Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Files3

Search terms highlighted
Eversource rate increase is on 6 pages across 2 files of the text below, highlighted. Go to the first matchClear highlighting
5 pages match
Words on different pages
  1. Page 106 of 276

    104 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Works Cited in Part II Austin Energy (2017). Residential electric rates & line items [Webpage]. Retrieved from https://austinenergy.com/ae/rates/residential-rates/residential-electric-rates-and-line-items Bonbright, J. (1961). Principles of public utility rates. New York, NY: Columbia University Press. Bureau of Reclamation. (1991). Permissible loading of oil-immersed transformers and regulators. Denver, CO: Author. Retrieved from https://www.usbr.gov/power/data/fist/fist1_5/vol1-5.pdf California Public Utilities Commission. (n.d.). Net energy metering (NEM) [Webpage]. Retrieved from https://www.cpuc.ca.gov/general.aspx?id=3800 California Public Utilities Commission. (2016, January 28). Decision adopting successor to net energy metering tariff. Decision No. 16-01-044. Retrieved from http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M158/ K181/158181678.pdf Denholm, P., Margolis, R., and Milford, J. (2008). Production cost modeling for high levels of photovoltaics penetration (TP-581-42305). Golden, CO: National Renewable Energy Laboratory. Retrieved from https://www.nrel.gov/docs/fy08osti/42305.pdf Electric Reliability Council of Texas. (2019). 2018 ERCOT hourly load data [Data set]. Retrieved from http://www.ercot.com/gridinfo/load/load_hist/ Federal Energy Regulatory Commission. (n.d.). Form No. 714 — Annual balancing authority area and planning area report [Webpage]. Retrieved from https://www.ferc.gov/docs-filing/forms/form-714/data.asp Federal Energy Regulatory Commission. (1979, September 28). Order 48: Final regulations in Docket RM79-6. Retrieved from https://elibrary.ferc.gov/idmws/file_list.asp?document_id=14005118 Flex-Core. (n.d.). Energy metering using potential and current transformers [Webpage]. Retrieved from https://www.flex-core.com/engineering-resources/application-whitepapers/energy-metering-using-potentialcurrent-transformers/ Hawaiian Electric Company. (2014, April 30). Minimum day time load calculation and screening. Distributed Generation Interconnection Collaborative (DGIC) webinar. Retrieved from https://www.energy.gov/sites/prod/ files/Hawaiian%20Electric%202014-04-30_minimum-day-time-load-calculation-and-screening.pdf Hledik, R., and Lazar, J. (2016). Distribution system pricing with distributed energy resources. Golden, CO: Lawrence Berkeley National Laboratory. Retrieved from https://www.osti.gov/servlets/purl/1375194 Hogan, M. (2016). Hitting the mark on missing money: How to ensure reliability at least cost to consumers. Montpelier, VT: Regulatory Assistance Project. Retrieved from https://www.raponline.org/knowledge-center/ hitting-mark-missing-money-ensure-reliability-least-cost-consumers/ International Telecommunication Union. (2009). Regulatory accounting guide. Retrieved from https://www.itu.int/ ITU-D/finance/Studies/Regulatory_accounting_guide-final1.1.pdf Kahn, A. (1970 and 1971). The economics of regulation: Principles and institutions (vols. 1 and 2). New York, NY: John Wiley & Sons.
