Prefiled testimony
Witness: Melissa Whited
Files3
Synapse - Eversource COS and Rate Design Testimony Final.pdf
PDF · 829 KB · 48 pagesText searchable
Download Synapse - Eversource COS and Rate Design Testimony Final.pdfRead the text of Synapse - Eversource COS and Rate Design Testimony Final.pdf
MW-2- Synapse Attachment.pdf
PDF · 4.6 MB · 276 pagesText searchable
Download MW-2- Synapse Attachment.pdfRead the text of MW-2- Synapse Attachment.pdf
MW-1 - Synapse Attachment.pdf
PDF · 734 KB · 13 pagesText searchable
Download MW-1 - Synapse Attachment.pdfRead the text of MW-1 - Synapse Attachment.pdf
Page 11 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 legacy AMR technology to AMI9 and has proposed a six-year implementation plan for 2 deploying AMI meters across the state.10 3 Q How does the Company propose to classify and allocate AMI costs? 4 A The Company states that it “is proposing to recover eligible AMI capital costs through 5 the proposed Performance Based Multi-Year Rate Plan (“PBMRP”) capital funding 6 mechanism,” and that costs would be allocated to rate classes on the basis of class 7 distribution revenue (class allocation factors) described in the tariff.11 However, in the 8 next rate case, AMI costs would presumably be moved to base rates, and the Company 9 has not indicated that it would deviate from its standard approach of classifying metering 10 and related costs as customer-related.12 11 Q 12 13 Do you have concerns with the classification of AMI meter costs as entirely customer-related? A Yes. Classifying traditional meters as customer-related is reasonable, because their 14 primary function is to measure each customer’s usage for billing. AMI meters have much 15 greater capabilities, including supporting time-varying rates, providing granular voltage 16 and load data, and enabling voltage optimization. Those additional capabilities provide 17 energy and demand savings to the system as a whole, rather than just serving as a 18 customer billing tool. Because the Company is about to replace meters across its entire 19 territory, now is the time to provide guidance to ensure that AMI costs are classified 20 appropriately. 9 In contrast, Eversource in Massachusetts began broad AMI deployment beginning in 2025. As of October 2026, Eversource’s Massachusetts website indicates 500,000 smart meters installed, representing approximately onethird of its 2028 deployment goal. https://www.mass.gov/info-details/grid-modernization-and-ami-resources 10 Exh. CLP-AMI-2, pp. 9-12. 11 Response to OCC-740. 12 Exh. CLP-ACOS-1, at 4:5-7. 9Page 12 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 Q 2 3 Has the classification of advanced meter costs been addressed in cost allocation literature? A Yes. The Regulatory Assistance Project addresses the issue directly. It explains that the 4 main purpose of meters was once customer billing, but that “advanced meters serve a 5 broader range of functions, including demand management, which in turn provides 6 system capacity benefits, and line loss reduction, which provides a system energy 7 benefit.” It concludes that “the benefits of these meters flow beyond individual 8 customers, and logically so should responsibility for the costs.”13 9 Q 10 11 Does Eversource’s own analysis show that AMI enables services beyond customerrelated functions? A Yes. Among the benefits listed in the Company’s benefit categories in its Benefit Cost 12 Analysis of AMI are system cost avoidance, volt/var optimization (“VVO”), and time 13 varying rates.14 The Company therefore expects AMI to: 14 • 15 reduce peak demand by enabling more sophisticated time-varying rates, thereby avoiding or deferring system costs that would otherwise increase with peak load; and • 16 17 reduce distribution losses and energy consumption through voltage optimization, using voltage data from AMI meters. 18 These operational improvements that Eversource recognized in its benefit cost analysis 19 clearly extend the role of AMI beyond traditional metering, which provides none of these 13 Lazar, J. et al., Electric Cost Allocation for a New Era: A Manual. Montpelier, VT: Regulatory Assistance Project (2020), at 18. 14 CLP-AMI-2, Figure 22, p. 91. 10Page 13 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 functions. Its cost classification should therefore recognize that the investment is 2 “largely justified by services other than billing.”15 3 Q How do you recommend that Eversource classify AMI meter costs? 