03 19 PFD No. 2 result as reflecting “the culmination of extensive stakeholder 20 engagement, iterative refinements, and Authority analysis.” 168 The record is also 166 167 168 OCC-423, at pages 3, 8. RE01 PFD, at page 10. RE03 PFD No. 2, at page 1. 77
  5. Page 81 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 78 of 90 1 balanced. The Authority stated that its purpose was “to document the substantial 2 stakeholder input” and to explain why it chose each mechanism it adopted. 169 The 3 proposed final decisions do exactly that. For each mechanism, the Authority 4 summarizes the straw proposal, sets out the positions of the participants, and then 5 explains its own analysis and conclusion. 170 The outcome is a framework that 6 reflects ratepayer, environmental, industrial, labor, and utility perspectives, 7 weighed against one another in the open. 8 The reopeners were designed to work together and to serve the objectives the 9 Authority established in Phase 1. The Authority has explained that planning, 10 revenue adjustment mechanisms, and performance evaluation are “mutually 11 constitutive of each other” and function “as an iterative whole” (RE03 PFD No. 2, 12 at page 7). 171 Each reopener was built expressly to advance the four regulatory 13 goals, five foundational considerations, and nine priority outcomes adopted in the 14 Phase 1 Decision. 172 15 Q. RECOMMEND THAT PURA ADOPT? 16 17 WHAT REVENUE ADJUSTMENT MECHANISMS DO YOU A. I recommend that the Authority adopt the revenue adjustment mechanisms 18 proposed in the RE01 PFD, for the reasons explained above. I emphasize one 19 element of that design that the Company’s proposal omits, and I recommend two 169 170 171 172 RE01 PFD, at page 1. Id., at pages 7-8. RE03 PFD No. 2, at page 7. RE01 PFD, at page 5; RE02 PFD No. 2, at page 1; RE03 PFD No. 2, at page 1. 78
  6. Page 82 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 79 of 90 1 changes to the RE01 PFD design. My full recommendations are set out in 2 Appendix C and reflect the RE01 PFD design, with the inclusion of the changes 3 described here. 4 First, the revenue cap formula should apply to the Company’s total revenue 5 requirement, covering both capital and OM&A costs, as the RE01 PFD proposes. 173 6 A revenue cap that covers only part of the revenue requirement cannot contain costs 7 because costs simply shift to the part the cap does not reach. 8 Second, the X-Factor should be based on a total factor productivity study that meets 9 the RE01 PFD’s proposed requirements, including the use of customer count, 10 delivered energy, and peak demand as outputs. 174 As a change to the RE01 PFD, 11 which allows the X-Factor to be positive or negative, I recommend the Authority 12 not approve a negative X-Factor based on a study that does not meet those 13 requirements. 175 14 Third, while the RE01 PFD would fund Capital Plan additions through the CT-Bar 15 beginning in Rate Year 1 176, I recommend the CT-Bar not fund capital additions, 16 including the Rate Year 1 CT-Bar additions the RE01 PFD would include in going- 17 in rates, until the Company has refiled its Targeted System Performance Plan in a 18 form that conforms to the IDSP requirements proposed in RE03 PFD No. 2 and the 19 Authority has reviewed it. Once the reviewed plan is in place, it should provide the 173 174 175 176 RE01 PFD, at pages 20–21 & n.19. Id., at pages 22-25. RE01 PFD, at page 22. RE01 PFD, at pages 33, 37 (Calculation Methodology, Step 2) & 40 (Guideline 9). 79
  7. Page 83 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 80 of 90 1 capital input to the CT-Bar for the remaining years of the plan. The RE01 PFD 2 assumes that the Capital Plan is supported by a reviewed IDSP. Here, no such plan 3 exists. 4 Q. AUTHORITY ADOPT? 5 6 WHAT PERFORMANCE MECHANISMS DO YOU RECOMMEND THE A. I recommend that the Authority adopt the performance mechanisms proposed in 7 RE02 PFD No. 2, which are set out in Appendix C, and make them effective 8 whether or not a multi-year rate plan is approved. I recommend the following 9 changes to the RE02 PFD No. 2 proposed design: 10 1. A Customer Reliability Scorecard, rather than an upside-only PIM with no 11 financial reward, that tracks Customers Experiencing Multiple Interruptions 12 (CEMI) and Customers Experiencing Long Interruption Duration (CELID), 13 focused specifically on repeat appearances by the same customers year over 14 year to identify chronically underserved customers, with the option to elevate it 15 to a downside-only PIM once sufficient data are available. 177 Reliable service 16 is a core obligation the Company already undertakes in exchange for its 17 authorized return. 18 2. A Time-Varying Rate Scorecard, or a Reported Metric that converts to a 19 Scorecard, with enrollment targets as AMI deployment is completed, reported 20 separately for LMI and non-LMI customers that tracks customer 177 The RE02 PFD No. 2 proposes to adopt Customer Reliability as an upside-only PIM that rewards the Company when its composite score falls below the five-year historical average plus one standard deviation (RE02 PFD No. 2, at pages 44-46). 80