  2. Page 107 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA Lazar, J. (2016). Teaching the “duck” to fly (2nd ed.). Montpelier, VT: Regulatory Assistance Project. Retrieved from https://www.raponline.org/knowledge-center/teaching-the-duck-to-fly-second-edition/ Lazar, J., and Baldwin, X. (2011). Valuing the contribution of energy efficiency to avoided marginal line losses and reserve requirements. Montpelier, VT: Regulatory Assistance Project. Retrieved from https://www.raponline.org/ knowledge-center/valuing-the-contribution-of-energy-efficiency-to-avoided-marginal-line-losses-and-reserverequirements/ Lefkowitz, K. (2016, April). Direct testimony on behalf of Potomac Electric Power Co. (Pepco). Application of Potomac Electric Power Co. for adjustments to its retail rates for the distribution of electric energy (Vol. 1). Maryland Public Service Commission Case No. 9418. Retrieved from https://www.psc.state.md.us/searchresults/?keyword=9418&x.x=34&x.y=18&search=all&search=case Moody’s Investor Service. (2017, June 23). Rating methodology, regulated electric and gas utilities. National Association of Regulatory Utility Commissioners. (1992). Electric utility cost allocation manual. Washington, DC: Author. Retrieved from https://pubs.naruc.org/pub/53A3986F-2354-D714-51BD-23412BCFEDFD National Economic Research Associates. (1977). A framework for marginal cost-based time-differentiated pricing in the United States. Palo Alto, CA: Electric Power Research Institute. New York Public Service Commission. (2017, March 9). Order on net energy metering transition, Phase One of value of distributed energy resources, and related matters. Case No. 15-E-0751. Retrieved from http://documents.dps.ny.gov/ public/Common/ViewDoc.aspx?DocRefId={5B69628E-2928-44A9-B83E-65CEA7326428} Nicholas, M., and Hall, D. (2018). Lessons learned on early electric vehicle fast-charging deployments. Washington, DC: The International Council on Clean Transportation. Retrieved from https://www.theicct.org/ sites/default/files/publications/ZEV_fast_charging_white_paper_final.pdf Potter, J., George, S., and Jimenez, L. (2014). SmartPricing options final evaluation. Sacramento, CA: Sacramento Municipal Utility District. Retrieved from https://www.smartgrid.gov/files/SMUD-CBS_Final_Evaluation_Submitted_ DOE_9_9_2014.pdf Pyper, J. (2018, August 29). Xcel to replace 2 Colorado coal units with renewables and storage. Greentech Media. Retrieved from https://www.greentechmedia.com/articles/read/xcel-retire-coal-renewable-energy-storage Rissman, J. (2017). The future of electric vehicles in the U.S. San Francisco, CA: Energy Innovation. Retrieved from https://energyinnovation.org/wp-content/uploads/2017/10/2017-09-13-Future-of-EVs-Research-Note_FINAL.pdf Seattle City Light. (n.d.). City Light rates: Tariffs and rules [Webpage]. Retrieved from https://www.seattle.gov/light/ rates/ratedetails.asp Shirley, W. (2001). Distribution system cost methodologies for distributed generation (Vol. 2, Appendices). Montpelier, VT: Regulatory Assistance Project. Retrieved from https://www.raponline.org/knowledge-center/distributionsystem-cost-methodologies-for-distributed-generation-volume-ii-appendices/ Slusarewicz, J., and Cohan, D. (2018). Assessing solar and wind complementarity in Texas. Renewables: Wind, Water and Solar (5)7. Retrieved from https://jrenewables.springeropen.com/articles/10.1186/s40807-018-0054-3 Trabish, H. (2017, November 2). In new trend, utilities propose separate rate classes for solar customers without rate increase. Utility Dive. Retrieved from https://www.utilitydive.com/news/in-new-trend-utilities-propose-separaterate-classes-for-solar-customers-w/508393/ | 105
  3. Page 108 of 276

    106 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® U.S. Department of Energy. (n.d.). Charging at home [Webpage]. Retrieved from https://www.energy.gov/eere/ electricvehicles/charging-home U.S. Energy Information Administration. (2019). Annual energy outlook 2019. Table 9. Washington, DC: Author. Retrieved from https://www.eia.gov/outlooks/aeo/data/browser/#/?id=9-AEO2019&cases=ref2019&sourcekey=0 Vermont Public Service Board. (2007, June 20). Investigation into least-cost integrated resource planning for Vermont Electric Power Company’s transmission system. Docket No. 7081. Retrieved from https://epuc.vermont.gov/?q=node/104/16200 Vermont System Planning Committee. (n.d.). Planning for the future of Vermont’s electric power grid [Webpage]. Retrieved from https://www.vermontspc.com/ Wood Mackenzie Power & Renewables and Solar Energy Industries Association. (2019, March). U.S. solar market insight. Retrieved from https://www.seia.org/research-resources/solar-market-insight-report-2018-year-review