4 A AMI meter costs should be classified in proportion to the net present value of the benefits 5 the Company has quantified, with each benefit assigned according to what drives the cost 6 it avoids. I recommend that benefits from metering, billing, and customer account 7 functions be classified as customer-related, benefits from voltage optimization and 8 reduced line losses as energy-related, and benefits from peak reduction, avoided VVO 9 line sensors, and improved outage restoration as demand-related. 10 Q 11 12 What percentage of AMI meter costs should be classified as demand-related and energy related? A The Company provides the present value of AMI benefits in Exhibit CLP-AMI-3. I have 13 reproduced these benefits in the table below, excluding carbon reduction, which is not a 14 utility system benefit, and system costs avoidance, which is primarily the avoided cost of 15 the customer information system and does not depend on the AMI meters themselves. 15 Lazar, J. et al., Electric Cost Allocation for a New Era: A Manual. Montpelier, VT: Regulatory Assistance Project (2020), at 157. 11Page 14 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 Table 1. Classification of AMI Costs According to System Impacts Benefits (NPV $M) $21.20 $160.30 $32.20 $5.70 $74.50 Benefit Category Meter Reading Avoided Meter Capital Remote Connect/Disconnect No Trouble Found Calls Reduced Bad Debt Recommended Classification Customer Customer Customer Customer Customer Reduced Soft Close Loss $24.30 Customer VVO Time-Varying Rates Asset Optimization Advanced Engineering Analysis Avoided Connectivity Survey Improved Restoration – Significant Storms Improved Restoration – Blue Sky Reduced Theft and Non-Technical Line Loss $163.80 $23.90 $96.40 $38.70 $6.70 $162.40 $2.50 Energy $106.2 / Demand $57.6 Demand Demand Demand Demand Demand Demand $16.50 Energy Customer-related Demand-related Energy-related $318.20 $388.20 $122.70 38% 47% 15% 2 Source: Avoided costs from Exhibit CLP-AMI-3, Figure 7. Classification is my own. 3 Thus, AMI meter costs should be classified as 38 percent customer-related, 47 percent 4 demand-related, and 15 percent energy-related. 5 Q Have other Commissions approved similar AMI meter classifications? 6 A Yes. The Maryland Public Service Commission approved “a benefits approach for 7 allocating AMI costs among rate classes” in 2016, when it approved a proposal to assign 8 25% of AMI costs using a customer-based allocator, 37.5% using a demand-based 9 allocator, and 37.5% using an energy-based allocator in Pepco’s distribution rate case.16 16 In the Matter of the Application of Potomac Electric Power Company for Adjustments to its Retail Rates for the Distribution of Electric Energy (Hereafter, “MD PSC, Case No. 9418”). Order No. 87884. November 15, 2016. https://psc.maryland.gov/wp-content/uploads/Order-No.-87884-Case-No.-9418-Pepco-Rate-Case-1.pdf at 105106. 12Page 15 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 The approved proposal was based on the fact that an early report on AMI benefits 2 assigned just over 75% of the benefits to energy and demand management outcomes, 3 justifying a customer-, demand-, and energy-based allocation.17 The PSC concluded that 4 the “hybrid approach most fairly spreads the costs and related benefits of AMI 5 throughout the Pepco service territory.”18 6 7 B. The Company’s minimum system method to classify distribution system costs does not reflect cost causation 8 Q What is a minimum system study? 9 A A minimum system study, or minimum system method, is a cost analysis that estimates 10 what the cost of the distribution system would be if the total system inventory was 11 composed of the smallest equipment size. 12 Q 13 14 How does the Company use the Minimum System Method to classify distribution costs? A The Company’s Minimum Distribution System (“MDS”) Study separates the costs of 15 distribution facilities into customer-related and demand-related components.19 Under this 16 approach, Eversource first identifies the cost of the hypothetical minimum sized system 17 (including minimum sized poles, conductors and conduits, and transformers) required to 18 connect customers. It then classifies the portion of distribution costs representing the 19 minimum system as customer-related, while the difference between total system costs 20 and customer-related costs is classified as demand-related.20 Table 2 below provides the 17 MD PSC, Case No. 9418. Direct Testimony of Shelley Norman. July 6, 2016. https://webpscxb.pscmaryland.com/DMS/case/9418 Item No. 33. At 21-23. 