  8. Page 84 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 81 of 90 1 enrollment/participation in time-varying (time-of-use) rate options. 178 Without 2 targets, there is no benchmark for judging whether the Company is enrolling 3 customers in time-varying rates. And without separate LMI reporting, the 4 Authority cannot tell whether the bill savings that time-of-use rates can offer 5 are reaching the customers who need them most. 6 3. Community Engagement Scorecard, rather than a Reported Metric, built on the 7 three consolidated sub-metrics in RE02 PFD No. 2 (number of activities, public 8 participation, and actionable outcomes), with targets for outreach activity and 9 an equity sub-metric for Environmental Justice community representation on 10 advisory boards, or at a minimum a Reported Metric with a stated path to a 11 Scorecard. 179 A Reported Metric only records what the Company chooses to 12 do, while targets set an expectation for meaningful engagement with the 13 communities that have historically had the least say in utility decisions. 14 4. A Level 2 DER Interconnection Scorecard that tracks the average number of 15 business days in Company-controlled processing steps for fast-track Level 2 16 DER interconnection projects, using the 4-step calculation in RE02 PFD No. 2, 17 benchmarked against the EDC interconnection guidelines and a five-year 18 historical average. If Level 2 processing times lengthen while Level 1 times 178 179 The RE02 PFD No. 2 proposes adopting Time-Varying Rates as a Reported Metric with no enrollment targets and only suggests that future versions “may benefit from” separate LMI reporting (RE02 PFD No. 2, at pages 70-71). The RE02 PFD No. 2 proposes adopting Community Engagement as a Reported Metric only (RE02 PFD No. 2, at pages 74-75). 81
  9. Page 85 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 82 of 90 1 improve, the Authority should consider elevating the Scorecard to a PIM. 180 A 2 financial incentive tied only to Level 1 projects could lead the Company to 3 prioritize smaller projects over larger ones, which deliver more clean energy 4 capacity, and RE02 PFD No. 2 itself recognizes that the Scorecard data would 5 provide “a basis for adjustments” in that scenario. 181 6 Q. ADOPT? 7 8 WHAT DISTRIBUTION PLANNING ELEMENTS SHOULD PURA A. I recommend that the Authority adopt the integrated distribution planning 9 requirements proposed in the RE03 PFD No. 2, which are set out in Appendix C, 10 with two additions specific to this case. First, I recommend that the Authority direct 11 Eversource to refile its Targeted System Performance Plan, either as a compliance 12 filing in this docket or in a subsequent docket, as the Authority deems appropriate, 13 so that it conforms to the IDSP requirements set out in RE03 PFD No. 2. Under this 14 approach, the Authority would set going-in rates for the first rate year in this docket 15 without relying on the Company’s capital forecast. The Company’s proposed 16 going-in revenue requirement already includes forecast capital additions through 17 the rate year, which is why it sets its first-year F-Factor at zero. 182 Consistent with 18 the RE01 Proposed Final Decision, going-in rates should instead reflect plant that 19 is in service, and shown to be prudent and used and useful, as of the close of the 180 181 182 RE02 PFD No. 2 proposes adopting the Level 2 DER Interconnection Scorecard without saying what adjustment would follow if Level 2 performance worsens (RE02 PFD No. 2, at pages 79-80). RE02 PFD No. 2, at pages 79-81. CLF-AC-001, at page 8 n.2. 82
  10. Page 86 of 121

    Docket No. 26-05-10 Direct Testimony of Lindsay J. Griffin October 21, 2026 Page 83 of 90 1 evidentiary record. 183 Once the refiled plan has been reviewed, the capital 2 investments it supports could be reflected in the capital funding component of the 3 revenue cap formula (the CT-Bar) for the remaining years of the plan. The IDSP 4 filing would not require the Authority to redesign the formula or reopen this rate 5 case. It would simply update the capital input to a formula approved in this docket, 6 much as the annual revenue adjustment mechanism updates other inputs each year. 7 Until the refiled plan has been reviewed, the CT-Bar should not fund capital 8 additions by reference to the Company’s current forecast. The refiled plan would 9 serve as the interim basis for capital funding until the Company files its first 10 Comprehensive IDSP under the final decision in Docket No. 21-05-15RE03. 11 Second, building on the Grid Needs Assessment and Hosting Capacity 12 Requirements proposed in the RE03 PFD No. 2 (recommendations #9 and #10 in 13 Appendix C), I recommend that the IDSP consider using N-1 capacity reserve to 14 host distributed energy resources. As proposed in the RE03 PFD No. 2, the Grid 15 Needs Assessment would include an N-1 contingency analysis, which tests whether 16 the distribution system can continue to serve load if a single component, such as a 17 substation transformer, is out of service. 184 To meet that standard, utilities hold 18 capacity in reserve at their substations and on their feeders. That reserve is needed 19 only during a contingency event; in most hours of the year, it is not used. 183 184 RE01 PFD, at pages 15, 19. RE03 PFD No. 2, at page 41. 83