  4. Page 109 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA Part III: Embedded Cost of Service Studies | 107
  5. Page 110 of 276

    108 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® 9. Generation in Embedded Cost of Service Studies T his chapter addresses the allocation of generation adequacy of generation supply to meet loads). Energy use is costs, including investment-related costs, operation sometimes broken into TOU periods, so that different types and maintenance costs and fuel costs. As noted of costs are spread over the hours in which they are used, as in Section 6.1, equivalent changes in the allocation of a discussed further in Section 9.2 and Chapter 17. cost category among classes can be achieved by changing When there are multiple cost-based approaches for functionalization, classification or the choice of allocation estimating a classification or allocation factor, a compromise factor.83 That section discusses the relevant issues at a high among the results may be appropriate. For example, various level, and this chapter delves more deeply into the underlying measures of reliability risk (emergency purchases, operation concepts and analytical techniques. of peakers, interruption of load, inadequate operating This chapter is not generally relevant to cost allocation reserve) may be distributed differently across the months, for utilities that have restructured and no longer procure and the regulator may reasonably select a generation demand generation resources, as long as the generation prices allocator averaging across the results of those measures. suppliers offer (directly to customers or to the utility for Similar conditions might apply for varying estimates of the default service) are differentiated by rate class. High-level firm-capacity equivalent for wind plants or other inputs. cost allocation issues with respect to generation and default service are discussed in Section 7.2. As discussed in Chapter 3, utilities acquire and maintain Some cost of service studies identify other classifications of generation costs, such as ancillary services. These components are generally very small compared with total different types of generation resources, with distinct generation costs, and some ancillary services (automatic operating capabilities, to meet a range of needs including generation control, black start capability, uplift) can be low-cost energy, reliability, load following and environmental difficult to relate to class load characteristics. compliance. Different classification and allocation methods may be necessary to equitably allocate the costs of different types of generation resources. In more recent years, energy efficiency, expanded demand response, distributed generation and energy storage — all of which can be located where load relief is most valuable — have expanded the utility’s options to meet load growth or reduce demands on aging assets without building transmission, distribution or central generation facilities. Fuel costs, purchased power and dispatch O&M costs, such as the short-run variable cost of pollution controls, are typically classified as energy-related. The other categories of generation costs have generally been classified as being driven 9.1 Identifying and Classifying Energy-Related Generation Costs Many regulators have recognized that energy needs are a significant driver of generation capital investments and nondispatch O&M costs. In modern utility systems, generation facilities are built both to serve demand (i.e., to meet capacity and reliability requirements) and to produce energy economically. The amount of capacity is largely determined by reliability considerations, but the selection of generation technologies and thus the cost of the capacity are by some combination of energy (total energy requirements to serve customers, plus losses) and demand (some measure of loads in the hours that contribute to concerns about the 83 As mentioned previously, the third step is usually called allocation, which is the same as the name of the entire process. Some analysts refer to this third step as factor allocation in an attempt to prevent confusion.