18 MD PSC, Case No. 9418. Order No. 87884. November 15, 2016. At 106. 19 Exhibit CLP-ACOS-1, p. 4. 20 Exh. CLP-ACOS, at 4:14-5:13. 13Page 16 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 resulting split between customer-related and demand-related costs resulting from this 2 method.21 3 Table 2. Minimum system study classification factors 4 5 Q How does the Company define customer-related costs? 6 A The Company defines customer-related costs as those that vary with the number of 7 customers on the system and are independent of the customer’s usage. The Company also 8 asserts that customer-related costs include a portion of the distribution system identified 9 with the Minimum Distribution System.22 10 Q Is it appropriate to classify the Minimum Distribution System as customer-related? 11 A No. While these costs are not directly related to customer demand, they are similarly not 12 directly related to the number of customers on the system. Rather, these costs are 13 primarily driven by the geographic dispersion of customers. As Professor Bonbright 14 explains, the primary justification put forward for classifying the costs of this “phantom, 15 minimum-sized distribution system” as customer related is that these costs vary directly 16 with the area of the distribution system or the lengths of the distribution lines and thus are 17 thought to vary indirectly with the number of customers.23 However, he noted that the 21 Exh. CLP-ACOS-1 at 5, Table 1. Exh. CLP-ACOS-1 at 4:3-7. 23 James Bonbright. 1961. Principles of Public Utility Rates, pp. 347-348. 22 14Page 17 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 correlation between the area (or mileage) of a distribution system and the number of 2 customers is “very weak,” because “it makes no allowance for the density factor 3 (customers per linear mile or per square mile),” and that “an increase in number of 4 customers does not necessarily betoken any increase whatever in the costs of a minimum- 5 sized distribution system.”24 6 In other words, using customer counts as the allocator for the minimum system 7 does not capture the higher cost of serving sprawling or remote populations relative to 8 dense urban centers. For example, if the Company adds a new residential customer with a 9 negligible level of demand in a populated area, the additional distribution costs to serve 10 that customer—aside from dedicated customer infrastructure—would generally also be 11 negligible, because the system has already been constructed to serve customers in that 12 area. In contrast, a new customer located in a rural area may require investments in 13 additional distribution system poles and wires to extend service to the customer’s 14 residence. These hypotheticals illustrate that distribution system costs associated with 15 connecting a new customer to the grid tend to vary more with geographic density than the 16 number of customers. 17 Q 18 19 How did Professor Bonbright recommend minimum distribution system costs be classified? A 20 Professor Bonbright argued that the costs of the minimum system should be excluded from demand-related costs, but also that classifying them as customer-related is “clearly 24 Id., at 348. 15Page 18 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 indefensible.”25 Instead, in Bonbright’s opinion, these costs “should be recognized as a 2 strictly unallocable portion of total costs.”26 3 Q 4 5 Are there any alternative methods that would better account for customer density in cost of service models? A Yes. The Ontario Energy Board approved the use of a density factor, calculated as 6 customers per kilometer of line,27 to inform categorization of customer-related and 7 demand-related costs. The Ontario Energy Board’s examination identified low, medium, 8 and high customer density “bins” to establish the percentage of customer-related costs. 9 Transformers were part of the cost pool subjected to the minimum plant categorization 10 based on customer density.28 This method could also be applied to Eversource’s system 11 in the future. 12 Q Do you have any other concerns regarding the minimum system method? 