  6. Page 111 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 109 largely determined by energy requirements.84 For variable from competitive wholesale markets. This is followed by four renewables, particularly wind and solar, the effective capacity different classification approaches and two joint classification (in terms of the reliability contribution) of the generators is and allocation approaches, then a discussion of other much smaller than their nameplate capacity, and the costs technologies and issues. are mostly undertaken to provide energy without fuel costs or air emissions. Energy storage systems provide both energy benefits (by shifting energy from low-cost to high-cost hours) and reliability benefits, while demand response is used primarily to increase reliability. 9.1.1 Insights and Approaches From Competitive Wholesale Markets The ISOs/RTOs that operate energy (and in some cases, capacity) markets — specifically ISO-NE, NYISO, PJM, As discussed in the text box on pages 78-79, some older ERCOT, MISO and the SPP — provide examples of how the cost of service studies classified a wide range of capital and recovery of capital investment and nondispatch O&M costs nondispatch O&M costs as demand-related on the grounds naturally splits between energy and demand. The pricing that the costs were in some manner fixed, without regard for in these markets can provide both a competitive proxy for cost causation. This approach, known as straight fixed/vari- classifying generation costs and a benchmark to check the able, is anachronistic and does not reflect cost causation.85 reasonableness of other techniques. Table 12 shows the capital and O&M costs estimated for ERCOT has no capacity market, and all costs are new conventional generation units from the 2018 Lazard’s recovered through time-varying energy charges. Those energy Levelized Cost of Energy Analysis report.86 Although the origi- charges are heavily weighted toward a small number of hours, nal costs and current plant in service and O&M costs of older which do not tend to have particularly high loads; the highest- units will vary, the general relationships have been consistent. load hours are not the highest-cost hours. Figure 30 on the This section first discusses the insights on this issue next page shows the hourly load and Houston Hub prices Table 12. Cost components of conventional generation, 2018 midpoint estimates Technology Combustion turbine Capital cost (per kW) Fixed Variable operations and operations and maintenance maintenance (per kW-year) (per MWh) $825 $12.50 $7.40 Combined cycle $1,000 $5.75 $2.80 Coal $3,000 $40.00 $2.00 Nuclear $9,375 $125.00 $0.80 Source: Lazard. (2018). Lazard’s Levelized Cost of Energy Analysis — Version 12.0 84 “Citing both past operating experience and future resource planning, the Division [the PSC intervention staff] notes that resources with higher energy availability are chosen over those with lower energy availability. Since energy plays a role in the selection of least-cost resources, the Division concludes that some weight needs to be given to energy in planning for new capacity, and the current weight of 25 percent is reasonable. We find the qualitative argument offered by the Division to be … convincing.” (Utah Public Service Commission, 1999, p. 82). See also Washington Utilities and Transportation Commission (1993, pp. 8-9). 85 The term “straight fixed/variable” is imported from FERC’s rate design method for wholesale gas supply, where utilities, marketers and very large customers contract for capacity in a portfolio of individual pipeline and storage facilities. As is true for many electric wholesale purchased for 2017 (Electric Reliability Council of Texas, 2018, for load data; ENGIE Resources, n.d., for pricing data). Prices generally trend upward with load, but the highestpriced hours are spread nearly evenly across load levels. In 2017, the highest-priced 1% of hours (with prices over $160 per MWh) would have provided 18% of the annual net margin for a baseload plant with no variable cost, 53% of the margin for a plant with a variable cost of $20 per MWh (perhaps a combined cycle unit), and 77% of the margin for a plant with a $30-per-MWh variable cost (such as a recently built combustion turbine), assuming ideal dispatch and no power contracts, these gas contracts require that the buyers pay for investment-related costs regardless of how they use the resources and pay for variable costs in proportion to their usage. This approach is workable at the wholesale level but is not applicable to retail cost allocation, where the utility bundles a portfolio of generation assets for all of its customers. 86 The coal cost in the table is Lazard’s low end, since the high-end cost “incorporates 90% carbon capture and compression” (Lazard, 2018, p. 2), which is in use on only one existing utility coal unit, SaskPower’s Boundary Dam. The $3,000/kW value is also consistent with the costs of the last three coal plants completed by U.S. regulated utilities (Turk, Virginia City and Rogers/Cliffside 6, all completed in 2012). Actual current costs of various vintages of resources will vary for each utility.