13 A Yes. The minimum system includes poles, conductors, and transformers that are capable 14 of serving some amount of demand. In some cases, the “minimum system” as defined by 15 the utility may even be capable of serving most or all of a typical residential customer’s 16 peak demand. This infrastructure is classified as customer-related, while the remaining 17 demand-related costs are allocated using each class’s full non-coincident peak demand, 18 including the portion the minimum system already serves. Unless each class’s demand 19 allocator is reduced to account for the load-carrying capability of the minimum system, 20 classes with many small customers will be charged twice for the same capacity: once 21 through the customer classification and again through the demand allocator. The 25 Ibid. Ibid. 27 Ontario Energy Board, EB-2007-0667, Board Staff Discussion Paper, p. 12. 28 Ibid. 26 16Page 19 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 residential class bears most of this double counting, because it has the most customers 2 and the lowest demand per customer. 3 This issue was identified by the Staff of the Ontario Energy Board, who wrote 4 that “[a] Minimum System has a certain load carrying capability which can be viewed as 5 being demand-related. As a result, the customer-related costs will have a demand 6 component in them. If no adjustment is made, some customers (e.g., small users) may be 7 allocated a disproportionate share of demand-related costs. If the Minimum System 8 Method is preferred for categorization, Staff would recommend that distributors be 9 required to also adjust for the [Peak Load Carrying Capacity] of the assumed Minimum 10 System.”29 11 Q 12 13 Has the Authority previously approved a load carrying adjustment for the minimum system? A Yes. In Docket No. 24-10-04, the Authority determined that “it is appropriate to use the 14 Company’s load-carrying capacity adjustment values for poles and conductors,” as well 15 as conductors and line transformers.30 16 Q Did Eversource implement such an adjustment? 17 A No. When asked whether the Company “considered the minimum system’s load carrying 18 capacity when allocating demand-related costs,” the Company responded that it did not 19 “revise the demand classification percentage based on the minimum system carrying 29 Ontario Energy Board. Cost Allocation Review: Staff Discussion Paper. September 2005. At 21-22. Available at https://www.oeb.ca/documents/cases/EB-2005-0317/staffdiscussionpaper_160905.pdf. 30 Final Order in Docket 24-10-04, October 28, 2025, pp. 198-199. 17Page 20 of 48
Docket No. 26-05-10 Prefiled Direct Testimony of Melissa Whited 1 capacity,” and that the ACOS study relied on the “traditionally applied MDS approach as 2 applied in prior rate cases and as per the NARUC Manual.”31 3 Q 4 5 Do you agree that the Company applied the minimum system method in a manner consistent with the NARUC manual? A No. The NARUC Manual states that “[w]hen using this distribution method, the analyst 6 must be aware that the minimum-size distribution equipment has a certain load-carrying 7 capability, which can be viewed as a demand-related cost.”32 8 Q What are your recommendations for the minimum system method? 9 A I recommend that the Authority reject the minimum system method. Instead, my primary 10 recommendation for this proceeding is that the Authority adopt the basic customer 11 method, under which the costs that are directly classified as being customer-related are 12 the costs of metering (including the service drop), meter reading, and billing. In some 13 cases, the cost of the secondary line transformer is also included. This method limits 14 customer-related costs to those clearly related to the cost associated with serving a new 15 customer. All other costs should be classified as demand-related until the Company 16 completes a study that appropriately allocates “minimum system” costs according to 17 customer density. To accomplish this, I recommend that the Authority direct Eversource 18 to develop a geographic dispersion allocator, similar to that approved for Ontario’s 19 Minimum System Studies, where the Company applies density bins (e.g., urban, rural, 20 and mixed) measured in customers per mile to differentiate customer-related cost 21 percentages. 31 32 OCC-738(a). NARUC (1992) Electric Cost Allocation Manual, at 95. 18