  7. Page 112 of 276

    110 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Figure 30. ERCOT load and real-time prices in 2017 $2,250 Hourly price per megawatt-hour $2,000 $1,750 $1,500 $1,250 $1,000 $750 $500 $250 $0 -$250 20,000 25,000 30,000 35,000 40,000 45,000 50,000 55,000 60,000 65,000 70,000 Hourly load in megawatts Sources: Electric Reliability Council of Texas. (2018). 2017 ERCOT Hourly Load Data; ENGIE Resources. Historical Data Reports outages. Those 88 hours representing the costliest 1% occurred estimated that the net revenues available to pay the capital in every month and almost the whole range of annual loads. investment and nondispatch O&M costs of a typical recently In contrast, the 1% of highest-load hours would have built gas combined cycle unit would have been about provided 5.1% of the margin for the baseload plant, 2.4% for 25% to 60% from the energy market and the remainder the intermediate plant and 2% for the combustion turbine. from the capacity market, depending on the year (Patton, This cost pattern suggests that, at least in some systems, LeeVanSchaick and Chen, 2017, p. 13). The comparable values generation costs should be time-differentiated but that load for nuclear units were almost all from the energy market is not a good proxy for the highest-price periods. Classes with (Patton et al., 2017, p. 17). the ability to shape load to low-cost periods (with demand The PJM independent market monitor reports the response or storage) may be much less expensive to serve capacity revenues and the net energy revenues (i.e., energy than those with inflexible load patterns. revenue in excess of fuel and variable O&M) for a variety of Regardless of how the top hours are chosen, the ERCOT plant types (Monitoring Analytics, 2014, pp. 219-222, 2019, data indicate that most of the long-term power supply costs pp. 335-339). These are the revenues available to pay for the are not recovered from the few peak hours and thus should capital investment and nondispatch O&M costs and thus not be considered demand-related. For a load shaped like the represent the market allocation of these costs for the plants. ERCOT average load, only about 3% of the generation costs Figure 31 on the next page shows the portion of these costs were associated with the 1% of highest-load hours, and about recovered through capacity payments for four types of new 20% were associated with the 1% of highest-price hours. plants (gas-fired combustion turbine and combined cycle In New England, the ISO-NE external market monitor units, and hypothetical new coal and nuclear) in each year
  8. Page 113 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 111 Figure 31. Capacity revenue percentage in relation to capacity factor in PJM 100% Capacity revenue as percentage of total revenue Combustion turbine 90% Combined cycle Coal 80% Nuclear Trend 70% 60% 50% 40% 30% 20% 10% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Capacity factor Data sources: Monitoring Analytics. (2014 and 2019). 2013 State of the Market Report for PJM, 2018 State of the Market Report for PJM 2009 through 2017 (Monitoring Analytics, 2014, 2019).87 prices, while the Hudson Valley and New York City have very The concept displayed here is that units with a high high capacity prices, and Long Island has intermediate prices. capacity factor tend to make more of their revenue from Both capacity and energy revenues vary among zones within energy markets instead of from the capacity market. In this each of these three areas, between load pockets within zones set of PJM data, energy revenues cover 14% to 60% of the and among combustion turbine types. combustion turbine costs, 38% to 74% of combined cycle costs, 56% to 73% of baseload coal plant costs, about Table 13. Energy portion of 2017 net revenue for New York ISO 34% of the costs of economically dispatched coal units, Generator type and 77% to 89% of nuclear costs over the nine-year period. The values for 2017 were 39% for modern combustion Zone Combustion turbines turbines, 87% for combined cycle units, 65% for coal and Upstate 72% to 80% 71% to 79% 42% to 55% 20% for nuclear. Current values for PJM or the relevant load Long Island 52% to 70% 62% to 76% 21% to 57% Hudson Valley and 31% to 49% New York City 34% to 55% 6% to 29% zones could be used as the demand classification percentages for vertically integrated utilities in PJM (e.g., IOUs in Kentucky, Virginia and West Virginia, and municipal and cooperative utilities in several states). The market monitoring unit of the NYISO provided similar analyses for the various pricing zones of that RTO, as shown in Table 13 (Patton, LeeVanSchaick, Chen and Palavadi Naga, 2018, Table A-14, with additional calculations by the authors). The upstate zones have relatively low capacity Combined cycle Steam Sources: Patton, D., LeeVanSchaick, P., Chen, J., and Palavadi Naga, R. (2018). 2017 State of the Market Report for the New York ISO Markets; additional calculations by the authors 87 The independent market monitor assumed that a nuclear plant would operate at a 75% capacity factor and made the same assumption for the coal plant through 2015; the capacity factors for the gas-fired plants and for coal in 2016 and 2017 are determined from the economic operation of the units.
  9. Page 114 of 276

    112 | ELECTRIC COST ALLOCATION FOR A NEW ERA 9.1.2 Classification Approaches REGULATORY ASSISTANCE PROJECT (RAP)® The system load factor, and hence the average-and-peak Many utilities and regulators acknowledge that a large approach more generally, varies over time independent of the portion of generation investment and nondispatch O&M mix of the utility’s generation resources and does not respond costs is incurred to serve energy requirements. There are two to changes in that mix unless those changes are accompanied categories of methods to classifying these costs as energy- by retail pricing that follows the cost structure. related and demand-related. First, average-and-peak is a In addition to changing as loads change, the average-and- top-down approach that uses high-level data on system loads peak approach ignores the mix of resources and costs. This and costs. Second, there is a range of bottom-up approaches approach would produce the same classification of plant for that examine the drivers for costs on a plant-specific basis: a system that was entirely composed of gas-fired combustion • Base-peak and related methods. turbines (with low capital costs and high fuel costs) or of • Equivalent peaker method. coal-fired plants (with high capital costs to produce lower • Operational characteristics methods. fuel costs). As a general matter, the bottom-up approaches are Thus, while the average-and-peak method for generation preferable for classifying generation costs. The average-and- costs may sometimes fall in the range of reasonable results, peak approach is well suited for shared distribution system it is neither logical nor consistent. costs, as discussed in Section 11.2. Average-and-Peak Method The average-and-peak approach can be applied Base-Peak Methods Various utilities and other analysts have proposed to subfunctionalize generation resources (in the simplest case, in classification, when classifying a portion of costs as between baseload and peaking plants) and classify each energy-related and the remainder as demand-related, or category of generation in a different manner. For example, in developing a generation capacity allocator that reflects peakers may be classified 100% as demand-related, while both energy and demand. When using this approach as a baseload resources are classified 75% to demand and 25% to classification method, the system load factor percentage is energy, or some other location- and situation-specific ratio. classified as energy-related and the remainder as demand- More advanced analyses have subfunctionalized related.88 When used as an allocation factor, the average- generation among base, intermediate and peak categories, and-peak factor for each class is:89 known as BIP classification. The base generation might be defined as all nuclear and coal plants, with the intermediate being gas-fired steam and combined cycle plants and the Where A = annual average load = energy ÷ 8,760 peak units being combustion turbines, storage and demand P = peak load response. Alternatively, base plants might be any unit that C = class operated at more than a certain capacity factor (for example, S = system 60%), peakers those that ran at less than 5%, and intermediate SLF = system load factor = (annual energy) ÷ (peak load × 8,760) anything between those 5% and 60% capacity factors. Or, rather than using capacity factor (which can be low due to forced outages, maintenance or economic dispatch), the 88 This method is sometimes called the system load factor approach. It has also been called “average and excess” because a fraction of cost equal to the system load factor is allocated on energy and the excess of costs on a measure of peak loads (Coyle, 1982, pp. 51-52). 89 This average-and-peak allocator should not be confused with the averageand-excess demand allocator described in the 1992 NARUC Electric Utility Cost Allocation Manual, which allocates a portion of costs in proportion to average load and the excess in proportion to each class’s excess of peak load over its average use. That legacy average-and-excess allocator is essentially just a peak allocator (Meyer, 1981).
  10. Page 115 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 113 generation classes can be defined using operating factor (the output renewable resources, additional storage and economic ratio of output to equivalent availability). At an extreme, each demand response reduces the accuracy of those simple generation type, or even each unit, can be classified separately. models. Resources like wind and solar do not fit neatly into While the base-peak classification approach and related the BIP categories, providing service in distinct time patterns methods are highly flexible, that is both their greatest strength that may not be related to system loads. At the same time, and a great weakness. The strength is that the method can many utilities have access to much more granular detail on be modified to accommodate the diversity of generation hourly consumption by customer.91 The BIP method can be resources; the weakness is that the method requires a set of expanded to reflect conditions (output by several classes of decisions about the definition of the generation classes and conventional generation, solar, wind and storage; energy the classification percentage for each class. The base-peak use for storage; usage by class) in as many time periods (or method is connected to actual utility planning only at the load levels, or bins combining consumption and generation highest conceptual level and provides limited guidance for the conditions) as desired, even down to an hourly allocation nitty-gritty details of traditional classification. method. Usage and hence costs could thus be assigned One of the challenges of the base-peak approach relates to the changing usage of generation resources. directly to the classes using power at the times that each resource provides service.92 For example, several units that were built to burn coal in baseload operation have been converted to burn natural gas Equivalent Peaker Method and thus run mostly on high-load summer days.90 These The equivalent peaker method,93 discussed at length units operate as peak or intermediate resources (depending in the 1992 NARUC Electric Utility Cost Allocation Manual, on the definitions used in the particular analysis), but most attributes as demand-related the portion of investment in of the capital costs are attributable to the original baseload each resource that would have been incurred to secure a design. This problem may be ameliorated by removing those peaking resource, such as demand response or a combustion additional costs from the base-peak or BIP computation and turbine.94 Peaking resources are usually treated as 100% directly classifying them as energy-related. demand-related, while intermediate and baseload plants are Recent technological changes pose additional challenges and opportunities for expanding the base-peak approach classified as partly energy and partly demand. If only peak load had been higher (and other needs were from two generation profiles, or the three profiles of the BIP already satisfied) in the years in which the utility made the method, to a full analysis of the use of generation resources. bulk of its generation construction decisions, it would have Decades ago, it was reasonably accurate to treat generation likely met that increased load by adding peaker capacity.95 resources as being stacked neatly under the load duration Utilities historically have justified building baseload capacity curve in order of variable costs. The growing role of variable by relying on these plants’ long hours of use and lower fuel 90 Some coal plants that once ran as baseload resources have been taken out of service in low-load months to reduce O&M costs. This includes Nova Scotia Power’s Lingan 1 and 2 (Barrett, 2012), Luminant’s Monticello and Martin Lake (Henry, 2012) and the Texas Municipal Power Agency’s Gibbons Creek (Institute for Energy Economics and Financial Analysis, 2019). way: 34% (the ratio of minimum to peak load) to energy; 36% (the 90% ratio of winter peak to summer peak, minus the 34% energy allocation, or 56%, times the 65% of the peak-period hours that occur in winter) to the winter peak demand; and the remaining 30% to the summer peak demand (Seelye, 2016, Exhibit WSS-11). This approach has no cost basis. 93 In some jurisdictions, this is called the peak credit method. 91 Most utilities have long known the hourly generation by unit. 92 Some utilities refer to their classification method as BIP, even though it does not reflect the differences in costs among the various types of generation. For example, the Louisville Gas & Electric and Kentucky Utilities 2018 “BIP” computation classified nondispatch generation costs this 94 This approach is sketched out in Johnson (1980, pp. 33-35) and described in more detail in Chernick and Meyer (1982, pp. 47-65). 95 To some extent, the peakier load would likely allow for development of more demand response and load management. Estimating the potential and costs for these resources under hypothetical load shapes may be difficult.
1 page match

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Melissa Whited [26-05-10]

This filing on the current system (opens in a new tab)